FR2468696A1 - METHOD FOR PRESSING PRECONTRATED CONCRETE HELICOIDAL CONCRETE PILES BY TORSION PENETRATION AND PRECONTRATED CONCRETE HELICOID PILES FOR CARRYING OUT THE PROCESS - Google Patents

METHOD FOR PRESSING PRECONTRATED CONCRETE HELICOIDAL CONCRETE PILES BY TORSION PENETRATION AND PRECONTRATED CONCRETE HELICOID PILES FOR CARRYING OUT THE PROCESS Download PDF

Info

Publication number
FR2468696A1
FR2468696A1 FR8009960A FR8009960A FR2468696A1 FR 2468696 A1 FR2468696 A1 FR 2468696A1 FR 8009960 A FR8009960 A FR 8009960A FR 8009960 A FR8009960 A FR 8009960A FR 2468696 A1 FR2468696 A1 FR 2468696A1
Authority
FR
France
Prior art keywords
concrete
pile
piles
helical
precontrated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
FR8009960A
Other languages
French (fr)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of FR2468696A1 publication Critical patent/FR2468696A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/56Screw piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

La présente invention concerne un procédé pour enfoncer des pieux hélicoïdaux en béton précontraint par pénétration par torsion et des pieux hélicoïdaux en béton précontraint pour la mise en oeuvre du procédé. Dans ce procédé, on munit un pieu en béton a d'un flasque hélicoïdal 1, on fait pénétrer ledit pieu en béton dans le sol en le faisant tourner avec un certain couple sans évacuer les terres et on confère une force portante audit pieu en béton de sorte que le pieu en béton en lui-même présente une force portante telle que celle des pieux à frottement ou des pieux porteurs. Ce procédé est utilisé sur des chantiers de génie civil et de construction des bâtiments.The present invention relates to a method for driving helical concrete piles prestressed by twisting penetration and prestressed concrete helical piles for carrying out the method. In this process, a concrete pile is fitted with a helical flange 1, said concrete pile is made to penetrate into the ground by rotating it with a certain torque without removing the earth and a load-bearing force is given to said concrete pile so that the concrete pile itself has a load-bearing force such as that of friction piles or load-bearing piles. This process is used on civil engineering and building construction sites.

Description

Procédé pour enfoncer des pieux hélicoïdaux en béton précon-Method for driving helical piles of precast concrete

traint par pénétration par torsion? et pieux hélicoïdaux en  trailed by torsional penetration? and helical piles in

béton précontraint pour la mise en oeuvre du procédé.  prestressed concrete for the implementation of the method.

La présente invention concerne un procédé pour enfoncer-des pieux hélicoïdaux en béton précontraint par pénétration par torsion et des pieux hélicoïdaux en béton précontraint pour  The present invention relates to a method for driving-helical piles of prestressed concrete by torsion penetration and helical piles of prestressed concrete for

la mise en oeuvre dudit procédé.the implementation of said method.

En général les chantiers de génie civil et de construction des bâtiments et immeubles en agglomération sont souvent situés près des zones résidentielles. Les bruits et vibrations divers produits par ces constructions bien que temporaires, influent souvent sur les conditions de vie des habitants de cette zone  In general, civil engineering and construction sites of buildings and buildings in built-up areas are often located near residential areas. The various noises and vibrations produced by these constructions, although temporary, often influence the living conditions of the inhabitants of this area.

et les maisons et constructions voisines de la cité en cons-  and houses and buildings close to the city in con-

truction sont souvent endommagées. De ce fait, ce problème est devenu actuellement un des grands problèmes sociaux. En conséquence, certains travaux de construction dans les zones urbaines ou à leur périphérie demandent souvent de longs délais à cause des limitations en ce qui concerne les heures de travail et les coûts de construction tendent à s'accroître en raison des modifications dans les méthodes et modes de construction et ces facteurs entraînent des difficultés pour  truction are often damaged. As a result, this problem has become a major social problem. As a result, some construction work in or around urban areas often requires long lead times because of limitations in working hours and construction costs tend to increase due to changes in methods and procedures. methods of construction and these factors lead to difficulties in

le développement de la construction et la réduction des coûts.  construction development and cost reduction.

En particulier, à cause des règlements sur le bruit et les vibrations, il est en pratique difficile d'utiliser des outils faisant du bruit tels que des moutons à moteurs diesel  In particular, because of the regulations on noise and vibration, it is in practice difficult to use noise-making tools such as diesel-powered sheep.

ou des moutons vibrants pour l'enfoncement des pieux néces-  or vibrating sheep for the driving of the piles necessary for

saires à la construction des fondations des immeubles et constructions similaires dans les zones urbaines. Ainsi, en  construction of foundations of buildings and similar constructions in urban areas. So, in

vue de la nécessité sociale d'assurer une réduction impor-  the social need to ensure a significant reduction

tante des bruits et des vibrations produits par les procédés de fonçage de pieux conventionnels, un procédé de-construc- tion du type dit sans bruit et sans vibration a été développé  In the noise and vibration produced by conventional pile driving processes, a construction method of the so-called noise-free and vibration-free type has been developed.

à la place des procédés de battage des pieux conventionnels.  instead of conventional pile driving methods.

