EP2322770A1 - Valve open/close timing controller - Google Patents

Valve open/close timing controller Download PDF

Info

Publication number
EP2322770A1
EP2322770A1 EP10755783A EP10755783A EP2322770A1 EP 2322770 A1 EP2322770 A1 EP 2322770A1 EP 10755783 A EP10755783 A EP 10755783A EP 10755783 A EP10755783 A EP 10755783A EP 2322770 A1 EP2322770 A1 EP 2322770A1
Authority
EP
European Patent Office
Prior art keywords
fluid
switching valve
passageway
valve
feeding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP10755783A
Other languages
German (de)
French (fr)
Other versions
EP2322770B1 (en
EP2322770A4 (en
Inventor
Masaaki Kaneko
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Aisin Corp
Original Assignee
Aisin Seiki Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Aisin Seiki Co Ltd filed Critical Aisin Seiki Co Ltd
Publication of EP2322770A1 publication Critical patent/EP2322770A1/en
Publication of EP2322770A4 publication Critical patent/EP2322770A4/en
Application granted granted Critical
Publication of EP2322770B1 publication Critical patent/EP2322770B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01LCYCLICALLY OPERATING VALVES FOR MACHINES OR ENGINES
    • F01L1/00Valve-gear or valve arrangements, e.g. lift-valve gear
    • F01L1/34Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift
    • F01L1/344Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear
    • F01L1/3442Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear using hydraulic chambers with variable volume to transmit the rotating force
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01LCYCLICALLY OPERATING VALVES FOR MACHINES OR ENGINES
    • F01L1/00Valve-gear or valve arrangements, e.g. lift-valve gear
    • F01L1/02Valve drive
    • F01L1/022Chain drive
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01LCYCLICALLY OPERATING VALVES FOR MACHINES OR ENGINES
    • F01L1/00Valve-gear or valve arrangements, e.g. lift-valve gear
    • F01L1/34Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift
    • F01L1/344Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear
    • F01L1/3442Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear using hydraulic chambers with variable volume to transmit the rotating force
    • F01L2001/34423Details relating to the hydraulic feeding circuit
    • F01L2001/34426Oil control valves
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01LCYCLICALLY OPERATING VALVES FOR MACHINES OR ENGINES
    • F01L1/00Valve-gear or valve arrangements, e.g. lift-valve gear
    • F01L1/34Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift
    • F01L1/344Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear
    • F01L1/3442Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear using hydraulic chambers with variable volume to transmit the rotating force
    • F01L2001/34423Details relating to the hydraulic feeding circuit
    • F01L2001/34426Oil control valves
    • F01L2001/3443Solenoid driven oil control valves
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01LCYCLICALLY OPERATING VALVES FOR MACHINES OR ENGINES
    • F01L1/00Valve-gear or valve arrangements, e.g. lift-valve gear
    • F01L1/34Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift
    • F01L1/344Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear
    • F01L1/3442Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear using hydraulic chambers with variable volume to transmit the rotating force
    • F01L2001/3445Details relating to the hydraulic means for changing the angular relationship
    • F01L2001/34453Locking means between driving and driven members
    • F01L2001/34463Locking position intermediate between most retarded and most advanced positions
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01LCYCLICALLY OPERATING VALVES FOR MACHINES OR ENGINES
    • F01L1/00Valve-gear or valve arrangements, e.g. lift-valve gear
    • F01L1/34Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift
    • F01L1/344Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear
    • F01L1/3442Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear using hydraulic chambers with variable volume to transmit the rotating force
    • F01L2001/3445Details relating to the hydraulic means for changing the angular relationship
    • F01L2001/34453Locking means between driving and driven members
    • F01L2001/34466Locking means between driving and driven members with multiple locking devices
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01LCYCLICALLY OPERATING VALVES FOR MACHINES OR ENGINES
    • F01L1/00Valve-gear or valve arrangements, e.g. lift-valve gear
    • F01L1/34Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift
    • F01L1/344Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear
    • F01L1/3442Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear using hydraulic chambers with variable volume to transmit the rotating force
    • F01L2001/3445Details relating to the hydraulic means for changing the angular relationship
    • F01L2001/34453Locking means between driving and driven members
    • F01L2001/34473Lock movement perpendicular to camshaft axis
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01LCYCLICALLY OPERATING VALVES FOR MACHINES OR ENGINES
    • F01L1/00Valve-gear or valve arrangements, e.g. lift-valve gear
    • F01L1/34Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift
    • F01L1/344Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear
    • F01L1/3442Valve-gear or valve arrangements, e.g. lift-valve gear characterised by the provision of means for changing the timing of the valves without changing the duration of opening and without affecting the magnitude of the valve lift changing the angular relationship between crankshaft and camshaft, e.g. using helicoidal gear using hydraulic chambers with variable volume to transmit the rotating force
    • F01L2001/3445Details relating to the hydraulic means for changing the angular relationship
    • F01L2001/34453Locking means between driving and driven members
    • F01L2001/34476Restrict range locking means

