EP1020245A2 - Method and apparatus for producing a gas turbine blade by means of directional solidification of a melt - Google Patents

Method and apparatus for producing a gas turbine blade by means of directional solidification of a melt Download PDF

Info

Publication number
EP1020245A2
EP1020245A2 EP00104497A EP00104497A EP1020245A2 EP 1020245 A2 EP1020245 A2 EP 1020245A2 EP 00104497 A EP00104497 A EP 00104497A EP 00104497 A EP00104497 A EP 00104497A EP 1020245 A2 EP1020245 A2 EP 1020245A2
Authority
EP
European Patent Office
Prior art keywords
metal
bath
melt
cover layer
mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP00104497A
Other languages
German (de)
French (fr)
Other versions
EP1020245B1 (en
EP1020245A3 (en
Inventor
Robert Prof. Dr. Singer
Thomas Dr. Fitzgerald
Peter Dipl.-Ing. Krug
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens AG
Original Assignee
Siemens AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens AG filed Critical Siemens AG
Publication of EP1020245A2 publication Critical patent/EP1020245A2/en
Publication of EP1020245A3 publication Critical patent/EP1020245A3/en
Application granted granted Critical
Publication of EP1020245B1 publication Critical patent/EP1020245B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C30CRYSTAL GROWTH
    • C30BSINGLE-CRYSTAL GROWTH; UNIDIRECTIONAL SOLIDIFICATION OF EUTECTIC MATERIAL OR UNIDIRECTIONAL DEMIXING OF EUTECTOID MATERIAL; REFINING BY ZONE-MELTING OF MATERIAL; PRODUCTION OF A HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; SINGLE CRYSTALS OR HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; AFTER-TREATMENT OF SINGLE CRYSTALS OR A HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; APPARATUS THEREFOR
    • C30B11/00Single-crystal growth by normal freezing or freezing under temperature gradient, e.g. Bridgman-Stockbarger method
    • C30B11/003Heating or cooling of the melt or the crystallised material
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D27/00Treating the metal in the mould while it is molten or ductile ; Pressure or vacuum casting
    • B22D27/04Influencing the temperature of the metal, e.g. by heating or cooling the mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D27/00Treating the metal in the mould while it is molten or ductile ; Pressure or vacuum casting
    • B22D27/04Influencing the temperature of the metal, e.g. by heating or cooling the mould
    • B22D27/045Directionally solidified castings
    • CCHEMISTRY; METALLURGY
    • C30CRYSTAL GROWTH
    • C30BSINGLE-CRYSTAL GROWTH; UNIDIRECTIONAL SOLIDIFICATION OF EUTECTIC MATERIAL OR UNIDIRECTIONAL DEMIXING OF EUTECTOID MATERIAL; REFINING BY ZONE-MELTING OF MATERIAL; PRODUCTION OF A HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; SINGLE CRYSTALS OR HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; AFTER-TREATMENT OF SINGLE CRYSTALS OR A HOMOGENEOUS POLYCRYSTALLINE MATERIAL WITH DEFINED STRUCTURE; APPARATUS THEREFOR
    • C30B11/00Single-crystal growth by normal freezing or freezing under temperature gradient, e.g. Bridgman-Stockbarger method

Definitions

  • multi-crystalline structure which consists of elongated, stem-shaped crystallites exist all along are aligned with a specific axis. This structure is particularly resistant to loads along the Axis are directed.
  • a single crystal structure indeed understood the structure of a single crystal, ultimately a workpiece, which is essentially a single one Is crystal. Information on this can be found in EP 0 092 496 B1.
  • DE-AS 19 53 716 already shows a container with a Bath for cooling a melt in a casting mold, the Surface of the bath with a heat-insulating top layer is covered.
  • the bath is made of liquid lead.
  • the heat insulating Layer has the sense of oxidizing and overly prevent excessive cooling of the bath.
  • the cooling melt has no direct relationship with any Heater; the bathroom is used by first the empty mold and then with the one to be solidified Melt is filled. A directed freeze the melt is not intended. Achievement is just as little a special distribution of the temperature inside the melt or the casting formed from it a topic.
  • the invention is a largely complete for the first time It is possible to prevent significant heat input into the bathroom, while a melt solidifies in a directed manner becomes.
  • the invention enables substantial enlargement the temperature gradient effective when a melt solidifies and allowed due to the achievable fast Cooling the achievement of better properties as well as a high productivity in the series production of castings.
  • the invention also enables the rational and series production of castings with clearly larger dimensions and / or larger bunches of castings than before and opens up the application of directional solidification for components of stationary gas turbines with Power ratings up to 200 MW and beyond, in particular for turbine blades.
  • the cover layer can be done with relatively little effort and inexpensively are generated by flowable to their formation and isolatable solids can be used.
  • Solid bodies come in particular ceramic hollow bodies, preferably Hollow balls, for use.
  • These hollow bodies exist preferably made of alumina-silica ceramic, in particular Mullite, and have outer diameters between 0.5 mm and 3 mm, preferably about 1 mm.
  • the mullite mentioned is to be used preferably in Shape of hollow spheres.
  • the top layer should preferably be used a bed of balls with matching outer diameters be, for outside diameter of about 1 mm particularly good results are expected.
  • the bed of powder particles should exist, the outer diameter between one lower limit of 0.06 mm and an upper limit of 0.4 mm lie.
  • the same can be done for such a cover layer commercially available ceramic powder can be used.
  • the method of any configuration is preferably used for directional solidification of a first metal in Form of a nickel-based or cobalt-based alloy, in particular a super alloy, such as those used in connection with turbine blades commonly considered for gas turbines becomes.
  • the covering layer 4 has the task of introducing heat from the Heating zone 7, in which the mold 2 with the melt 1 initially is kept and which is at a very high first temperature, in particular around 1600 ° C, in the bath 3 too prevent so that in the interior of the cover layer 4 as possible high temperature gradient, corresponding to a particular one high temperature gradients. Because of the heat into the melt 1 and the mold 2 in the heating zone 7 and due to the heat output from the melt 1 and Casting mold 2 in the bath 3 turns into the melt 1 in the Area where it crosses the top layer 4, also high temperature gradient, which is a directed solidification the melt 1 to a workpiece or several workpieces, in particular a turbine blade 8 (see FIG. 4), with a crystalline or single crystal structure.

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Crystallography & Structural Chemistry (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Mechanical Engineering (AREA)
  • Turbine Rotor Nozzle Sealing (AREA)
  • Crystals, And After-Treatments Of Crystals (AREA)

Abstract

Process is for the directional solidification of a melt (1) of a first metal in a casting mould (2), whereby the melt (1) is introduced into the mould at a temp. above the m. pt. of the first metal and then cooled in the mould (2) by dipping the mould (2) into a bath (3) of a molten second metal at a second temp. below the m. pt. of the first metal. The bath (3) is covered with a free-flowing, floating layer (4) of loose thermally insulating material (5,6) through which the mould (2) contg. the melt (1) is dipped. Appts. for carrying out the method is also claimed.

Description

Die Erfindung betrifft ein Verfahren und eine Vorrichtung zur Herstellung einer Gasturbinenschaufel mittels gerichtetem Erstarren einer Schmelze eines ersten Metalls in einer Gießform, wobei das Verfahren das Bereitstellen der Schmelze in der Gießform auf einer ersten Temperatur oberhalb des Schmelzpunktes des ersten Metalls und anschließendes Abkühlen der Schmelze in der Gießform durch Eintauchen der Gießform in ein Bad aus einem flüssigen zweiten Metall, welches sich auf einer zweiten Temperatur befindet, welche unterhalb des Schmelzpunktes des ersten Metalls liegt, umfaßt und wobei die Vorrichtung eine Heizkammer, welche eine Heizzone zur Warmhaltung der Schmelze und der Gießform auf einer ersten Temperatur oberhalb des Schmelzpunktes des ersten Metalls, einen unterhalb der Heizkammer angeordneten Tiegel mit einem Bad aus einem flüssigen zweiten Metall, welches sich auf einer zweiten Temperatur befindet, die unterhalb des Schmelzpunktes des ersten Metalls liegt, sowie eine Fahreinrichtung zur Bewegung der Gießform aus der Heizzone in das Bad umfaßt.The invention relates to a method and an apparatus for Production of a gas turbine blade by directional solidification a melt of a first metal in a casting mold, the method comprising providing the melt in the mold at a first temperature above the Melting point of the first metal and subsequent cooling the melt in the mold by dipping the mold in a bath of a liquid second metal, which is on a second temperature, which is below the Melting point of the first metal, comprises and wherein the Device a heating chamber, which has a heating zone for keeping warm the melt and the mold at a first temperature above the melting point of the first metal, one crucibles with a bath arranged below the heating chamber from a liquid second metal, which is on a second temperature is below the melting point of the first metal, and a driving device for movement the mold from the heating zone into the bath.

Ein Verfahren bzw. eine Vorrichtung zum gerichteten Erstarren einer Schmelze wird angewendet, wenn aus einer Schmelze ein Gußstück mit stengelkristallinem oder einkristallinem Gefüge gebildet werden soll. Dies kommt insbesondere in Frage bei der Herstellung einer Turbinenschaufel für eine Gasturbine aus einer Schmelze einer Nickelbasis- oder Kobaltbasis-Legierung, insbesondere einer Superlegierung.A method or a device for directional solidification a melt is applied when coming from a melt Cast with a crystalline or single crystal structure to be formed. This is particularly relevant the manufacture of a turbine blade for a gas turbine from a melt of a nickel-based or cobalt-based alloy, especially a super alloy.

Unter einem stengelkristallinen Gefüge wird in jedem Fall ein vielkristallines Gefüge verstanden, welches aus langgestreckten, stengelförmigen Kristalliten besteht, die alle entlang einer bestimmten Achse ausgerichtet sind. Dieses Gefüge ist besonders widerstandsfähig gegen Belastungen, die entlang der Achse gerichtet sind. Unter einem einkristallinen Gefüge wird in der Tat das Gefüge eines Einkristalls verstanden, letztlich also ein Werkstück, welches im wesentlichen ein einziger Kristall ist. Hinweise dazu sind der EP 0 092 496 B1 entnehmbar.In any case, under a columnar crystalline structure understood multi-crystalline structure, which consists of elongated, stem-shaped crystallites exist all along are aligned with a specific axis. This structure is particularly resistant to loads along the Axis are directed. Under a single crystal structure indeed understood the structure of a single crystal, ultimately a workpiece, which is essentially a single one Is crystal. Information on this can be found in EP 0 092 496 B1.