De plus avec l'augmentation des travaux de construction en  Moreover with the increase of the construction works in

zone urbaine de nombreuses méthodes de construction différen-  urban area many different construction methods

tes utilisant la méthode sans bruit et sans vibration ont été proposées. Cependant une telle méthode de construction sans bruit et sans vibration conventionnelle comporte diverses étapes et ses coûts augmentent beaucoup plus que ceux des procédés bruyants de fonçage des pieux conventionnels. Ces nouvelles méthodes de construction décrites ci-dessus sont  using the method without noise and without vibration have been proposed. However, such a method of construction without noise and without conventional vibration has various stages and its costs increase much more than those of noisy methods of driving conventional piles. These new construction methods described above are

basées sur l'excavation du sol de sorte qu'il y a une possi-  based on the excavation of the soil so that there is a possibility

bilitê accrue de réduction de la force portante par suite  increased stability of load-bearing reduction

d'une désintégration et d'un ameublissement des sols.  disintegration and soil loosening.

La présente invention concerne un procédé pour enfoncer des pieux hélicoïdaux en béton précontraint par pénétration par torsion et des pieux hélicoïdaux en béton précontraint pour  The present invention relates to a method for driving helical piles of prestressed concrete by torsion penetration and helical piles made of prestressed concrete for

la mise en oeuvre du procédé. -the implementation of the method. -

Un des buts principaux de la présente invention est de four-  One of the main aims of the present invention is to provide

nir un nouveau procédé de construction dans lequel les incon-  a new construction process in which the incon-

vénients mentionnés ci-dessus sont éliminés.  The above mentioned exceptions are eliminated.

Un autre but de la présente invention est de fournir un pro-  Another object of the present invention is to provide a

cédé de construction sans bruit et sans vibration qui est économique et assure une force portante élevée du pieu et  yielding noise-free and vibration-free construction that is economical and provides high pile

avec lequel la construction des fondations peut être effec-  with which the construction of the foundations can be carried out

tuée plus simplement.killed more simply.

Un autre but encore de la présente invention est.de fournir  Yet another object of the present invention is to provide

un nouveau procédé de construction sans bruit et sans vibra-  a new construction process without noise and vibration

tion utilisant un procédé d'enfoncement d'un pieu hélicoïdal en béton précontraint par pénétration par torsion et un pieu hélicoïdal en béton précontraint pour la mise en oeuvre du procédé dans lequel le travail de base d'enfoncement du pieu peut être effectué en un seul stade en faisant pénétrer di- rectement le pieu en béton dans le sol sans évacuation de terre.  using a method of driving a torsion-penetrating prestressed concrete helical pile and a prestressed concrete helical pile for carrying out the method in which the basic driving work of the pile can be carried out in a single stadium by directly penetrating the concrete pile into the soil without drainage.

Selon une caractéristique de la présente invention, le pro-  According to a feature of the present invention, the

cédé de construction-par enfoncement d'un pieu hélicoïdal en  yielded by construction-by driving a helical pile into

béton précontraint par pénétration par torsion est caracté-  prestressed concrete by torsion penetration is

risé en ce qu'un pieu en béton avec un flasque hélicoïdal est engagé dans le sol en le faisant tourner par application d'un couple et sans évacuer la terre de sorte que le pieu en béton en lui-même peut avoir une force portante analogue à celle  in that a concrete pile with a helical flange is engaged in the ground by rotating it by applying torque and without discharging the earth so that the concrete pile itself may have a similar load-bearing capacity to her

d'un pieu à frottement ou d'un pieu porteur.  a friction pile or a bearing pile.

Selon une autre caractéristique de la présente invention, le pieu hélicoïdal en béton précontraint est caractérisé en ce que le pieu en béton avec une partie en forme de flasque hélicoïdal sur toute la longueur du pieu ou une partie de celui-ci est réalisé de manière à assurer un béton à très  According to another characteristic of the present invention, the prestressed concrete helical pile is characterized in that the concrete pile with a helical flange-shaped part over the entire length of the pile or a part thereof is made in such a way as to ensure a very concrete

haute résistance par mélange à celui-ci de fibres d'acier.  high strength by mixing with it steel fibers.

D'autres buts et avantages de la présente invention apparaî-  Other objects and advantages of the present invention appear

tront à la lecture de la description faite ci-après avec  will read the description given below with

référence aux dessins ci-annexés dans lesquels: La figure 1 est une vue en élévation d'une partie  reference to the accompanying drawings, in which: FIG. 1 is an elevational view of a portion

importante d'un pieu hélicoïdal en béton pré-  of a helical pile made of precast concrete

contraint-conforme à la présente invention; la  constraint-according to the present invention; the

figure 2 est une vue en élévation et coupe par-  FIG. 2 is an elevational and sectional view of

tielle d'une partie importante du pieu hélicoïdal en béton précontraint de figure 1, et la figure 3 est une vue en coupe de la partie formant flasque  of a substantial portion of the prestressed concrete helical pile of FIG. 1, and FIG. 3 is a sectional view of the flange portion

du pieu.of the stake.

