EP0348012B1 - A method for applying a sheet pile wall, and auxiliary profile to be used therewith - Google Patents

A method for applying a sheet pile wall, and auxiliary profile to be used therewith Download PDF

Info

Publication number
EP0348012B1
EP0348012B1 EP19890201662 EP89201662A EP0348012B1 EP 0348012 B1 EP0348012 B1 EP 0348012B1 EP 19890201662 EP19890201662 EP 19890201662 EP 89201662 A EP89201662 A EP 89201662A EP 0348012 B1 EP0348012 B1 EP 0348012B1
Authority
EP
European Patent Office
Prior art keywords
sheet pile
sheet
section
longitudinal edge
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP19890201662
Other languages
German (de)
French (fr)
Other versions
EP0348012A1 (en
Inventor
Tijmen Van Halteren
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of EP0348012A1 publication Critical patent/EP0348012A1/en
Application granted granted Critical
Publication of EP0348012B1 publication Critical patent/EP0348012B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/02Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers specially adapted for placing or removing bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/24Placing by using fluid jets

Definitions

  • the invention relates to a method for applying a sheet pile wall by successively driving sheet piles into the ground and causing the longitudinal edges of said sheet piles to interlock and guide each other.
  • US-A-2 400 694 already discloses (in particular in figure 11 and page 3 left-hand column, lines 20 to 58) a method for driving a sheet pile wall by successively driving sheet piles of concrete into the ground and causing the longitudinal edges of said sheet piles to engage and guide each other (see in particular lines 47 to 58 of the above cited column), wherein each time a (following) sheet pile is driven an auxiliary section made of several parts is "inserted", whereby a complementarily formed longitudinal edge of said section is caused to engage the free longitudinal edge of said sheet pile, said section functioning as a support for at least one nozzle through which an hydraulic liquid is injected adjacent the free longitudinal edge of said sheet pile and said auxiliary section being retracted from the ground prior to driving a following sheet pile (see page 3, left hand column, lines 41 to 43).
  • the invention aims at providing an improved method of driving original sheet piles of steel i.e. interlockingly formed sheet piles of steel by enlightening the driving of such sheet piles while providing for conditions for a better water-tightness of the sheet pile wall when formed of relatively long sheet piles (i.c. a length of 30 m).
  • the invention provides a method for driving a sheet pile wall by successively driving sheet piles of steel into the ground and causing the longitudinal edges of said sheet piles to interlock and guide each other, whereby each time a (following) sheet pile is driven an auxiliary section is inserted and a complementarily formed longitudinal edge of said section is caused to engage the free longitudinal edge of said sheet pile, said section functioning as a support for at least one nozzle, through which an hydraulic liquid, such as water, is injected adjacent the free longitudinal edge of said sheet pile, and said auxiliary section being retracted from the ground prior to driving a following sheet pile.
  • the insertion and retraction of the auxiliary section is carried out in an intermediary phase between the insertion of two successive sheet piles or sheet pile pairs.
  • the effect of the auxiliary section is to be seen in that the soil in the area around the free longitudinal edge of the last driven sheet pile is loosened up and pressed away, so that a next sheet pile (pair) may "smoothly" run into the key-way of the last driven sheet pile.
  • the advantage of the effect of the auxiliary section may be taken even in an earlier stage by driving it each time simultaneously with a sheet pile (pair) into the ground.
  • a particular performance of the method of the invention is achieved by filling the hollow space which is created around the free longitudinal edge of the last driven sheet pile as a result of the retraction of the section, by a sealing substance, such as bentonite, which is injected under pressure through said nozzle.
  • a sealing substance such as bentonite
  • This manner of performing the method according to the invention is particularly suitable for applications such as those, whereby polluted soil areas have to be isolated.
  • the method according to the invention offers substantial advantages over the method which been used until sofar and according to which at first "bentonit piles" are formed into the ground at locations where - in a later stage - the joints between the individual sheet piles of the future sheet pile wall are expected to be located. With such a method there is a great chance that in the process of drilling said bentonite piles an undesired deviation will take place which may not be simply controllable, while with the subsequent driving of the sheet pile wall horizontal deviations relative to the location of the previously inserted bentonite piles may also easily occur.
  • the sheet pile wall according to fig. 1 is composed of sheet piles 1 having a trapezoidal cross-section, the longitudinal edges of said piles engaging one another.
  • the sheet piles are e.g. in sets of two previously interconnected sheet piles driven into the ground in a manner known per se, i.e. by hammering or vibrating.
  • the sheet piles 1c and 1d constitute a set which is the latest one driven into the ground, while the sheet pile 1b has been driven in in an earlier stage.
  • the key-way connection 2 between the sheet piles 1c and 1d may be easily rendered watertight by applying, beforehand, to the key-way of both of said sheet piles a substance adapted to form a sealing mass when it gets into contact with water.
  • the drawing shows the right hand edge (key-way) 3 of the sheet pile set 1c, 1d in engagement with the auxiliary section 4 according to the invention.
  • a so-called "delta" section which is normally used to connect two sheet piles which are positioned perpendicularly to the other when seen in a horizontal plane.
  • Said tube 6 is positioned at a slight distance opposite to the opening of the key-way 7 of the profile which has been formed complementarily to the key-way 3 at the longitudinal edge of the sheet pile 1d.
  • a second tube 8 is connected to the side of the key-way wall 7a turned away from said tube 6.
  • the tubes 6 and 8 have a rectangular cross-section.
  • the wall of the tube 6 facing to the opening of the key-way 7 may also function as a guide for the key-way wall 3a (vide fig. 2).
  • conduits (not shown) may be connected, by means of which a liquid under pressure may be supplied. For example water may be supplied when driving section 4.
  • the tubes 6 and 8 may be further untilized to inject a sealing substance, such as bentonite, into the space left around the key-way 3 when retracting the section.
  • a sealing substance such as bentonite

