EP1280388A1 - Electronic ballast with preheating mode - Google Patents

Electronic ballast with preheating mode Download PDF

Info

Publication number
EP1280388A1
EP1280388A1 EP02012639A EP02012639A EP1280388A1 EP 1280388 A1 EP1280388 A1 EP 1280388A1 EP 02012639 A EP02012639 A EP 02012639A EP 02012639 A EP02012639 A EP 02012639A EP 1280388 A1 EP1280388 A1 EP 1280388A1
Authority
EP
European Patent Office
Prior art keywords
control circuit
circuit
supply voltage
failure
electronic ballast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP02012639A
Other languages
German (de)
French (fr)
Other versions
EP1280388B1 (en
Inventor
Stefan Zudrell-Koch
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tridonicatco GmbH and Co KG
Original Assignee
Tridonicatco GmbH and Co KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tridonicatco GmbH and Co KG filed Critical Tridonicatco GmbH and Co KG
Publication of EP1280388A1 publication Critical patent/EP1280388A1/en
Application granted granted Critical
Publication of EP1280388B1 publication Critical patent/EP1280388B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H05ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
    • H05BELECTRIC HEATING; ELECTRIC LIGHT SOURCES NOT OTHERWISE PROVIDED FOR; CIRCUIT ARRANGEMENTS FOR ELECTRIC LIGHT SOURCES, IN GENERAL
    • H05B41/00Circuit arrangements or apparatus for igniting or operating discharge lamps
    • H05B41/14Circuit arrangements
    • H05B41/26Circuit arrangements in which the lamp is fed by power derived from dc by means of a converter, e.g. by high-voltage dc
    • H05B41/28Circuit arrangements in which the lamp is fed by power derived from dc by means of a converter, e.g. by high-voltage dc using static converters
    • H05B41/295Circuit arrangements in which the lamp is fed by power derived from dc by means of a converter, e.g. by high-voltage dc using static converters with semiconductor devices and specially adapted for lamps with preheating electrodes, e.g. for fluorescent lamps
    • H05B41/298Arrangements for protecting lamps or circuits against abnormal operating conditions
    • H05B41/2981Arrangements for protecting lamps or circuits against abnormal operating conditions for protecting the circuit against abnormal operating conditions
    • H05B41/2983Arrangements for protecting lamps or circuits against abnormal operating conditions for protecting the circuit against abnormal operating conditions against abnormal power supply conditions
    • HELECTRICITY
    • H05ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
    • H05BELECTRIC HEATING; ELECTRIC LIGHT SOURCES NOT OTHERWISE PROVIDED FOR; CIRCUIT ARRANGEMENTS FOR ELECTRIC LIGHT SOURCES, IN GENERAL
    • H05B41/00Circuit arrangements or apparatus for igniting or operating discharge lamps
    • H05B41/14Circuit arrangements
    • H05B41/26Circuit arrangements in which the lamp is fed by power derived from dc by means of a converter, e.g. by high-voltage dc
    • H05B41/28Circuit arrangements in which the lamp is fed by power derived from dc by means of a converter, e.g. by high-voltage dc using static converters
    • H05B41/295Circuit arrangements in which the lamp is fed by power derived from dc by means of a converter, e.g. by high-voltage dc using static converters with semiconductor devices and specially adapted for lamps with preheating electrodes, e.g. for fluorescent lamps