Les figures 1 et 2 représentent un pieu hélicoïdal en béton précontraint conforme à la-présente invention dans lequel des barres d'acier 5, des barres de renfort 5a et des barres de renfort hélicoïdales 5b sont assemblées et sont placées dans un châssis pour formage par la force centrifuge (non repré- senté). Du béton à haute résistance 4 mélangé avec des fibres d'acier 3 est injecté dans le châssis et un pieu en béton a présentant un flasque hélicoïdal 1 est finalement obtenu par moulage par centrifugation. Le pieu en lui-même présentera une force portante analogue à celle d'un pieu à frottement ou d'un pieu porteur en lui assurant une rotation par un couple-et en le faisant pénétrer dans le sol sans  Figures 1 and 2 show a prestressed concrete helical pile according to the present invention in which steel bars 5, reinforcement bars 5a and helical reinforcement bars 5b are assembled and are placed in a frame for forming by centrifugal force (not shown). High strength concrete 4 mixed with steel fibers 3 is injected into the frame and a concrete pile 1 having a helical flange 1 is finally obtained by centrifugal molding. The pile itself will have a load-bearing force similar to that of a friction pile or a bearing pile by rotating it by a couple-and causing it to penetrate into the ground without

évacuer les terres. Dans-ce cas cependant il n'était pas pos-  evacuate the land. In this case, however, it was not possible

sible de réaliser sur un pieu en béton conventionnel un. -  sible to perform on a conventional concrete pile a. -

flasque présentant une capacité de pénétration suffisante en raison des fissures et des ruptures produites dans le béton conventionnel par une pénétration en porte-à-faux et une  flange having sufficient penetration capacity due to cracks and breaks produced in conventional concrete by cantilever penetration and

rencontre avec les rochers se trouvant dans le sol.  encounter with rocks in the ground.

Afin de remédier à ces problèmes, on a mis au point un béton' avec fibres d'acier qui est beaucoup plus renforcé que le béton conventionnel. Par exemple, un béton renforcé avec des fibres d'acier ayant un diamètre de 0, 3 à 0,5 mm et une longueur d'environ de 25 à 30 mm, les fibres d'acier 3 étant  In order to overcome these problems, a concrete with steel fibers has been developed which is much stronger than conventional concrete. For example, a concrete reinforced with steel fibers having a diameter of 0.3 to 0.5 mm and a length of about 25 to 30 mm, the steel fibers 3 being

mélangées uniformément dans le-béton, présente les caracté-  uniformly mixed in the concrete, presents the characteristics

ristiques suivantes qui n'ont jamais été constatées dans le  following features which have never been found in the

béton conventionnel.conventional concrete.

(a) Il a une rigidité suffisante et une caractéristique de résistance élevée;  (a) It has sufficient rigidity and a high strength characteristic;

(b) Il a une résistance à la traction élevée et une résistan-  (b) It has a high tensile strength and a resistance

ce à la flexion élevée; (c) Il est moins sujet à des fissures et ruptures dans ses parties d'extrémité et parties de coin; (d) Il a une caractéristique de résistance à la fatique élevée,et, (e) Il a une caractéristique de résistance à la chaleur et une  this at high flexion; (c) It is less subject to cracks and breaks in its end portions and corner portions; (d) It has a high fatigue resistance characteristic, and, (e) It has a heat resistance characteristic and a

résistance au froid et à la fusion élevées.  resistance to cold and high melting.

En utilisant un tel béton renforcé par des fibres d'acier, on peut réaliser une partie formant flasque 1 qui n'est pas sujette à des fissures et à des ruptures et qui présente une  By using such a concrete reinforced with steel fibers, it is possible to produce a flange portion 1 which is not subject to cracks and breaks and which has a

résistance suffisante. Selon l'éprouvette pour essai de com-  sufficient resistance. According to the test specimen

pression du béton qui est utilisée dans le pieu hélicoïdal en béton précontraint a de l'invention, la résistance normale après 28 jours était a28 = 750 kg/cm2 ou plus et elle avait été fabriquée à partir du mélange suivant: *(par mélange,on entend une substance qui protège le ciment,  the concrete pressure used in the prestressed concrete helical pile of the invention, the normal strength after 28 days was 28 = 750 kg / cm 2 or more and was made from the following mixture: we mean a substance that protects the cement,

qui accélère la prise et qui augmente les propriétés de résis-  which accelerates the setting and increases the resistance properties

tance du ciment à l'eau de mer ou aux solutions salines et  cement with seawater or saline solutions and

d'étanchéité telle que le pozzolane).  sealing such as pozzolan).

- La résistance à la compression à 28 jours du béton armé aux fibres d'acier présentant cette composition était a28 = 767 kg/cm2. Elle était presque égale à la résistance à la compression a28 = 753 kg/cm2 d'un béton sans mélange avec les fibres d'acier.2Toutefois la résistance à la traction était at = 83 kg/cm contre 59 kg/cm, ce qui correspond à Quantité de Dimension maximale Eau/ciment Aggrégat fibres de l'aggrégat(e/c) s/A) d'acier grossier (Vol. %) (mm) (%) (%)  The compressive strength at 28 days of steel fiber reinforced concrete having this composition was 287.7 kg / cm 2. It was almost equal to the compressive strength a28 = 753 kg / cm2 of unmixed concrete with steel fibers.2However the tensile strength was at = 83 kg / cm against 59 kg / cm, which corresponds to Quantity of Maximum Size Water / cement Aggregate aggregates (e / c) s / A fibers of coarse steel (Vol.%) (mm) (%) (%)

1,0 15 45,0 50,01.0 15 45.0 50.0

Q.uantité.unitaire (kg/m) Eau Ciment Aggrégat fin Aggrégat Fibres grossier d'acier  Q.unit.unit (kg / m) Water Cement Aggregate Fine Aggregate Coarse Steel Fiber

194 460 780 881 78194 460 780 881 78

Mélange * (Total 1000) Agent de réduction d'eau (fort)  Mixture * (Total 1000) Water Reducing Agent (Strong)

% 1,0%% 1.0%

(par rapport au poids de (par rapport au poids de ciment) ciment)  (relative to the weight of (relative to cement weight) cement)

--,. . _ ,.,,,.,._,,.......- ,. . _,. ,,,., ._ ,, .......

un accroissement de la résistance à la traction d'environ 1,4  an increase in tensile strength of about 1.4

fois dans le cas d'un mélange avec des fibres d'acier.  times in the case of a mixture with steel fibers.