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

  • The invention relates to a method for applying a sheet pile wall by successively driving sheet piles into the ground and causing the longitudinal edges of said sheet piles to interlock and guide each other.
  • US-A-2 400 694 already discloses (in particular in figure 11 and page 3 left-hand column, lines 20 to 58) a method for driving a sheet pile wall by successively driving sheet piles of concrete into the ground and causing the longitudinal edges of said sheet piles to engage and guide each other (see in particular lines 47 to 58 of the above cited column), wherein each time a (following) sheet pile is driven an auxiliary section made of several parts is "inserted", whereby a complementarily formed longitudinal edge of said section is caused to engage the free longitudinal edge of said sheet pile, said section functioning as a support for at least one nozzle through which an hydraulic liquid is injected adjacent the free longitudinal edge of said sheet pile and said auxiliary section being retracted from the ground prior to driving a following sheet pile (see page 3, left hand column, lines 41 to 43).
  • The invention aims at providing an improved method of driving original sheet piles of steel i.e. interlockingly formed sheet piles of steel by enlightening the driving of such sheet piles while providing for conditions for a better water-tightness of the sheet pile wall when formed of relatively long sheet piles (i.c. a length of 30 m).
  • Accordingly the invention provides a method for driving a sheet pile wall by successively driving sheet piles of steel into the ground and causing the longitudinal edges of said sheet piles to interlock and guide each other, whereby each time a (following) sheet pile is driven an auxiliary section is inserted and a complementarily formed longitudinal edge of said section is caused to engage the free longitudinal edge of said sheet pile, said section functioning as a support for at least one nozzle, through which an hydraulic liquid, such as water, is injected adjacent the free longitudinal edge of said sheet pile, and said auxiliary section being retracted from the ground prior to driving a following sheet pile.
  • In a practical embodiment of the method of the invention the insertion and retraction of the auxiliary section is carried out in an intermediary phase between the insertion of two successive sheet piles or sheet pile pairs. The effect of the auxiliary section is to be seen in that the soil in the area around the free longitudinal edge of the last driven sheet pile is loosened up and pressed away, so that a next sheet pile (pair) may "smoothly" run into the key-way of the last driven sheet pile. The advantage of the effect of the auxiliary section may be taken even in an earlier stage by driving it each time simultaneously with a sheet pile (pair) into the ground.
  • A particular performance of the method of the invention is achieved by filling the hollow space which is created around the free longitudinal edge of the last driven sheet pile as a result of the retraction of the section, by a sealing substance, such as bentonite, which is injected under pressure through said nozzle.
  • This means that upon driving of a next sheet pile a high degree of water-tightness of the connection between the two sheet piles or sheet pile pairs is obtained, because the interconnected edges will become embedded in a column of the said sealing substance.
  • This manner of performing the method according to the invention is particularly suitable for applications such as those, whereby polluted soil areas have to be isolated. In this case the method according to the invention offers substantial advantages over the method which been used until sofar and according to which at first "bentonit piles" are formed into the ground at locations where - in a later stage - the joints between the individual sheet piles of the future sheet pile wall are expected to be located. With such a method there is a great chance that in the process of drilling said bentonite piles an undesired deviation will take place which may not be simply controllable, while with the subsequent driving of the sheet pile wall horizontal deviations relative to the location of the previously inserted bentonite piles may also easily occur.
  • The invention will be hereinafter explaned by way of example with reference to the accompanying drawing.
    • Fig. 1 is a perspective view of a part of a sheet pile wall of steel, showing the last driven sheet pile in engagement with an auxiliary profile according to this invention;
    • fig. 2 is a cross-sectional view of a sheet pile and the auxiliary profile in engagement therewith and
    • fig. 3 is a cross-sectional view on an enlarged scale of the auxiliary profile according to this invention.
  • The sheet pile wall according to fig. 1 is composed of sheet piles 1 having a trapezoidal cross-section, the longitudinal edges of said piles engaging one another. The sheet piles are e.g. in sets of two previously interconnected sheet piles driven into the ground in a manner known per se, i.e. by hammering or vibrating. In Fig. 1 the sheet piles 1c and 1d constitute a set which is the latest one driven into the ground, while the sheet pile 1b has been driven in in an earlier stage. The key-way connection 2 between the sheet piles 1c and 1d may be easily rendered watertight by applying, beforehand, to the key-way of both of said sheet piles a substance adapted to form a sealing mass when it gets into contact with water. The drawing shows the right hand edge (key-way) 3 of the sheet pile set 1c, 1d in engagement with the auxiliary section 4 according to the invention. In the example shown use is made of an existing section, a so-called "delta" section, which is normally used to connect two sheet piles which are positioned perpendicularly to the other when seen in a horizontal plane. The web 5 of this well-known section constitutes a strip shaped carrier for a tube 6 which is connected thereto e.g. by welding and which extends substantially along the entire length (= length of the sheet pile) of the section. Said tube 6 is positioned at a slight distance opposite to the opening of the key-way 7 of the profile which has been formed complementarily to the key-way 3 at the longitudinal edge of the sheet pile 1d. A second tube 8 is connected to the side of the key-way wall 7a turned away from said tube 6. The tubes 6 and 8 have a rectangular cross-section. As a result of this the wall of the tube 6 facing to the opening of the key-way 7 may also function as a guide for the key-way wall 3a (vide fig. 2). To the upper ends of the tubes 6 and 8 conduits (not shown) may be connected, by means of which a liquid under pressure may be supplied. For example water may be supplied when driving section 4. The water which discharges from the tubes 6 and 8 at the lower ends of the latter will remove the soil from the area of the key-way 3 of the sheet pile 1d, as a result of which a next sheet pile may run easier into the key-way 3 of sheet pile 1d.
  • The tubes 6 and 8 may be further untilized to inject a sealing substance, such as bentonite, into the space left around the key-way 3 when retracting the section.