Definitions

  • the present invention relates to a valve timing control apparatus used for controlling opening/closing timing of an exhaust valve or an intake value in a valve operated device of an internal combustion engine.
  • an apparatus including a rotation transmitting member rotatably mounted on a valve opening/closing rotational shaft to be rotatable relative thereto over a predetermined range and receiving a rotational drive force from a crank pulley, a vane mounted on a rotational shaft comprised of a cam shaft and an inner rotor provided integrally therewith, a fluid pressure chamber formed between the rotational shaft and the rotation transmitting member and divided into an advanced angle chamber and a retarded angle chamber, a first fluid passageway for feeding/discharging fluid to/from the advanced angle chamber, a second fluid passageway for feeding/discharging fluid to/from the retarded angle chamber, a retracting hole formed in the rotation transmitting member for receiving therein a lock pin urged toward the rotational shaft, a receiving hole formed in the rotational shaft for receiving the head of the lock pin when the rotational shaft and the rotation transmitting member come into a predetermined phase synchronization or registry with each other, and
  • Patent Document 1 provides a first switching valve for controlling feeding/discharging of the fluid to/from the first fluid passageway and the second fluid passageway and a second switching valve for controlling feeding/discharging of the fluid to/from the third fluid passageway, so that the feeding/discharging of the fluid to/from the third fluid passageway may take place independently of the feeding/discharging of the fluid to/from the first and second fluid passageways.
  • Patent Document 1 Japanese Patent Application "Kokai" No. 10-220207
  • Pulsating displacements due to such torque variations described above will occur conspicuously in particular when the pressure of the fluid fed from the pump is low. And, this phenomenon occurs also in the course of switchover of the phase of the cam shaft relative to the crank shaft to a target phase on the retarded angle side from the advanced angle side.
  • a pressure drop due to the pulsating pressure may lower a lock released state maintaining pressure of the lock mechanism, as a result of which the locking mechanism may be brought into its locking state inadvertently.
  • a lock pin provided as a restricting member for the locking mechanism pivots about the outer periphery of a receiving hole while this lock pin is being accommodated within a retracting hole.
  • the object of the present invention is to provide a valve timing control apparatus capable of avoiding inadvertent realization of a locked state by effectively preventing pulsating pressure of fluid generated in association with torque variation of a cam shaft from having any effect on a fluid passageway for lock releasing, thereby to restrict occurrence of inadvertent realization of the locked state during driving of the internal combustion engine.
  • the apparatus comprises:
  • a check valve that inhibits communication of the fluid from the first switching valve to the second switching valve and allows communication of the fluid from the second switching valve to the first switching valve. Therefore, it is possible to prevent pulsating pressure that occurs in association with torque variation in the rotational shaft from being transmitted from the first switching valve to the second switching valve. Hence, stable fluid free from the influence of the pulsating pressure can be fed from the second switching valve to the third fluid passageway. As a result, the locking mechanism can effectively maintain its lock-released state by this stable fluid pressure and the inadvertent locking of the mechanism can be avoided.
  • the fluid fed from said pump can be fed to said first switching valve with bypassing said second switching valve and can be fed to said second switching valve with bypassing said first switching valve.
  • passage resistance of the first switching valve and the passage resistance of the second switching valve do not affect each other. Hence, controlling operation of rotational phase and controlling operations of the locking mechanism can be effected more speedily.
  • the fluid fed from said pump can be fed to said first switching valve through said check valve and can be fed to said second switching valve with bypassing said check valve.
  • the check valve is interposed between the pump and the first switching valve, it is possible to prevent pulsating pressure of the fluid occurring due to torque variation in the rotational shaft from being transmitted to the pump. Therefore, the pulsating pressure will not affect the second switching valve via the pump. As a result, the locking mechanism can effectively maintain its lock-released state by this even more stable fluid pressure.
  • the apparatus further comprises:
  • passage resistance of the first switching valve and the passage resistance of the second switching valve do not affect each other.
  • controlling operation of rotational phase and controlling operations of the locking mechanism can be effected more speedily.
  • the pulsating pressure does not affect the second switching valve via the pump.
  • the locking mechanism can effectively maintain its lock-released state by this even more stable fluid pressure.
  • an aperture area of said check valve when the fluid is being fed from said pump to said first switching valve is greater than a passageway aperture area of said first connecting passageway.
  • the passageway aperture area of said first connecting passageway is greater than the passageway aperture area of said second connecting passageway.
  • a valve timing control apparatus of the invention shown in Fig. 1 and Fig. 2 includes a driven rotational body consisting essentially of a cam shaft ("rotational shaft") 10, an inner rotor 30 and vanes (partitioning portions) 50 attached to the inner rotor 30, and a driving rotational body consisting essentially of an outer rotor 40 rotatably mounted on the driven rotational body to be rotatable relative thereto over a predetermined range, lock plates 60a, 60b, a timing sprocket 70, etc.
  • the outer periphery of the cam shaft 10 is rotatably supported by a cylinder head 81.
  • the timing sprocket 70 is configured to receive a rotational force in the clockwise direction in Fig. 2 from a crank shaft (not shown) via a timing chain (not shown).
  • the cam shaft 10 includes a cam (not shown) which per se is well known, for opening/closing an intake valve (not shown) or an exhaust valve (not shown).
  • a cam (not shown) which per se is well known, for opening/closing an intake valve (not shown) or an exhaust valve (not shown).
  • Fig. 1 and Fig. 2 inside the cam shaft 10, there are formed an advanced angle passageway 11, a retarded angle passageway 12 and a pilot passageway 13 extending along the axial direction.
  • the advanced angle passageway 11 is formed within an attaching hole for an attaching bolt 16 provided in the cam shaft 10, and this passageway 11 is connected to a connection port 101 of a first switching valve 100 via an annular passageway 91 and a connecting passageway 92 provided on the outer peripheral side of the supported portion of the cam shaft 10.
  • the retarded angle passageway 12 is connected to a connection port 102 of the first switching valve 100 via an annular passageway 93 and a connecting passageway 94 also provided on the outer peripheral side of the supported portion of the cam shaft 10.
  • the pilot passageway 13 is connected to a connection port 111 of a second switching valve 110 via an annular passageway 95 and a connecting passageway 96 also provided on the outer peripheral side of the supported portion of the cam shaft 10.
  • the first switching valve 100 is controlled for its switching operations by a controller (not shown). Under the condition shown in Fig. 1 and Fig. 2 wherein the valve 100 is switched to an angle advanced position (energized state), a supply port 103 connected to an oil pump 120 via a check valve 140 is connected and communicated to the connection port 101 and also the connection port 102 is connected and communicated to an exhaust port 104 connected to an oil pan 130. Further, under the condition (non-energization) wherein the valve 100 is switched to the most retarded angle position shown on the right hand in the figure, the supply port 103 is connected and communicated to the connection portion 102 and also the connection port 101 is connected and communicated to the exhaust port 104.
