ES2160276T3 - Procedimiento y sistema para la optimizacion y administracion del consumo de energia electrica en plantas industriales. - Google Patents

Procedimiento y sistema para la optimizacion y administracion del consumo de energia electrica en plantas industriales.

Info

Publication number
ES2160276T3
ES2160276T3 ES97105779T ES97105779T ES2160276T3 ES 2160276 T3 ES2160276 T3 ES 2160276T3 ES 97105779 T ES97105779 T ES 97105779T ES 97105779 T ES97105779 T ES 97105779T ES 2160276 T3 ES2160276 T3 ES 2160276T3
Authority
ES
Spain
Prior art keywords
electrical energy
optimization
administration
procedure
energy consumption
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
ES97105779T
Other languages
English (en)
Inventor
Manfred Dipl-Ing Weiss
Gerhart Dipl-Ing Becke
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens AG
Original Assignee
Siemens AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens AG filed Critical Siemens AG
Application granted granted Critical
Publication of ES2160276T3 publication Critical patent/ES2160276T3/es
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J1/00Circuit arrangements for dc mains or dc distribution networks
    • H02J1/14Balancing the load in a network
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00002Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by monitoring
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/26Pc applications
    • G05B2219/2639Energy management, use maximum of cheap power, keep peak load low
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32021Energy management, balance and limit power to tools
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/10Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/10Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/30State monitoring, e.g. fault, temperature monitoring, insulator monitoring, corona discharge

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Compounds Of Unknown Constitution (AREA)
  • Inorganic Compounds Of Heavy Metals (AREA)
  • General Factory Administration (AREA)
  • Control Of Electric Motors In General (AREA)
  • Crystals, And After-Treatments Of Crystals (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

EL PROCEDER HABITUAL PARA LAS NECESIDADES DE ENERGIA EN UN PROCESO DE PRODUCCION ES MEDIR UNA POTENCIA DE REFERENCIA GLOBAL EN ENERGIA POR UNIDAD DE TIEMPO POR UN LADO Y POTENCIAS DE REFERENCIA ESPECIFICAS DE CONSUMIDORES POR OTRO LADO, Y A PARTIR DE AHI DETERMINAR LA CONEXION Y/O DESCONEXION DE LOS DISTINTOS CONSUMIDORES DURANTE EL PROCESO DE PRODUCCION. LA INVENCION PROPONE EL ANALISIS DESCENTRALIZADO DE LA POTENCIA DE REFERENCIA CORRESPONDIENTE Y A LA VISTA DE LOS CALCULOS DESCENTRALIZADOS SELECCIONAR INMEDIATAMENTE LOS CONSUMIDORES QUE PUEDEN CONECTARSE O DESCONECTARSE EN RELACION TECNICA Y RACIONAL CON LA EJECUCION DEL PROCESO. EL SISTEMA PROPUESTO TIENE UNA ESTRUCTURA DESCENTRALIZADA, MODULAR Y ABIERTA CON AL MENOS UN CONTROL NORMALIZADO PROGRAMABLE EN MEMORIA (SPS) Y UN ORDENADOR PERSONAL CORRIENTE DEL MERCADO (PC).
ES97105779T 1996-04-22 1997-04-08 Procedimiento y sistema para la optimizacion y administracion del consumo de energia electrica en plantas industriales. Expired - Lifetime ES2160276T3 (es)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19615959A DE19615959C1 (de) 1996-04-22 1996-04-22 Verfahren und System zur Optimierung und zum Management des Verbrauches an elektrischer Energie in Industriebetrieben

Publications (1)

Publication Number Publication Date
ES2160276T3 true ES2160276T3 (es) 2001-11-01

Family

ID=7792055

Family Applications (1)

Application Number Title Priority Date Filing Date
ES97105779T Expired - Lifetime ES2160276T3 (es) 1996-04-22 1997-04-08 Procedimiento y sistema para la optimizacion y administracion del consumo de energia electrica en plantas industriales.

