DE347680C - Method for lowering concrete piles in loose soil - Google Patents

Method for lowering concrete piles in loose soil

Info

Publication number
DE347680C
DE347680C DE1918347680D DE347680DD DE347680C DE 347680 C DE347680 C DE 347680C DE 1918347680 D DE1918347680 D DE 1918347680D DE 347680D D DE347680D D DE 347680DD DE 347680 C DE347680 C DE 347680C
Authority
DE
Germany
Prior art keywords
concrete piles
pile
lowering
loose soil
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DE1918347680D
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baugesellschaft Moebus & Co G
Original Assignee
Baugesellschaft Moebus & Co G
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baugesellschaft Moebus & Co G filed Critical Baugesellschaft Moebus & Co G
Application granted granted Critical
Publication of DE347680C publication Critical patent/DE347680C/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/24Placing by using fluid jets

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Description

Verfahren zum Absenken von Betonpfählen in lockerem Erdreich. Die Erfindung betrifft ein Verfahren zum Absenken von Betonpfählen in lockerem Erdreich. Das Neue besteht darin, daß die in der Nähe des Umfangs sowie in der Mitte mit längsgerichteten Kanälen und am Fuße mit einem nach unten vorstehenden Ring versehenen Betonpfähle durch Spülung und gleichzeitiges leichtes Rammen abgesenkt werden, worauf der untere Ringraum und die Längskanäle mit Beton ausgefüllt werden. Hierdurch wird nur das in dem unteren Hohlraum befindliche Erdreich entfernt, wogegen das seitlich an den Pfahl herangedrückte lockere Erdreich durch den den unteren Hohlraum bildenden Ring daran gehindert wird, von dem Spülstrom erfaßt zu werden. Ein Nachrutschen von Erdreich ist daher durch das neue Verfahren verhindert, während das Absenken des Pfahles schneller vor sich geht, da nur das unmittelbar unter dem Pfahl liegende Erdreich beseitigt wird, welches zum Eintreiben unbedingt entfernt werden muß.Method for lowering concrete piles in loose soil. the The invention relates to a method for lowering concrete piles in loose soil. The novelty is that those near the circumference as well as in the middle with longitudinal ones Channels and concrete piles with a downwardly protruding ring at the foot be lowered by flushing and simultaneous light ramming, whereupon the lower Annular space and the longitudinal channels are filled with concrete. Through this will only the soil located in the lower cavity is removed, whereas the one to the side Loose soil pressed against the post through the cavity forming the lower cavity Ring is prevented from being caught by the purge flow. Slipping down of soil is therefore prevented by the new method while the lowering of the stake is faster because only the one immediately below the stake Soil is removed, which must be removed for driving.

In der Zeichnung sind beispielsweise mehrere Ausführungen zur Durchführung des neuen Verfahrens dargestellt.In the drawing, for example, there are several implementations of the new procedure.

Abb. I zeigt einen abgebrochenen dargestellten Betonpfahl im Langschnitt und Abb. 2 im Querschnitt nach der Linie A-B der Abb. I. Abb. 3 zeigt das untere Ende eines anderen Betonpfahles und Abb. 4. eine weitere Querschnittsausbildung eines Betonpfahles.Fig. I shows a broken concrete pile shown in a long section and Fig. 2 in cross section along the line A-B of Fig. I. Fig. 3 shows the lower one End of another concrete pile and Fig. 4. Another cross-sectional formation a concrete pile.

Der Betonpfahl I hat nach Abb. I und a einen kreisrunden Querschnitt und ist in der Nähe seines Umfanges mit längsgerichteten Kanälen 2 sowie in seiner Mitte mit einem Kanal 3 von größerem Querschnitt versehen. In die Kanäle 2, 3, die in der oberen und unteren Stirnwand des Pfahles münden, sind Eisenröhren 4, 3 eingebettet, die nicht ganz bis an das obere Stirnende des Pfahles I reichen. Von den Kanälen 2, 3 sind oberhalb der Röhren 4, 5 Stutzen 6, 7 abgezweigt. Die Stutzen 6 sind durch Schlauchleitungen 8 mit den Spülwasserleitungen verbinden, während der Stutzen 7 zu einem Ausguß führt. Die Kanäle 2, 3 sind an ihrer oberen Mündung während des Absenkens des Pfahles I durch Pfropfen 9, 10 abgeschlossen: Am unteren Ende des Pfahles I ist ein Fußring II angebracht, dessen Höhe sich nach der Beschaffenheit des Erdreichs 12 und dem Druck des Spülwassers richtet. Durch den Ring II wird am unteren Ende des Pfahles I ein Hohlraum I3 gebildet.According to Fig. I and a, the concrete pile I has a circular cross-section and is near its perimeter with longitudinal channels 2 as well as in its Center provided with a channel 3 of larger cross-section. In channels 2, 3, the open into the upper and lower end wall of the pile, iron tubes 4, 3 are embedded, which do not reach all the way to the upper front end of post I. From the canals 2, 3 are branched off above the tubes 4, 5 nozzles 6, 7. The nozzle 6 are through Connect the hose lines 8 to the rinsing water lines while the nozzle 7 leads to a sink. The channels 2, 3 are at their upper mouth during the Lowering of post I completed by plug 9, 10: At the lower end of the Pile I a foot ring II is attached, the height of which depends on the nature of the soil 12 and the pressure of the flushing water. Through the ring II is on lower end of the pile I formed a cavity I3.