Die Bildung von Einkristallen aus Schmelzen ist auch auf dem Gebiet der Halbleitertechnik bekannt, wobei hier bislang andere als die bisher beschriebenen Verfahren und Vorrichtungen eingesetzt werden. In letzter Zeit gibt es aber Forschungsanstrengungen, bei denen Verfahren und Vorrichtungen ähnlich den für metallische Werkstoffe bekannten eingesetzt werden. Im Zusammenhang mit der gerichteten Erstarrung metallischer Schmelzen sind mehrere Möglichkeiten zur Erzielung eines einkristallinen Gefüges bekannt. Die bevorzugte Möglichkeit liegt nach der EP 0 092 496 B1 darin, die Schmelze in einer Gießform erstarren zu lassen, die an ihrem unteren Ende eine spiralförmig gekrümmte Einschnürung aufweist, wobei unterhalb der Einschnürung zunächst ein stengelkristallines Gefüge entsteht, von dem aus nur ein einziger Stengelkristall die Einschnürung durchwachsen und somit zum Ausgangspunkt der Kristallisation der Schmelze oberhalb der Einschnürung werden kann. Alternativ dazu ist es möglich, in die Gießform einen sogenannten Impfkristall, d.h. einen kleinen Einkristall, einzulegen, von dem aus die Schmelze unter Beibehaltung der Orientierung des Impfkristalls kristallisieren kann. Hierbei sind selbstverständlich Vorkehrungen erforderlich, um ein vollständiges Aufschmelzen des mit der zu erstarrenden Schmelze zu bedeckenden Impfkristalls zu vermeiden.The formation of single crystals from melts is also on the Known in the field of semiconductor technology, but so far others than the methods and devices described so far be used. Recently there have been research efforts where processes and devices are similar the known for metallic materials are used. In connection with the directional solidification of metallic Melting are several ways to achieve a single crystal Known structure. The preferred option According to EP 0 092 496 B1, the melt is in one Let the mold solidify, the one at its lower end Spirally curved constriction, being below the constriction initially creates a crystalline structure, from which only a single stem crystal constricted grow through and thus to the starting point of crystallization the melt above the constriction can. Alternatively, it is possible to put one in the mold so-called seed crystal, i.e. a small single crystal, insert from which the melt while maintaining the Orientation of the seed crystal can crystallize. Here of course, precautions are required to get one complete melting of the solidified with Avoid melting seed crystal to be covered.

Ein Verfahren und eine Vorrichtung der eingangs genannten Art gehen hervor aus der DE 28 15 818 A1. Das in jedem Fall vorgesehene Eintauchen der Gießform in das kühlende Bad, welches insbesondere aus flüssigem Zinn besteht, dient dazu, in der Gießform und der Schmelze eine Zone mit einem steilen vertikalen Temperaturgradienten zu erzeugen, die mit zunehmendem Eintauchen der Gießform in das Bad entgegen der Richtung, in der die Gießform eingetaucht wird, durch die Schmelze wandert. Ein möglichst steiler Temperaturgradient ist erwünscht, weil er die Bildung eines günstigen Gefüges bewirkt. Er geht einher mit einer hohen Abkühlungsrate beim Eintauchen der Gießform mit der Schmelze in das Bad. Unter einem günstigen Gefüge versteht man in diesem Fall ein Gefüge, das weitgehend frei ist von Inhomogenitäten, Segregationen, niedrig schmelzenden Nichtgleichgewichtsphasen und Poren und somit gute mechanische Eigenschaften aufweist. Ein weiterer Vorteil des steilen Temperaturgradienten ist, daß er einen schnellen und kostengünstigen Fertigungsprozeß ermöglicht. Die Ausbildung eines hohen Temperaturgradienten wird allerdings konterkariert durch eine von der Heizzone ausgehende intensive Wärmestrahlung, die bedingt ist durch die in der Heizzone herrschende hohe Temperatur von üblicherweise um 1600 °C. Diese Wärmestrahlung kann das Bad stark aufheizen, was zu einer beträchtlichen Verringerung des erzielbaren Temperaturgradienten und zu einem Verdampfen des Bades führen kann, insbesondere dann, wenn gemäß üblicher Praxis das gerichtete Erstarren der Schmelze unter Vakuum erfolgen soll. Um diese nachteiligen Effekte auszuschließen und zu verhindern, daß Strahlung aus der Heizkammer das Bad erwärmt, ist an der Unterseite der Heizkammer ein zur Gießform hin gerichteter, allgemein als "Baffle" bezeichneter Strahlungsschirm vorgesehen, der das Bad gegen die Heizzone abschirmen soll. Zusätzlich schwimmt auf der Kühlschmelze eine Trennplatte aus einem wärmeisolierenden Material, welche zum Eintauchen der Gießform in die Kühlschmelze eine Öffnung hat. Die mit dieser Anordnung erzielbare Wärmedämmung ist allerdings unvollkommen, insbesondere dann, wenn ein Gußstück mit variablem Querschnitt hergestellt werden soll und demgemäß eine Gießform mit ebenfalls stark veränderlichem Querschnitt verwendet werden muß. In diesem Fall müssen Strahlungsschirm und Trennplatte auf den größten Querschnitt der Gießform abgestimmt sein. Dies führt allerdings dann, wenn ein Bereich der Gießform mit deutlich verringertem Querschnitt durch das Baffle und die Trennplatte in das Bad eintreten soll, zur Entstehung eines Spaltes, der das Durchtreten von Wärmestrahlung zu dem Kühlbad erlaubt und sich demgemäß nachteilig auf den erzielbaren Temperaturgradienten auswirkt.A method and a device of the type mentioned at the beginning emerge from DE 28 15 818 A1. That which is provided in every case Immerse the mold in the cooling bath, which consists in particular of liquid tin, serves in the Mold and melt a zone with a steep vertical To generate temperature gradients, which with increasing Immerse the mold in the bath against the direction in which the mold is immersed, migrates through the melt. A temperature gradient that is as steep as possible is desirable because it creates a favorable structure. He goes accompanied by a high cooling rate when immersing the Casting mold with the melt in the bath. Under a cheap Structure in this case is understood to be a structure that is largely is free of inhomogeneities, segregations, low melting Non-equilibrium phases and pores and therefore good mechanical Has properties. Another advantage of steep temperature gradient is that it has a fast and enables inexpensive manufacturing process. Training a high temperature gradient is counteracted due to intense heat radiation from the heating zone, which is due to the prevailing in the heating zone high temperature of usually around 1600 ° C. This Radiant heat can heat up the bathroom considerably, resulting in considerable Reduction of the achievable temperature gradient and can lead to evaporation of the bath, in particular when, according to customary practice, directional solidification the melt should take place under vacuum. To disadvantage this Exclude effects and prevent radiation from the heating chamber the bathroom is heated, is on the bottom the heating chamber is directed towards the casting mold, generally provided as a "baffle" radiation shield, to shield the bathroom from the heating zone. In addition a separating plate made of heat-insulating floats on the cooling melt Material used to immerse the mold has an opening in the cooling melt. The one with this arrangement achievable insulation is imperfect, especially when a casting with a variable cross-section to be produced and accordingly a mold can also be used with a highly variable cross-section got to. In this case, radiation shield and partition plate matched to the largest cross-section of the mold his. However, this leads to an area of the mold with a significantly reduced cross section through the baffle and the partition plate is to enter the bathroom, for the creation a gap that prevents the passage of heat radiation to the Cooling bath allowed and accordingly adversely affect the achievable Temperature gradient.

Die DE-AS 19 53 716 zeigt bereits einen Behälter mit einem Bad zur Abkühlung einer Schmelze in einer Gießform, wobei die Oberfläche des Bades mit einer wärmeisolierenden Deckschicht bedeckt ist. Das Bad besteht aus flüssigem Blei. Die wärmeisolierende Schicht hat den Sinn, ein Oxidieren und ein übermäßig starkes Abkühlen des Bades zu verhindern. Die Kühlschmelze steht in keinerlei unmittelbarer Beziehung zu einer Heizvorrichtung; das Bad wird benutzt, indem zunächst die leere Gießform hineingegeben und anschließend mit der zu erstarrenden Schmelze befüllt wird. Ein gerichtetes Erstarren der Schmelze ist nicht vorgesehen. Ebensowenig ist die Erzielung einer besonderen Verteilung der Temperatur im Inneren der Schmelze oder des daraus gebildeten Gußstücks ein Thema.DE-AS 19 53 716 already shows a container with a Bath for cooling a melt in a casting mold, the Surface of the bath with a heat-insulating top layer is covered. The bath is made of liquid lead. The heat insulating Layer has the sense of oxidizing and overly prevent excessive cooling of the bath. The cooling melt has no direct relationship with any Heater; the bathroom is used by first the empty mold and then with the one to be solidified Melt is filled. A directed freeze the melt is not intended. Achievement is just as little a special distribution of the temperature inside the melt or the casting formed from it a topic.

Aus der DE 22 42 111 B2 ist es bei einem Verfahren und bei einer Vorrichtung der eingangs genannten Art bekannt, die Oberfläche des Bades so dicht unterhalb der Heizkammer vorzusehen, daß eine am unteren Ende der Gießform vorgesehene Kühlplatte schon vor dem Eintauchen der eigentlichen Gießform zumindest teilweise in das Bad eintaucht. Hierdurch wird die Kühlplatte auch dann auf einer der Temperatur des Bades entsprechenden Temperatur gehalten, wenn die Gießform sich noch in der Heizzone befindet und womöglich noch nicht gefüllt ist. Hierdurch wird die Kühlung der Schmelze am unteren Ende der Gießform intensiviert und darüber hinaus eine gewisse zusätzliche Abschirmung des Bades vor der von der Heizzone ausgehenden Hitzestrahlung erreicht. Ergänzend ist an einem unteren Ende der Heizkammer ein besonderer Hitzeschild vorgesehen. Zur Vergleichmäßigung der Temperatur in dem Bad ist eine Rührvorrichtung vorgesehen, mit der das Bad umgewälzt werden kann. From DE 22 42 111 B2 it is in a method and known a device of the type mentioned To provide the surface of the bath so close below the heating chamber that one provided at the lower end of the mold Cooling plate even before immersing the actual mold at least partially immersed in the bathroom. This will make the Cooling plate also at a temperature corresponding to the bath Temperature maintained when the mold is still up located in the heating zone and possibly not yet filled is. This will cool the melt at the bottom the mold intensified and also a certain additional Shield the bathroom from the one coming from the heating zone Heat radiation reached. Complementary is on a lower one A special heat shield is provided at the end of the heating chamber. To even out the temperature in the bath is a Stirring device is provided with which the bath is circulated can.