Definitions

  • the present invention relates to an electronic ballast for operating at least one gas discharge lamp according to the preamble of claim 1.
  • the ignition of a gas discharge lamp is for their spirals a relatively high load.
  • the lamp filaments are usually pre-heated before the ignition of the lamp, since the ignition process is gentler for the coils, if they already have a certain temperature , In this case, a heating current is applied to the coils for a short period of time. Only when this has reached a suitable temperature, the ignition voltage required for ignition is applied to the lamp.
  • Modern ballasts are typically designed to automatically perform such a preheat cycle prior to each ignition of the lamp.
  • an electronic ballast which has a control circuit which determines the duration of the power failure in the event of a power failure. If the duration of the power failure exceeds a predetermined maximum time, the lamp filaments are preheated before the lamp is restarted, but if the duration of the power failure is shorter than the maximum time, preheating of the lamp filaments is dispensed with and the lamp is immediately extinguished ignited.
  • the determination of the duration of the power failure takes place in the abovementioned WO 99/34648 A1 in that an RC element connected to the control circuit is charged to a specific supply voltage potential after the lamp has been ignited. If the power supply fails at a later time, then the capacitor discharged with a predetermined by the elements of the RC element and thus known dynamics. When the power supply returns, the control circuit determines the voltage still applied to the capacitor and compares it with a reference value which corresponds to the predetermined maximum duration up to which no preheating operation is to be performed. If the voltage applied to the capacitor of the RC element voltage is above the reference voltage, the gas discharge lamp is ignited instantly, however, is the voltage below the reference value, a regular lamp start is performed with preheating.
  • the control circuit as well as the other components of the electronic ballast for the duration of the power failure receives no energy and is thus completely disabled. Accordingly, to determine the duration of the power failure, an external element such as the RC element must be used, which is relatively expensive for this purpose. Rather, there is a need to avoid such an external element and to integrate the determination of the duration of the power failure in the control circuit itself.
  • the present invention is therefore based on the object to design an electronic ballast for operating a gas discharge lamp such that a control circuit for controlling the operation of the gas discharge lamp without the use of an external element is able to determine the duration of a temporary power failure.
  • the ballast according to the invention comprises a rectifier circuit which is connectable to a supply voltage, a connected to the output of the rectifier circuit smoothing circuit for generating a DC link voltage, an energy storage element, which is fed with the DC link voltage, a connected to the energy storage element inverter at the output of a terminal for the lamp-containing load circuit is connected, and a control circuit for controlling the operation of the gas discharge lamp.
  • the control circuit starts the gas discharge lamp after a temporary failure of the supply voltage depending on the duration of this failure either with a preheat operation for preheating the lamp filaments or without preheating. For this purpose, it monitors the state of the supply voltage and stops the inverter for the duration of the failure on detection of a failure of the supply voltage.
  • control circuit is powered by the energy storage element during the failure.
  • the control circuit remains activated during the power failure at least to the extent that it is itself able to determine the duration of the failure, since it continues to monitor the value of the input voltage to detect the restoration of the power supply.
  • the use of an external time determination element can thus be dispensed with.
  • Another advantage of the present invention is that there is the possibility of storing in the control circuit the current state of the lamp so that it can then operate the lamp in the same state as before the power failure after a return of the power supply. This is also made possible by the fact that the control circuit uses the residual energy present in the energy storage element during the power failure.
  • the control circuit preferably also shuts down the smoothing circuit in order to minimize the power consumption of the entire electronic ballast.
  • the smoothing circuit is preferably a switching regulator, in particular a boost converter, the energy storage element is preferably formed by a storage capacitor.
  • a particularly advantageous embodiment of the ballast according to the invention is that the control circuit operates digitally at least in terms of monitoring the duration of a power failure.
  • the control circuit has an analog / digital converter on the input side, which converts the rectified supply voltage supplied to the smoothing circuit into a digital value.
  • this digital operating parameter is compared with a reference value, wherein the control circuit switches off the inverter immediately when the internal reference value is undershot.
  • a digitally configured timer circuit is provided, which measures the duration of the power failure.
  • the ballast is connected on the input side via a high-frequency filter 1 to the mains supply voltage U 0 .
  • a rectifier circuit 2 in the form of a full-bridge rectifier, which converts the mains supply voltage U 0 in a rectified input voltage U i for the smoothing circuit 3.
  • the smoothing circuit 3 in turn serves for harmonic filtering and smoothing of the input voltage U i and for this purpose comprises a smoothing capacitor C1 and an inductor L1, a controllable switch in the form of a MOS field effect transistor S1 and a diode D1 having boost converter.
  • boost converter shown here, other switching regulators can be used.
  • an intermediate circuit voltage U z applied across the storage circuit C2 following the smoothing circuit 3 is generated, which is supplied to the inverter 4.
  • the inverter 4 is formed by two arranged in a half-bridge arrangement MOS field effect transistors S2 and S3, wherein an alternating voltage is generated by a high frequency driving these two field effect transistors S2, S3 at the center tap, which is supplied to the load circuit 5 with the gas discharge lamp LA connected thereto. This is done in a known manner and should therefore not be further explained below.
  • the driving of the three MOS field effect transistors S1 to S3 of the smoothing circuit 3 and of the inverter 4 is effected by a control circuit 6 which generates corresponding switching information and transmits it to a driver circuit 7 adjoining the control circuit 6.
  • the driver circuit 7 converts the switching information into corresponding control signals and controls the gates of the three MOS field-effect transistors S1 to S3 via the lines 14 to 16.
  • the load circuit 5 in particular contains two heating circuits H1 and H2, in each of which one of the two coils W1, W2 of the gas discharge lamp LA is arranged. In order to preheat the two coils W1, W2 before igniting the gas discharge lamp LA, a corresponding heating current is applied to the two heating circuits H1, H2.
  • the two coils W1 and W2 which represent ohmic resistances, are heated until they reach a temperature at which the lamp LA can be ignited with as little stress as possible for the two coils W1, W2.
  • the control circuit 6 is supplied via the line 12 with the supply voltage rectified by the rectifier 2, which represents the input voltage U i for the smoothing circuit 3.
  • the analog input signal is converted by a located in the control circuit 6 analog / digital converter ADC into a digital signal, a the analog / digital converter ADC downstream voltage detection block 8 compares the digital value with a predetermined reference value.
  • the voltage detection block 8 and the other components of the control circuit 6 operate completely digitally, whereby the greatest possible integration of the various functions is achieved.
  • a central clock 9 is provided, which generates a clock signal and transmitted to all components of the control circuit 6.
  • the control circuit 6 Based on the performed by the voltage detection block 8 comparison between the input voltage U i for the smoothing circuit 3 corresponding digital value and the reference value, it is determined whether a proper power supply is present at the input of the electronic ballast. If the detected voltage U i falls below the reference value, this is interpreted as a failure of the power supply. The control circuit 6 then immediately transmits a corresponding signal to the driver circuit 7 in order to shut down the two MOS field-effect transistors S2, S3 of the inverter 4. As a result, further consumption of the energy stored in the storage capacitor C2 is immediately prevented by the inverter 4. In addition, the switch S1 of the boost converter is shut down.
  • a possible immediate shutdown of the inverter 4 is therefore important, since the stored energy in the storage capacitor C2 during the failure of the Power supply for the control circuit 6 is used.
  • the storage capacitor C2 ensures the energy supply of the control circuit 6 as an energy storage element for the duration of the power failure. This is achieved in that the voltage applied to the storage capacitor C2 DC link voltage U Z via a supply line 13, in which a resistor R1 is, the control circuit 6 is supplied.
  • the further operation of the control circuit 6 is made possible for a certain period of time.
  • the functionality of the control circuit 6 is ensured at least for the period in which, after a return of the mains supply, no preheating operation is carried out for the lamp filaments W1 and W2 but the lamp LA is to be ignited instantaneously.
  • the duration of the failure of the power supply is determined by a provided in the control circuit 6 timer circuit 10, which may be formed, for example in the form of a digital counter, which begins to count backwards after a failure of the mains supply voltage. Alternatively, another embodiment of the timer circuit 10 would be possible.
  • the signals of the current detection block 8 and the timer circuit 10 are fed to a control block 11, which performs a corresponding operation of the electronic ballast depending on the signals.
  • the control block after a power failure for the instantaneous shutdown of the inverter 4 and the smoothing circuit 3. If later detected by the current detection block 8, the restoration of the power supply, the control block 11 provides for the duration of the power supply failure corresponding restart of the lamp LA , In particular, this means that a preheating of the lamp filaments W1, W2, is dispensed with when the supply voltage U 0 before the completion of the counting cycle of the timer circuit 10 returns. If, on the other hand, the end of the counting cycle has already been reached, a normal preheating operation is carried out before the lamp LA is ignited.
  • the operation of the control circuit 6 according to the invention is schematically summarized in the block diagram in Fig. 2, which illustrate the various phases of lamp operation.
  • the first step 20 consists in switching on the mains supply voltage. Then, in the subsequent blocks 21 and 22, an initialization of the entire ballast and a preheating of the lamp filaments is performed. After completion of the Vorholiczyklusses in step 23, the ignition of the lamp, which is then in the normal operating state 24.
  • This waiting state 25 is characterized in that the smoothing circuit 3 and in particular the inverter 4 of the ballast are shut down and the power supply of the control circuit 6 is effected by the storage capacitor C2.
  • the control circuit 6 continuously checks whether the normal mains supply has been restored. If this is the case, the lamp is ignited immediately, avoiding the pre-heating cycle, but only if the mains supply returns within a specified period of time. In the waiting state 25, therefore, the elapsed time t since the power supply failure is determined. Corresponds to the elapsed time t a predetermined maximum value T max and thus was exceeded the allowable time for a restart without preheating, the control circuit goes into a second wait state 26 on.
  • control circuit merely waits for the mains supply to be restored. If so, a conventional lamp start is performed, i. the control circuit reverts to the state of the initialization phase 21, carries out a normal preheating of the lamp filaments and then an ignition of the lamp.
  • the solution according to the invention thus ensures that it can be determined with high reliability whether the maximum time duration for a failure of the power supply, in which after a return of the supply voltage no preheating operation must be performed before a renewed ignition of the lamp has been exceeded.
  • the control circuit can also be designed so that it "remembers" the state of the lamp, which was present just before the failure of the power supply, and continues to operate the lamp in exactly the same state after restoration of the power supply.
  • control circuit This can also be kept very compact and dispensed with the use of an external element for measuring the duration of the power failure.

Landscapes

  • Circuit Arrangements For Discharge Lamps (AREA)
  • Dc-Dc Converters (AREA)
  • Inverter Devices (AREA)

Abstract

The electronic voltage adapter has a rectifier stage (2), a smoothing stage (3), an energy storage element (C2) and a control circuit (6) that monitors the state of a supply voltage, whereby the control circuit deactivates the converter for the duration of a supply voltage drop-out and supplies power from the energy storage element.

Description

Die vorliegende Erfindung betrifft ein elektronisches Vorschaltgerät zum Betreiben mindestens einer Gasentladungslampe gemäß dem Oberbegriff des Anspruches 1.The present invention relates to an electronic ballast for operating at least one gas discharge lamp according to the preamble of claim 1.

Das Zünden einer Gasentladungslampe stellt für deren Wendeln eine verhältnismäßig hohe Belastung dar. Um diese Belastung dennoch möglichst niedrig zu halten, werden die Lampenwendeln vor dem Zünden der Lampe üblicherweise vorgeheizt, da der Zündvorgang für die Wendeln schonender ist, wenn sie bereits eine gewisse Temperatur aufweisen. Dabei wird an die Wendeln für einen kurzen Zeitraum ein Heizstrom angelegt. Erst wenn hierdurch eine geeignete Temperatur erreicht wurde, wird an die Lampe die zum Zünden erforderliche Zündspannung angelegt. Moderne Vorschaltgeräte sind üblicherweise derart ausgebildet, daß sie einen solchen Vorheizzyklus automatisch vor jedem Zünden der Lampe durchführen.The ignition of a gas discharge lamp is for their spirals a relatively high load. In order to keep this burden as low as possible, the lamp filaments are usually pre-heated before the ignition of the lamp, since the ignition process is gentler for the coils, if they already have a certain temperature , In this case, a heating current is applied to the coils for a short period of time. Only when this has reached a suitable temperature, the ignition voltage required for ignition is applied to the lamp. Modern ballasts are typically designed to automatically perform such a preheat cycle prior to each ignition of the lamp.