  • an amount of oil is fed from the oil pump 120 via the check valve 140 to the advanced angle passageway 11 and also an amount of oil is discharged from the retarded angle passageway 12 to the oil pan 130.
  • an amount of oil is fed from the oil pump 120 via the check valve 140 to the retarded angle passageway 12 and also an amount of oil is discharged from the advanced angle passageway 11 to the oil pan 130.
  • the second switching valve 110 is controlled for its switching operations by the controller (not shown). Under the condition shown in Fig. 1 wherein the valve 110 is switched to the feeding position (energized state), the connection port 111 is connected and communicated to the supply port 114 connected to the oil pump 120 and at the same time, its communication to an exhaust port 113 connected to the oil pan 130 is blocked. Further, under the condition shown in Fig. 2 wherein the valve 110 is switched to the exhausting position (non-energized state), the connection port 111 is connected and communicated to the exhaust port 113 whereas the supply port 114 is blocked. Therefore, under this supplying position condition, oil is supplied to the pilot passageway 13 and under the exhausting position condition, oil is discharged through the pilot passageway 13 to the oil pan 130.
  • the inner rotor 30 is fixedly and integrally attached to the cam shaft 10 by the bolt 16 and includes vane grooves 31 for allowing attachment of the four respective vanes 50 along the radial direction. Further, the inner rotor 30 includes also a receiving groove 32, a connecting passageway 33 connecting the bottom of the receiving groove 32 to the pilot passageway 13, a connecting passageway 34 connecting an advanced angle chamber R1 sectioned by each vane 50 and the advanced angle passageway 11 and a connecting passageway 37 connecting a retarded angle chamber R2 sectioned by each vane 50 and the retarded angle passageway 12. Incidentally, each vane 50 is urged in the radially outward direction by means of a spring 51 mounted on the bottom of the vane groove 31.
  • the receiving groove 32 is a groove for receiving a head of the lock plate 60a, 60b by a predetermined engagement amount under the condition shown in Fig. 2 , i.e. the condition wherein the relative phases of the driven rotational body such as the cam shaft 10, the inner rotor 30, etc. and the driving rotational body such as the outer rotor 40, the timing sprocket 70, etc. come into synchronization or registry with each other at a predetermined phase (an intermediate phase between the most advanced angle phase and the most retarded angle phase suitable for startup of the internal combustion engine).
  • a predetermined phase an intermediate phase between the most advanced angle phase and the most retarded angle phase suitable for startup of the internal combustion engine.
  • the outer rotor 40 is assembled to the outer periphery of the inner rotor 30 to be rotatable relative thereto over a predetermined range. And, on opposed sides of the outer rotor 40, a front plate 41 and a rear plate 42 are integrally fastened by means of a bolt 43. Further, in the outer rotor 40, there are formed, by the inner rotor 30, a plurality of operational chambers R0 each of which accommodates the vane 50 corresponding thereto and which is divided into an advanced angle chamber R1 and a retarded angle chamber R2.
  • retracting grooves 46a, 46b for accommodating the lock plates 60a, 60b and springs 61a, 61b for urging these plates 60a, 60b toward the inner rotor 30.
  • the lock plates 60a, 60b are engaged in the retracting grooves 46a, 46b to be movable along the radial direction of the outer rotor 40 and are urged by the springs 61a, 61b toward the inner rotor 30.
  • the springs 61a, 61b are compression springs interposed between the lock plates 60a, 60b and retainers 62a, 62b and these retainers 62a, 62b are fixedly assembled to the outer rotor 40.
  • the engine is started up under the condition shown in Fig. 2 , that is, the condition wherein the heads of the lock plates 60a, 60b are engaged and locked within the receiving grooves 32 at a predetermined phase suitable for startup of the internal combustion engine.
  • the oil pump 120 is driven to start feeding of an amount of oil.
  • the oil discharged from the oil pump 120 is supplied via the check valve 140 from the supply port 103 of the first switching valve 100 through the connection port 101, the connecting passageway 92, the annular passageway 91, the advanced angle passageway 11, the connecting passageway 34 to the advanced angle chamber R1.
  • an amount of oil fed from the oil pump 120 to the second switching valve 110 is not supplied to the pilot passageway 13 because the supply port 114 of the second switching valve 110 is currently blocked, so a locking state is maintained.
  • the first switching valve 100 is energized by a signal from the controller (not shown), as shown in Fig. 5 , the amount of oil discharged from the oil pump 120 is supplied via the check valve 140 from the supply port 103 of the first switching valve 100 through the connection port 102, the connecting passageway 94, the annular passageway 93, the retarded angle passageway 12 and the connecting passageway 37 to the retarded angle chamber R2.
  • an amount of oil is discharged from the advanced angle chamber R1 through the advanced angle passageway 11, the switching valve 100, etc. into the oil pan 130.
  • the driven rotational body including the cam shaft 10, the inner rotor 30 and the vanes 50, etc.
  • Fig. 5 i.e. the condition of the most retarded angle wherein the volume of the advanced angle chamber R1 is rendered minimum.
  • the valve opening/closing timing is controlled to an optimal phase as shuttling between the most advanced angle state and the most retarded angle state.
  • the condition of the lock plate 60a accommodated in the retracting groove 46a is maintained.
  • the condition of the lock plate 60b accommodated in the retracting groove 46b needs to be maintained.
  • the check valve 140 which allows communication of oil to the first switching valve 100 and inhibits (checks) communication of oil to the oil pump 120.
  • the second switching valve 110 for controlling feeding/discharging of oil to/from the pilot passageway 13 is connected to the oil pump 120 via the second connecting passageway 84 branched from a branching point 83 of the first connecting passageway 82 connecting between the oil pump 120 and the check valve 140.
  • the check valve 140 pulsating pressure of oil that occurs due to torque variation in the cam shaft 10 can be prevented from being transmitted from the first switching valve 100 to the oil pump 120.
  • the second switching valve 110 is supplied with oil through the second connecting passageway 84 branched from the first connecting passageway 82 connecting between the oil pump 120 and the check valve 140, the second switching valve 110 is free from any effect of the pulsating pressure of oil that occurs due to torque variation in the cam shaft 10. So that, the oil can be supplied in a stable manner from this second switching valve 110 to the pilot passageway 13. As a result, the stable oil can be supplied to the receiving groove 32, so that the condition of the lock plates 60a, 60b being accommodated within the retracting grooves 46a, 46b can be maintained, thereby to prevent occurrence of inadvertent locking.
  • the aperture area of the check valve 140 be greater than the passageway aperture area of the first connecting passageway 82. Further, for preferential supply of oil to the operational chamber R0 during the advanced/retarded angle control operations, it is preferred that the passageway aperture area of the first connecting passageway 82 be greater than the passageway aperture area of the second connecting passageway 84.
  • the predetermined phase being an intermediate phase between the most advanced angle phase and the most retarded angle phase suitable for startup of the internal combustion engine.
  • the invention is not limited thereto. Instead, the "predetermined phase” can be the most retarded angle phase or the most advanced angle phase, as a matter of course.
  • the present invention is applicable to a valve timing control apparatus used for controlling opening/closing timing of an exhaust valve or an intake value in a valving device of an internal combustion engine.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Valve Device For Special Equipments (AREA)