Zu allen bekannten Verfahren und Vorrichtungen zum gerichteten Erstarren einer Schmelze sei festgestellt, daß sie zur Herstellung von Gußstücken mit Abmessungen, die einen Wert von 10 cm deutlich überschreiten, nur bedingt geeignet sind. Der Grund liegt im wesentlichen darin, daß die bisher erzielbaren Temperaturgradienten für ein zuverlässiges gerichtetes Erstarren größerer Schmelzen nicht ausreichen, wobei sich die geschilderte Problematik aufgrund der Einstrahlung von Wärme aus der Heizzone in das Bad bei größeren Gußstücken mit variierenden Querschnitten zusätzlich störend auswirkt. Probleme stellen sich bei den bekannten Verfahren und Vorrichtungen auch ein, wenn vielzählige, nach Art einer Traube untereinander und mit einem gemeinsamen Eingußkanal verbundene Gußstücke gleichzeitig hergestellt werden sollen, da in einem solchen Fall die in den Gußstücken erzielbaren Temperaturgradienten wegen weiter verringerten Abschirmmöglichkeit nochmals verringert sind.For all known methods and devices for directed Solidification of a melt is said to lead to Manufacture of castings with dimensions that have a value of 10 cm, are only suitable to a limited extent. The reason is essentially that the previously achievable Temperature gradients for a reliable directional Solidification of larger melts is not sufficient described problem due to the radiation of heat from the heating zone into the bathroom with larger castings with varying Cross-sections additionally disruptive. Problems arise in the known methods and devices also one, if numerous, like a grape among each other and castings connected to a common sprue should be produced at the same time, as in such Case the temperature gradients achievable in the castings because of the further reduced shielding possibility again are reduced.

Die Aufgabe, von der die Erfindung ausgeht, liegt daher darin, das Verfahren und die Vorrichtung der eingangs genannten Art derart weiterzuentwickeln, daß eine gegenüber dem Stand der Technik wesentlich verbesserte Abschirmung des Bades und ein gegenüber den Möglichkeiten des Standes der Technik wesentlich höherer Temperaturgradient beim Einführen der Gießform mit der Schmelze in das Bad erzielt wird. Vorzugsweise sollen ein günstigeres Gefüge für die erstarrte Schmelze und eine kürzere Herstellungszeit erreicht werden. Es sollen auch größere Gußstücke unter Gewährleistung des gerichteten Erstarrens und unter Vermeidung einer Überhitzung und/oder Verdampfung des Bades hergestellt werden können.The object on which the invention is based is therefore the method and the device of the aforementioned Art to develop in such a way that one compared to the state the technology of the bathroom has been significantly improved and an essential compared to the possibilities of the prior art higher temperature gradient when inserting the mold is achieved with the melt in the bath. Preferably are said to be a more favorable structure for the solidified melt and a shorter manufacturing time can be achieved. It should also larger castings while ensuring directional solidification and avoiding overheating and / or evaporation of the bath can be made.

Zur Lösung der Aufgabe, soweit sie sich auf ein Verfahren bezieht, wird ein Verfahren zur Herstellung einer Gasturbinenschaufel mittels gerichtetem Erstarren einer Schmelze eines ersten Metalls in einer Gießform angegeben, umfassend Bereitstellung der Schmelze in der Gießform auf einer ersten Temperatur oberhalb des Schmelzpunktes des ersten Metalls und anschließendes Abkühlen der Schmelze in der Gießform durch Eintauchen der Gießform in ein Bad aus einem flüssigen zweiten Metall, welches sich auf einer zweiten Temperatur befindet, die unterhalb des Schmelzpunktes des ersten Metalls liegt, wobei das Bad bedeckt ist von einer schwimmenden, fließfähigen Deckschicht aus einem wärmeisolierenden Schüttgut und die Gießform mit der Schmelze durch die Deckschicht hindurch in das Bad eingetaucht wird.To solve the problem, insofar as it relates to a method, discloses a method of manufacturing a gas turbine blade by means of directed solidification of a melt specified first metal in a casting mold, comprising provision the melt in the mold at a first temperature above the melting point of the first metal and subsequent Cool the melt in the mold by immersion the mold into a bath from a liquid second Metal that is at a second temperature which is below the melting point of the first metal, the bath is covered by a floating, flowable Top layer of a heat-insulating bulk material and the Casting mold with the melt through the top layer in the bath is immersed.

Die erfindungsgemäß eingesetzte Deckschicht aus fließfähigem Material schirmt das Bad vollständig ab, auch während die Gießform in das Bad eintritt, da das fließfähige Schüttgut die Gießform stets eng umschließt selbst dann, wenn sich ihr Querschnitt während des Durchdringens der Deckschicht verändert und auch dann, wenn die Gießform eingerichtet ist zur Aufnahme mehrerer voneinander beabstandeter Schmelzen, wie dies im Stand der Technik gelegentlich beschrieben und oben bereits erläutert ist.The top layer used according to the invention made of flowable Material completely shields the bathroom, even during the Casting mold enters the bath because the flowable bulk material the mold is always tight, even when you are Cross section changed during penetration of the cover layer and even if the mold is set up for Inclusion of several spaced melts, such as this is occasionally described in the prior art and above is already explained.

Mit der Erfindung ist erstmalig eine weitgehend vollständige Verhinderung eines wesentlichen Wärmeeintrags in das Bad möglich, während eine Schmelze in gerichteter Weise erstarrt wird. Dabei ermöglicht die Erfindung eine wesentliche Vergrößerung des beim Erstarren einer Schmelze wirksamen Temperaturgradienten und erlaubt aufgrund der erreichbaren schnellen Abkühlung die Erzielung besserer Eigenschaften sowie eine hohe Produktivität bei der Serienfertigung von Gußstücken. Auf dieser Grundlage ermöglicht die Erfindung auch die rationelle und serienweise Fertigung von Gußstücken mit deutlich größeren Abmessungen und/oder größeren Trauben von Gußstücken als bisher und erschließt die Anwendung der gerichteten Erstarrung für Komponenten von stationären Gasturbinen mit Nennleistungen bis 200 MW und darüber hinaus, insbesondere für Turbinenschaufeln.With the invention is a largely complete for the first time It is possible to prevent significant heat input into the bathroom, while a melt solidifies in a directed manner becomes. The invention enables substantial enlargement the temperature gradient effective when a melt solidifies and allowed due to the achievable fast Cooling the achievement of better properties as well as a high productivity in the series production of castings. On this basis, the invention also enables the rational and series production of castings with clearly larger dimensions and / or larger bunches of castings than before and opens up the application of directional solidification for components of stationary gas turbines with Power ratings up to 200 MW and beyond, in particular for turbine blades.

Die Deckschicht kann mit relativ geringem Aufwand und kostengünstig erzeugt werden, indem zu ihrer Bildung fließfähige und isolierfähige Festkörper verwendet werden. Als solche Festkörper kommen insbesondere keramische Hohlkörper, vorzugsweise Hohlkugeln, zum Einsatz. Diese Hohlkörper bestehen vorzugsweise aus Aluminiumoxid-Siliziumdioxid-Keramik, insbesondere Mullit, und haben Außendurchmesser zwischen 0,5 mm und 3 mm, vorzugsweise von etwa 1 mm.The cover layer can be done with relatively little effort and inexpensively are generated by flowable to their formation and isolatable solids can be used. As such Solid bodies come in particular ceramic hollow bodies, preferably Hollow balls, for use. These hollow bodies exist preferably made of alumina-silica ceramic, in particular Mullite, and have outer diameters between 0.5 mm and 3 mm, preferably about 1 mm.

Anforderungen an die Materialien, die zur Bildung der Deckschicht in Frage kommen, sind eine geringe Wärmeleitfähigkeit und gute Schwimmfähigkeit auf dem Bad, sowie, zur Gewährleistung der Fließfähigkeit der Deckschicht, eine möglichst geringe Neigung, bei den an der Deckschicht, anliegenden Temperaturen untereinander zu verkleben oder zu versintern. Auch ist bedeutsam, daß die Bestandteile der Deckschicht nicht wesentlich von dem zweiten Metall benetzbar sind, da derart sichergestellt ist, daß das zweite Metall sich nicht in die Deckschicht eingelagert und bis zu der der Heizzone ausgesetzten Oberfläche transportiert wird, wobei mit einer Verdampfung sowie mit Beeinträchtigungen der Isolierfähigkeit und Fließfähigkeit der Deckschicht zu rechnen wäre.Requirements for the materials used to form the top layer are low thermal conductivity and good buoyancy on the bathroom, as well, to ensure the flowability of the top layer, the lowest possible Inclination at the temperatures at the top layer to glue or to sinter together. Also is significant that the components of the top layer are not essential are wettable by the second metal, as this ensures is that the second metal is not in the Cover layer stored and exposed to the heating zone Surface is transported, with evaporation as well as with impairments of the insulation ability and flowability of the top layer would have to be expected.

Ein Werkstoff, der den vorgenannten Anforderungen gerecht wird, ist das erwähnte Mullit, zu verwenden vorzugsweise in Form von Hohlkugeln. Die Deckschicht sollte dabei vorzugsweise eine Schüttung von Kugeln mit übereinstimmenden Außendurchmessern sein, wobei für Außendurchmesser von etwa 1 mm besonders gute Ergebnisse erwartet werden. Die Verwendung von Hohlkugeln mit deutlich größeren Außendurchmessern sowie die Verwendung von Kugeln mit unterschiedlichen Durchmessern werden als weniger günstig betrachtet.A material that meets the aforementioned requirements , the mullite mentioned is to be used preferably in Shape of hollow spheres. The top layer should preferably be used a bed of balls with matching outer diameters be, for outside diameter of about 1 mm particularly good results are expected. The use of Hollow balls with significantly larger outer diameters as well as the Use balls with different diameters considered less favorable.

Neben keramischen Hohlkörpern eignen sich ebenfalls keramische Vollkörper, die eine gute Schwimmfähigkeit auf dem Bad und eine geringe Wärmeleitfähigkeit aufweisen. Als Material für diese Vollkörper, welche bevorzugterweise als Vollkugeln ausgebildet sind, kommen keramische Oxide, wie das erwähnte Mullit, sowie Aluminium-, Magnesium- oder Zirkonoxid in Frage. Bevorzugtermaßen haben die Vollkörper einen Durchmesser zwischen 0,5 mm und 3 mm, vorzugsweise etwa 1 mm. Die Verwendung von Vollkugeln zeichnet sich durch eine besonders gute Raumausnutzung ohne wesentliche Hohlräume zwischen den Vollkugeln aus, wodurch eine gute Wärmeisolierung gegeben ist.In addition to ceramic hollow bodies, ceramic ones are also suitable Full body that has good buoyancy on the bathroom and have low thermal conductivity. As a material for these solid bodies, which are preferably solid spheres are formed, come ceramic oxides, like the one mentioned Mullite, as well as aluminum, magnesium or zirconium oxide in Question. The solid bodies preferably have a diameter between 0.5 mm and 3 mm, preferably about 1 mm. The Use of solid balls is characterized by a special good use of space without significant voids between the Solid balls, which gives good heat insulation is.