Wurde die Lampe allerdings nur für eine sehr kurze Zeit ausgeschaltet, beispielsweise bei einem vorübergehenden Ausfall der Stromversorgung für das Vorschaltgerät, so möchte man die Lampe nach der Wiederkehr der Stromversorgung möglichst schnell neustarten. Oftmals besitzen die Lampenwendeln zu diesem Zeitpunkt noch eine genügend hohe Temperatur, die ein sofortiges erneutes Zünden zulassen würde, so daß durch ein Vorheizen unnötig Zeit verbraucht werden würde. Darüber hinaus stellt in diesem Fall das Vorheizen der Lampenwendeln neben einem Zeitverlust auch einen unnötigen Energieverbrauch dar, wobei sich dieses Problem sowohl bei dem Wiederkommen der normalen Versorgungsspannung nach einem kurzfristigen Ausfall als auch bei dem Einschalten einer Notstromversorgung ergibt.However, if the lamp has only been turned off for a very short time, such as a temporary loss of power to the ballast, you would like to restart the lamp as soon as possible after the power returns. Often, the lamp filaments still have a sufficiently high temperature at this time, which would allow an immediate re-ignition, so that unnecessary time would be consumed by preheating. In addition, in this case, preheating the lamp filaments, in addition to a loss of time, also represents an unnecessary power consumption, this problem resulting both in the return of the normal supply voltage after a short-term failure and when switching on an emergency power supply.

Um das oben geschilderte Problem zu vermeiden, ist beispielsweise aus der WO 99/34648 A1 ein elektronisches Vorschaltgerät bekannt, welches eine Steuerschaltung aufweist, die für den Fall eines Ausfalls der Stromversorgung die zeitliche Dauer des Stromausfalls bestimmt. Überschreitet die Dauer des Stromausfalls eine vorgegebenen Maximalzeit, werden die Lampenwendeln nach einem Wiederkommen der Stromversorgung vorgeheizt, bevor die Lampe erneut gezündet wird, ist die zeitliche Dauer des Stromausfalls allerdings kürzer als die Maximalzeit, so wird auf ein Vorheizen der Lampenwendeln verzichtet und die Lampe sofort gezündet.To avoid the above-described problem, for example, from WO 99/34648 A1 an electronic ballast is known, which has a control circuit which determines the duration of the power failure in the event of a power failure. If the duration of the power failure exceeds a predetermined maximum time, the lamp filaments are preheated before the lamp is restarted, but if the duration of the power failure is shorter than the maximum time, preheating of the lamp filaments is dispensed with and the lamp is immediately extinguished ignited.

Die Bestimmung der Dauer des Stromausfalls erfolgt in der oben genannten WO 99/34648 A1 dadurch, daß ein mit der Steuerschaltung verbundenes RC-Glied nach einem Zünden der Lampe auf ein bestimmtes Versorgungsspannungspotential aufgeladen wird. Fällt zu einem späteren Zeitpunkt die Stromversorgung aus, so wird der Kondensator mit einer durch die Elemente des RC-Gliedes vorgegebenen und damit bekannten Dynamik entladen. Beim Wiederkommen der Stromversorgung bestimmt die Steuerschaltung die an dem Kondensator noch anliegende Spannung und vergleicht diese mit einem Referenzwert, der der vorgegebenen Maximaldauer, bis zu der kein Vorheizbetrieb durchgeführt werden soll, entspricht. Liegt die an dem Kondensator des RC-Gliedes anliegende Spannung oberhalb der Referenzspannung, so wird die Gasentladungslampe augenblicklich gezündet, liegt hingegen die Spannung unterhalb des Referenzwertes, wird ein regulärer Lampenstart mit Vorheizbetrieb durchgeführt.The determination of the duration of the power failure takes place in the abovementioned WO 99/34648 A1 in that an RC element connected to the control circuit is charged to a specific supply voltage potential after the lamp has been ignited. If the power supply fails at a later time, then the capacitor discharged with a predetermined by the elements of the RC element and thus known dynamics. When the power supply returns, the control circuit determines the voltage still applied to the capacitor and compares it with a reference value which corresponds to the predetermined maximum duration up to which no preheating operation is to be performed. If the voltage applied to the capacitor of the RC element voltage is above the reference voltage, the gas discharge lamp is ignited instantly, however, is the voltage below the reference value, a regular lamp start is performed with preheating.

Bei dieser bekannten Lösung erhält die Steuerschaltung ebenso wie die weiteren Komponenten des elektronischen Vorschaltgeräts für die Dauer des Stromausfalls keine Energie und ist damit vollständig deaktiviert. Dementsprechend muß zum Bestimmen der zeitlichen Dauer des Stromausfalls ein externes Element - wie beispielsweise das RC-Glied - verwendet werden, was für diesen Zweck allerdings verhältnismäßig aufwendig ist. Vielmehr besteht das Bedürfnis, ein solches externes Element zu vermeiden und die Bestimmung der zeitlichen Dauer des Stromausfalls in die Steuerschaltung selbst zu integrieren.In this known solution, the control circuit as well as the other components of the electronic ballast for the duration of the power failure receives no energy and is thus completely disabled. Accordingly, to determine the duration of the power failure, an external element such as the RC element must be used, which is relatively expensive for this purpose. Rather, there is a need to avoid such an external element and to integrate the determination of the duration of the power failure in the control circuit itself.

Der vorliegenden Erfindung liegt daher die Aufgabe zugrunde, ein elektronisches Vorschaltgerät zum Betreiben einer Gasentladungslampe derart zu gestalten, daß eine Steuerschaltung zum Steuern des Betriebs der Gasentladungslampe ohne die Verwendung eines externen Elements in der Lage ist, die zeitliche Dauer eines vorübergehenden Stromausfalls zu bestimmen.The present invention is therefore based on the object to design an electronic ballast for operating a gas discharge lamp such that a control circuit for controlling the operation of the gas discharge lamp without the use of an external element is able to determine the duration of a temporary power failure.

Diese Aufgabe wird durch ein elektronisches Vorschaltgerät, welches die Merkmale des Anspruches 1 aufweist, gelöst.This object is achieved by an electronic ballast having the features of claim 1.

Das erfindungsgemäße Vorschaltgerät umfaßt eine Gleichrichterschaltung, die an eine Versorgungsspannung anschließbar ist, eine an den Ausgang der Gleichrichterschaltung angeschlossene Glättungsschaltung zum Erzeugen einer Zwischenkreisspannung, ein Energiespeicherelement, welches mit der Zwischenkreisspannung gespeist wird, einen mit dem Energiespeicherelement verbundenen Wechselrichter, an dessen Ausgang ein Anschluß für die Lampe enthaltender Lastkreis angeschlossen ist, sowie eine Steuerschaltung zum Steuern des Betriebs der Gasentladungslampe. Die Steuerschaltung startet dabei die Gasentladungslampe nach einem vorübergehenden Ausfall der Versorgungsspannung abhängig von der Dauer dieses Ausfalls entweder mit einem Vorheizbetrieb zum Vorheizen der Lampenwendeln oder ohne Vorheizbetrieb. Hierzu überwacht sie den Zustand der Versorgungsspannung und legt bei Erkennen eines Ausfalls der Versorgungsspannung den Wechselrichter für die Dauer des Ausfalls still.The ballast according to the invention comprises a rectifier circuit which is connectable to a supply voltage, a connected to the output of the rectifier circuit smoothing circuit for generating a DC link voltage, an energy storage element, which is fed with the DC link voltage, a connected to the energy storage element inverter at the output of a terminal for the lamp-containing load circuit is connected, and a control circuit for controlling the operation of the gas discharge lamp. The control circuit starts the gas discharge lamp after a temporary failure of the supply voltage depending on the duration of this failure either with a preheat operation for preheating the lamp filaments or without preheating. For this purpose, it monitors the state of the supply voltage and stops the inverter for the duration of the failure on detection of a failure of the supply voltage.