Abstract

Disclosed is a valve timing control apparatus capable of avoiding inadvertent realization of a locked state by effectively preventing pulsating pressure of fluid generated in association with torque variation of a cam shaft from having any effect on a fluid passageway used for lock releasing. The apparatus includes a first fluid passageway for feeding/discharging fluid to/from an advanced angle chamber, a second fluid passageway for feeding/discharging fluid to/from a retarded angle chamber, a third fluid passageway for feeding/discharging fluid to/from a locking mechanism capable of locking relative rotation between an inner rotor and an outer rotor, a first switching valve for controlling the feeding/discharging of the fluid to/from the first fluid passageway and the second fluid passageway, a second switching valve for controlling the feeding/discharging of the fluid to/from the third fluid passageway, a pump for feeding fluid to the first switching valve and the second switching valve, and a check valve for inhibiting communication of the fluid from the first switching valve to the second switching valve and allowing communication of the fluid from the second switching valve to the first switching valve.

Description

    Technical Field
  • The present invention relates to a valve timing control apparatus used for controlling opening/closing timing of an exhaust valve or an intake value in a valve operated device of an internal combustion engine.
  • Background Art
  • Conventionally, as an example of a valve timing control apparatus, there is disclosed an apparatus including a rotation transmitting member rotatably mounted on a valve opening/closing rotational shaft to be rotatable relative thereto over a predetermined range and receiving a rotational drive force from a crank pulley, a vane mounted on a rotational shaft comprised of a cam shaft and an inner rotor provided integrally therewith, a fluid pressure chamber formed between the rotational shaft and the rotation transmitting member and divided into an advanced angle chamber and a retarded angle chamber, a first fluid passageway for feeding/discharging fluid to/from the advanced angle chamber, a second fluid passageway for feeding/discharging fluid to/from the retarded angle chamber, a retracting hole formed in the rotation transmitting member for receiving therein a lock pin urged toward the rotational shaft, a receiving hole formed in the rotational shaft for receiving the head of the lock pin when the rotational shaft and the rotation transmitting member come into a predetermined phase synchronization or registry with each other, and a third fluid passageway for feeding/discharging fluid to/from this receiving hole (see e.g. Patent Document 1).
  • The invention described in Patent Document 1 provides a first switching valve for controlling feeding/discharging of the fluid to/from the first fluid passageway and the second fluid passageway and a second switching valve for controlling feeding/discharging of the fluid to/from the third fluid passageway, so that the feeding/discharging of the fluid to/from the third fluid passageway may take place independently of the feeding/discharging of the fluid to/from the first and second fluid passageways.
  • Prior Art Document Patent Document
  • Patent Document 1: Japanese Patent Application "Kokai" No. 10-220207
  • Summary of the Invention Object to be Achieved by Invention
  • However, with such valve timing control apparatus as above, torque variation which the cam shaft receives from the intake valve or the exhaust valve when this intake or exhaust valve is driven to be opened or closed is transmitted to the vane, which results in application of torque variation alternately to the inner rotor to the retarded angle side and to the advanced angle side, relative to the outer rotor.
  • For instance, let us suppose a case when fluid is fed to the advanced angle chamber to vary the phase of the cam shaft relative to the crank shaft from the retarded angle side to a target phase on the advanced angle side. In this case, if the inner rotor is exposed to torque variation to the retarded angle side, this torque variation results in displacement of the inner rotor to the direction for decreasing the volume of the advanced angle chamber. As a result, the fluid inside the advanced angle chamber is subject to an outflowing force from this advanced angle chamber. Conversely, if the inner rotor is exposed to torque variation to the advanced angle side, this torque variation results in displacement of the inner rotor to the direction for increasing the volume of the advanced angle chamber. As a result, the advanced angle chamber generates a force to draw in the fluid. Pulsating displacements due to such torque variations described above will occur conspicuously in particular when the pressure of the fluid fed from the pump is low. And, this phenomenon occurs also in the course of switchover of the phase of the cam shaft relative to the crank shaft to a target phase on the retarded angle side from the advanced angle side.
  • If the pulsating pressure of fluid due to torque variation of the cam is applied to the locking mechanism from the advanced angle chamber and/or the retarded angle chamber through the first fluid passageway and/or the second fluid passageway, the first switching valve, the second switching valve and the third fluid passageway, a pressure drop due to the pulsating pressure may lower a lock released state maintaining pressure of the lock mechanism, as a result of which the locking mechanism may be brought into its locking state inadvertently.
  • In the case of a valve timing control apparatus of the so-called "intermediate locking type" configured such that the relative phase between the rotational shaft and the rotation transmitting member is locked at an intermediate phase between the most advanced angle phase and the most retarded angle phase, a lock pin provided as a restricting member for the locking mechanism pivots about the outer periphery of a receiving hole while this lock pin is being accommodated within a retracting hole. Under this condition, if there occurs pulsation in the fluid pressure used for holding the lock pin in the receiving hole, the pressure pulsation will cause repeated exit and entry (retraction) of the pin from/into the retracting hole. As a result, the lock pin may accidentally enter the receiving hole, thus providing a locked state.
  • The object of the present invention is to provide a valve timing control apparatus capable of avoiding inadvertent realization of a locked state by effectively preventing pulsating pressure of fluid generated in association with torque variation of a cam shaft from having any effect on a fluid passageway for lock releasing, thereby to restrict occurrence of inadvertent realization of the locked state during driving of the internal combustion engine.
  • Solution for Accomplishing the Object
  • According to the first characterizing feature of a valve timing control apparatus, the apparatus comprises:
    • an inner rotor rotatable in unison with a valve opening/closing rotational shaft of an internal combustion engine;
    • an outer rotor mounted to be rotatable relative to said inner rotor over a predetermined range and rotatable by a force transmitted thereto from a crank shaft of the internal combustion engine;
    • a fluid pressure chamber formed between said inner rotor and said outer rotor and divided by a partitioning portion into an advanced angle chamber and a retarded angle chamber;
    • a first fluid passageway for feeding/discharging fluid to/from said advanced angle chamber;
    • a second fluid passageway for feeding/discharging fluid to/from said retarded angle chamber;
    • a locking mechanism capable of locking relative rotation between said inner rotor and said outer rotor;
    • a third fluid passageway for feeding fluid to said locking mechanism to cause this locking mechanism to release its locking state and discharging fluid from said locking mechanism to cause this locking mechanism to provide the locking state;
    • a first switching valve for controlling the feeding/discharging of the fluid to/from said first fluid passageway and said second fluid passageway;
    • a second switching valve for controlling the feeding/discharging of the fluid to/from said third fluid passageway;
    • a pump for feeding fluid to said first switching valve and said second switching valve; and
    • a check valve for inhibiting communication of the fluid from said first switching valve to said second switching valve and allowing communication of the fluid from said second switching valve to said first switching valve.
  • With the characterizing feature described above, there is provided a check valve that inhibits communication of the fluid from the first switching valve to the second switching valve and allows communication of the fluid from the second switching valve to the first switching valve. Therefore, it is possible to prevent pulsating pressure that occurs in association with torque variation in the rotational shaft from being transmitted from the first switching valve to the second switching valve. Hence, stable fluid free from the influence of the pulsating pressure can be fed from the second switching valve to the third fluid passageway. As a result, the locking mechanism can effectively maintain its lock-released state by this stable fluid pressure and the inadvertent locking of the mechanism can be avoided.
  • According to the second characterizing feature, the fluid fed from said pump can be fed to said first switching valve with bypassing said second switching valve and can be fed to said second switching valve with bypassing said first switching valve.
  • With the characterizing feature described above, passage resistance of the first switching valve and the passage resistance of the second switching valve do not affect each other. Hence, controlling operation of rotational phase and controlling operations of the locking mechanism can be effected more speedily.