Als Alternative zu den Hohlkugeln aus Mullit ist eine Deckschicht in Form einer Schüttung aus Aluminium-, Magnesium- oder Zirkonoxid denkbar, wobei die Schüttung aus Pulverteilchen bestehen sollte, deren Außendurchmesser zwischen einer unteren Grenze von 0,06 mm und einer oberen Grenze von 0,4 mm liegen. Für eine derart ausgebildete Deckschicht kann entsprechendes marktgängiges keramisches Pulver verwendet werden.As an alternative to the hollow balls made of mullite, there is a top layer in the form of a bed of aluminum, magnesium or Zirconium oxide conceivable, the bed of powder particles should exist, the outer diameter between one lower limit of 0.06 mm and an upper limit of 0.4 mm lie. The same can be done for such a cover layer commercially available ceramic powder can be used.

Eine weitere mögliche Alternative ist die Verwendung einer Salzschmelze als Deckschicht.Another possible alternative is to use a Melting salt as a top layer.

Eine bevorzugte Weiterbildung des Verfahrens besteht darin, die Gießform mit der Schmelze zunächst in einer Heizzone auf der ersten Temperatur zu halten und anschließend aus der Heizzone in das Bad einzutauchen, wobei zumindest dann, wenn die Gießform in die Deckschicht eintaucht, die Deckschicht unmittelbar an die Heizzone heranreicht. Der Abstand zwischen der Heizzone und dem Bad muß möglichst klein sein, um einen möglichst großen Temperaturgradienten in der zu erstarrenden Schmelze zu erhalten. Bei einer entsprechenden Anordnung ist außerdem gewährleistet, daß eine besonders günstige Anfangsposition für die Gießform möglich ist. In dieser Anfangsposition taucht eine unter der Gießform befindliche Kühlplatte bereits in das Bad ein, während die noch zu befüllende Gießform etwa mit dem unteren Ende der Heizzone abschließt. So ist beim Eintauchen der Gießform eine besonders hohe anfängliche Erstarrungsgeschwindigkeit erreichbar. Für diese Maßnahme sind mehrere Realisierungsmöglichkeiten denkbar. So kann z. B. ein Tiegel, der das Bad enthält, so groß gemacht werden, daß er bis an die Heizzone heranreicht und über dem Bad bis an die Heizzone mit dem die Deckschicht bildenden Schüttgut gefüllt wird; eine Alternative liegt darin, den Tiegel und eine Heizkammer, in der die Heizzone vorgesehen ist, gegeneinander beweglich auszuführen und vor dem Eintauchen der Gießform in das Bad einander entsprechend anzunähern.A preferred further development of the method consists in the mold with the melt first in a heating zone the first temperature and then from the Immerse the heating zone in the bathroom, at least if the mold dips into the top layer, the top layer directly reaches the heating zone. The distance between the heating zone and the bathroom must be as small as possible to get one temperature gradients as large as possible in the solidified To get melt. With an appropriate arrangement also ensures that a particularly favorable starting position is possible for the mold. In this starting position dips a cooling plate under the mold already in the bath while the mold to be filled ends approximately with the lower end of the heating zone. So is a particularly high initial when immersing the mold Solidification rate achievable. For this measure several implementation options are conceivable. So can e.g. B. made a crucible that contains the bathroom so large be that it reaches up to the heating zone and above the Bath up to the heating zone with the one forming the top layer Bulk goods are filled; an alternative is to use the Crucible and a heating chamber in which the heating zone is provided is to be movable against each other and before immersing Approach the mold in the bathroom accordingly.

Generell wird für die Deckschicht eine Dicke zwischen 30 mm und 50 mm bevorzugt, wobei diese Dicke zumindest während des Eintauchens der Gießform in das Bad gewährleistet sein sollte. Eine solche Dicke wird den Isolierungsanforderungen aufgrund der intensiven Wärmestrahlung, mit der die Deckschicht im Regelfall beaufschlagt wird, in besonderer Weise gerecht.Generally there is a thickness between 30 mm for the top layer and 50 mm preferred, this thickness at least during the Immersion of the mold in the bath should be ensured. Such a thickness is due to the insulation requirements the intense heat radiation with which the top layer is usually acted upon in a special way.

Mit weiterem Vorzug erfolgt die Durchführung des Verfahrens unter Ausschluß von Sauerstoff, vorzugsweise unter Vakuum, zum Zwecke der Vermeidung oxidischer Schlacken auf dem Bad. Dies ist wichtig, um ein durch Schlacken u. U. begünstigtes Verkleben des Schüttgutes in der Deckschicht zu vermeiden. Vor allem dann, wenn als zweites Metall Zinn verwendet wird, wird bevorzugtermaßen die Deckschicht unter einem Vakuum mit einem Restdruck von höchstens 10-3 mbar, weiter bevorzugt von höchstens 10-4 mbar, gehalten. Neben der Vermeidung der Neuentstehung von Oxid aus dem zweiten Metall wird, wenn das zweite Metall Zinn ist oder Zinn enthält, bei einem solchen Vakuum auch die Zersetzung eventuell bereits vorliegenden Zinnoxids und damit eine Reinigung des Bades und der Deckschicht erreicht. Dieser Effekt beruht auf der chemischen Instabilität und entsprechender Neigung zur Zersetzung des Zinnoxids bei den für das Bad üblicherweise in Frage kommenden Temperaturen; wird durch Bereitstellung eines hinreichend guten Vakuums die Abfuhr des bei der Zersetzung anfallenden Sauerstoffs gesichert, so kann eventuell vorliegendes Zinnoxid vollständig beseitigt werden. The process is more preferably carried out in the absence of oxygen, preferably under vacuum, for the purpose of avoiding oxidic slags in the bath. This is important in order to avoid To avoid favored sticking of the bulk material in the top layer. Especially when tin is used as the second metal, the cover layer is preferably kept under a vacuum with a residual pressure of at most 10 -3 mbar, more preferably of at most 10 -4 mbar. In addition to avoiding the new formation of oxide from the second metal, if the second metal is tin or contains tin, the decomposition of any tin oxide which may already be present and thus a cleaning of the bath and the top layer is achieved with such a vacuum. This effect is based on the chemical instability and corresponding tendency to decompose the tin oxide at the temperatures that are usually suitable for the bath; If the removal of the oxygen resulting from the decomposition is ensured by providing a sufficiently good vacuum, any tin oxide that may be present can be completely eliminated.

Das Verfahren jedweder Ausgestaltung findet vorzugsweise Verwendung zum gerichteten Erstarren eines ersten Metalls in Form einer Nickelbasis- oder Kobaltbasis-Legierung, insbesondere einer Superlegierung, wie sie im Zusammenhang mit Turbinenschaufeln für Gasturbinen üblicherweise in Betracht gezogen wird.The method of any configuration is preferably used for directional solidification of a first metal in Form of a nickel-based or cobalt-based alloy, in particular a super alloy, such as those used in connection with turbine blades commonly considered for gas turbines becomes.

Das zweite Metall, welches das Bad bildet, ist vorzugsweise Aluminium oder Zinn, wobei dem Zinn ein besonderer Vorzug gebührt. Unter Verwendung von Zinn kann das Bad auf einer zweiten Temperatur unterhalb von 500 °C, vorzugsweise bei etwa 300 °C, gehalten werden, und somit ist eine besonders hohe Temperaturdifferenz zwischen dem Schmelzpunkt des ersten Metalls und der Temperatur des Bades möglich. Eine möglichst niedrige zweite Temperatur bewirkt außerdem eine Verringerung der Gefahr, daß das zweite Metall in nennenswertem Umfang verdampft.The second metal that forms the bath is preferred Aluminum or tin, with tin being particularly preferred. Using tin, the bath can be done on a second Temperature below 500 ° C, preferably at about 300 ° C, are kept, and is therefore a particularly high Temperature difference between the melting point of the first metal and the temperature of the bath possible. One if possible low second temperature also causes a decrease the risk that the second metal to a significant extent evaporates.

Mit dem Verfahren jedweder Ausgestaltung wird insbesondere durch gerichtetes Erstarren der Schmelze eine Komponente für eine Gasturbine, insbesondere eine Turbinenschaufel, erzeugt.With the method of any configuration in particular by directional solidification of the melt a component for a gas turbine, in particular a turbine blade, is generated.

Zur Lösung der der Erfindung im Hinblick auf eine Vorrichtung zugrundeliegenden Aufgabe wird eine Vorrichtung zur Herstellung einer Gasturbinenschaufel mittels gerichtetem Erstarren einer Schmelze eines ersten Metalls in einer Gießform angegeben, umfassend eine Heizkammer, welche eine Heizzone zur Warmhaltung der Schmelze und der Gießform auf einer ersten Temperatur oberhalb des Schmelzpunktes des ersten Metalls, einen unterhalb der Heizkammer angeordneten Tiegel mit einem Bad aus einem flüssigen zweiten Metall, welches sich auf einer zweiten Temperatur befindet, die unterhalb des Schmelzpunktes des ersten Metalls liegt, sowie eine Fahreinrichtung zur Bewegung der Gießform aus der Heizzone in das Bad, wobei das Bad bedeckt ist von einer schwimmenden, fließfähigen und von der Gießform durchdringbaren Deckschicht aus einem wärmeisolierenden Schüttgut.To solve the invention with regard to a device underlying task is a device for manufacturing a gas turbine blade by directional solidification a melt of a first metal in a casting mold, comprising a heating chamber which a heating zone for Keeping the melt and the casting mold warm on a first Temperature above the melting point of the first metal, a crucible arranged below the heating chamber with a Bath from a liquid second metal, which is on a second temperature is below the melting point of the first metal, as well as a driving device to move the mold from the heating zone into the bathroom, whereby the bath is covered by a floating, flowable and of the casting mold penetrable cover layer of a heat insulating Bulk goods.

Hinsichtlich der Vorteile, die diese erfindungsgemäße Vorrichtung bietet, gelten alle zu dem erfindungsgemäßen Verfahren gemachten Ausführungen, von deren Wiederholung an dieser Stelle abgesehen wird.With regard to the advantages of this device according to the invention offers, all apply to the inventive method statements made, from their repetition on this Place is disregarded.

Wie bereits ausgeführt, sind die Heizkammer und der Tiegel vorzugsweise gegeneinander bewegbar, um zur gerichteten Erstarrung der Schmelze in der Gießform die Heizzone in der Heizkammer und die Deckschicht in dem Tiegel in eine gewünschte enge räumliche Beziehung zueinander bringen zu können.As already stated, the heating chamber and the crucible are preferably movable against each other in order to solidify the melt in the mold the heating zone in the Heating chamber and the top layer in the crucible in a desired to bring close spatial relationship to each other.