De plus, pour comparer la résistance aux fissures et aux ruptures sous l'effet d'un choc ou d'un impact entre le béton armé de fibres d'acier conforme à la présente invention et le béton conventionnel ne contenant aucune fibre d'acier  In addition, to compare the resistance to cracks and fractures under the effect of impact or impact between the reinforced steel fiber concrete according to the present invention and the conventional concrete containing no steel fiber

en mélange, on a essayé et contrôlé la fréquence de produc-  In a mixture, the frequency of production was tested and

tion des fissures et le nombre de destructions en supportant  cracks and the number of destructions by supporting

simplement l'échantillon pour essai de flexion, avec une por-  simply the bending test sample, with a

tée de 45 cm, pendant 28 jours, et en faisant tomber de manière répétée une bille d'acier d'un poids de 7,5 kg au  45 cm, for 28 days, and repeatedly dropping a steel ball weighing 7.5 kg

milieu de la portée depuis une hauteur de 30 cm. Comme résul-  middle of the reach from a height of 30 cm. As a result

tat, les fissures se produisaient avec un nombre de chocs de l'ordre de trois dans le béton qui ne contenait pas de fibres d'acier et la destruction se produisait presque simultanément  tat, the cracks occurred with a number of shocks of the order of three in the concrete that did not contain steel fibers and the destruction occurred almost simultaneously

Par contre, dans le béton contenant des fibres d'acier, con-  On the other hand, in concrete containing steel fibers,

forme à la présente invention, des fissures se produisaient après 41 chocs et la destruction était obtenue à la 164ème  form of the present invention, cracks occurred after 41 shocks and the destruction was obtained at the 164th

fois.time.

Cependant, il s'est avéré qu'avec un flasque 1 de -dimension appropriée pour assurer une pénétration suffisante, le pieu hélicoïdal présente une résistance suffisante contre les fissures et les ruptures lorsqu'il rencontre des pierres dans le sol ou lorsqu'une pénétration non appropriée de celui-ci est effectuée. Dans le pieu hélicoïdal en béton précontraint a conforme à la présente invention, une résistance très  However, it has been found that with a flange 1 of appropriate size to ensure sufficient penetration, the helical pile has sufficient resistance against cracks and breaks when it encounters stones in the ground or when a penetration inappropriate of this one is performed. In the prestressed concrete helical pile according to the present invention, a very high strength

élevée du béton renforcé aux fibres-d'acier avec la résistan-  Steel Reinforced Concrete reinforced with the strength of

ce normalisée à 28 jours de a28 750 kg/cm2 ou plus a été  this normalized to 28 days of a28 750 kg / cm2 or more was

constatée pour l'échantillon-d'essai de compression standard.  found for the standard compression test sample.

De plus, du fait que le pieu hélicoïdal en béton précontraint a est moulé en utilisant la force centrifuge, la résistance du pieu est augmentée d'environ 20% par un processus de compactage et de déshydratation. Dans ce béton à résistance élevée, la résistance à la traction augmente naturellement, ce qui produit une résistance à la traction égale au 1/5ème de la résistance à la compression. De plus, la résistance à la traction est augmentée de 1,5 fois par l'armement aux  In addition, because the prestressed concrete helical pile is molded using centrifugal force, the pile strength is increased by about 20% by a compaction and dewatering process. In this high strength concrete, the tensile strength increases naturally, resulting in tensile strength equal to 1 / 5th of the compressive strength. In addition, the tensile strength is increased by 1.5 times

fibres d'acier.steel fibers.

Lorsqu'on exerce un couple sur le pieu, une force de cisail- lement est produite dans la section du pieu et la contrainte de cisaillement la plus importante se produit à la périphérie du pieu. L'état dans lequel la contrainte de cisaillement est exercée sur la surface externe du pieu par le couple, se  When torque is applied to the pile, a shearing force is produced in the pile section and the largest shear stress occurs at the periphery of the pile. The state in which the shear stress is exerted on the external surface of the pile by the couple,

produit dans ce cas.produced in this case.

En supposant que la contrainte de cisaillement est X, les contraintes principales a1 et a2 deviennent: - -a2 T La direction de la contrainte principale a, par rapport à l'axe du pieu devient tang 2= =450 et la contrainte de traction de a1 T est produite dans la direction faisant un angle de 45 avec l'axe du pieu et à son tour une contrainte de compression a2 -T est produite  Assuming that the shear stress is X, the principal stresses a1 and a2 become: - -a2 T The direction of the main stress, with respect to the axis of the pile becomes tang 2 = = 450 and the tensile stress of a1 T is produced in the direction making an angle of 45 with the axis of the pile and in turn a compressive stress a2 -T is produced

perpendiculairement à la contrainte de traction.  perpendicular to the tensile stress.