  • According to the third characterizing feature, the fluid fed from said pump can be fed to said first switching valve through said check valve and can be fed to said second switching valve with bypassing said check valve.
  • With the characterizing feature described above, since the check valve is interposed between the pump and the first switching valve, it is possible to prevent pulsating pressure of the fluid occurring due to torque variation in the rotational shaft from being transmitted to the pump. Therefore, the pulsating pressure will not affect the second switching valve via the pump. As a result, the locking mechanism can effectively maintain its lock-released state by this even more stable fluid pressure.
  • According to the fourth characterizing feature of the invention, the apparatus further comprises:
    • a first connecting passageway for connecting said pump to said first switching valve; and
    • a second connecting passageway for connecting a branching point of said first connecting passageway to said second switching valve;
    • wherein said check valve is disposed between said branching point and said first switching valve.
  • With the characterizing feature described above, passage resistance of the first switching valve and the passage resistance of the second switching valve do not affect each other. Hence, controlling operation of rotational phase and controlling operations of the locking mechanism can be effected more speedily. At the same time, the pulsating pressure does not affect the second switching valve via the pump. As a result, the locking mechanism can effectively maintain its lock-released state by this even more stable fluid pressure.
  • According to the fifth characterizing feature of the present invention, an aperture area of said check valve when the fluid is being fed from said pump to said first switching valve is greater than a passageway aperture area of said first connecting passageway.
  • Normally, presence of a check valve within a passageway in which fluid flows provides a passageway resistance, so that an amount of fluid needed for relative rotational movement between the inner rotor and the outer rotor may not be fed speedily to the fluid pressure chamber. With the inventive feature described above, since the aperture area of the check valve when the fluid is being fed from the pump to the first switching valve is greater than a passageway aperture area of the first connecting passageway, the presence of the check valve does not hinder speedy supply of the fluid to the fluid pressure chamber.
  • According to the sixth characterizing feature of the present invention, the passageway aperture area of said first connecting passageway is greater than the passageway aperture area of said second connecting passageway.
  • At the time of a normal advanced/retarded angle control operation, the locking mechanism is maintained under its lock-released state, so the second connecting passageway is maintained under its fluid flowing state. On the other hand, there occurs constant and frequent change in the fluid flowing condition in the first connecting passageway since this first connecting passageway is used for switching over between the advanced angle control and the retarded angle control. Therefore, there exists higher need to supply fluid to the first connecting passageway more readily than to the second connecting passageway. With the characterizing feature described above, since the passageway aperture area of the first connecting passageway is made greater than the passageway aperture area of the second connecting passageway, fluid can be fed more readily to the first connecting passageway, so that the advanced angle control and the retarded angle control can be effected speedily.
  • Brief Description of the Drawings
    • [Fig. 1] is a general construction diagram showing an embodiment of a valve timing control apparatus relating to the present invention,
    • [Fig. 2] is a general construction diagram showing the valve timing control apparatus under its locking state,
    • [Fig. 3] is a general construction diagram showing the valve timing control apparatus under its lock-releasing state,
    • [Fig.4] is a general construction diagram showing the valve timing control apparatus under its most advanced angle state, and
    • [Fig.5] is a general construction diagram showing the valve timing control apparatus under its most retarded angle state.
    Modes of Embodying the Invention
  • Next, embodiments of the present invention will be described with reference to the accompanying drawings. A valve timing control apparatus of the invention shown in Fig. 1 and Fig. 2 includes a driven rotational body consisting essentially of a cam shaft ("rotational shaft") 10, an inner rotor 30 and vanes (partitioning portions) 50 attached to the inner rotor 30, and a driving rotational body consisting essentially of an outer rotor 40 rotatably mounted on the driven rotational body to be rotatable relative thereto over a predetermined range, lock plates 60a, 60b, a timing sprocket 70, etc. The outer periphery of the cam shaft 10 is rotatably supported by a cylinder head 81. Further, as well-known, the timing sprocket 70 is configured to receive a rotational force in the clockwise direction in Fig. 2 from a crank shaft (not shown) via a timing chain (not shown).
  • The cam shaft 10 includes a cam (not shown) which per se is well known, for opening/closing an intake valve (not shown) or an exhaust valve (not shown). As shown in Fig. 1 and Fig. 2, inside the cam shaft 10, there are formed an advanced angle passageway 11, a retarded angle passageway 12 and a pilot passageway 13 extending along the axial direction. The advanced angle passageway 11 is formed within an attaching hole for an attaching bolt 16 provided in the cam shaft 10, and this passageway 11 is connected to a connection port 101 of a first switching valve 100 via an annular passageway 91 and a connecting passageway 92 provided on the outer peripheral side of the supported portion of the cam shaft 10. The retarded angle passageway 12 is connected to a connection port 102 of the first switching valve 100 via an annular passageway 93 and a connecting passageway 94 also provided on the outer peripheral side of the supported portion of the cam shaft 10. The pilot passageway 13 is connected to a connection port 111 of a second switching valve 110 via an annular passageway 95 and a connecting passageway 96 also provided on the outer peripheral side of the supported portion of the cam shaft 10.
  • The first switching valve 100 is controlled for its switching operations by a controller (not shown). Under the condition shown in Fig. 1 and Fig. 2 wherein the valve 100 is switched to an angle advanced position (energized state), a supply port 103 connected to an oil pump 120 via a check valve 140 is connected and communicated to the connection port 101 and also the connection port 102 is connected and communicated to an exhaust port 104 connected to an oil pan 130. Further, under the condition (non-energization) wherein the valve 100 is switched to the most retarded angle position shown on the right hand in the figure, the supply port 103 is connected and communicated to the connection portion 102 and also the connection port 101 is connected and communicated to the exhaust port 104.
  • Therefore, under the advanced angle position state described above, an amount of oil is fed from the oil pump 120 via the check valve 140 to the advanced angle passageway 11 and also an amount of oil is discharged from the retarded angle passageway 12 to the oil pan 130. On the other hand, under a state of retarded angle position, an amount of oil is fed from the oil pump 120 via the check valve 140 to the retarded angle passageway 12 and also an amount of oil is discharged from the advanced angle passageway 11 to the oil pan 130.
  • The second switching valve 110 is controlled for its switching operations by the controller (not shown). Under the condition shown in Fig. 1 wherein the valve 110 is switched to the feeding position (energized state), the connection port 111 is connected and communicated to the supply port 114 connected to the oil pump 120 and at the same time, its communication to an exhaust port 113 connected to the oil pan 130 is blocked. Further, under the condition shown in Fig. 2 wherein the valve 110 is switched to the exhausting position (non-energized state), the connection port 111 is connected and communicated to the exhaust port 113 whereas the supply port 114 is blocked. Therefore, under this supplying position condition, oil is supplied to the pilot passageway 13 and under the exhausting position condition, oil is discharged through the pilot passageway 13 to the oil pan 130.
  • The inner rotor 30 is fixedly and integrally attached to the cam shaft 10 by the bolt 16 and includes vane grooves 31 for allowing attachment of the four respective vanes 50 along the radial direction. Further, the inner rotor 30 includes also a receiving groove 32, a connecting passageway 33 connecting the bottom of the receiving groove 32 to the pilot passageway 13, a connecting passageway 34 connecting an advanced angle chamber R1 sectioned by each vane 50 and the advanced angle passageway 11 and a connecting passageway 37 connecting a retarded angle chamber R2 sectioned by each vane 50 and the retarded angle passageway 12. Incidentally, each vane 50 is urged in the radially outward direction by means of a spring 51 mounted on the bottom of the vane groove 31. The receiving groove 32 is a groove for receiving a head of the lock plate 60a, 60b by a predetermined engagement amount under the condition shown in Fig. 2, i.e. the condition wherein the relative phases of the driven rotational body such as the cam shaft 10, the inner rotor 30, etc. and the driving rotational body such as the outer rotor 40, the timing sprocket 70, etc. come into synchronization or registry with each other at a predetermined phase (an intermediate phase between the most advanced angle phase and the most retarded angle phase suitable for startup of the internal combustion engine).