Claims (4)

  1. A method for driving a sheet pile wall by successively driving sheet piles (1) of steel into the ground and causing the longitudinal edges (3) of said sheet piles (1) to interlock and guide each other, whereby each time a sheet pile (1) is driven, an auxiliary section (4) is inserted and a complementarily formed longitudinal edge (7) of said section (4) is caused to engage the free longitudinal edge (3) of said sheet pile (1), said section functioning as a support for at least one nozzle (6; 8), through which an hydraulic liquid, such as water, is injected adjacent the free longitudinal edge (3) of said sheet pile, and said auxiliary section (4) being retracted from the ground prior to driving a following sheet pile.
  2. A method according to claim 1, characterized in that the insertion and retraction of the auxiliary section is carried out in an intermediary phase between the insertion of two successive sheet piles or sheet pile pairs.
  3. A method according to claim 1, characterized in that the auxiliary section and a sheet pile are simultaneously driven into the ground.
  4. A method according to claims 1-3, characterized in that the hollow space - which is created around the free longitudinal edge (3) of the last driven sheet pile (1) as a result of the retraction of the section (4) - is filled by a sealing substance, such as bentonite, which is injected under pressure through said nozzle (6; 8).
EP19890201662 1988-06-22 1989-06-22 A method for applying a sheet pile wall, and auxiliary profile to be used therewith Expired - Lifetime EP0348012B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL8801592A NL8801592A (en) 1988-06-22 1988-06-22 METHOD FOR APPLICATION OF A FILM WALL AND UTILITY PROFILE TO BE USED THEREIN
NL8801592 1988-06-22

Publications (2)

Publication Number Publication Date
EP0348012A1 EP0348012A1 (en) 1989-12-27
EP0348012B1 true EP0348012B1 (en) 1994-03-16

Family

ID=19852506

Family Applications (1)

Application Number Title Priority Date Filing Date
EP19890201662 Expired - Lifetime EP0348012B1 (en) 1988-06-22 1989-06-22 A method for applying a sheet pile wall, and auxiliary profile to be used therewith

Country Status (3)

Country Link
EP (1) EP0348012B1 (en)
DE (1) DE68913825T2 (en)
NL (1) NL8801592A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101068147B1 (en) 2010-03-25 2011-09-27 황현만 Pile driving apparatus for installing wide steel sheet pile and installing method of wide steel sheet pile using such guide apparatus