Lorsque la contrainte a1 atteint la contrainte de traction a  When the stress a1 reaches the tensile stress a

du béton, des fissures se produisent dans la direction per-  concrete, cracks occur in the direction of

pendiculaire à la contrainte de traction. A savoir la con-  pendicular to the tensile stress. To know the

trainte de cisaillement, au moment de l'apparition des fis-  shear train, at the moment of appearance of

sures est la suivante * = ci Donc la contrainte de cisaillement qui produit des fissures devient T = at Ensuite, lorsqu'on introduit une précontrainte correspondant à une force de compression ao dans le pieu, la condition de la contrainte sur la surface périphérique du pieu devient une  sures is the following * = ci So the shear stress that produces cracks becomes T = at Then, when we introduce a preload corresponding to a compressive force ao in the pile, the condition of the stress on the peripheral surface of the pile becomes a

combinaison de la contrainte de compression ao dans la direc-  combination of the compression constraint ao in the direc-

tîon de l'axe du pieu et de la contrainte de cisaillement T qui se produit en même temps. Dans ce cas, les contraintes principales a1 et a2 deviennent al C =__+ / O V2 + 2 Cr ao2 T Cr Cr (aO)2 +2 La direction de la contrainte principale al par rapport à l'axe du pieu devient tang 22 = _ 2 + T a0 La contrainte de traction a1 est produite dans une direction  the axis of the pile and the shear stress T which occurs at the same time. In this case, the main constraints a1 and a2 become al C = __ + / O V2 + 2 Cr ao2 T Cr Cr (aO) 2 +2 The direction of the principal stress al with respect to the axis of the pile becomes tangent 22 = _ 2 + T a0 The tensile stress a1 is produced in one direction

d'angle 4 par rapport à l'axe du pieu, tandis que la con-  angle 4 with respect to the axis of the pile, while the

trainte de compression a2 se produit dans une direction per-  compressive train a2 occurs in a direction perm

pendiculaire à celle-ci.pendicular to it.

Lorsque la contrainte principale a atteint la résistance à la traction at du béton, des fissures-se produiront. De ce  When the main stress has reached tensile strength and concrete, cracks will occur. From this

fait la contrainte de cisaillement Tcr qui produit des fissu-  makes the shear stress Tcr which produces cracking

res devient Tcr t(at+ a0) et la direction des fissures par rapport à l'axe du pieu devient A -ttang- F at (% + a0) Dans le béton présentant une résistance normalisée a28 750 kg/cm. après 28 jours qui est utilisé pour le pieu en béton précontraint a conforme à la présente invention, la  res becomes Tcr t (at + a0) and the direction of the cracks with respect to the pile axis becomes A-tan-F at (% + a0) In the concrete having a standardized strength a28 750 kg / cm. after 28 days which is used for the prestressed concrete pile according to the present invention, the

résistance de compression se trouve accrue de 20% et a.  compressive strength is increased by 20% and a.

devient environ 900 kg/cm suite au moulage par centrifuga-  becomes about 900 kg / cm after centrifugally

tion.tion.

La résistance à la traction est environ 1/15ème de la résis-  The tensile strength is about 1 / 15th of the resistance

tance à la compression; a 60 kg/cm. Une résistance à la traction de at 78 kg/cm qui est 1,3 fois plus importante que les résistances conventionnelles peut être obtenue par renforcement en utilisant des fibres d'acier. Dans ce cas, la résistance au cisaillement au moment de l'apparition des fissures devient T-r = aC = 78 kg/cm2 sous la condition que la précontrainte ne soit pas introduite. Cependant lorsqu'une précontrainte de 100 kg/cm2 est introduite, la contrainte de cisaillement devient Tcr = 118 kg/cm2 avec a. = 100 kg/cm2 et la direction des fissures devient c' - 250 par rapport à l'axe du pieu. De plus lorsqu'on introduit une précontrainte de 200 kg/cm, la contrainte de cisaillement devient  compressive strength; at 60 kg / cm. A tensile strength of at 78 kg / cm which is 1.3 times greater than conventional strengths can be obtained by reinforcement using steel fibers. In this case, the shear strength at the time of crack formation becomes T-r = aC = 78 kg / cm 2 provided that the prestressing is not introduced. However, when a prestress of 100 kg / cm 2 is introduced, the shear stress becomes Tcr = 118 kg / cm 2 with a. = 100 kg / cm2 and the direction of the cracks becomes c '- 250 with respect to the axis of the pile. In addition, when a prestress of 200 kg / cm is introduced, the shear stress becomes

TCr = 147 kg/cm2 et la direction des fissures devient j' 18 .  TCr = 147 kg / cm 2 and the crack direction becomes 18.

Cr 2 A savoir, lorsqu'une précontrainte de 100 kg/cm est introduite dans le pieu, le couple qui produit des fissures est environ  Cr 2 Namely, when a prestress of 100 kg / cm is introduced into the pile, the couple that produces cracks is about

1,5 fois plus élevé que celui lorsqu'il n'y a pas introduc-  1.5 times higher than when there is no introduction

tion de précontrainte dans le pieu et il est environ 1,9 fois  prestressing in the pile and it is about 1.9 times

plus élevé pour une précontrainte de 200 kg/cm2.  higher for prestressing of 200 kg / cm2.