  • The outer rotor 40 is assembled to the outer periphery of the inner rotor 30 to be rotatable relative thereto over a predetermined range. And, on opposed sides of the outer rotor 40, a front plate 41 and a rear plate 42 are integrally fastened by means of a bolt 43. Further, in the outer rotor 40, there are formed, by the inner rotor 30, a plurality of operational chambers R0 each of which accommodates the vane 50 corresponding thereto and which is divided into an advanced angle chamber R1 and a retarded angle chamber R2. Still further, in the outer rotor 40 along its radial direction, there are formed retracting grooves 46a, 46b for accommodating the lock plates 60a, 60b and springs 61a, 61b for urging these plates 60a, 60b toward the inner rotor 30.
  • The lock plates 60a, 60b are engaged in the retracting grooves 46a, 46b to be movable along the radial direction of the outer rotor 40 and are urged by the springs 61a, 61b toward the inner rotor 30. The springs 61a, 61b are compression springs interposed between the lock plates 60a, 60b and retainers 62a, 62b and these retainers 62a, 62b are fixedly assembled to the outer rotor 40.
  • Next, operations of the valve timing control apparatus having the above-described construction of the instant embodiment will be described. At the time of startup of the internal combustion engine, the engine is started up under the condition shown in Fig. 2, that is, the condition wherein the heads of the lock plates 60a, 60b are engaged and locked within the receiving grooves 32 at a predetermined phase suitable for startup of the internal combustion engine. Upon startup of the internal combustion engine, the oil pump 120 is driven to start feeding of an amount of oil. The oil discharged from the oil pump 120 is supplied via the check valve 140 from the supply port 103 of the first switching valve 100 through the connection port 101, the connecting passageway 92, the annular passageway 91, the advanced angle passageway 11, the connecting passageway 34 to the advanced angle chamber R1. On the other hand, an amount of oil fed from the oil pump 120 to the second switching valve 110 is not supplied to the pilot passageway 13 because the supply port 114 of the second switching valve 110 is currently blocked, so a locking state is maintained.
  • After the startup of the internal combustion engine, once the second switching valve 110 is energized by a signal from a controller (not shown), as shown in Fig. 3, oil discharged from the oil pump 120 is supplied from the supply port 114 of the second switching valve 110 through the connection port 111, the connecting passageway 96, the annular passageway 95, the pilot passageway 13 and the connecting passageway 33 to the receiving groove 32. Upon this supply of oil to the receiving groove 32, the lock plates 60a, 60b are pushed radially outward against the springs 61a, 61b to move out of the receiving grooves 32 and then are retracted into the retracting grooves 46a, 46b respectively. In this way, the locking state by the lock plates 60a, 60b is released, whereby the driven rotational body or components such as the cam shaft 10, the inner rotor 30, the vanes 50, etc. become rotatable relative to the driving rotational body such as the outer rotor 40, etc.
  • Further, under the condition shown in Fig. 3 wherein the locking by the lock plates 60a, 60b is released, if an amount of oil is supplied from the oil pump 120 through the first switching valve 100, the advanced angle passageway 11, etc. into the advanced angle chamber R1, an amount of oil is discharged from the retarded angle chamber R2 through the retarded angle passageway 12 and the switching valve 100, etc. to the oil pan 130. In response to this, the driven rotational body including the cam shaft 10, the inner rotor 30 and the vanes 50, etc. is rotated clockwise in Fig. 3 relative to the driving rotational body including the outer rotor 40, etc., thus providing a condition shown in Fig. 4, i.e. the condition of the most advanced angle wherein the volume of the retarded angle chamber R2 is rendered minimum.
  • Further, under the most advanced angle condition shown in Fig. 4, if the first switching valve 100 is energized by a signal from the controller (not shown), as shown in Fig. 5, the amount of oil discharged from the oil pump 120 is supplied via the check valve 140 from the supply port 103 of the first switching valve 100 through the connection port 102, the connecting passageway 94, the annular passageway 93, the retarded angle passageway 12 and the connecting passageway 37 to the retarded angle chamber R2. On the other hand, an amount of oil is discharged from the advanced angle chamber R1 through the advanced angle passageway 11, the switching valve 100, etc. into the oil pan 130. In response to this, the driven rotational body including the cam shaft 10, the inner rotor 30 and the vanes 50, etc. is rotated counterclockwise in Fig. 4 relative to the driving rotational body including the outer rotor 40, etc., thus providing a condition shown in Fig. 5, i.e. the condition of the most retarded angle wherein the volume of the advanced angle chamber R1 is rendered minimum.
  • During driving of the internal combustion engine, in accordance with the operational conditions of the internal combustion engine, the valve opening/closing timing is controlled to an optimal phase as shuttling between the most advanced angle state and the most retarded angle state. In this, in the case of transition from the most advanced angle state shown in Fig. 4 to the most retarded angle state shown in Fig. 5, the condition of the lock plate 60a accommodated in the retracting groove 46a is maintained. Conversely, in the case of transition from the most retarded angle state shown in Fig. 5 to the most advanced angle state shown in Fig. 4, the condition of the lock plate 60b accommodated in the retracting groove 46b needs to be maintained.
  • In the instant embodiment, in the connecting passageway between the first switching valve 100 for controlling feeding/discharging of oil to/from the advanced angle passageway 11 and the retarded angle passageway 13 and the oil pump 120 for discharging oil, there is incorporated the check valve 140 which allows communication of oil to the first switching valve 100 and inhibits (checks) communication of oil to the oil pump 120. And, the second switching valve 110 for controlling feeding/discharging of oil to/from the pilot passageway 13 is connected to the oil pump 120 via the second connecting passageway 84 branched from a branching point 83 of the first connecting passageway 82 connecting between the oil pump 120 and the check valve 140. Therefore, by the check valve 140, pulsating pressure of oil that occurs due to torque variation in the cam shaft 10 can be prevented from being transmitted from the first switching valve 100 to the oil pump 120. Further, since the second switching valve 110 is supplied with oil through the second connecting passageway 84 branched from the first connecting passageway 82 connecting between the oil pump 120 and the check valve 140, the second switching valve 110 is free from any effect of the pulsating pressure of oil that occurs due to torque variation in the cam shaft 10. So that, the oil can be supplied in a stable manner from this second switching valve 110 to the pilot passageway 13. As a result, the stable oil can be supplied to the receiving groove 32, so that the condition of the lock plates 60a, 60b being accommodated within the retracting grooves 46a, 46b can be maintained, thereby to prevent occurrence of inadvertent locking.
  • In order to reduce the effect of passageway resistance due to the presence of the check valve 140 so as to allow speedy supply of oil to the operational chamber R0 for achieving smooth advanced/retarded angle control operations, it is preferred that the aperture area of the check valve 140 be greater than the passageway aperture area of the first connecting passageway 82. Further, for preferential supply of oil to the operational chamber R0 during the advanced/retarded angle control operations, it is preferred that the passageway aperture area of the first connecting passageway 82 be greater than the passageway aperture area of the second connecting passageway 84.
  • Incidentally, in the foregoing description of the embodiment, there has been described the case of the predetermined phase being an intermediate phase between the most advanced angle phase and the most retarded angle phase suitable for startup of the internal combustion engine. However, the invention is not limited thereto. Instead, the "predetermined phase" can be the most retarded angle phase or the most advanced angle phase, as a matter of course.
  • Industrial Applicability
  • The present invention is applicable to a valve timing control apparatus used for controlling opening/closing timing of an exhaust valve or an intake value in a valving device of an internal combustion engine.
  • Description of Reference Marks/Numerals
  • 10
    cam shaft (rotational shaft)
    11
    advanced angle passageway (first fluid passageway)
    12
    retarded angle passageway (second fluid passageway)
    13
    pilot passageway (third fluid passageway)
    30.
    inner rotor
    32
    receiving groove (lock mechanism)
    40
    outer rotor
    41
    front plate
    42
    rear plate
    46a, 46b
    retracting grooves
    50
    vanes (partitioning portions)
    60a, 60b
    lock plates (lock mechanism)
    81
    cylinder head
    82
    first connecting passageway
    83
    branching point
    84
    second connecting passageway
    100
    first switching valve second switching valve
    120
    oil pump (pump)
    130
    oil pan
    140
    check valve
    R0
    operational chamber (fluid pressure chamber)
    R1
    advanced angle chamber
    R2
    retarded angle chamber