Gleichzeitig wird die Steuerschaltung während des Ausfalls von dem Energiespeicherelement gespeist.At the same time, the control circuit is powered by the energy storage element during the failure.

Bei dieser erfindungsgemäßen Lösung bleibt somit die Steuerschaltung während des Ausfalls der Stromversorgung zumindest soweit aktiviert, daß sie selbst in der Lage ist, die zeitliche Dauer des Ausfalls zu bestimmen, da sie weiterhin den Wert der Eingangsspannung überwacht, um das Wiederherstellen der Stromversorgung zu erkennen. Auf die Verwendung eines externen Zeitbestimmungselements kann somit verzichtet werden. Ein weiterer Vorteil der vorliegenden Erfindung besteht darin, daß die Möglichkeit besteht, in der Steuerschaltung den aktuellen Zustand der Lampe zu speichern, so daß diese dann die Lampe nach einer Wiederkehr der Stromversorgung in dem gleichen Zustand betreiben kann, der vor dem Stromausfall vorlag. Dies wird ebenfalls dadurch ermöglicht, daß die Steuerschaltung während des Stomausfalls die in dem Energiespeicherelement vorhandene Restenergie nutzt.In this solution according to the invention, therefore, the control circuit remains activated during the power failure at least to the extent that it is itself able to determine the duration of the failure, since it continues to monitor the value of the input voltage to detect the restoration of the power supply. The use of an external time determination element can thus be dispensed with. Another advantage of the present invention is that there is the possibility of storing in the control circuit the current state of the lamp so that it can then operate the lamp in the same state as before the power failure after a return of the power supply. This is also made possible by the fact that the control circuit uses the residual energy present in the energy storage element during the power failure.

Weiterbildungen der Erfindung sind Gegenstand der Unteransprüche.Further developments of the invention are the subject of the dependent claims.

So legt die Steuerschaltung nach einem Ausfall der Versorgungsspannung vorzugsweise auch die Glättungsschaltung still, um den Stromverbrauch des gesamten elektronischen Vorschaltgeräts zu minimieren. Bei der Glättungsschaltung handelt es sich vorzugsweise um einen Schaltregler, insbesondere um einen Hochsetzsteller, das Energiespeicherelement wird vorzugsweise durch einen Speicherkondensator gebildet.Thus, after a failure of the supply voltage, the control circuit preferably also shuts down the smoothing circuit in order to minimize the power consumption of the entire electronic ballast. The smoothing circuit is preferably a switching regulator, in particular a boost converter, the energy storage element is preferably formed by a storage capacitor.

Eine besonders vorteilhafte Ausgestaltung des erfindungsgemäßen Vorschaltgeräts besteht darin, daß die Steuerschaltung zumindest bezüglich der Überwachung der zeitlichen Dauer eines Stromausfalls digital arbeitet. Dies wird dadurch erreicht, daß die Steuerschaltung eingangsseitig einen Analog/Digital-Wandler aufweist, der die der Glättungsschaltung zugeführte gleichgerichtete Versorgungsspannung in einen Digitalwert umsetzt. Innerhalb der Steuerschaltung wird dieser digitale Betriebsparameter mit einem Referenzwert verglichen, wobei die Steuerschaltung den Wechselrichter augenblicklich abschaltet, wenn der interne Referenzwert unterschritten wird. Darüber hinaus ist eine digital ausgestaltete Timerschaltung vorgesehen, welche die zeitliche Dauer des Stromausfalls mißt.A particularly advantageous embodiment of the ballast according to the invention is that the control circuit operates digitally at least in terms of monitoring the duration of a power failure. This is achieved in that the control circuit has an analog / digital converter on the input side, which converts the rectified supply voltage supplied to the smoothing circuit into a digital value. Within the control circuit, this digital operating parameter is compared with a reference value, wherein the control circuit switches off the inverter immediately when the internal reference value is undershot. In addition, a digitally configured timer circuit is provided, which measures the duration of the power failure.

Im folgenden soll die Erfindung anhand der beiliegenden Zeichnung näher erläutert werden. Es zeigen:

Fig. 1
ein Schaltbild eines erfindungsgemäßen Vorschaltgeräts;
Fig.2
ein Blockdiagramm zur Erläuterung der Funktionsweise des in Fig 1 dargestellten elektronischen Vorschaltgeräts.
In the following the invention will be explained in more detail with reference to the accompanying drawings. Show it:
Fig. 1
a circuit diagram of a ballast according to the invention;
Fig.2
a block diagram for explaining the operation of the illustrated in Figure 1 electronic ballast.

Bevor ausführlich die erfindungsgemäße Überwachung eines Ausfalls der Stromversorgung beschrieben wird, soll zunächst der allgemeine Aufbau des in Fig. 1 dargestellten Vorschaltgeräts erläutert werden.Before describing in detail the monitoring according to the invention of a failure of the power supply, the general structure of the ballast shown in FIG. 1 will first be explained.

Das Vorschaltgerät ist eingangsseitig über ein Hochfrequenzfilter 1 an die Netzversorgungsspannung U0 angeschlossen. Am Ausgang des Hochfrequenzfilters 1 befindet sich eine Gleichrichterschaltung 2 in Form eines Vollbrückengleichrichters, welche die Netzversorgungsspannung U0 in eine gleichgerichtete Eingangsspannung Ui für die Glättungsschaltung 3 umsetzt. Die Glättungsschaltung 3 wiederum dient zur Oberwellenfilterung und Glättung der Eingangsspannung Ui und umfaßt hierzu einen Glättungskondensator C1 sowie einen eine Induktivität L1, einen steuerbaren Schalter in Form eines MOS-Feldeffekttransistors S1 und eine Diode D1 aufweisenden Hochsetzsteller. Anstelle des hier dargestellten Hochsetzstellers können auch andere Schaltregler verwendet werden.The ballast is connected on the input side via a high-frequency filter 1 to the mains supply voltage U 0 . At the output of the high-frequency filter 1 is a rectifier circuit 2 in the form of a full-bridge rectifier, which converts the mains supply voltage U 0 in a rectified input voltage U i for the smoothing circuit 3. The smoothing circuit 3 in turn serves for harmonic filtering and smoothing of the input voltage U i and for this purpose comprises a smoothing capacitor C1 and an inductor L1, a controllable switch in the form of a MOS field effect transistor S1 and a diode D1 having boost converter. Instead of the boost converter shown here, other switching regulators can be used.

Durch ein entsprechendes Schalten des MOS-Feldeffekttransistors S1 wird eine über dem sich an die Glättungsschaltung 3 anschließenden Speicherkondensator C2 anliegende Zwischenkreisspannung Uz erzeugt, die dem Wechselrichter 4 zugeführt wird. Der Wechselrichter 4 wird durch zwei in einer Halbbrückenanordnung angeordnete MOS-Feldeffekttransistoren S2 und S3 gebildet, wobei durch ein hochfrequentes Ansteuern dieser beiden Feldeffekttransistoren S2, S3 an deren Mittenabgriff eine Wechselspannung erzeugt wird, die dem Lastkreis 5 mit der daran angeschlossenen Gasentladungslampe LA zugeführt wird. Dies erfolgt in bekannter Weise und soll daher im folgenden nicht weiter erläutert werden.By means of a corresponding switching of the MOS field effect transistor S1, an intermediate circuit voltage U z applied across the storage circuit C2 following the smoothing circuit 3 is generated, which is supplied to the inverter 4. The inverter 4 is formed by two arranged in a half-bridge arrangement MOS field effect transistors S2 and S3, wherein an alternating voltage is generated by a high frequency driving these two field effect transistors S2, S3 at the center tap, which is supplied to the load circuit 5 with the gas discharge lamp LA connected thereto. This is done in a known manner and should therefore not be further explained below.