Ebenfalls ist es bevorzugt, die Deckschicht in der Vorrichtung seitlich zu umgrenzen von einem auf dem Bad schwimmenden und durch den Auftrieb dichtend gegen die Heizkammer gepreßten Ring. Ein dichtendes Anliegen des Rings an der Unterseite der Heizkammer kann ermöglicht sein durch die vorstehend beschriebene Ausführung, bei der die Heizkammer und der Tiegel gegeneinander bewegbar sind. Der Ring trägt wesentlich dazu bei, die Deckschicht gegenüber der Heizzone und der Oberfläche des Bades zu fixieren, wobei ein Austreten von Wärmestrahlung aus der Heizkammer in Richtung des Bades zuverlässig verhindert werden kann. Damit ist auch gewährleistet, daß die Deckschicht unmittelbar mit der hohen Temperatur der Heizzone beaufschlagt und somit innerhalb der Deckschicht ein besonders hoher Temperaturgradient erreicht wird. Der Ring kann gegebenenfalls begleitet sein von einem geeignet ausgebildeten Überlauf an dem Tiegel, über den das zweite Metall aus dem Bad entweichen kann, wenn eine Gießform eingetaucht wird. Die Frage, ob ein Überlauf vonnöten ist, ist selbstverständlich in jedem Einzelfall unter Berücksichtigung aller Gegebenheiten, insbesondere der Geometrie des Bades und des jeweils von einer Gießform zu verdrängenden Volumens zu entscheiden. It is also preferred to have the cover layer in the device bounded laterally by a floating on the bathroom and pressed against the heating chamber by the buoyancy Ring. A sealing contact of the ring on the underside the heating chamber can be made possible by the one described above Version in which the heating chamber and the crucible are movable against each other. The ring contributes significantly to this at, the top layer opposite the heating zone and the surface fix the bath, causing an escape of heat radiation reliably from the heating chamber towards the bathroom can be prevented. This also ensures that the top layer immediately with the high temperature of the Heating zone applied and thus within the top layer particularly high temperature gradient is achieved. The ring can be accompanied by a suitably trained person if necessary Overflow on the crucible over which the second metal can escape from the bath when a mold is immersed becomes. The question of whether an overflow is necessary is self-evident in each individual case taking into account all Conditions, in particular the geometry of the bathroom and the to decide in each case from a mold to be displaced.

Hinsichtlich der Bildung der Deckschicht mit Schüttgut aus von dem zweiten Metall nicht benetzbaren Festkörpern, insbesondere keramischen Hohlkörpern aus Mullit oder dergleichen oder pulverförmigen Zubereitungen aus Aluminium-, Magnesium- oder Zirkonoxid, jeweils mit bestimmten Abmessungen, sei auf die obigen Ausführungen zu entsprechenden Weiterbildungen des erfindungsgemäßen Verfahrens verwiesen.With regard to the formation of the top layer with bulk material solid bodies that are not wettable by the second metal, in particular ceramic hollow bodies made of mullite or the like or powdered preparations made of aluminum, magnesium or Zirconium oxide, each with certain dimensions, is on the above statements on corresponding further developments of referenced method according to the invention.

Die Deckschicht ist vorzugsweise so ausgeführt und angeordnet, daß der Abstand zwischen der Heizzone und der Oberfläche des Bades möglichst klein ist, um einen möglichst großen Temperaturgradienten zu erzeugen.The cover layer is preferably designed and arranged in such a way that that the distance between the heating zone and the surface of the bath is as small as possible in order to achieve the largest possible temperature gradient to create.

Vorzugsweise hat die Deckschicht eine Dicke zwischen 30 mm und 50 mm, um eine ausreichende Wärmeisolierung zu gewährleisten.The cover layer preferably has a thickness of between 30 mm and 50 mm to ensure adequate thermal insulation.

Die Vorrichtung ist mit weiterem Vorzug umschlossen von einem evakuierbaren und/oder mit einem Schutzgas befüllbaren Schutzgefäß. Dadurch kann die Einwirkung schädlicher Gase wie z. B. Sauerstoff auf das erste Metall oder das zweite Metall oder, durch Bildung eines Vakuums in dem Schutzgefäß, die Ausbreitung von Wärme durch Konvektion verhindert werden. In diesem Zusammenhang sei unter Vakuum eine Atmosphäre verstanden, die einen Wert von 10-3 mbar nicht überschreitet, vorzugsweise unter 10-4 mbar liegt. Die Temperatur im Inneren des Schutzgefäßes kann auf einem Wert bis zu 300 °C liegen, was insbesondere auch sicherstellt, daß organische Ablagerungen durch den zur Aufrechterhaltung des Vakuums erforderlichen Pumpprozeß entfernt werden und weder die Vorrichtung noch die darin befindlichen flüssigen Metalle beeinträchtigen können. Ausführungsbeispiele der Erfindung gehen aus der Zeichnung hervor. Zur Verdeutlichung spezifischer Einzelheiten ist die Zeichnung nicht maßstabsgetreu und gegebenenfalls leicht verzerrt ausgeführt. Im einzelnen zeigen:

  • FIG 1 einen vertikalen Schnitt durch eine erfindungsgemäße Vorrichtung mit einer Gießform, die eine abzukühlende Schmelze enthält;
  • FIG 2 und FIG 3 Ansichten des Bades mit jeweils einem Ausführungsbeispiel für die Deckschicht.
  • FIG 4 eine gerichtet erstarrte Turbinenschaufel mit stengelkristallinem Gefüge.
  • The device is more preferably enclosed by an evacuable and / or protective gas tank. This can cause the action of harmful gases such. B. oxygen on the first metal or the second metal or, by forming a vacuum in the protective vessel, the spread of heat can be prevented by convection. In this context, vacuum is understood to mean an atmosphere which does not exceed a value of 10 -3 mbar, preferably less than 10 -4 mbar. The temperature inside the protective vessel can be up to 300 ° C, which in particular also ensures that organic deposits are removed by the pumping process required to maintain the vacuum and can neither affect the device nor the liquid metals contained therein. Embodiments of the invention are evident from the drawing. In order to clarify specific details, the drawing is not true to scale and may be slightly distorted. In detail show:
  • 1 shows a vertical section through a device according to the invention with a casting mold which contains a melt to be cooled;
  • 2 and 3 show views of the bath, each with an embodiment for the cover layer.
  • 4 shows a directionally solidified turbine blade with a crystalline structure.
  • Figur 1 zeigt eine Schmelze 1 eines ersten Metalls in einer Gießform 2, welche zum Zwecke der Abkühlung in ein Bad 3 eines flüssigen zweiten Metalls, welches sich auf einer zweiten Temperatur befindet, die wesentlich geringer ist als die erste Temperatur der Schmelze 1, einzutauchen ist. Als zweites Metall findet vorzugsweise Zinn Verwendung, wobei die zweite Temperatur auf einen Wert unterhalb von 300° C, selbstverständlich jedoch oberhalb des Schmelzpunktes des Zinns bei 254° C, eingestellt wird. Das Bad 3 ist abgedeckt von einer Deckschicht 4, die aus einem fließfähigen, wärmeisolierenden Schüttgut 5, 6 (vgl. hierzu Figuren 2 und 3) abgedeckt ist. Die Deckschicht 4 hat die Aufgabe, einen Wärmeeintrag aus der Heizzone 7, in der die Gießform 2 mit der Schmelze 1 zunächst gehalten wird und die sich auf einer sehr hohen ersten Temperatur, insbesondere um 1600° C, befindet, in das Bad 3 zu verhindern, so daß sich im Inneren der Deckschicht 4 ein möglichst hohes Temperaturgefälle, entsprechend einem besonders hohen Temperaturgradienten, einstellt. Aufgrund des Wärmeein_ trags in die Schmelze 1 und die Gießform 2 in der Heizzone 7 und aufgrund des Wärmeaustrags aus der Schmelze 1 und der Gießform 2 in dem Bad 3 stellt sich in der Schmelze 1 in dem Bereich, wo sie die Deckschicht 4 durchquert, ebenfalls ein hoher Temperaturgradient ein, welcher ein gerichtetes Erstarren der Schmelze 1 zu einem Werkstück oder mehreren Werkstücken, insbesondere einer Turbinenschaufel 8 (vgl. Figur 4), mit stengelkristallinem oder einkristallinem Gefüge bewirkt. Die Heizzone 7 befindet sich in einer Heizkammer 9, die auf einen Tiegel 10 aufgesetzt ist, welcher das Bad 3 enthält. In das Innere der Heizkammer 9 ragt eine Fahreinrichtung 11, symbolisiert durch ein Haltegestell 11, mit der bzw. mit dem die Gießform 2 verfahrbar und insbesondere aus der Heizzone 7 in das Bad 3 eintauchbar ist. Eine Abdichtung des Bades 3, und damit verbunden eine gewünschte Positionierung des Bades 3 und der Deckschicht 4 relativ zur Heizzone 7, wird erreicht mittels eines auf dem Bad 3 schwimmenden und die Deckschicht 4 umgrenzenden Rings 12. Die ganze Vorrichtung ist umschlossen von einem schematisch angedeuteten Schutzgefäß 13, insbesondere zu dem Zweck, Sauerstoff, welcher das Bad 3 oder die Schmelze 1 oxidieren könnte, aus der Vorrichtung fernzuhalten. Zu diesem Zweck kann das Schutzgefäß 13 evakuiert und/oder mit einem geeigneten Schutzgas, wie z.B. Argon, befüllt werden.Figure 1 shows a melt 1 of a first metal in a Casting mold 2, which is used for cooling in a bath 3 a liquid second metal, which is on a second Temperature is much lower than the first Temperature of the melt 1, is immersed. As a second Metal is preferably used in tin, the second Temperature to a value below 300 ° C, of course however above the melting point of the tin at 254 ° C, is set. The bathroom 3 is covered by one Cover layer 4, which consists of a flowable, heat-insulating Bulk material 5, 6 (see FIGS. 2 and 3) is covered. The covering layer 4 has the task of introducing heat from the Heating zone 7, in which the mold 2 with the melt 1 initially is kept and which is at a very high first temperature, in particular around 1600 ° C, in the bath 3 too prevent so that in the interior of the cover layer 4 as possible high temperature gradient, corresponding to a particular one high temperature gradients. Because of the heat into the melt 1 and the mold 2 in the heating zone 7 and due to the heat output from the melt 1 and Casting mold 2 in the bath 3 turns into the melt 1 in the Area where it crosses the top layer 4, also high temperature gradient, which is a directed solidification the melt 1 to a workpiece or several workpieces, in particular a turbine blade 8 (see FIG. 4), with a crystalline or single crystal structure. The heating zone 7 is located in a heating chamber 9 which a crucible 10 is placed, which contains the bath 3. In the interior of the heating chamber 9 protrudes a driving device 11, symbolized by a holding frame 11, with or with the the mold 2 is movable and in particular from the heating zone 7 is immersed in the bath 3. Sealing the bath 3, and associated with this a desired positioning of the bath 3 and the cover layer 4 relative to the heating zone 7 is reached by means of a floating on the bath 3 and the top layer 4 surrounding ring 12. The whole device is enclosed of a schematically indicated protective vessel 13, in particular for the purpose of oxygen, which is the bath 3 or the Oxidize melt 1 could keep away from the device. For this purpose, the protective vessel 13 can be evacuated and / or with a suitable protective gas, e.g. Argon, filled become.