Country Status (7)

Country Link
EP (1) EP0803956B1 (es)
AT (1) ATE202660T1 (es)
DE (2) DE19615959C1 (es)
DK (1) DK0803956T3 (es)
ES (1) ES2160276T3 (es)
GR (1) GR3036652T3 (es)
PT (1) PT803956E (es)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19827345B4 (de) * 1998-06-19 2005-04-14 Fünfgeld, Christian, Dipl.-Ing. Verfahren zur Ableitung der Wirkleistung elektrischer Verbraucher
DE29812097U1 (de) 1998-07-08 1998-11-05 Funk-Electronic Froitzheim Industrieelektronik GmbH, 51149 Köln Meß-, Steuer- und Regelsystem
DE10009325A1 (de) * 2000-02-22 2001-08-23 Deutsche Telekom Ag Verfahren zur Überwachung der Leistungsbilanz in einem Energieversorgungsnetz und hierfür geeignetes Überwachungssystem
DE10014431C2 (de) * 2000-03-16 2002-05-08 Frako Kondensatoren Und Anlage Verfahren zur Einhaltung eines oberen Grenzwertes der mittleren Gesamtleistung von n räumlich getrennten Gruppen von Verbrauchern
DE10019130A1 (de) * 2000-04-18 2001-10-31 Franz Schreier Verfahren zum Erfassen und Abgleichen des Verbraucherstrombedarfs
US6686831B2 (en) * 2001-01-23 2004-02-03 Invensys Systems, Inc. Variable power control for process control instruments
DE10334397A1 (de) 2003-07-28 2005-03-10 Siemens Ag Verfahren zur Reduzierung der Energiekosten in einem industriell geführten Betrieb
DE102005050044A1 (de) * 2005-10-19 2007-05-03 Moeller Gmbh Vorrichtung zur Strombegrenzung
DE102007062287A1 (de) 2007-12-21 2009-06-25 Manroland Ag Verfahren zum Herstellen eines Druckprodukts
DE102007063513B4 (de) 2007-12-27 2017-07-27 Convia Gmbh Produktionsenergiedatenerfassungs- und -analysesystem
ATE518172T1 (de) 2008-11-28 2011-08-15 Siemens Ag Steuerungskomponente und verfahren für ein energiemanagement einer industriellen automatisierungsanordnung
DE202011005048U1 (de) * 2011-04-08 2011-10-11 Rudolf Baier Elektrische Energieverteilungsvorrichtung für ein Gebäude
DE102011106114A1 (de) * 2011-06-09 2012-12-13 Mvv Energie Ag Verfahren zur Verteilung von elektrischer Energie in einem Stromnetzwerk mit einer Vielzahl von Verteilungszellen
DE102012211657A1 (de) 2012-07-04 2014-01-09 Robert Bosch Gmbh Verfahren und Steuervorrichtung zur pulsweitenmodulierten Ansteuerung einer Vielzahl von Verbrauchern
WO2014029420A1 (de) 2012-08-21 2014-02-27 Siemens Aktiengesellschaft Verfahren zum begrenzen der elektrischen energieaufnahme

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4324987A (en) * 1978-05-26 1982-04-13 Cyborex Laboratories, Inc. System and method for optimizing shed/restore operations for electrical loads
US4264960A (en) * 1979-07-02 1981-04-28 Sangamo Weston, Inc. System for controlling power distribution to customer loads
US4620283A (en) * 1983-11-29 1986-10-28 Lehigh University Programmable load controller
DE3426542A1 (de) * 1984-07-16 1986-01-16 Heliowatt Werke Elektrizitäts- Gesellschaft mbH, 1000 Berlin Einrichtung zur lastbegrenzung in niederspannungsnetzen
US5414640A (en) * 1991-07-05 1995-05-09 Johnson Service Company Method and apparatus for adaptive demand limiting electric consumption through load shedding
IT1268536B1 (it) * 1993-12-23 1997-03-04 Zeltron Spa Dispositivo perfezionato per la gestione energetica di carichi elettrici
DE4434553A1 (de) * 1994-09-28 1996-04-04 Wolfgang Schenk Felddaten-Digitalwandler
DE19502786C2 (de) * 1995-01-28 1997-02-20 Daimler Benz Ag Schaltungsanordnung und Verfahren zur gezielten Spannungsversorgung von an einem Versorgungsnetz angeschlossenen elektrischen Geräten