Der Pfahl I wird durch leichte Schläge mittels eines Rammbärs 14 (Abb. I) auf das obere Ende des Pfahles und durch gleichzeitige Zuführung von Spülwasser durch die Schlauchleitungen 8 abgesenkt. Das am inneren Umfange des Ringes II durch die Röhren 4 eintretende Spülwasser wird im Sinne der in Abb. I eingezeichneten Pfeile unter Eindringen in das innerhalb dss Ringes II befindliche Erdreich nach der Mitte des Hohlraumes 13 abgelenkt und tritt zusammen mit dem aufgelockerten Erdreich durch das Rohr 5 und den Stutzen 7 aus.Pile I is driven by light blows with a battering ram 14 (Fig. I) on the upper end of the pile and by simultaneously supplying rinsing water lowered by the hose lines 8. The on the inner circumference of the ring II through the rinsing water entering the tubes 4 is shown in the sense of FIG Arrows penetrating into the soil located inside the ring II the center of the cavity 13 is deflected and occurs together with the loosened Earth through the pipe 5 and the nozzle 7.

Der Druck des Spülwassers wird mit Rücksicht auf die Beschaffenheit des Erdreichs 12 hierbei so gewählt, daß nur das im Hohlraum 13 befindliche Erdreich 12 fortgespült wird der Strahl des Spülwassers also nicht bis unter den Ring II gelangt. Um dies zu sichern, wird der Pfahl I so eingetrieben, . daß die untere Kante des als Schneide wirkenden Ringes II etwas tiefer als die durch das Spülwasser unmittelbar getroffene Erdschicht liegt, sich also in dem Ring II noch eine Schicht nicht aufgelockerten Bodens befindet (Abb. i).The pressure of the rinsing water is adjusted with regard to the condition of the soil 12 here selected so that only the soil located in the cavity 13 12, the jet of rinsing water is not washed away to below ring II got. To ensure this, the post I is driven in as follows. that the lower Edge of the ring II acting as a cutting edge a little deeper than that caused by the rinse water immediately hit layer of earth is, so there is another layer in ring II not loosened soil (Fig. i).

Nach Abb. 3 ist der Hohlraum am unteren, Pfahlende zum Teil durch den Innenraum 15 eines Fußringes 16 und zum Teil durch eine an der unteren Stirnfläche des Pfahles I vorgesehene, zweckmäßig glockenförmig ausgestaltete Höhlung 17 gebildet, wodurch im Bedarfsfalle aii@ Metall gespart wird, da die Bauhöhe des Ringes 16 kleiner ausfällt.According to Fig. 3, the cavity at the lower end of the pile is partially through the interior 15 of a foot ring 16 and partly by one on the lower end face of the pile I provided, expediently bell-shaped cavity 17 is formed, whereby if necessary aii @ metal is saved, since the overall height of the ring 16 is smaller fails.

Bei länglichen OuerscAnitten des Pfahles i werden vorteilhaft mehrere Röhren 5 (Abb. 4) im inneren Teil des Pfahles angeordnet, durch welche das Spülwasser austreten kann, um durch Erzielung möglichst gleicher Abstände der Rohre 4 von den mittleren Rohren eine gleichmäßige Strömung des Spülwassers nach der Mitte des Hohlraumes 13 oder 15, 17 hin zu erzielen.In the case of elongated cross sections of the pile i, several Tubes 5 (Fig. 4) arranged in the inner part of the pile, through which the flushing water can emerge in order to achieve the same distances as possible between the tubes 4 from the middle pipes a uniform flow of the flushing water to the center of the cavity 13 or 15, 17 to achieve.

Nach erfolgtem Absenken cies Pfahles i werden die Pfropfen 9, io herausgenommen und die Röhren ¢, 5 mit flüssigem Zement ausgegossen, wobei zuvor zur Erhöhung der Steifigkeit des Pfahles i in die Röhren Rundeisenstäbe eingeführt werden.After lowering the post i, the plugs 9, io are removed and the tubes ¢, 5 poured with liquid cement, having previously been used to increase the Rigidity of the pile i inserted into the tubes round iron bars.