Claims (6)

  1. A valve timing control apparatus comprising:
    an inner rotor rotatable in unison with a valve opening/closing rotational shaft of an internal combustion engine;
    an outer rotor mounted to be rotatable relative to said inner rotor over a predetermined range and rotatable by a force transmitted thereto from a crank shaft of the internal combustion engine;
    a fluid pressure chamber formed between said inner rotor and said outer rotor and divided by a partitioning portion into an advanced angle chamber and a retarded angle chamber;
    a first fluid passageway for feeding/discharging fluid to/from said advanced angle chamber;
    a second fluid passageway for feeding/discharging fluid to/from said retarded angle chamber;
    a locking mechanism capable of locking relative rotation between said inner rotor and said outer rotor;
    a third fluid passageway for feeding fluid to said locking mechanism to cause this locking mechanism to release its locking state and discharging fluid from said locking mechanism to cause this locking mechanism to provide the locking state;
    a first switching valve for controlling the feeding/discharging of the fluid to/from said first fluid passageway and said second fluid passageway;
    a second switching valve for controlling the feeding/discharging of the fluid to/from said third fluid passageway;
    a pump for feeding fluid to said first switching valve and said second switching valve; and
    a check valve for inhibiting communication of the fluid from said first switching valve to said second switching valve and allowing communication of the fluid from said second switching valve to said first switching valve.
  2. The valve timing control apparatus according to claim 1, wherein the fluid fed from said pump can be fed to said first switching valve with bypassing said second switching valve and can be fed to said second switching valve with bypassing said first switching valve.
  3. The valve timing control apparatus according to claim 1, wherein the fluid fed from said pump can be fed to said first switching valve through said check valve and can be fed to said second switching valve with bypassing said check valve.
  4. The valve timing control apparatus according to any one of claims 1-3, wherein the apparatus further comprises:
    a first connecting passageway for connecting said pump to said first switching valve; and
    a second connecting passageway for connecting a branching point of said first connecting passageway to said second switching valve;
    wherein said check valve is disposed between said branching point and said first switching valve.
  5. The valve timing control apparatus according to claim 4, wherein an aperture area of said check valve when the fluid is being fed from said pump to said first switching valve is greater than a passageway aperture area of said first connecting passageway.
  6. The valve timing control apparatus according to claim 4 or 5, wherein the passageway aperture area of said first connecting passageway is greater than the passageway aperture area of said second connecting passageway.
EP10755783.7A 2009-03-25 2010-02-16 Valve open/close timing controller Not-in-force EP2322770B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2009074114A JP2010223172A (en) 2009-03-25 2009-03-25 Valve opening-closing timing control device
PCT/JP2010/052267 WO2010109982A1 (en) 2009-03-25 2010-02-16 Valve open/close timing controller

Publications (3)

Publication Number Publication Date
EP2322770A1 true EP2322770A1 (en) 2011-05-18
EP2322770A4 EP2322770A4 (en) 2012-01-11
EP2322770B1 EP2322770B1 (en) 2013-05-01

Family

ID=42780678

Family Applications (1)

Application Number Title Priority Date Filing Date
EP10755783.7A Not-in-force EP2322770B1 (en) 2009-03-25 2010-02-16 Valve open/close timing controller

Country Status (5)

Country Link
US (1) US20110162606A1 (en)
EP (1) EP2322770B1 (en)
JP (1) JP2010223172A (en)
CN (1) CN102165147B (en)
WO (1) WO2010109982A1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013064261A1 (en) * 2011-11-02 2013-05-10 Schaeffler Technologies AG & Co. KG Camshaft adjustment mechanism having a locking apparatus
EP2636858A1 (en) * 2012-03-08 2013-09-11 Aisin Seiki Kabushiki Kaisha Variable valve timing control apparatus
EP2899377A1 (en) * 2013-07-30 2015-07-29 Aisin Seiki Kabushiki Kaisha Variable valve timing control device
EP2708707A3 (en) * 2012-09-18 2015-07-29 Aisin Seiki Kabushiki Kaisha Valve opening-closing timing control apparatus

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011236781A (en) * 2010-05-07 2011-11-24 Aisin Seiki Co Ltd Device for control of valve timing
EP2474713B1 (en) 2010-11-08 2015-07-22 Toyota Jidosha Kabushiki Kaisha Control device for hydraulic variable valve timing mechanism
WO2012137336A1 (en) 2011-04-07 2012-10-11 トヨタ自動車 株式会社 Variable valve timing device
US9200543B2 (en) 2011-05-13 2015-12-01 Toyota Jidosha Kabushiki Kaisha Variable valve timing device
JP5928158B2 (en) 2012-05-25 2016-06-01 アイシン精機株式会社 Valve timing control device
CN103485853B (en) * 2012-06-13 2016-12-28 日立汽车***株式会社 The variable valve gear of internal combustion engine
JP5839239B2 (en) * 2013-05-14 2016-01-06 株式会社デンソー Valve timing adjustment device
US9464543B2 (en) 2013-05-30 2016-10-11 Aisin Seiki Kabushiki Kaisha Valve opening/closing timing control device
JP6183094B2 (en) * 2013-09-19 2017-08-23 アイシン精機株式会社 Valve timing control unit
JP2017008791A (en) * 2015-06-19 2017-01-12 アイシン精機株式会社 Valve opening/closing timing controller
US10865666B2 (en) * 2018-11-05 2020-12-15 Borgwarner Inc. Check valve for exhausting flow of fluid from a variable cam timing phaser