Also Published As

Publication number Publication date
DE19615959C1 (de) 1997-10-16
GR3036652T3 (en) 2001-12-31
DE59703887D1 (de) 2001-08-02
ATE202660T1 (de) 2001-07-15
EP0803956A3 (de) 1999-01-27
EP0803956A2 (de) 1997-10-29
DK0803956T3 (da) 2001-10-22
EP0803956B1 (de) 2001-06-27
PT803956E (pt) 2001-12-28

Similar Documents

Publication Publication Date Title
ES2160276T3 (es) Procedimiento y sistema para la optimizacion y administracion del consumo de energia electrica en plantas industriales.
ITTO920865A0 (it) Metodo per il miglioramento della gestione delle reti di distribuzionein particolare di gas, acqua, energia elettrica, calore.
BRPI0606994A2 (pt) processo para otimização do funcionamento de vários agregados compressores e correspondente dispositivo
DE502005008428D1 (de) Verfahren und anordnung zum energiesparenden betrieb von spülmaschinen
NO20011642L (no) Fremgangsmåte og apparat for å motta en universell inngangsspenning i en kraftkilde for sveising, plasma elleroppvarming vil v¶re åpenbare for fagfolk i teknikken
EP1499165A3 (en) Load driving device and portable apparatus utilizing such driving device
BRPI0502862B8 (pt) sistema de alimentação de uma rede de tração e subestação de alimentação elétrica
FI20011221A0 (fi) Valinnaisella lähtöjännitteellä toimiva älykäs virranjakelujärjestelmä
WO2006074213A3 (en) Output current and input power regulation with a power converter
TW200511684A (en) Configuration for N consumers of electric energy, of which M consumers are simultaneously supplied with energy
FI101413B (fi) Jätelämmön hyödyntämismenetelmä esim. voimalaitoksissa
SI1527656T1 (sl) Indukcijsko kuhalno polje z grelnimi conami s strukturo, ki jo je moc na novo konfigurirati, in postopek za povecanje maksimalne moci teh grelnih con
DE50110991D1 (de) Verfahren und System zur Steuerung der Energieversorgung von elektrischen Verbrauchern
WO2005067463A3 (en) Power distribution web node and power management process
DK0893941T3 (da) Fremgangsmåde og anlæg til drift og overvågning af diskontinuerligt drevne elektriske forbrugere via disses forsyningsledninger
ES1050814Y (es) Seguidor solar para central electrica fotovoltaica
GB0303820D0 (en) Method and program product for evaluating a circuit
SE9801950D0 (sv) Method and arrangement for choosing supply voltage
SG10201609493PA (en) System and method for operating a mains power grid
EP1766764A4 (en) METHOD FOR SWITCHING LOW POWER USING AC AND SYSTEM FOR ITS IMPLEMENTATION AND POWER SUPPLY TO USE THE SYSTEM
DE60026957D1 (de) Krafterzeugungsverfahren mit hohem Wirkungsgrad
DE50301403D1 (de) Vorrichtung zur Spannungserhaltung eines elektrischen Wechselspannungsnetzes sowie Verfahren zum Betrieb einer solchen Vorrichtung
DE60330881D1 (de) Spannungsversorgung mit zwei schaltnetzteileinheiten
CN103344860A (zh) 一种节能型老化测试台
CN107800386A (zh) 一种基于lna的光伏蓄电池智能检测及显示***

Legal Events

Date Code Title Description
FG2A Definitive protection

Ref document number: 803956