Claims (1)

PATENT-ANSPRUCH: Verfahren zum Absenken von Betonpfählen in lockerem Erdreich, dadurch gekennzeichnet, daß die in der Nähe des Umfangs sowie in der Mitte mit längsgerichteten Kanälen (4,3) und am Fuße mit einem nach unten vorstehenden Rin-1 t . (ii) versehenen Betonpfähle (i) durch Spülung und gleichzeitiges leichtes Rammen abgesenkt werden, worauf der untere Ringraum (i2) und die Längskanäle (4, 3) mit Beton ausgefüllt werden.PATENT CLAIM: A method for lowering concrete piles in loose soil, characterized in that in the vicinity of the circumference and in the middle with longitudinal channels (4,3) and at the foot with a downwardly protruding Rin-1 t . (ii) provided concrete piles (i) are lowered by flushing and simultaneous light ramming, whereupon the lower annular space (i2) and the longitudinal channels (4, 3) are filled with concrete.
DE1918347680D 1918-12-24 1918-12-24 Method for lowering concrete piles in loose soil Expired DE347680C (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE347680T 1918-12-24

Publications (1)

Publication Number Publication Date
DE347680C true DE347680C (en) 1922-01-24

Family

ID=6256494

Family Applications (1)

Application Number Title Priority Date Filing Date
DE1918347680D Expired DE347680C (en) 1918-12-24 1918-12-24 Method for lowering concrete piles in loose soil

Country Status (1)

Country Link
DE (1) DE347680C (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3084518A (en) * 1958-07-18 1963-04-09 Hochstrasser Robert Tubular pile with driving cap
US4659257A (en) * 1984-10-29 1987-04-21 Funderingstechnieken Verstraeten B.V. Method for making a hole in the ground, and hollow body open at the lower and upper sides and adapted for use in this method
DE102021126015A1 (en) 2021-10-07 2023-04-13 Rwe Renewables Gmbh Foundation pile, especially offshore foundation pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3084518A (en) * 1958-07-18 1963-04-09 Hochstrasser Robert Tubular pile with driving cap
US4659257A (en) * 1984-10-29 1987-04-21 Funderingstechnieken Verstraeten B.V. Method for making a hole in the ground, and hollow body open at the lower and upper sides and adapted for use in this method
DE102021126015A1 (en) 2021-10-07 2023-04-13 Rwe Renewables Gmbh Foundation pile, especially offshore foundation pile

Similar Documents

Publication Publication Date Title
DE3603048A1 (en) METHOD FOR IMPROVING THE FOUNDATION AND DEVICE FOR IMPLEMENTING THE METHOD
DE1634340A1 (en) Method and device for driving piles in underwater layers, in particular for drilling platforms
DE2365445C2 (en) Process for producing a sand drain and vibrating ram for carrying out the process
DE347680C (en) Method for lowering concrete piles in loose soil
DE2029487C3 (en) Device for making compacted sand piles
DE2260473A1 (en) METHOD AND DEVICE FOR THE PRODUCTION OF DRAENS, PLUG COMPACTIONS OD. DGL
EP0110818B1 (en) Equipment and method for making cast-in-situ concrete piles
DE2014368A1 (en) Method and device for producing a thin, filtering or non-filtering wall in the ground, starting from a vertical borehole
DE580118C (en) Drift for the production of cast concrete sheet piling in the ground
DE608092C (en) Device for the production of reinforced concrete place posts
DE616706C (en) Process for the production of plug-like concrete foundation bodies
DE630256C (en) Process for the production of in-situ concrete piles with clubfoot using a jacking pipe and a shut-off body closing the mouth
DE407614C (en) Pierced driving point
DE368271C (en) Rammers for making concrete stakes
DE102005044104B3 (en) Foundation element capping method e.g. for upper end, involves capping upper end of element from concrete with jet arrangement provided which provides, under high pressure rinsing water or water air mixture across nozzle
DE578703C (en) Method of filling the joints between the planks of a concrete sheet pile wall
AT102030B (en) Device for inserting hollow piles into the ground using the flushing method.
DE609976C (en) Process for the production of a watertight construction pit enclosure
DE673827C (en) Procedure for dismantling with flushing offset
DE577682C (en) Method for driving jacking pipes
DE3841523A1 (en) Method of cutting off the top end of foundation elements of cast-in-situ concrete, and apparatus for carrying out the method
DE414955C (en) Method and device for the manufacture of site stakes from concrete
DE858973C (en) Process for the production of compressed air foundations on an inclined and possibly overlaid rock soil
DE410355C (en) Driving routes and making shafts in salt
DE1634150C (en) Process for bank reinforcement and concrete block and device for carrying out the process