De plus, la direction des fissures est à À' = 450 par rap-  In addition, the direction of the cracks is at A = 450 with respect to

port à l'axe du pieu lorsqu'une précontrainte n'est pas in-  port to the pile axis when prestressing is not in-

troduite tandis que cette direction s'incline dans la direc-  while this direction is inclined in the direc-

tion du pieu par l'introduction de la précontrainte et l'an-  tion of the pile by introducing prestressing and

gle des fissures devient petit. En conséquence, plus la force de la précontrainte croit plus le couple qui produit  The cracks become small. As a result, the more the prestressing force increases, the more torque that produces

des fissures augmente et ainsi l'angle formé par les fissu-  cracks increase and so the angle formed by the cracks

res avec l'axe du pieu peut être rendu petit. On notera en conséquence que dans un pieu hélicoïdal en béton précontraint qui est engagé dans le sol par rotation sous l'action d'un couple, le béton à résistance élevée avec une précontrainte  res with the axis of the pile can be made small. It should be noted therefore that in a prestressed concrete helical pile which is engaged in the ground by rotation under the action of a couple, the high-strength concrete with a prestressing

élevée est plus avantageux que les bétons conventionnels.  high is more advantageous than conventional concretes.

Lorsque les barres de renfort hélicoïdales 5b sont disposées sensiblement perpendiculairement à la direction des fissures, le couple qui produit l'apparition de fissures peut être augmenté. Le Tableau suivant présente le résultat d'un essai de torsion sur un pieu en béton précontraint conventionnel avec un diamètre de 300 mm et une épaisseur de 60 mm et un pieu hélicoïdal en béton précontraint a avec une longueur de  When the helical reinforcing bars 5b are disposed substantially perpendicular to the direction of the cracks, the couple which produces the appearance of cracks can be increased. The following table presents the result of a torsion test on a conventional prestressed concrete pile with a diameter of 300 mm and a thickness of 60 mm and a prestressed concrete helical pile with a length of

1,2 m.1.2 m.

Si un. pieu en béton a sensiblement le même moment de torsion qu'un pieu qui peut être obtenu avec un béton renforcé aux fibres d'acier, la pénétration des pieux en béton par torsion dans le sol nécessaire pour établir la fondation du pieu  If a. Concrete pile has substantially the same torsional moment as a pile that can be obtained with steel fiber reinforced concrete, the penetration of concrete piles by torsion into the ground necessary to establish the foundation of the pile

deviendra suffisante en prenant en considération un coeffi-  will become sufficient by taking into account a coeffi-

cient de sécurité.security.

Le pieu hélicoïdal en béton précontraint conforme à la pré-  The prestressed concrete helical pile conforms to

sente invention peut être enfoncé dans le sol en le faisant tourner sous l'effet d'un couple sans évacuer les terres de  This invention can be driven into the ground by rotating it under the effect of a couple without evacuating the lands of

sorte qu'une désagrégation et un ameublissement du sol peu-  so that disintegration and loosening of the soil can

vent être évités contrairement aux autres procédés de cons-  can be avoided, unlike other

Types de béton Précontrainte Moment de torsion Remarques (kg/cm 2 produisant des fissures (tonne-M) Béton à haute 47,0 3,19 Moyenne pou résistance quatre pieu ,0 4,08 Moyenne pou deux pieux ,0 4,23 Moyenne pou -deux pieux Béton avec 100,0 4,82 Moyenne pour fibres d'acier trois pieux ,0 5,58 Moyenne pou trois pieux il  Types of concrete Prestressing Moment of torsion Remarks (kg / cm 2 producing cracks (ton-M) High concrete 47.0 3.19 Medium for resistance four piles, 0 4.08 Medium for two piles, 0 4.23 Medium for two piles Concrete with 100.0 4.82 Average for steel fibers three piles, 0 5.58 Medium for three piles

truction sans bruit et sans vibration. De plus une force por-  truction without noise and without vibration. In addition, a force

tante importante peut être obtenue du fait que le sol sera fortement consolidé et que le flasque est solidaire du pieu lui-même et que de même le frottement entre le béton et les fondations peut être beaucoup augmenté. De plus il est aussi possible d'améliorer un sol mou en faisant pénétrer un pieu hélicoïdal en béton précontraint a  An important aunt can be obtained because the soil will be strongly consolidated and the flange is integral with the pile itself and that the friction between the concrete and the foundations can be greatly increased. In addition, it is also possible to improve soft ground by penetrating a helical pile made of prestressed concrete.

dans un sol mou sans produire de bruit et de vibration.  in soft ground without producing noise and vibration.

Le pieu hélicoïdal en béton précontraint conforme à la pré-  The prestressed concrete helical pile conforms to

sente invention est plus économique que le pieu en béton pré-  This invention is more economical than the pre-formed concrete pile.

contraint conventionnel pour le procédé de fonçage par batta-  conventional constraint for the battling sinking process.

ge et une force portante plus importante peut être obtenue, garantissant ainsi une meilleure sécurité des constructions  ge and a higher load-bearing capacity can be obtained, thus guaranteeing better

tout en assurant les autres effets industriel du battage.  while ensuring the other industrial effects of threshing.