    Die Gießform 2 ruht auf einer Kühlplatte 14, die auch dann teilweise in das Bad 3 eintauchen soll, wenn die Gießform 2 selbst dies nicht tut. Dies dient dazu, den unteren Bereich der Gießform 2 gegebenenfalls bereits vor dem Eingießen der Schmelze 1 abzukühlen, um für die gerichtete Erstarrung der Schmelze 1, welche durch langsames Eintauchen der Gießform 2 in das Bad 3 bewerkstelligt wird, eine geeignete anfängliche Temperaturverteilung sicherzustellen. Die Kühlplatte 14 kann gegebenenfalls entfallen. In der Heizzone 7 vertikal übereinander angeordnet sind mehrere Heizelemente 15, beispielsweise Widerstandsheizelemente, induktiv wirkende Suszeptoren oder dergleichen, und die Heizkammer 9 ist ausgekleidet mit einer Isolierauskleidung 16. Abgedeckt ist die Heizkammer 9 mit einem Deckel 17, der einen entsprechenden Durchlaß für das Haltegestell 11 aufweist. Zwischen den Heizelementen 15 angeordnet sind Isolierringe 18, die es je nach Größe und Gestalt der Gießform 2 gegebenenfalls gestatten, eines oder mehrere der Heizelemente 15, beginnend von oben, unbenutzt zu lassen oder in der jeweils erzeugten Heizleistung im Hinblick auf eine gewünschte Verteilung der Temperatur anzupassen.The mold 2 rests on a cooling plate 14, which then partially immersed in the bath 3 when the mold 2 itself doesn't. This serves the bottom area the mold 2, if necessary, even before pouring the Cool melt 1 in order for the directional solidification of the Melt 1, which by slowly immersing the mold 2 is accomplished in the bath 3, a suitable initial Ensure temperature distribution. The cooling plate 14 can possibly omitted. In the heating zone 7 vertically one above the other several heating elements 15 are arranged, for example Resistance heating elements, inductively acting susceptors or the like, and the heating chamber 9 is lined with a Insulating lining 16. The heating chamber 9 is covered with a Cover 17, the corresponding passage for the support frame 11 has. Arranged between the heating elements 15 are insulating rings 18, depending on the size and shape if necessary allow the mold 2, one or more the heating elements 15, starting from above, to be left unused or in terms of the heating power generated in each case to adjust a desired distribution of the temperature.

    Figur 2 und Figur 3 zeigen Ausführungsbeispiele für die Deckschicht 4 auf dem Bad 3. Die besonders bevorzugte Ausführung gemäß Figur 3 zeigt eine Deckschicht 4, gebildet aus keramischen Hohlkugeln 5. Wie bereits erläutert, sind solche Hohlkugeln 5 aufgrund ihrer guten Schwimmfähigkeit für den angestrebten Zweck besonders geeignet. Ein geeigneter Werkstoff für diese Hohlkugeln ist die Siliziumdioxid-Aluminiumoxid-Keramik Mullit. Diese Keramik wird auch nicht von Metallen wie Zinn und Aluminium benetzt und kann somit eine besonders gute Abschirmung des üblicherweise höchstens 500° C, vorzugsweise höchstens 300° C, heißen Bades 3 gegen die Heizzone 7, von der eine Wärmestrahlung ausgeht, die einer Temperatur der Größenordnung von 1600° C entsprechen kann, bewirken. Es versteht sich, daß die Deckschicht 4 so dick sein muß, daß sie diese Wärmestrahlung weitgehend vollständig abschirmt, daß sie, mit anderen Worten gesagt, für Wärmestrahlung "optisch dicht" ist.Figure 2 and Figure 3 show embodiments of the cover layer 4 on the bathroom 3. The particularly preferred version 3 shows a cover layer 4 formed from ceramic Hollow balls 5. As already explained, such hollow balls are 5 due to their good buoyancy for the aimed Purpose particularly suitable. A suitable material for these hollow spheres is the silicon dioxide-aluminum oxide ceramic Mullite. This ceramic is also not like metals Tin and aluminum wetted and can therefore be a particularly good one Shielding of usually at most 500 ° C, preferably at most 300 ° C, hot bath 3 against the heating zone 7, of which emits heat radiation that corresponds to a temperature of Order of magnitude of 1600 ° C. It understands themselves that the cover layer 4 must be so thick that it this heat radiation largely completely shields that in other words, they are "optically" for heat radiation is tight ".

    Gemäß Figur 3 besteht die Deckschicht aus pulvrigem Schüttgut mit Pulverteilchen 6. Als Werkstoff für solches Schüttgut kommen Aluminiumoxid, Magnesiumoxid und Zirkonoxid in Frage, wobei gegebenenfalls marktgängige pulvrige Zubereitungen dieser Oxide verwendet werden können. Zu vorteilhaften Dimensionierungen sei auf die entsprechenden obigen Ausführungen verwiesen.According to FIG. 3, the cover layer consists of powdery bulk material with powder particles 6. As a material for such bulk goods aluminum oxide, magnesium oxide and zirconium oxide are possible, where appropriate, commercially available powdery preparations of these Oxides can be used. To advantageous dimensions please refer to the corresponding statements above.

    Figur 4 zeigt eine Turbinenschaufel 8, die durch gerichtetes Erstarren einer Schmelze 1, wie dargestellt in Figur 1, erhalten wird. Das stengelkristalline Gefüge 19, das an der Oberfläche einer Turbinenschaufel 8 in aller Regel deutlich sichtbar ist, ist dargestellt durch entsprechende Linien. Dieses Gefüge 19 vermag die Belastbarkeit der Turbinenschaufel 8 gegenüber einer konventionell gegossenen Turbinenschaufel deutlich zu verbessern, wenn es entlang derjenigen Richtung 20 ausgerichtet ist, entlang derer die Turbinenschaufel 8 hauptsächlich belastet wird. Diese Richtung 20 ist die Längsachse 20, entlang derer unter betrieblicher Belastung Zentrifugalkräfte sowie die wesentlichen Wärmedehnungen gerichtet sind. Der übliche Aufbau der Turbinenschaufel 8 ist ansatzweise angedeutet: sie besitzt einen (nur teilweise sichtbaren) Blatteil 21, der das funktionell wesentliche Teil ist, und einen Fußteil 22, an dem sie zu befestigen ist.FIG. 4 shows a turbine blade 8 which is directed through Solidification of a melt 1, as shown in Figure 1, obtained becomes. The columnar crystalline structure 19, which on the Surface of a turbine blade 8 is usually clear is visible, is represented by corresponding lines. This structure 19 is capable of withstanding the strength of the turbine blade 8 compared to a conventionally cast turbine blade improve significantly if it's along that direction 20 is aligned along which the turbine blade 8 is mainly charged. This direction 20 is the Longitudinal axis 20, along which under operational load Centrifugal forces and the essential thermal expansions directed are. The usual structure of the turbine blade 8 is to begin with: it has one (only partially visible) leaf part 21, which is the functionally essential part and a foot portion 22 to which it is to be attached.

    Claims (25)