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5938375A (en) * 1997-12-17 1999-08-17 Sevonson Environmental Services, Inc. Method of sealing joints between adjacent sheet piling sections to form a continuous barrier and barriers formed using said method
US6428244B1 (en) * 2000-07-21 2002-08-06 Georg Wall Connecting element for sheet piles
EP2699734B1 (en) * 2011-04-21 2015-01-28 PilePro LLC Universal connecting element for sheet pile wall components
US9549657B2 (en) 2011-09-21 2017-01-24 Whirlpool Corporation Dishwasher with multi-piece tub
CN107794933B (en) * 2017-11-09 2019-02-26 周登楷 Hermetic seal structure and its construction method are encircled and hunted down in a kind of underwater construction

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE446471C (en) * 1927-07-04 Johannes Guckes Method for flushing sheet pile walls
US1847655A (en) * 1927-09-16 1932-03-01 Herbert M Knight Piling
DE657158C (en) * 1933-11-09 1938-02-25 Gerhard Zur Nedden Retaining wall
GB518727A (en) * 1938-08-29 1940-03-06 Harley Hugh Dalrymple Hay Improvements in or relating to interlocking sheet metal piling
US2400694A (en) * 1944-02-10 1946-05-21 Hood Andrew Concrete piling wall unit
NL6406159A (en) * 1964-06-01 1965-12-02
NL140917B (en) * 1969-11-22 1974-01-15 Nederhorst Grondtechniek B V METHOD FOR COMPOSITE IN-GROUND OF A DAMPER WALL FROM DAMPER WALL PROFILES; AS WELL AS DAMPER WALL PROFILE, EQUIPPED FOR USE IN THIS METHOD.

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101068147B1 (en) 2010-03-25 2011-09-27 황현만 Pile driving apparatus for installing wide steel sheet pile and installing method of wide steel sheet pile using such guide apparatus

Also Published As

Publication number Publication date
EP0348012A1 (en) 1989-12-27
DE68913825D1 (en) 1994-04-21
DE68913825T2 (en) 1994-09-22
NL8801592A (en) 1990-01-16

Similar Documents

Publication Publication Date Title
EP0348012B1 (en) A method for applying a sheet pile wall, and auxiliary profile to be used therewith
JP4295272B2 (en) Friction cut plate used in open shield method and its fixing method
EP1181418B1 (en) Method to build a waterproof, creep limit increasing cutoff
EP0610992B1 (en) Method for providing a sheet pile wall in the ground and a prefabricated wall element for carrying out such method
JP3116098B2 (en) Construction method for underground structures
JPS622116B2 (en)
JP2933476B2 (en) Underground pipe laying method
JP2003020640A (en) Steel pipe column soil retaining wall, method of constructing the retaining wall, and water cut-off member used for the method
KR100496619B1 (en) beam for cut-off wall construction method
JPS5516172A (en) Excavation work method and apparatus for preventing landslide at ditch scooping
JPH0875046A (en) Laying method for pipe member
JPH0642286A (en) Method and device for constructing underground structure
JPS6322916A (en) Construction of continuous underground wall in artificial islet
SU1191520A1 (en) Method of constructing drainage
JP3473915B2 (en) Small diameter pipe burial method
JP3586744B2 (en) Construction method of impermeable wall
JPH07180485A (en) Construction method and construction device for underground structure
SU1599465A1 (en) Method of making antiseepage screen
JPH03147923A (en) Construction method for underground continuous wall with curvature
JPS5848691B2 (en) Earth retention device for trench excavation
JP3144289B2 (en) Underground installation method of bottom impermeable structure and bottom impermeable structure
JP3506501B2 (en) Construction method and shield machine of horizontal slab structure underground
JPH0811919B2 (en) Open shield method and open shield machine
JPH0141777B2 (en)
JPS61196016A (en) Joining method for cut-off sheet

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): BE DE FR GB IT NL

17P Request for examination filed

Effective date: 19900621

17Q First examination report despatched

Effective date: 19910711

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): BE DE FR GB IT NL

REF Corresponds to:

Ref document number: 68913825

Country of ref document: DE

Date of ref document: 19940421

ET Fr: translation filed
ITF It: translation for a ep patent filed

Owner name: MODIANO & ASSOCIATI S.R.L.

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20021031

Year of fee payment: 14

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20021119

Year of fee payment: 14

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20021122

Year of fee payment: 14

Ref country code: FR

Payment date: 20021122

Year of fee payment: 14

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BE

Payment date: 20021125

Year of fee payment: 14

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20030622

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20030630

BERE Be: lapsed

Owner name: *VAN HALTEREN TIJMEN

Effective date: 20030630

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20040101

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20040101

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20030622

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20040227

NLV4 Nl: lapsed or anulled due to non-payment of the annual fee

Effective date: 20040101

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.

Effective date: 20050622