Un pieu hélicoïdal en béton précontraint conforme à la pré-  A prestressed concrete helical pile in accordance with

sente invention est de préférence fabriqué sous les condi-  This invention is preferably manufactured under the conditions

tions suivantes: Quantité de fibres d'acier: -0,6 à 1,2% en volume Dimension maximale de l'agrégat grossier: 13 à 20 mm Rapport eau/béton 30 à 45% Taux de l'agrégat fin, s/A: 45 à 55% Dosage du ciment: 460 à 500 kg/m3 Taux du mélange par rapport au poids du ciment 7 à 12% Taux de l'agent de réduction d'eau par rapport au poids du  following: Quantity of steel fibers: -0.6 to 1.2% by volume Maximum size of the coarse aggregate: 13 to 20 mm Water to concrete ratio 30 to 45% Fine aggregate rate, s / A: 45 to 55% Determination of cement content: 460 to 500 kg / m3 Mixture ratio to cement weight 7 to 12% Rate of water reducing agent in relation to the weight of the cement

ciment: 1,0 à 1,4%.cement: 1.0 to 1.4%.

Claims (3)

Revendicationsclaims 1. Un procédé pour enfoncer des pieux hélicoïdaux en béton précontraint par pénétration par torsion caractérisé en ce qu'on munit un pieu en béton d'un flasque hélicoïdal, on fait pénétrer ledit pieu en béton dans le sol en le faisant tourner avec un certain couple sans évacuer les terres et on confère une force portante audit pieu en béton de sorte que le pieu en béton en lui-même présente une force portante telle que celle des pieux à frottement ou des pieux porteurs.  1. A method for driving concrete helical piles prestressed by torsional penetration characterized in that a concrete pile is provided with a helical flange, said concrete pile is penetrated into the ground by rotating it with a certain amount of torque without discharging the lands and imparting a bearing force to said concrete pile so that the concrete pile itself has a load-bearing force such as that of friction piles or bearing piles. 2. Un pieu hélicoïdal en béton précontraint pour pénétration par torsion dans lequel la partie à flasque hélicoïdal est prévue sur la surface du pieu sur une partie ou la totalité de la longueur du pieu et des fibres d'acier sont mélangés dans le pieu en béton de manière à mouler un pieu en béton2. A torsion-penetrated concrete helical pile in which the helical flange portion is provided on the pile surface over part or all of the length of the pile and steel fibers are mixed into the concrete pile. in order to mold a concrete pile présentant une résistance élevée.  having a high resistance. 3. Un pieu hélicoïdal en béton précontraint selon la reven-  3. A prestressed concrete helical pile according to the dication 2, caractérisé en ce qu'il présente: une teneur en fibres d'acier de 0,6 à 1,2% en volume une dimension maximale de l'agrégat grossier de 13 à 20 mm un rapport eau/ciment de 30 à 45% un rapport d'agrégat fin s/A de 45 à 55% un dosage en ciment de 460 à 500 kg/m3 un taux de mélange par rapport au poids du.ciment de 7 à 12% un taux d'agent de réduction d'eau par rapport au poids du  2, characterized in that it has: a steel fiber content of 0.6 to 1.2% by volume a maximum size of the coarse aggregate of 13 to 20 mm a water / cement ratio of 30 to 45% a finite aggregate ratio s / A from 45 to 55% a cement dosage of 460 to 500 kg / m3 a mixing ratio based on the weight of the cement from 7 to 12% a reduction agent level of water relative to the weight of ciment de 1,0 à 1,4%.cement from 1.0 to 1.4%.
FR8009960A 1979-10-31 1980-05-05 METHOD FOR PRESSING PRECONTRATED CONCRETE HELICOIDAL CONCRETE PILES BY TORSION PENETRATION AND PRECONTRATED CONCRETE HELICOID PILES FOR CARRYING OUT THE PROCESS Withdrawn FR2468696A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP54140585A JPS5854211B2 (en) 1979-10-31 1979-10-31 Torsion penetrating type PC spiral pile

Publications (1)

Publication Number Publication Date
FR2468696A1 true FR2468696A1 (en) 1981-05-08

Family

ID=15272105

Family Applications (1)

Application Number Title Priority Date Filing Date
FR8009960A Withdrawn FR2468696A1 (en) 1979-10-31 1980-05-05 METHOD FOR PRESSING PRECONTRATED CONCRETE HELICOIDAL CONCRETE PILES BY TORSION PENETRATION AND PRECONTRATED CONCRETE HELICOID PILES FOR CARRYING OUT THE PROCESS

Country Status (6)

Country Link
JP (1) JPS5854211B2 (en)
DE (2) DE8029098U1 (en)
FR (1) FR2468696A1 (en)
GB (1) GB2062073B (en)
IT (1) IT1127376B (en)
NL (1) NL8002777A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1985765A1 (en) 2007-04-25 2008-10-29 Jean-Marie Renovation Device and method for installing a helical foundation micro-pile

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58185627U (en) * 1982-06-07 1983-12-09 丹羽 友道 Screw-in PC concrete pile
NL8301556A (en) * 1983-05-03 1984-12-03 Pieter Faber CONCRETE FOUNDATION POLE, APPARATUS FOR MANUFACTURING AND APPARATUS FOR GROUNDING THEREOF.
DE3521627A1 (en) * 1985-06-15 1986-12-18 Strabag Bau-AG, 5000 Köln Method of producing an inclined composite grouted pile
DE3617025A1 (en) * 1986-05-21 1987-11-26 Delmag Maschinenfabrik PRE-PREPARED CONCRETE PILE AND METHOD AND DEVICE FOR ITS PLACING INTO THE GROUND
GB8816849D0 (en) * 1988-07-15 1988-08-17 Helix Reinforcements Ltd Improvements relating to earth reinforcement
DE3827703A1 (en) * 1988-08-16 1990-02-22 Bilfinger Berger Bau Supporting elements for forming foundation bodies
DE4020757C2 (en) * 1990-06-29 1996-08-01 Pfleiderer Verkehrstechnik Reinforced concrete foundation pile and process for its manufacture
DE19743415A1 (en) * 1997-10-01 1999-06-10 Josef Dipl Ing Behrens Self boring concrete pile
NL1007476C2 (en) * 1997-11-07 1999-05-10 Peter Cornelis Peters Method for manufacturing a reinforced elongated longitudinal load-bearing concrete product, and a pile.
GB2362672A (en) * 2000-05-22 2001-11-28 Laing Rail Ltd Conical foundation pile having a screw thread for urging the pile into the ground