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19918910A1 (en) * 1998-04-27 1999-11-04 Aisin Seiki Adjustable hydraulic valve timing control appliance for IC engines
WO2006122690A1 (en) * 2005-05-20 2006-11-23 Aft Atlas Fahrzeugtechnik Gmbh Device for variably setting the control times of gas exchange valves of an internal combustion engine

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4202440B2 (en) 1997-02-06 2008-12-24 アイシン精機株式会社 Valve timing control device
US6510824B2 (en) * 1997-12-11 2003-01-28 Diesel Engine Retarders, Inc. Variable lost motion valve actuator and method
DE19756016A1 (en) * 1997-12-17 1999-06-24 Porsche Ag Device for the hydraulic rotation angle adjustment of a shaft to a drive wheel
US6311655B1 (en) * 2000-01-21 2001-11-06 Borgwarner Inc. Multi-position variable cam timing system having a vane-mounted locking-piston device
JP4001070B2 (en) * 2003-07-22 2007-10-31 アイシン精機株式会社 Valve timing control device
JP4145563B2 (en) * 2002-05-09 2008-09-03 株式会社日本自動車部品総合研究所 Valve timing adjustment device
JP4214972B2 (en) * 2003-08-28 2009-01-28 アイシン精機株式会社 Valve timing control device
JP2006144766A (en) * 2004-10-20 2006-06-08 Aisin Seiki Co Ltd Valve opening/closing timing control device
JP4534147B2 (en) * 2005-03-22 2010-09-01 アイシン精機株式会社 Oil supply device
JP2008069649A (en) * 2006-09-12 2008-03-27 Denso Corp Valve timing adjusting device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19918910A1 (en) * 1998-04-27 1999-11-04 Aisin Seiki Adjustable hydraulic valve timing control appliance for IC engines
WO2006122690A1 (en) * 2005-05-20 2006-11-23 Aft Atlas Fahrzeugtechnik Gmbh Device for variably setting the control times of gas exchange valves of an internal combustion engine

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of WO2010109982A1 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013064261A1 (en) * 2011-11-02 2013-05-10 Schaeffler Technologies AG & Co. KG Camshaft adjustment mechanism having a locking apparatus
EP2636858A1 (en) * 2012-03-08 2013-09-11 Aisin Seiki Kabushiki Kaisha Variable valve timing control apparatus
CN103306769A (en) * 2012-03-08 2013-09-18 爱信精机株式会社 Variable valve timing control apparatus
US8776748B2 (en) 2012-03-08 2014-07-15 Aisin Seiki Kabushiki Kaisha Variable valve timing control apparatus
CN103306769B (en) * 2012-03-08 2016-04-06 爱信精机株式会社 Variable valve timing control apparatus
EP2708707A3 (en) * 2012-09-18 2015-07-29 Aisin Seiki Kabushiki Kaisha Valve opening-closing timing control apparatus
EP2899377A1 (en) * 2013-07-30 2015-07-29 Aisin Seiki Kabushiki Kaisha Variable valve timing control device
US9157343B2 (en) 2013-07-30 2015-10-13 Aisin Seiki Kabushiki Kaisha Variable valve timing control device

Also Published As

Publication number Publication date
US20110162606A1 (en) 2011-07-07
EP2322770B1 (en) 2013-05-01
CN102165147B (en) 2013-09-11
CN102165147A (en) 2011-08-24
EP2322770A4 (en) 2012-01-11
JP2010223172A (en) 2010-10-07
WO2010109982A1 (en) 2010-09-30

Similar Documents

Publication Publication Date Title
EP2322770B1 (en) Valve open/close timing controller
EP2412944B1 (en) Valve open/close timing controller
JP4459892B2 (en) Valve timing adjustment device
US7841310B2 (en) Spool valve for VCT locking pin release mechanism
JP5403341B2 (en) Valve timing control device
JP5267264B2 (en) Valve timing control device
JP5376227B2 (en) Valve timing control device
JP2006046315A (en) Valve-timing adjusting device
KR20150128748A (en) Dual lock pin phaser
JP2008175128A (en) Valve timing adjusting device
EP1357260B1 (en) VCT lock pin having a tortuous path providing a hydraulic delay
US8813700B2 (en) Camshaft adjustment mechanism having a locking apparatus
JP2015045242A (en) Control valve and structure for attaching the same
US20160069227A1 (en) Camshaft phaser
EP2881620B1 (en) Variable Valve Timing Control Apparatus
JP2002357106A (en) Valve timing adjusting device
EP2434111B1 (en) Valve timing changing device
EP2891773B1 (en) Variable valve timing control apparatus
JP4459893B2 (en) Valve timing adjustment device
JP2010216407A (en) Valve opening/closing timing control device
JP2002004820A (en) Valve-timing regulating device

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20110316

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

AX Request for extension of the european patent

Extension state: AL BA RS

A4 Supplementary search report drawn up and despatched

Effective date: 20111213

RIC1 Information provided on ipc code assigned before grant

Ipc: F01L 1/344 20060101ALI20111207BHEP

Ipc: F01L 1/34 20060101AFI20111207BHEP

DAX Request for extension of the european patent (deleted)
REG Reference to a national code

Ref country code: DE

Ref legal event code: R079

Ref document number: 602010006828

Country of ref document: DE

Free format text: PREVIOUS MAIN CLASS: F01L0001340000

Ipc: F01L0001020000

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

RIC1 Information provided on ipc code assigned before grant

Ipc: F01L 1/02 20060101AFI20120817BHEP

Ipc: F01L 1/344 20060101ALI20120817BHEP

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

Ref country code: AT

Ref legal event code: REF

Ref document number: 610082

Country of ref document: AT

Kind code of ref document: T

Effective date: 20130515

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602010006828

Country of ref document: DE

Effective date: 20130704

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 610082

Country of ref document: AT

Kind code of ref document: T

Effective date: 20130501

REG Reference to a national code

Ref country code: NL

Ref legal event code: VDEP

Effective date: 20130501

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130901

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130802

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130812

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130902

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130801

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130801

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20140204

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602010006828

Country of ref document: DE

Effective date: 20140204

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20140216

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20140216

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140228

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140228

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140216

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140216

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 7

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20100216

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 8

REG Reference to a national code

Ref country code: DE

Ref legal event code: R084

Ref document number: 602010006828

Country of ref document: DE

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 9

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20130501

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20211230

Year of fee payment: 13

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20220118

Year of fee payment: 13

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602010006828

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230228

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230901