Das Ansteuern der drei MOS-Feldeffekttransitoren S1 bis S3 der Glättungsschaltung 3 und des Wechselrichters 4 erfolgt durch eine Steuerschaltung 6, welche entsprechende Schaltinformationen erzeugt und an eine sich an die Steuerschaltung 6 anschließende Treiberschaltung 7 übermittelt. Die Treiberschaltung 7 setzt die Schaltinformationen in entsprechende Steuersignale um und steuert über die Leitungen 14 bis 16 die Gates der drei MOS-Feldeffekttransistoren S1 bis S3 an.The driving of the three MOS field effect transistors S1 to S3 of the smoothing circuit 3 and of the inverter 4 is effected by a control circuit 6 which generates corresponding switching information and transmits it to a driver circuit 7 adjoining the control circuit 6. The driver circuit 7 converts the switching information into corresponding control signals and controls the gates of the three MOS field-effect transistors S1 to S3 via the lines 14 to 16.

Der Lastkreis 5 enthält insbesondere zwei Heizkreise H1 und H2, in denen jeweils eine der beiden Wendeln W1, W2 der Gasentladungslampe LA angeordnet ist. Um die beiden Wendeln W1, W2 vor einem Zünden der Gasentladungslampe LA vorzuheizen, wird ein entsprechender Heizstrom an die beiden Heizkreise H1, H2 angelegt.The load circuit 5 in particular contains two heating circuits H1 and H2, in each of which one of the two coils W1, W2 of the gas discharge lamp LA is arranged. In order to preheat the two coils W1, W2 before igniting the gas discharge lamp LA, a corresponding heating current is applied to the two heating circuits H1, H2.

Hierdurch werden die beiden Wendeln W1 und W2, die ohm'sche Widerstände darstellen, aufgeheizt, bis sie eine Temperatur erreicht haben, bei der die Lampe LA mit einer möglichst geringen Belastung für die beiden Wendeln W1, W2 gezündet werden kann.As a result, the two coils W1 and W2, which represent ohmic resistances, are heated until they reach a temperature at which the lamp LA can be ignited with as little stress as possible for the two coils W1, W2.

Ein derartiger Vorheizbetrieb soll allerdings nur dann durchgeführt werden, wenn er auch wirklich notwendig ist. Besitzen hingegen die beiden Wendeln W1 und W2 nach einem vorübergehenden Stromausfall noch eine genügend hohe Temperatur, so soll auf die Durchführung dieses zeit- und energieverbrauchenden Vorheizbetriebs verzichtet werden. Dies wird durch die erfindungsgemäße Steuerschaltung 6 ermöglicht, die im folgenden erläutert wird.However, such a preheat operation should only be carried out if it is really necessary. If, on the other hand, the two coils W1 and W2 still have a sufficiently high temperature after a temporary power failure, the implementation of this time-consuming and energy-consuming preheating operation should be dispensed with. This is made possible by the control circuit 6 according to the invention, which is explained below.

Um den Zustand der Stromversorgungsspannung U0 überwachen zu können, wird der Steuerschaltung 6 die von dem Gleichrichter 2 gleichgerichtete Versorgungsspannung, welche die Eingangsspannung Ui für die Glättungsschaltung 3 darstellt, über die Leitung 12 zugeführt. Das analoge Eingangssignal wird von einem in der Steuerschaltung 6 befindlichen Analog/Digital-Wandler ADC in ein digitales Signal umgesetzt, ein dem Analog/Digital-Wandler ADC nachgeschalteter Spannungserfassungblock 8 vergleicht den Digitalwert mit einem vorgegebenen Referenzwert.In order to be able to monitor the state of the power supply voltage U 0 , the control circuit 6 is supplied via the line 12 with the supply voltage rectified by the rectifier 2, which represents the input voltage U i for the smoothing circuit 3. The analog input signal is converted by a located in the control circuit 6 analog / digital converter ADC into a digital signal, a the analog / digital converter ADC downstream voltage detection block 8 compares the digital value with a predetermined reference value.

Der Spannungserfassungblock 8 sowie die weiteren Komponenten der erfindungsgemäßen Steuerschaltung 6 arbeiten vollständig digital, wodurch eine größtmögliche Integration der verschiedenen Funktionen erzielt wird. Innerhalb der Steuerschaltung 6 ist ein zentraler Taktgeber 9 vorgesehen, der ein Taktsignal erzeugt und an alle Komponenten der Steuerschaltung 6 übermittelt.The voltage detection block 8 and the other components of the control circuit 6 according to the invention operate completely digitally, whereby the greatest possible integration of the various functions is achieved. Within the control circuit 6, a central clock 9 is provided, which generates a clock signal and transmitted to all components of the control circuit 6.

Anhand des von dem Spannungserfassungblock 8 durchgeführten Vergleichs zwischen dem der Eingangsspannung Ui für die Glättungsschaltung 3 entsprechenden Digitalwert und dem Referenzwert wird festgestellt, ob eine ordnungsgemäße Stromversorgung am Eingang des elektronischen Vorschaltgeräts vorliegt. Fällt die erfaßte Spannung Ui unterhalb des Referenzwertes, wird dies als Ausfall der Stromversorgung interpretiert. Die Steuerschaltung 6 übermittelt dann augenblicklich ein entsprechendes Signal an die Treiberschaltung 7, um die beiden MOS-Feldeffekttransistoren S2, S3 des Wechselrichters 4 stillzulegen. Hierdurch wird umgehend ein weiterer Verbrauch der in dem Speicherkondensator C2 gespeicherten Energie durch den Wechselrichter 4 verhindert. Darüber hinaus wird auch der Schalter S1 des Hochsetzstellers stillgelegt.Based on the performed by the voltage detection block 8 comparison between the input voltage U i for the smoothing circuit 3 corresponding digital value and the reference value, it is determined whether a proper power supply is present at the input of the electronic ballast. If the detected voltage U i falls below the reference value, this is interpreted as a failure of the power supply. The control circuit 6 then immediately transmits a corresponding signal to the driver circuit 7 in order to shut down the two MOS field-effect transistors S2, S3 of the inverter 4. As a result, further consumption of the energy stored in the storage capacitor C2 is immediately prevented by the inverter 4. In addition, the switch S1 of the boost converter is shut down.

Ein möglichst umgehendes Stillegen des Wechselrichters 4 ist deshalb von Bedeutung, da die in dem Speicherkondensator C2 gespeicherte Energie während des Ausfalls der Stromversorgung für die Steuerschaltung 6 verwendet wird. Mit anderen Worten, der Speicherkondensator C2 stellt als Energiespeicherelement für die Dauer des Stromausfalls die Energieversorgung der Steuerschaltung 6 sicher. Dies wird dadurch erreicht, daß die an dem Speicherkondensator C2 anliegende Zwischenkreisspannung Uz über eine Versorgungsleitung 13, in der sich ein Widerstand R1 befindet, der Steuerschaltung 6 zugeführt wird. Hierdurch wird für einen bestimmten Zeitraum der weitere Betrieb der Steuerschaltung 6 ermöglicht. Insbesondere wird die Funktionsfähigkeit der Steuerschaltung 6 zumindest für den Zeitraum sichergestellt, in dem nach einer Wiederkehr der Netzversorgung kein Vorheizbetrieb für die Lampenwendeln W1 und W2 durchgeführt sondern die Lampe LA augenblicklich gezündet werden soll.A possible immediate shutdown of the inverter 4 is therefore important, since the stored energy in the storage capacitor C2 during the failure of the Power supply for the control circuit 6 is used. In other words, the storage capacitor C2 ensures the energy supply of the control circuit 6 as an energy storage element for the duration of the power failure. This is achieved in that the voltage applied to the storage capacitor C2 DC link voltage U Z via a supply line 13, in which a resistor R1 is, the control circuit 6 is supplied. As a result, the further operation of the control circuit 6 is made possible for a certain period of time. In particular, the functionality of the control circuit 6 is ensured at least for the period in which, after a return of the mains supply, no preheating operation is carried out for the lamp filaments W1 and W2 but the lamp LA is to be ignited instantaneously.