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE255282C (en) *
GB252975A (en) * 1925-10-23 1926-06-10 Alexander George Rotinoff Improvements relating to reinforced concrete
DE1634356A1 (en) * 1966-09-23 1970-06-18 Feidner Dipl Ing Erich Pile foundations for buildings as well as methods and tools for their production
FR2145293A5 (en) * 1971-07-06 1973-02-16 Battelle Development Corp
FR2369388A1 (en) * 1976-11-02 1978-05-26 Gillen William F Prefabricated reinforced concrete screw threaded pile - has spiral thread of small pitch, metal top and reinforced core

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE255282C (en) *
GB252975A (en) * 1925-10-23 1926-06-10 Alexander George Rotinoff Improvements relating to reinforced concrete
DE1634356A1 (en) * 1966-09-23 1970-06-18 Feidner Dipl Ing Erich Pile foundations for buildings as well as methods and tools for their production
FR2145293A5 (en) * 1971-07-06 1973-02-16 Battelle Development Corp
FR2369388A1 (en) * 1976-11-02 1978-05-26 Gillen William F Prefabricated reinforced concrete screw threaded pile - has spiral thread of small pitch, metal top and reinforced core

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1985765A1 (en) 2007-04-25 2008-10-29 Jean-Marie Renovation Device and method for installing a helical foundation micro-pile

Also Published As

Publication number Publication date
IT8048051A0 (en) 1980-02-29
NL8002777A (en) 1981-06-01
GB2062073B (en) 1983-03-16
JPS5719417A (en) 1982-02-01
DE8029098U1 (en) 1981-11-26
JPS5854211B2 (en) 1983-12-03
DE3041125A1 (en) 1981-05-14
GB2062073A (en) 1981-05-20
IT1127376B (en) 1986-05-21

Similar Documents

Publication Publication Date Title
FR2468696A1 (en) METHOD FOR PRESSING PRECONTRATED CONCRETE HELICOIDAL CONCRETE PILES BY TORSION PENETRATION AND PRECONTRATED CONCRETE HELICOID PILES FOR CARRYING OUT THE PROCESS
CN106431132A (en) High-ductility fiber concrete and construction method for reinforcing beam by using high-ductility fiber concrete
FR2502166A1 (en) COMPOSITION BASED ON CEMENT, BENTONITE AND WATER, FOR CONSOLIDATING A LOW CONSISTENCY SOIL AND METHOD FOR CONSOLIDATING SUCH SOIL BY IMPLEMENTING SAID COMPOSITION
JP5861985B2 (en) Seismic reinforcement method and repair method for reinforced concrete members
Holschemacher et al. Bond of reinforcement in ultra high strength concrete
CN102337742B (en) Prestressed composite superimposed large-diameter tube pile and manufacturing method thereof
Kennedy et al. Effect of corrosion on bond between steel and concrete of corroded and inhibitive reinforcement embedded in reinforced concrete structures in accelerated corrosive medium
EP1694611B1 (en) Metal fiber concrete
EP0887486A1 (en) Reinforced concrete composition with metal strips, method and building elements made thereof
EP1278925B1 (en) Compacted rolled fibre-reinforced concrete composition and method for producing a pavement based on same
Li et al. Experimental investigation of cement mixing to improve Champlain Sea clay
Ng Tensile behavior of fiber reinforced cemented soil: A short review
Weiße et al. Some aspects about the bond of reinforcement in ultra high strength concrete
SU1377331A1 (en) Method of constructing cast-in-place pile
EP0440523B1 (en) Mortar for the fabrication of pressure resistant pipes, pipe made from this mortar and process for its fabrication
CN206681149U (en) A kind of aluminium alloy compound concrete filled steel tubular member
Chen Test research on mechanical property of cemented soil strengthened with basalt fiber
Khabbaz et al. Chemical stabilisation of closed landfill sites using chemical agents
Plé et al. A mechanical approach for fibre-reinforced clay in landfill caps cover application
EP1780184A1 (en) In situ method for reinforcing a construction element and reinforced construction element
FR3076562A1 (en) PIEU IN BFUP - COMPOSITE PIEU
FR2558862A1 (en) Process for the treatment of soil by the use of a mortar obtained by the crushing and/or disintegration of the extracted materials with the addition of water and of a binder
Farzana et al. Engineering behaviour of cement treated soft clay at high water content
RU2788693C1 (en) Screw pile
FR2941451A1 (en) Fresh concrete composition, useful to produce slabs or inclined walls, comprises cement (Portland cement), sand, gravel and/or grit (crushed material of class A), water and small fibers (polypropylene fibers)

Legal Events

Date Code Title Description
ST Notification of lapse