    Verfahren zur Herstellung einer Gasturbinenschaufel mittels gerichtetem Erstarren einer Schmelze (1) eines ersten Metalls in einer Gießform (2), umfassend Bereitstellung der Schmelze (1) in der Gießform (2) auf einer ersten Temperatur oberhalb des Schmelzpunktes des ersten Metalls und anschließendes Abkühlen der Schmelze (1) in der Gießform (2) durch Eintauchen der Gießform (2) in ein Bad (3) aus einem flüssigen zweiten Metall, welches sich auf einer zweiten Temperatur befindet, die unterhalb des Schmelzpunktes des ersten Metalls liegt,
    wobei das Bad (3) bedeckt ist von einer schwimmenden, fließfähigen Deckschicht (4) aus einem wärmeisolierenden Schüttgut (5, 6) und die Gießform (2) mit der Schmelze (1) durch die Deckschicht (4) hindurch in das Bad (3) eingetaucht wird.
    A method for producing a gas turbine blade by directional solidification of a melt (1) of a first metal in a casting mold (2), comprising providing the melt (1) in the casting mold (2) at a first temperature above the melting point of the first metal and then cooling the Melt (1) in the casting mold (2) by immersing the casting mold (2) in a bath (3) made of a liquid second metal which is at a second temperature which is below the melting point of the first metal,
    The bath (3) is covered by a floating, flowable cover layer (4) made of a heat-insulating bulk material (5, 6) and the casting mold (2) with the melt (1) through the cover layer (4) into the bath (3 ) is immersed.
    Verfahren nach Anspruch 1, bei dem die Deckschicht (4) aus von dem zweiten Metall nicht benetzbaren Festkörpern (5, 6) besteht.The method of claim 1, wherein the cover layer (4) solid bodies (5, 6) that cannot be wetted by the second metal consists. Verfahren nach Anspruch 2, bei dem die Festkörper (5, 6) keramische Hohlkörper (5), insbesondere Hohlkugeln (5), sind.The method of claim 2, wherein the solids (5, 6) ceramic hollow bodies (5), in particular hollow spheres (5). Verfahren nach Anspruch 3, bei dem die Hohlkörper (5) aus Mullit bestehen und Außendurchmesser zwischen 0,5 mm und 3 mm, vorzugsweise von etwa 1 mm, haben.The method of claim 3, wherein the hollow body (5) Mullite exist and outside diameter between 0.5 mm and 3 mm, preferably of about 1 mm. Verfahren nach Anspruch 2, bei dem die Festkörper (5, 6) keramische Vollkörper (5), insbesondere Vollkugeln (5), sind.The method of claim 2, wherein the solids (5, 6) full ceramic bodies (5), in particular full spheres (5). Verfahren nach Anspruch 5, bei dem die Vollkörper (5) einen Durchmesser zwischen 0,5 mm und 3 mm, vorzugsweise von etwa 1 mm, haben. The method of claim 5, wherein the solid body (5) one Diameter between 0.5 mm and 3 mm, preferably from about 1 mm. Verfahren nach Anspruch 5 oder 6, bei dem die Vollkörper (5) aus Mullit, Aluminium-, Magnesium- oder Zirkonoxid bestehen.The method of claim 5 or 6, wherein the full body (5) consist of mullite, aluminum, magnesium or zirconium oxide. Verfahren nach Anspruch 2, bei dem die Festkörper (5, 6) Pulverteilchen (6) aus Aluminium-, Magnesium- oder Zirkonoxid mit Außendurchmessern zwischen 0,06 mm und 0,4 mm sind.The method of claim 2, wherein the solids (5, 6) Powder particles (6) made of aluminum, magnesium or zirconium oxide with outside diameters between 0.06 mm and 0.4 mm. Verfahren nach einem der vorhergehenden Ansprüche, bei dem die Gießform (2) mit der Schmelze (1) zunächst in einer Heizzone (7) auf der ersten Temperatur gehalten und anschließend aus der Heizzone (7) in das Bad (3) eingetaucht wird, wobei zumindest dann, wenn die Gießform (2) in die Deckschicht (4) eintaucht, die Deckschicht (4) unmittelbar an die Heizzone (7) heranreicht.Method according to one of the preceding claims, in which the mold (2) with the melt (1) first in a heating zone (7) kept at the first temperature and then from the heating zone (7) is immersed in the bath (3), wherein at least when the casting mold (2) in the cover layer (4) immersed, the cover layer (4) directly to the heating zone (7) reaches. Verfahren nach einem der vorhergehenden Ansprüche, bei dem die Deckschicht (4) während des Eintauchens der Gießform (2) in das Bad (3) eine Dicke zwischen 30 mm und 50 mm hat.Method according to one of the preceding claims, which the cover layer (4) during the immersion of the mold (2) in the bath (3) has a thickness between 30 mm and 50 mm. Verfahren nach einem der vorhergehenden Ansprüche, welches zur Vermeidung der Entstehung und/oder Beseitigung oxidischer Schlacken auf dem Bad (3) unter Ausschluß von Sauerstoff, vorzugsweise unter Vakuum, durchgeführt wird.Method according to one of the preceding claims, which to avoid the formation and / or elimination of oxidic Slags on the bath (3) in the absence of oxygen, preferably under vacuum. Verfahren nach Anspruch 11, bei dem die Deckschicht (4) unter einem Vakuum mit einem Restdruck von höchstens 10-3 mbar, vorzugsweise höchstens 10-4 mbar, gehalten wird.Method according to Claim 11, in which the cover layer (4) is held under a vacuum with a residual pressure of at most 10 -3 mbar, preferably at most 10 -4 mbar. Verfahren nach einem der vorhergehenden Ansprüche, bei dem das erste Metall eine Nickelbasis- oder Kobaltbasis-Legierung, insbesondere eine Superlegierung, ist.Method according to one of the preceding claims, which the first metal is a nickel-based or cobalt-based alloy, especially a superalloy. Verfahren nach einem der vorhergehenden Ansprüche, bei dem das zweite Metall Aluminium oder Zinn, vorzugsweise Zinn, ist. Method according to one of the preceding claims, the second metal is aluminum or tin, preferably tin, is. Verfahren nach Anspruch 14, bei dem das zweite Metall Zinn ist und die zweite Temperatur unterhalb von 500°C, vorzugsweise unterhalb von 300°C, liegt.The method of claim 14, wherein the second metal Tin and the second temperature is below 500 ° C, preferably below 300 ° C. Vorrichtung zur Herstellung einer Gasturbinenschaufel mittels gerichtetem Erstarren einer Schmelze (1) eines ersten Metalls in einer Gießform (2), umfassend eine Heizkammer (9), welche eine Heizzone (7) zur Warmhaltung der Schmelze (1) und der Gießform (2) auf eine erste Temperatur oberhalb des Schmelzpunktes des ersten Metalls, einen unterhalb der Heizkammer (9) angeordneten Tiegel (10) mit einem Bad (3) aus einem flüssigen zweiten Metall, welches sich auf einer zweiten Temperatur befindet, die unterhalb des Schmelzpunktes des ersten Metalls liegt, sowie eine Fahreinrichtung (11) zur Bewegung der Gießform (2) aus der Heizzone (7) in das Bad (3), wobei das Bad (3) bedeckt ist von einer schwimmenden, fließfähigen und von der Gießform (2) durchdringbaren Deckschicht (4) aus einem wärmeisolierenden Schüttgut (5, 6).Device for producing a gas turbine blade by means of directional solidification of a melt (1) of a first one Metal in a casting mold (2), comprising a heating chamber (9), which a heating zone (7) for keeping the melt (1) and the mold (2) to a first temperature above the Melting point of the first metal, one below the heating chamber (9) arranged crucible (10) with a bath (3) from a liquid second metal, which is on a second Temperature is below the melting point of the first metal, and a driving device (11) for movement the casting mold (2) from the heating zone (7) into the bath (3), the bath (3) being covered by a floating, flowable and of the casting mold (2) penetrable cover layer (4) from a heat-insulating bulk material (5, 6). Vorrichtung nach Anspruch 16, bei der die Heizkammer (9) und der Tiegel (10) gegeneinander bewegbar sind.Apparatus according to claim 16, wherein the heating chamber (9) and the crucible (10) can be moved relative to one another. Vorrichtung nach Anspruch 16 oder 17, bei der die Deckschicht (4) seitlich umgrenzt wird von einem auf dem Bad (3) schwimmenden und dichtend gegen die Heizkammer (9) preßbaren Ring (12).Apparatus according to claim 16 or 17, wherein the cover layer (4) is laterally bordered by one on the bathroom (3) floating and sealing against the heating chamber (9) can be pressed Ring (12). Vorrichtung nach einem der Ansprüche 16 bis 18, bei der die Deckschicht aus von dem zweiten Metall nicht benetzbaren Festkörpern (5, 6) besteht.Device according to one of claims 16 to 18, wherein the cover layer made of non-wettable by the second metal Solids (5, 6). Vorrichtung nach Anspruch 19, bei der die Festkörper (5, 6) keramische Hohlkörper (5), insbesondere Hohlkugeln (5), sind. Device according to Claim 19, in which the solid bodies (5, 6) ceramic hollow bodies (5), in particular hollow spheres (5), are. Vorrichtung nach Anspruch 20, bei der die Hohlkörper (5) aus Mullit bestehen und Außendurchmesser zwischen 0,5 mm und 3 mm, vorzugsweise von etwa 1 mm, haben.Device according to Claim 20, in which the hollow bodies (5) are made of mullite and have an outside diameter between 0.5 mm and 3 mm, preferably of about 1 mm. Vorrichtung nach Anspruch 19, bei dem die Festkörper (5, 6) Körner (6) aus Aluminium-, Magnesium- oder Zirkonoxid mit Außendurchmessern zwischen 0,06 mm und 0,4 mm sind.Device according to Claim 19, in which the solid bodies (5, 6) Grains (6) made of aluminum, magnesium or zirconium oxide Outside diameters are between 0.06 mm and 0.4 mm. Vorrichtung nach einem der Ansprüche 16 bis 22, bei der die Deckschicht (4) bis an die Heizkammer (9) heranreicht.Device according to one of claims 16 to 22, wherein the cover layer (4) reaches up to the heating chamber (9). Vorrichtung nach einem der Ansprüche 16 bis 23, bei der die Deckschicht (4) eine Dicke zwischen 30 mm und 50 mm hat.Device according to one of claims 16 to 23, wherein the cover layer (4) has a thickness between 30 mm and 50 mm. Vorrichtung nach einem der Ansprüche 16 bis 24, welche von einem evakuierbaren und/oder mit einem Schutzgas befüllbaren Schutzgefäß (13) umschlossen ist.Device according to one of claims 16 to 24, which from an evacuable and / or fillable with a protective gas Protective vessel (13) is enclosed.
    EP00104497A 1994-08-08 1995-08-07 Method for producing a gas turbine blade by means of directional solidification of a melt Expired - Lifetime EP1020245B1 (en)

    Applications Claiming Priority (3)

    Application Number Priority Date Filing Date Title
    WOPCT/DE94/00914 1994-08-08
    DE9400914 1994-08-08
    EP95927640A EP0775030B1 (en) 1994-08-08 1995-08-07 Method and device for directionally solidifiying a melt

    Related Parent Applications (1)

    Application Number Title Priority Date Filing Date
    EP95927640A Division EP0775030B1 (en) 1994-08-08 1995-08-07 Method and device for directionally solidifiying a melt

    Publications (3)

    Publication Number Publication Date
    EP1020245A2 true EP1020245A2 (en) 2000-07-19
    EP1020245A3 EP1020245A3 (en) 2000-08-09
    EP1020245B1 EP1020245B1 (en) 2001-11-07

    Family

    ID=6903461

    Family Applications (2)

    Application Number Title Priority Date Filing Date
    EP00104497A Expired - Lifetime EP1020245B1 (en) 1994-08-08 1995-08-07 Method for producing a gas turbine blade by means of directional solidification of a melt
    EP95927640A Expired - Lifetime EP0775030B1 (en) 1994-08-08 1995-08-07 Method and device for directionally solidifiying a melt

    Family Applications After (1)

    Application Number Title Priority Date Filing Date
    EP95927640A Expired - Lifetime EP0775030B1 (en) 1994-08-08 1995-08-07 Method and device for directionally solidifiying a melt

    Country Status (11)

    Country Link
    EP (2) EP1020245B1 (en)
    JP (1) JP3493027B2 (en)
    KR (1) KR970704537A (en)
    CN (1) CN1104982C (en)
    CZ (1) CZ291584B6 (en)
    DE (2) DE59509230D1 (en)
    DK (1) DK0775030T3 (en)
    ES (1) ES2157336T3 (en)
    RU (1) RU2146184C1 (en)
    UA (1) UA39902C2 (en)
    WO (1) WO1996005006A1 (en)