Die zeitliche Dauer des Ausfalls der Stromversorgung wird durch eine in der Steuerschaltung 6 vorgesehene Timerschaltung 10 bestimmt, welche beispielsweise in Form eines digitalen Zählers ausgebildet sein kann, der nach einem Ausfall der Netzversorgungsspannung rückwärts zu zählen beginnt. Alternativ dazu wäre auch eine andere Ausgestaltung der Timerschaltung 10 möglich.The duration of the failure of the power supply is determined by a provided in the control circuit 6 timer circuit 10, which may be formed, for example in the form of a digital counter, which begins to count backwards after a failure of the mains supply voltage. Alternatively, another embodiment of the timer circuit 10 would be possible.

Die Signale des Stromerfassungsblocks 8 und der Timerschaltung 10 werden einem Kontrollbock 11 zugeführt, der abhängig von den Signalen einen entsprechenden Betrieb des elektronischen Vorschaltgeräts durchführt. Insbesondere sorgt der Kontrollblock nach einem Ausfall der Stromversorgung für das augenblickliche Stillegen des Wechselrichters 4 und der Glättungsschaltung 3. Wird von dem Stromerfassungsblock 8 dann später die Wiederherstellung der Stromversorgung erkannt, so sorgt der Kontrollbock 11 für einen der Dauer des Stromversorgungsausfalls entsprechenden Neustart der Lampe LA. Insbesondere bedeutet dies, daß auf ein Vorheizen der Lampenwendeln W1, W2, verzichtet wird, wenn die Versorgungsspannung U0 vor der Beendigung des Zählzyklusses der Timerschaltung 10 wiederkehrt. Wurde hingegen bereits das Ende des Zählzyklusses erreicht, wird vor einem Zünden der Lampe LA ein normaler Vorheizbetrieb durchgeführt.The signals of the current detection block 8 and the timer circuit 10 are fed to a control block 11, which performs a corresponding operation of the electronic ballast depending on the signals. In particular, the control block after a power failure for the instantaneous shutdown of the inverter 4 and the smoothing circuit 3. If later detected by the current detection block 8, the restoration of the power supply, the control block 11 provides for the duration of the power supply failure corresponding restart of the lamp LA , In particular, this means that a preheating of the lamp filaments W1, W2, is dispensed with when the supply voltage U 0 before the completion of the counting cycle of the timer circuit 10 returns. If, on the other hand, the end of the counting cycle has already been reached, a normal preheating operation is carried out before the lamp LA is ignited.

Die erfindungsgemäße Funktionsweise der Steuerschaltung 6 ist schematisch in dem Blockdiagramm in Fig. 2 zusammengefaßt, welches die verschiedenen Phasen des Lampenbetriebs darstellen. Der erste Schritt 20 besteht dabei in einem Einschalten der Netzversorgungsspannung. Daraufhin wird in den darauffolgenden Blöcken 21 und 22 eine Initialisierung des gesamten Vorschaltgeräts sowie ein Vorheizen der Lampenwendeln durchgeführt. Nach Beendigung des Vorheizzyklusses erfolgt in Schritt 23 die Zündung der Lampe, die sich anschließend in dem Normalbetriebszustand 24 befindet.The operation of the control circuit 6 according to the invention is schematically summarized in the block diagram in Fig. 2, which illustrate the various phases of lamp operation. The first step 20 consists in switching on the mains supply voltage. Then, in the subsequent blocks 21 and 22, an initialization of the entire ballast and a preheating of the lamp filaments is performed. After completion of the Vorheizzyklusses in step 23, the ignition of the lamp, which is then in the normal operating state 24.

Wird während des Normalbetriebs 24 ein Ausfall der Netzversorgungsspannung festgestellt, so geht die Steuerschaltung in den Wartezustand 25 über, in dem eine minimale Stromaufnahme des gesamten Vorschaltgeräts vorliegt. Dieser Wartezustand 25 ist dadurch charakterisiert, daß die Glättungsschaltung 3 und insbesondere der Wechselrichter 4 des Vorschaltgeräts stillgelegt werden und die Energieversorgung der Steuerschaltung 6 durch den Speicherkondensator C2 erfolgt.If a failure of the mains supply voltage detected during normal operation 24, the control circuit goes into the waiting state 25, in which there is a minimum power consumption of the entire ballast. This waiting state 25 is characterized in that the smoothing circuit 3 and in particular the inverter 4 of the ballast are shut down and the power supply of the control circuit 6 is effected by the storage capacitor C2.

Während des Wartezustandes 25 wird durch die Steuerschaltung 6 fortwährend überprüft, ob die normale Netzversorgung wieder hergestellt wurde. Ist dies der Fall, wird die Lampe unter Vermeidung des Vorheizzyklusses sofort wieder gezündet, allerdings nur dann, wenn die Netzversorgung innerhalb eines vorgegebenen Zeitraums wiederkehrt. In dem Wartezustand 25 wird deshalb auch die seit dem Ausfall der Stromversorgung vergangene Zeit t bestimmt. Entspricht die abgelaufene Zeit t einem vorgegebenen Maximalwert Tmax und wurde damit die zulässige Zeit für einen Neustart ohne Vorheizung überschritten, so geht die Steuerschaltung in einen zweiten Wartezustand 26 über.During the wait state 25, the control circuit 6 continuously checks whether the normal mains supply has been restored. If this is the case, the lamp is ignited immediately, avoiding the pre-heating cycle, but only if the mains supply returns within a specified period of time. In the waiting state 25, therefore, the elapsed time t since the power supply failure is determined. Corresponds to the elapsed time t a predetermined maximum value T max and thus was exceeded the allowable time for a restart without preheating, the control circuit goes into a second wait state 26 on.

Ab dem Übergang in diesen zweiten Wartezustand 26 ist ein weiteres Messen der seit dem Ausfall der Stromversorgung vergangenen Zeit nicht mehr erforderlich. Vielmehr wartet die Steuerschaltung lediglich darauf, daß die Netzversorgung wieder hergestellt wird. Ist dies der Fall, wird ein herkömmlicher Lampenstart durchgeführt, d.h. die Steuerschaltung geht wieder in den Zustand der Initialisierungsphase 21 über, führt ein normales Vorheizen der Lampenwendeln und anschließend eine Zündung der Lampe durch.From the transition to this second waiting state 26, it is no longer necessary to measure the time that has elapsed since the failure of the power supply. Rather, the control circuit merely waits for the mains supply to be restored. If so, a conventional lamp start is performed, i. the control circuit reverts to the state of the initialization phase 21, carries out a normal preheating of the lamp filaments and then an ignition of the lamp.