    Families Citing this family (21)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    US5676191A (en) * 1996-06-27 1997-10-14 General Electric Company Solidification of an article extension from a melt using an integral mandrel and ceramic mold
    WO1998005450A1 (en) * 1996-08-06 1998-02-12 Siemens Aktiengesellschaft Process and device for directed solidification of a melt
    DE19647313A1 (en) * 1996-11-13 1998-05-14 Siemens Ag Method and device for the directional solidification of a melt
    US6557618B1 (en) 1997-09-12 2003-05-06 General Electric Company Apparatus and method for producing castings with directional and single crystal structure and the article according to the method
    US6446700B1 (en) * 1999-07-19 2002-09-10 General Electric Company Floating insulating baffle for high gradient casting
    US6311760B1 (en) * 1999-08-13 2001-11-06 Asea Brown Boveri Ag Method and apparatus for casting directionally solidified article
    CN1295050C (en) * 2002-03-11 2007-01-17 陈晴祺 Costing method for continuously heating casting liguor in pouring process
    CN100406161C (en) * 2005-04-29 2008-07-30 中国科学院金属研究所 Oriented freezing cast method
    WO2007012338A1 (en) 2005-07-22 2007-02-01 Siemens Aktiengesellschaft Method of repairing a component comprising a directed microstructure, by setting a temperature gradient during exposure to the laser heat; a component produced by such a method
    US20100147481A1 (en) * 2008-12-15 2010-06-17 General Electric Company Methods of manufacturing casted articles, and systems
    CN102069176B (en) * 2009-11-25 2012-10-03 中国科学院金属研究所 Liquid metal cooling directional solidification process
    CN101786156A (en) * 2010-03-17 2010-07-28 上海大学 Cooling method used for directional solidification and cooling device therefor
    US8186418B2 (en) * 2010-09-30 2012-05-29 General Electric Company Unidirectional solidification process and apparatus therefor
    PL222793B1 (en) * 2014-03-13 2016-09-30 Seco/Warwick Europe Spółka Z Ograniczoną Odpowiedzialnością Method for the oriented crystallization of gas turbine blades and the device for producing castings of the gas turbine blades with oriented and monocrystalline structure
    CN105364001B (en) * 2015-10-16 2017-10-27 沈阳工业大学 Liquid metal cooling directional solidification blade surface detinning method
    CN106825459B (en) * 2016-12-29 2019-02-19 深圳市鑫申新材料科技有限公司 A kind of vacuum casting device of TiAl intermetallic compound ingot
    CN114622281B (en) * 2020-12-11 2024-04-12 中国科学院金属研究所 Low-melting-point metal pollution control method in process of preparing monocrystal blade by liquid metal cooling directional solidification method
    CN114619020B (en) * 2020-12-11 2024-03-12 中国科学院金属研究所 Preparation method for high-efficiency closely-spaced monocrystalline blade by utilizing liquid metal cooling directional solidification technology
    CN113172215B (en) * 2021-03-27 2022-06-28 兰州交通大学 Alloy vacuum directional solidification device
    CN113512763B (en) * 2021-06-18 2022-10-25 西安交通大学 High-temperature alloy directional solidification device and solidification method
    CN114643348B (en) * 2022-03-31 2023-03-31 中国科学院金属研究所 Preparation method and device of alloy with near-equilibrium solidification structure

    Citations (3)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    DE2242111A1 (en) * 1971-09-15 1973-03-22 United Aircraft Corp METHOD AND DEVICE FOR CASTING OBJECTS WITH DIRECTLY SOLIDIZED JOINT
    DE2815818A1 (en) * 1977-04-21 1978-10-26 United Technologies Corp CASTING EQUIPMENT FOR THE DIRECTED SOLIDIZATION OF MELTED METAL
    EP0631832A1 (en) * 1993-07-02 1995-01-04 Leybold Durferrit GmbH Method and apparatus for directional solidification of a metal melt

    Family Cites Families (2)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    DE1953716C3 (en) 1968-10-28 1973-01-04 Matsunaga, Yonosuke, Yokohama City (Japan) Process for the production of an ingot
    US4190094A (en) * 1978-10-25 1980-02-26 United Technologies Corporation Rate controlled directional solidification method

    Patent Citations (3)

    * Cited by examiner, † Cited by third party
    Publication number Priority date Publication date Assignee Title
    DE2242111A1 (en) * 1971-09-15 1973-03-22 United Aircraft Corp METHOD AND DEVICE FOR CASTING OBJECTS WITH DIRECTLY SOLIDIZED JOINT
    DE2815818A1 (en) * 1977-04-21 1978-10-26 United Technologies Corp CASTING EQUIPMENT FOR THE DIRECTED SOLIDIZATION OF MELTED METAL
    EP0631832A1 (en) * 1993-07-02 1995-01-04 Leybold Durferrit GmbH Method and apparatus for directional solidification of a metal melt

    Also Published As

    Publication number Publication date
    JP3493027B2 (en) 2004-02-03
    EP1020245B1 (en) 2001-11-07
    RU2146184C1 (en) 2000-03-10
    EP0775030B1 (en) 2001-05-02
    CZ33497A3 (en) 1997-05-14
    ES2157336T3 (en) 2001-08-16
    DE59509816D1 (en) 2001-12-13
    KR970704537A (en) 1997-09-06
    JP2001520582A (en) 2001-10-30
    CN1169124A (en) 1997-12-31
    CZ291584B6 (en) 2003-04-16
    UA39902C2 (en) 2001-07-16
    CN1104982C (en) 2003-04-09
    WO1996005006A1 (en) 1996-02-22
    DE59509230D1 (en) 2001-06-07
    EP1020245A3 (en) 2000-08-09
    DK0775030T3 (en) 2001-08-20
    EP0775030A1 (en) 1997-05-28

    Similar Documents

    Publication Publication Date Title
    EP1020245B1 (en) Method for producing a gas turbine blade by means of directional solidification of a melt
    DE2242111C3 (en) Device and method for producing castings with a directionally solidified structure
    DE2461553A1 (en) METHOD FOR GENERATING SINGLE CRYSTALS
    DE19539770A1 (en) Process for producing a directionally solidified casting and device for carrying out this process
    DE102014113806B4 (en) Method and device for producing DS / SC castings
    DE19607098A1 (en) Directional solidification of large pure silicon ingot
    DE1933412A1 (en) Method and device for converting material from a liquid to a solid state
    DE2451921A1 (en) PROCESS AND INTEGRATED FURNACE FOR CONTINUOUS METAL CASTING
    EP0891828B1 (en) Method and apparatus for directional solidification of a metal melt
    DE19934940C2 (en) Device for producing directionally solidified blocks and operating method therefor
    DE2609949C3 (en) Method and device for producing a casting from a metal alloy solidified in one direction
    WO1998020995A2 (en) Method and device for directed solidification of a molten mass
    DE1941968C3 (en) Method and device for the production of single crystals
    DE3207777A1 (en) METHOD AND DEVICE FOR PRODUCING TUBES FROM REACTIVE METALS
    DE112006000461T5 (en) casting process
    DE102009010034A1 (en) Method and casting plant for the directional solidification of a casting made of aluminum or an aluminum alloy
    DE2161461C3 (en) Process for the melt-metallurgical production of alloys for permanent magnets
    DE60019877T2 (en) Investment casting using a casting pool reservoir with inverted melt feed gate
    WO1998005450A1 (en) Process and device for directed solidification of a melt
    DE3502532A1 (en) DEVICE FOR THE CONTINUOUS PRODUCTION OF HOLLOW METAL CASTING BLOCKS
    DE2646299C2 (en) Process for the production of rotationally symmetrical silicon moldings
    DE2349898C3 (en) Metallurgical mold for the production of metallic workpieces
    DE2038690C3 (en) Process for the production of shaped pieces from sapphire single crystals
    DE558685C (en) Melting difficult to melt metals while avoiding the absorption of impurities
    DE2143445C3 (en) Method and device for the production of metallic blocks

    Legal Events

    Date Code Title Description
    PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

    Free format text: ORIGINAL CODE: 0009012

    PUAL Search report despatched

    Free format text: ORIGINAL CODE: 0009013

    17P Request for examination filed

    Effective date: 20000519

    AC Divisional application: reference to earlier application

    Ref document number: 775030

    Country of ref document: EP

    AK Designated contracting states

    Kind code of ref document: A2

    Designated state(s): DE FR GB IT

    RIC1 Information provided on ipc code assigned before grant

    Free format text: 7B 22D 27/04 A, 7C 30B 11/00 B

    AK Designated contracting states

    Kind code of ref document: A3

    Designated state(s): AT BE CH DE DK ES FR GB GR IE IT LI LU MC NL PT SE

    17Q First examination report despatched

    Effective date: 20000821

    GRAG Despatch of communication of intention to grant

    Free format text: ORIGINAL CODE: EPIDOS AGRA

    RTI1 Title (correction)

    Free format text: METHOD FOR PRODUCING A GAS TURBINE BLADE BY MEANS OF DIRECTIONAL SOLIDIFICATION OF A MELT

    RTI1 Title (correction)

    Free format text: METHOD FOR PRODUCING A GAS TURBINE BLADE BY MEANS OF DIRECTIONAL SOLIDIFICATION OF A MELT

    GRAG Despatch of communication of intention to grant

    Free format text: ORIGINAL CODE: EPIDOS AGRA

    GRAH Despatch of communication of intention to grant a patent

    Free format text: ORIGINAL CODE: EPIDOS IGRA

    AKX Designation fees paid

    Free format text: DE FR GB IT

    GRAH Despatch of communication of intention to grant a patent

    Free format text: ORIGINAL CODE: EPIDOS IGRA

    GRAA (expected) grant

    Free format text: ORIGINAL CODE: 0009210

    AC Divisional application: reference to earlier application

    Ref document number: 775030

    Country of ref document: EP

    AK Designated contracting states

    Kind code of ref document: B1

    Designated state(s): DE FR GB IT

    REF Corresponds to:

    Ref document number: 59509816

    Country of ref document: DE

    Date of ref document: 20011213

    REG Reference to a national code

    Ref country code: GB

    Ref legal event code: IF02

    GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

    Effective date: 20020208

    PLBE No opposition filed within time limit

    Free format text: ORIGINAL CODE: 0009261

    STAA Information on the status of an ep patent application or granted ep patent

    Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

    26N No opposition filed
    REG Reference to a national code

    Ref country code: GB

    Ref legal event code: 732E

    REG Reference to a national code

    Ref country code: FR

    Ref legal event code: TQ

    PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

    Ref country code: GB

    Payment date: 20120809

    Year of fee payment: 18

    PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

    Ref country code: IT

    Payment date: 20120823

    Year of fee payment: 18

    Ref country code: FR

    Payment date: 20120823

    Year of fee payment: 18

    PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

    Ref country code: DE

    Payment date: 20121019

    Year of fee payment: 18

    GBPC Gb: european patent ceased through non-payment of renewal fee

    Effective date: 20130807

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: DE

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20140301

    REG Reference to a national code

    Ref country code: DE

    Ref legal event code: R119

    Ref document number: 59509816

    Country of ref document: DE

    Effective date: 20140301

    REG Reference to a national code

    Ref country code: FR

    Ref legal event code: ST

    Effective date: 20140430

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: IT

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20130807

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: GB

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20130807

    PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

    Ref country code: FR

    Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

    Effective date: 20130902