Die erfindungsgemäße Lösung stellt somit sicher, daß mit hoher Zuverlässigkeit festgestellt werden kann, ob die zeitliche Maximaldauer für einen Ausfall der Stromversorgung, bei dem nach einer Wiederkehr der Versorgungsspannung kein Vorheizbetrieb vor einem erneuten Zünden der Lampe durchgeführt werden muß, überschritten worden ist. Darüber hinaus kann die Steuerschaltung auch derart ausgebildet sein, daß sie sich den Zustand der Lampe, der unmittelbar vor dem Ausfall der Stromversorgung vorlag, "merkt" und die Lampe nach Wiederherstellung der Stromversorgung in exakt dem gleichen Zustand weiterbetreibt.The solution according to the invention thus ensures that it can be determined with high reliability whether the maximum time duration for a failure of the power supply, in which after a return of the supply voltage no preheating operation must be performed before a renewed ignition of the lamp has been exceeded. In addition, the control circuit can also be designed so that it "remembers" the state of the lamp, which was present just before the failure of the power supply, and continues to operate the lamp in exactly the same state after restoration of the power supply.

Durch die vorteilhafte digitale Ausgestaltung der Steuerschaltung kann diese ferner sehr kompakt gehalten und auf die Verwendung eines externen Elements zum Messen der Dauer des Stromausfalls verzichtet werden.The advantageous digital design of the control circuit, this can also be kept very compact and dispensed with the use of an external element for measuring the duration of the power failure.

Claims (9)

Elektronisches Vorschaltgerät zum Betreiben mindestens einer Gasentladungslampe (LA), mit
einer an eine Versorgungsspannung (U0) anschließbaren Gleichrichterschaltung (1),
einer an den Ausgang der Gleichrichterschaltung (1) angeschlossenen Glättungsschaltung (3) zum Erzeugen einer Zwischenkreisspannung (Uz),
einem mit der Zwischenkreisspannung (Uz) gespeisten Energiespeicherelement (C2),
einem mit dem Energiespeicherelement (C2) verbundenen Wechselrichter (4), an dessen Ausgang ein Anschlüsse für die Lampe (LA) enthaltender Lastkreis (5) angeschlossen ist,
sowie einer Steuerschaltung (6) zum Steuern des Betriebs der Gasentladungslampe (LA), die nach einem vorübergehenden Ausfall der Versorgungsspannung (U0) die Gasentladungslampe (LA) abhängig von der Dauer des Ausfalls entweder mit einem Vorheizbetrieb zum Vorheizen der Lampenwendeln der Gasentladungslampe (LA) oder ohne Vorheizbetrieb startet,
dadurch gekennzeichnet,
daß die Steuerschaltung (6) den Zustand der Versorgungsspannung (U0) überwacht, wobei sie für die Dauer des Ausfalls der Versorgungsspannung (U0) den Wechselrichter (4) stillegt und von dem Energiespeicherelement (C2) gespeist wird.
Electronic ballast for operating at least one gas discharge lamp (LA), with
a rectifier circuit (1) which can be connected to a supply voltage (U 0 ),
a smoothing circuit (3) connected to the output of the rectifier circuit (1) for generating an intermediate circuit voltage (U z ),
one with the intermediate circuit voltage (U z ) powered energy storage element (C2),
a connected to the energy storage element (C2) inverter (4), at whose output a terminals for the lamp (LA) containing load circuit (5) is connected,
and a control circuit (6) for controlling the operation of the gas discharge lamp (LA) after a temporary failure of the supply voltage (U 0 ), the gas discharge lamp (LA) depending on the duration of the failure either with a preheat operation for preheating the lamp filaments of the gas discharge lamp (LA ) or without preheating starts,
characterized,
in that the control circuit (6) monitors the state of the supply voltage (U 0 ), whereby it shuts off the inverter (4) for the duration of the failure of the supply voltage (U 0 ) and is fed by the energy storage element (C2).
Elektronisches Vorschaltgerät nach Anspruch 1,
dadurch gekennzeichnet,
daß die Steuerschaltung (6) nach einem Ausfall der Versorgungsspannung (U0) auch die Glättungsschaltung (3) stillegt.
Electronic ballast according to claim 1,
characterized,
that the control circuit (6) after a failure of the supply voltage (U 0 ) and the smoothing circuit (3) stops.
Elektronisches Vorschaltgerät nach Anspruch 2,
dadurch gekennzeichnet,
daß die Glättungsschaltung (3) durch einen Schaltregler gebildet wird, wobei die Steuerschaltung (6) nach dem Ausfall der Versorgungsspannung (U0) ein weiteres Schalten eines steuerbaren Schalters (S1) des Schaltreglers verhindert.
Electronic ballast according to claim 2,
characterized,
in that the smoothing circuit (3) is formed by a switching regulator, wherein the control circuit (6) prevents further switching of a controllable switch (S1) of the switching regulator after the failure of the supply voltage (U 0 ).
Elektronisches Vorschaltgerät nach Anspruch 3,
dadurch gekennzeichnet,
daß der Schaltregler ein Hochsetzsteller ist.
Electronic ballast according to claim 3,
characterized,
that the switching regulator is a boost converter.
Elektronisches Vorschaltgerät nach einem der vorherigen Ansprüche,
dadurch gekennzeichnet,
daß das Energiespeicherelement ein Speicherkondensator (C2) ist.
Electronic ballast according to one of the preceding claims,
characterized,
that the energy storage element is a storage capacitor (C2).
Elektronisches Vorschaltgerät nach einem der vorherigen Ansprüche,
dadurch gekennzeichnet,
daß die Steuerschaltung (6) die Gasentladungslampe (LA) mit einem Vorheizbetrieb startet, wenn die Dauer des Ausfalls der Versorgungsspannung (U0) eine vorgegebene Maximaldauer (Tmax) überschreitet.
Electronic ballast according to one of the preceding claims,
characterized,
in that the control circuit (6) starts the gas discharge lamp (LA) with a preheating operation when the duration of the failure of the supply voltage (U 0 ) exceeds a predetermined maximum duration (T max ).
Elektronisches Vorschaltgerät nach einem der vorherigen Ansprüche,
dadurch gekennzeichnet,
daß die Steuerschaltung (6) zum Überwachen des Zustands der Versorgungsspannung (U0) die von dem Gleichrichter (2) abgegebene Eingangsspannung (Ui) für die Glättungsschaltung (3) erfaßt und mit einem Referenzwert vergleicht.
Electronic ballast according to one of the preceding claims,
characterized,
in that the control circuit (6) for monitoring the state of the supply voltage (U 0 ) detects the input voltage (U i ) for the smoothing circuit (3) output by the rectifier (2) and compares it with a reference value.
Elektronisches Vorschaltgerät nach Anspruch 7,
dadurch gekennzeichnet,
daß die Steuerschaltung (6) einen Analog/Digital-Wandler (ADC) zum Umsetzen der erfaßten Eingangsspannung (Ui) in einen Digitalwert sowie einen Spannungserfassungsblock (8) aufweist, der den von dem Analog/Digital-Wandler (ADC) erzeugten Digitalwert mit einem digitalen Referenzwert vergleicht.
Electronic ballast according to claim 7,
characterized,
in that the control circuit (6) has an analogue-to-digital converter (ADC) for converting the detected input voltage (U i ) into a digital value and a voltage detection block (8) which includes the digital value produced by the analogue / digital converter (ADC) compares to a digital reference value.
Elektronisches Vorschaltgerät nach einem der vorherigen Ansprüche,
dadurch gekennzeichnet,
daß die Steuerschaltung zum Bestimmen der zeitlichen Dauer des Ausfalls der Versorgungsspannung (U0) eine digitale Timerschaltung (10) aufweist.
Electronic ballast according to one of the preceding claims,
characterized,
that the control circuit for determining the temporal duration of the failure having the supply voltage (U 0), a digital timer circuit (10).
EP02012639A 2001-07-16 2002-06-06 Electronic ballast with preheating mode Expired - Lifetime EP1280388B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE10134566A DE10134566A1 (en) 2001-07-16 2001-07-16 Electronic ballast with preheating mode
DE10134566 2001-07-16

Publications (2)

Publication Number Publication Date
EP1280388A1 true EP1280388A1 (en) 2003-01-29
EP1280388B1 EP1280388B1 (en) 2004-09-08

Family

ID=7691978

Family Applications (1)

Application Number Title Priority Date Filing Date
EP02012639A Expired - Lifetime EP1280388B1 (en) 2001-07-16 2002-06-06 Electronic ballast with preheating mode

Country Status (3)

Country Link
EP (1) EP1280388B1 (en)
AT (1) ATE275811T1 (en)
DE (2) DE10134566A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007025976A1 (en) * 2005-08-31 2007-03-08 Patent-Treuhand-Gesellschaft für elektrische Glühlampen mbH Ballast for a discharge lamp with adaptive preheating
WO2007028777A1 (en) * 2005-09-07 2007-03-15 Patent-Treuhand-Gesellschaft für elektrische Glühlampen mbH Circuit arrangement and method for the operation of a discharge lamp
DE102008030412B4 (en) 2007-07-17 2019-09-05 Infineon Technologies Austria Ag Method for controlling a lamp ballast and drive circuit

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005058574B4 (en) * 2005-12-08 2016-03-24 Hella Kgaa Hueck & Co. Apparatus for controlling the auxiliary power of a gas discharge lamp with an oscillator whose frequency is changed to replace an RC timer

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0439240A2 (en) * 1990-01-20 1991-07-31 SEMPERLUX GmbH, LICHTTECHNISCHES WERK Electronic ballast
WO1995010168A1 (en) * 1993-10-01 1995-04-13 C.M. Personnel Participation B.V. Electronic ballast for gas discharge lamps
WO1997043878A1 (en) * 1996-05-10 1997-11-20 Philips Electronics N.V. Electronic ballast
WO1998046053A2 (en) * 1997-04-10 1998-10-15 Koninklijke Philips Electronics N.V. Anti-flicker scheme for a fluorescent lamp ballast driver
WO1999034648A1 (en) * 1997-12-23 1999-07-08 Tridonic Bauelemente Gmbh Electronic lamp ballast

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0439240A2 (en) * 1990-01-20 1991-07-31 SEMPERLUX GmbH, LICHTTECHNISCHES WERK Electronic ballast
WO1995010168A1 (en) * 1993-10-01 1995-04-13 C.M. Personnel Participation B.V. Electronic ballast for gas discharge lamps
WO1997043878A1 (en) * 1996-05-10 1997-11-20 Philips Electronics N.V. Electronic ballast
WO1998046053A2 (en) * 1997-04-10 1998-10-15 Koninklijke Philips Electronics N.V. Anti-flicker scheme for a fluorescent lamp ballast driver
WO1999034648A1 (en) * 1997-12-23 1999-07-08 Tridonic Bauelemente Gmbh Electronic lamp ballast

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007025976A1 (en) * 2005-08-31 2007-03-08 Patent-Treuhand-Gesellschaft für elektrische Glühlampen mbH Ballast for a discharge lamp with adaptive preheating
US8134297B2 (en) 2005-08-31 2012-03-13 Osram Ag Ballast for a discharge lamp with adaptive preheating
WO2007028777A1 (en) * 2005-09-07 2007-03-15 Patent-Treuhand-Gesellschaft für elektrische Glühlampen mbH Circuit arrangement and method for the operation of a discharge lamp
DE102005042527B4 (en) * 2005-09-07 2015-10-29 Osram Gmbh Circuit arrangement and method for operating a discharge lamp
DE102008030412B4 (en) 2007-07-17 2019-09-05 Infineon Technologies Austria Ag Method for controlling a lamp ballast and drive circuit

Also Published As

Publication number Publication date
DE10134566A1 (en) 2003-02-06
DE50200946D1 (en) 2004-10-14
EP1280388B1 (en) 2004-09-08
ATE275811T1 (en) 2004-09-15

Similar Documents

Publication Publication Date Title
EP1333707B1 (en) Electronic ballast for a discharge lamp
EP0338109B1 (en) Converter for a discharge lamp
EP1872630B1 (en) Intelligent flyback-heating
DE19723625B4 (en) Circuit arrangement for starting and operating a discharge lamp
DE102008027029A1 (en) Lamp type detection by power factor correction circuit
EP0791282B1 (en) Device for operating a gas discharge lamp
EP0114370A1 (en) Method of operating a gas-discharge lamp
DE19622803B4 (en) Circuit arrangement for high-pressure discharge lamp
DE19708791A1 (en) Control circuit and electronic ballast with such a control circuit
EP2138015B1 (en) Circuit configuration for generating an auxiliary voltage and for operating at least one discharge lamp
EP0738455B1 (en) Device for operating a gas discharge lamp
EP1280388B1 (en) Electronic ballast with preheating mode
DE10221450A1 (en) Resonance converter circuit has a pair of switching stages operated by a controller to generate a chopper voltage that is applied to a rectifier
EP2132965B1 (en) Circuit for coil heating
EP1992203B1 (en) Electronic ballast and method for operating an electrical lamp
EP1590993B1 (en) Electronic ballast
DE60009222T2 (en) CONTROL DEVICE OF A FLUORESCENT LAMP
EP2468078B1 (en) Electronic ballast and method for operating at least one discharge lamp
EP3195698B1 (en) Electronic ballast and method for controlling a load
DE4143464C2 (en) Lighting circuit for high-pressure discharge lamp for vehicle
EP1189486B1 (en) Electronic Ballast
WO2002104081A1 (en) Electronic ballast
WO2001063978A1 (en) Circuit arrangement for a fluorescent lamp
DE202004004460U1 (en) Circuit for emergency lighting operation, has push-pull transformer operating at variable drive frequency
DE10217481A1 (en) Method for operating a switching power supply and switching power supply

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

AX Request for extension of the european patent

Extension state: AL LT LV MK RO SI

17P Request for examination filed

Effective date: 20030509

AKX Designation fees paid

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20040908

Ref country code: IE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20040908

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20040908

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20040908

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: A. BRAUN, BRAUN, HERITIER, ESCHMANN AG PATENTANWAE

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: GERMAN

REF Corresponds to:

Ref document number: 50200946

Country of ref document: DE

Date of ref document: 20041014

Kind code of ref document: P

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20041208

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20041208

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20041208

GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

Effective date: 20050111

ET Fr: translation filed
REG Reference to a national code

Ref country code: IE

Ref legal event code: FD4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050606

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20050606

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050630

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050630

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20050609

BERE Be: lapsed

Owner name: *TRIDONICATCO G.M.B.H. & CO. K.G.

Effective date: 20050630

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050208

REG Reference to a national code

Ref country code: CH

Ref legal event code: PFA

Owner name: TRIDONICATCO GMBH & CO. KG

Free format text: TRIDONICATCO GMBH & CO. KG#FAERBERGASSE 15#6850 DORNBIRN (AT) -TRANSFER TO- TRIDONICATCO GMBH & CO. KG#FAERBERGASSE 15#6850 DORNBIRN (AT)

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20110702

Year of fee payment: 10

REG Reference to a national code

Ref country code: NL

Ref legal event code: V1

Effective date: 20130101

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130101

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20130628

Year of fee payment: 12

REG Reference to a national code

Ref country code: CH

Ref legal event code: PCAR

Free format text: NEW ADDRESS: HOLBEINSTRASSE 36-38, 4051 BASEL (CH)

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: IT

Payment date: 20140626

Year of fee payment: 13

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140630

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140630

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 14

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20150630

Year of fee payment: 14

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20150630

Year of fee payment: 14

Ref country code: AT

Payment date: 20150626

Year of fee payment: 14

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150606

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 275811

Country of ref document: AT

Kind code of ref document: T

Effective date: 20160606

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20160606

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20170228

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20160630

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20160606

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20160606

REG Reference to a national code

Ref country code: DE

Ref legal event code: R084

Ref document number: 50200946

Country of ref document: DE

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20190830

Year of fee payment: 18

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 50200946

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES