DE3146267A1 - "METHOD AND DEVICE FOR PREVENTING THE OUTFLOW OF IMPURITIES TOGETHER WITH MELT-LIQUID GOODS" - Google Patents

"METHOD AND DEVICE FOR PREVENTING THE OUTFLOW OF IMPURITIES TOGETHER WITH MELT-LIQUID GOODS"

Info

Publication number
DE3146267A1
DE3146267A1 DE19813146267 DE3146267A DE3146267A1 DE 3146267 A1 DE3146267 A1 DE 3146267A1 DE 19813146267 DE19813146267 DE 19813146267 DE 3146267 A DE3146267 A DE 3146267A DE 3146267 A1 DE3146267 A1 DE 3146267A1
Authority
DE
Germany
Prior art keywords
melting
holding furnace
molten material
plate
pouring opening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
DE19813146267
Other languages
German (de)
Other versions
DE3146267C2 (en
Inventor
Heini 8774 Rothenfels Hofmann
Manfred 8770 Lohr Scherer
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bosch Rexroth AG
Original Assignee
Mannesmann Rexroth AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mannesmann Rexroth AG filed Critical Mannesmann Rexroth AG
Priority to DE19813146267 priority Critical patent/DE3146267A1/en
Priority to EP82110138A priority patent/EP0080087B1/en
Priority to AT82110138T priority patent/ATE13148T1/en
Publication of DE3146267A1 publication Critical patent/DE3146267A1/en
Application granted granted Critical
Publication of DE3146267C2 publication Critical patent/DE3146267C2/de
Granted legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/04Continuous casting of metals, i.e. casting in indefinite lengths into open-ended moulds
    • B22D11/045Continuous casting of metals, i.e. casting in indefinite lengths into open-ended moulds for horizontal casting
    • B22D11/047Means for joining tundish to mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D41/00Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like
    • B22D41/14Closures
    • B22D41/44Consumable closure means, i.e. closure means being used only once
    • B22D41/48Meltable closures
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F27FURNACES; KILNS; OVENS; RETORTS
    • F27DDETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS, OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE
    • F27D3/00Charging; Discharging; Manipulation of charge
    • F27D3/14Charging or discharging liquid or molten material

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Vertical, Hearth, Or Arc Furnaces (AREA)
  • Processing Of Solid Wastes (AREA)
  • Gasification And Melting Of Waste (AREA)
  • Manufacture And Refinement Of Metals (AREA)
  • Furnace Charging Or Discharging (AREA)
  • Furnace Details (AREA)

Abstract

1. An apparatus for preventing the outflow of impurities, more especially slag, together with molten material, more especially metal, from a casting aperture (22), which is provided with a melting plate (25), of a container for the reception of molten material, the melting plate (25) being insertable into the casting aperture (22) and being meltable within a predetermined period by the molten material which is subsequently introduced into the container, characterised in that the melting plate (25) is provided with a predetermined melting point (26) which reduces its thickness and which is melted prior to the rest of the melting plate (25) by the molten material in the container and which, in the state in which it has melted through, has a section of passage for molten material which is substantially smaller than that of the molten melting plate (25).

Description

3U62673U6267

DlPL-IlNG. Kl= PO&IE€ PATENTANWALT · D 7300 ESSUNGEN BEI STUTTGART . HINDENBURGSTRASSEDlPL-IlNG. Kl = PO & IE € PATENTANWALT · D 7300 ESSUNGEN AT STUTTGART. HINDENBURGSTRASSE

- 3·- 3

PotontanwoH PIHR-D 7300 Esding«n (Netkor), HindgnbiTflstrcSa 44 PotontanwoH PIHR-D 7300 Esding «n (Netkor), HindgnbiTflstrcSa 44

22. Sept. 1981 BySept. 22, 1981 By

P 6738 121.619FP 6738 121.619F

Mannesmann Rexroth GmbH, Jahnstraße 3-5, 8770 Lohr/MainMannesmann Rexroth GmbH, Jahnstrasse 3-5, 8770 Lohr / Main

"Verfahren und Vorrichtung zum Verhindern des Ausströmens von Verunreinigungen zusammen mit schmelzflüssigem Gut""Method and Apparatus for Preventing Leakage of Contaminants along with molten material "

Die Erfindung bezieht sich auf ein Verfahren entsprechend dem Oberbegriff des Anspruches 1 und auf eine Vorrichtung entsprechend dem Oberbegriff des Anspruches 3-The invention relates to a method according to the preamble of claim 1 and to a Device according to the preamble of claim 3-

Bei einer bekannten Vorrichtung der vorgenannten Art besteht die Gefahr, daß beim Füllen des Warmhalteofens Verunreinigungen des schmelzflüssigen Gutes in die Kokille fließen, solange sich der Spiegel des schmelzflüssigen Gutes noch unterhalb des oberen Randes der Gießöffnung befindet (DE-CS 27 07 533).In a known device of the aforementioned type there is a risk that when filling the holding furnace Impurities in the molten material flow into the mold as long as the level of the molten material is Good is still below the upper edge of the pouring opening (DE-CS 27 07 533).

Der vorliegeaden Erfindung liegt die Aufgabe zugrunde, beim Füllen des Warmhalteofens das übertreten von Verunreinigungen des schmelzflüssigeri Gutes aus dem Warmhalteofen in die Kokille zu verhindern, solange sich der Spiegel des schmelzflüssigen Gutes noch unterhalb des oberen Randes der Gießöffnung befindet. Diese Aufgabe wird durch die Merkmale in den Kennzeiehr.ungsteilen der Ansprüche 1 und 3 er f ι ndungs^err.äJi gelost.The present invention is based on the object When filling the holding furnace, the transfer of impurities from the molten material To prevent holding furnace in the mold as long as the level of the molten material is still below of the upper edge of the pouring opening is located. This task is carried out by the characteristics in the labeling parts of the claims 1 and 3 it founding ^ err.äJi solved.

-U--U-

3U62673U6267

-^- 22. Sept. 1981 By- ^ - Sept. 22, 1981 By

P 6738 121. 169FP 6738 121, 169F

Die die Gießöffnung verschliehendt,· Schmelzplatte verhindert beim Einfüllen von schmelzflüssigem Gut in den Warmhalteofen das Ausfließen dieses Gutes und von Verunreinigungen so lange, solange sich der Spiegel des schmelzflüssigen Gutes noch unterhalb des oberen Randes der Gießöffnung befindet. Das in den Warmhalteofen eingefüllte schmelzflüssige Gut übersteigt den schmelzbaren Teil der Schmelzplatte, ehe dieser geschmolzer, ist, so daß aus dem geschmolzenen Teil der Schmelzplatte nur schmelzflüssiges Gut austritt, das keine auf ihm schwimmende Verunreinigungen mit sich führt.Which closes the pouring opening, prevents the melting plate when pouring molten material into the holding furnace, the outflow of this material and from Impurities as long as the level of the molten material is still below the upper edge the pouring opening is located. The molten material poured into the holding furnace exceeds the fusible material Part of the melting plate before it melts, is, so that only molten material emerges from the molten part of the melting plate, which does not have any carries floating impurities with him.

Durch die Merkmale des Anspruches 2 wird erreicht, daß ein bestimmter Teil der Schmelzplatte schmilzt, bevor die ganze Schmelzplatte zum Schmelzen kommt. Aus dem nach dem Übersteigen durch das schmelzflüssige Gut geschmolzenen Teil der Schmelzplatte fließendes flussiges Gut ist frei von Verunreinigungen. Hierdurch ist es möglich, anfangs einen kleineren Querschnitt als den von der Schmelzplatte bedeckten Querschnitt frei zu schweißen und mindestens anfangs einen kleineren Gutstrom in die Kokille fließen zu lassen. Die Dicke der Sollschmelzstelle und/oder der Schr.elzplatte kann den jeweils gewünschten Temperaturen des schmelzflüssiger. Gutes und dem Querschnitt der Kokille angepaßt werden.The features of claim 2 ensure that a certain part of the melting plate melts before the whole melting plate melts. From the after having passed through the molten material, the molten part of the melting plate flows in liquid Good is free from contamination. This makes it possible to initially have a smaller cross-section than the free to weld the cross-section covered by the melting plate and at least initially a smaller material flow to flow into the mold. The thickness of the predetermined melting point and / or the Schr.elzplatte can each desired temperature of the molten. Good and adapted to the cross section of the mold.

Weitere Vorteile ergeben sich aus den übrigen Ansprüchen, der Beschreibung und der Zeichnung. In dieser ist ein Warmhalteofen als AusführurifT.sbeir.piel des Gegenstandes der Erfindung schematisch dargestellt. Fs zeigenFurther advantages emerge from the remaining claims, the description and the drawing. In this is a holding furnace as the implementation of the object of the invention shown schematically. Show fs

Fig. 1 einen lotrechten Schnitt,Fig. 1 is a vertical section,

Fig. 2 einen Ausschnitt aus Fi^. 1 nut zusätzlichen Tf il en. Cj Fig. 2 shows a section from Fi ^. 1 with additional tiles. Cj

.:.*." -i. I λ'Ο .1 3H6267.:. *. "-i. I λ'Ο .1 3H6267

-ί»- 22, Sept. 1981 By-ί »- Sept. 22, 1981 By

P 6738 121.619FP 6738 121.619F

Ein Ofenmantel 1 irt aus Grobblechplatten zusammengeschweißt und mit feuerfesten Steinen 2 und einer Schicht 3 aus einer feuerfesten Masse ausgekleidet. Der Warrr.halteofen hat auf einer Seite eine Gießöffnung 22. Lie Gießöffnung i.'? durchsetzt eine auf dem Ofenmantel 1 befestigte gußeiserne Frontplatte 4. An dicsrr ist ein Zwiscbenflansch b (Fig. 2) mit Kokille 6 und dieser zugeordneten Kühler 7 befestigt. An der Unterseite des Warmhalteofens ist ein am Ofenmantel fest angeschweißter Flansch zur Anbringung eines Induktors 9 vorgesehen. Auf der Oberseite des Warmhalteofens ist ein abnehr.barer Deckel 10 angeordnet, der mit einer feuerfesten Masse ausgegossen ist und einen Brennerstein 1? zur Aufnahme eines nicht dargestellten Brenners aufweist. Im unteren Bereich des Warmhalteofens ist eine Temperaturmeßstelle 13 vorgesehen, die ein Thermoelement IiJ hat. Die Lage des Zwischenflansches 5 auf der Frontplatte 4 ist mittels Paßstiften genau festgelegt. Der Bereich zwischen der Kokille 6 und der die Steine bedeckenden Schicht 3 wird durch einen von einem Isolierkörper 16 umgebenen Zuführtrichter 17 überbrückt. Der Isolierkörper 16 besteht aus einer Isoliermasse und der Zufuhrtrichter 17 aus einer feuerfesten Masse. An der Stoßstelle zwischen der Mündung der Gießöffnung 22 und dem Zuführtrichter 17 sind die lichten Ausnehmungen jeweils gleich, liier ist eine Schmelzplatte 25 eingesetzt, die die Gießöffnung 22 ausfüllt und von den Zuführtrichter 17 gehalten wird. Die Schmelzplatte 2b hat an der Unterseite eine Sollschnelzstelle 26 geringerer Dicke. Der Werkstoff der Schmel zplatte 25>, deren Dicke und die Dicke der Sollschnelzstelle ist den das schmelzflussige Gut jeweils aufweisenden Temperaturen ur.d der, Querschnitten der Kokille 6 angepaßt.A furnace shell 1 is welded together from heavy plate plates and lined with refractory bricks 2 and a layer 3 made of a refractory mass. The holding furnace has a pouring opening 22 on one side . Lie pouring opening i. '? penetrates a cast-iron front plate 4 fastened to the furnace shell 1. An intermediate flange b (FIG. 2) with a mold 6 and a cooler 7 associated therewith is fastened to it. On the underside of the holding furnace, a flange that is permanently welded to the furnace shell is provided for attaching an inductor 9. On the top of the holding furnace, a removable cover 10 is arranged, which is filled with a refractory mass and a burner block 1? has for receiving a burner, not shown. In the lower area of the holding furnace, a temperature measuring point 13 is provided which has a thermocouple IiJ. The position of the intermediate flange 5 on the front plate 4 is precisely determined by means of dowel pins. The area between the mold 6 and the layer 3 covering the stones is bridged by a feed funnel 17 surrounded by an insulating body 16. The insulating body 16 consists of an insulating compound and the feed funnel 17 of a refractory compound. At the joint between the mouth of the pouring opening 22 and the feed funnel 17, the clear recesses are always the same; a melting plate 25 is inserted here, which fills the pouring opening 22 and is held by the feed funnel 17. The melting plate 2b has a predetermined melting point 26 of smaller thickness on the underside. The material of the melting plate 25>, its thickness and the thickness of the predetermined melting point are adapted to the temperatures and the cross-sections of the mold 6, respectively, of the melted material.

-6--6-

-6- 22. Sept. 1981 By-6- Sept. 22, 1981 By

- P6738 121.619F- P6738 121.619F

Zwischen der Frontplatte 4 und den Zwischenflansch 5 ist eine Dichtung 19 in Form einer Asbestplatte oder dgl. vorgesehen. Der die Kokille 6 umgebende Kühler ist mit seinem Flansch an einem Haltering 20 mittels Schrauben lösbar befestigt, der seinerseits.an den Zwischenflansch 5 ebenfalls mittelfs Schrauben lösbar befestigt ist. Zum Ausrichten der Kokille können an Befestigungsflansch des Kühlers.7 Langlöcher vorgesehen sein. Es ist möglich, an dem .Zwischenflansch 5 mehrere Kokillen 6 anzuordnen.Between the front plate 4 and the intermediate flange 5 A seal 19 in the form of an asbestos plate or the like is provided. The cooler surrounding the mold 6 is releasably attached with its flange to a retaining ring 20 by means of screws, which in turn.an the Intermediate flange 5 can also be released by means of screws is attached. To align the mold, elongated holes can be provided on the mounting flange of the cooler. 7 be. It is possible on the intermediate flange 5 several To arrange molds 6.

Beim Einfüllen von schmelzflüssigen) Cut in den Warmhalteofen 1 übersteigt dieses die f.ollschmelzstelle und die Schmelzplatte 25 jeweils bevor die Sollschmelzstelle 26 bzw. die Schmelzplatte 25 schmilzt. Dadurch wird verhindert, daß auf dem schnelzflüssigen Gut, insbesondere Metall, schwimmende Verunreinigungen, insbesondere Schlacke, in die Kokille fließen. Die Gießöffnung 22 ist derart ausgebildet, daß sich bein Füllen des Warmhalteofens keine Verunreinigungen darin fangen und diese von den die Gießöffnung 22 übersteigenden schmelzflüssigen Gut mitgenommen werden. Die Sollschmelzstelle 26 und die Schmelzplatte 25 schmelzen · jeweils nach einer vorbestimmten Zeit. Die Schmelzplatte 25 kann auch ohne Sollschmelzstelle 26 ausgebildet sein.When pouring molten) cut into the holding furnace 1, it exceeds the full melting point and the melting plate 25 in each case before the desired melting point 26 or the melting plate 25 melts. Through this it is prevented that on the high-viscosity material, in particular metal, floating impurities, in particular Slag, flowing into the mold. The pouring opening 22 is formed so that when filling of the holding furnace do not catch any impurities in it and these from those exceeding the pouring opening 22 molten goods are taken away. The predetermined melting point 26 and the melting plate 25 melt in each case after a predetermined time. The melting plate 25 can also be designed without a predetermined melting point 26.

L eerseiteL eerseite

Claims (5)

-Γ: ;. 3U6267 DJPL-JNG. Kl» PQEiOK PATENTANWALT · D 7300 ESSUNGEN BEI STUTTGART ■ HtNDENBURGSTRASSE Patoiianwoll PI N K . D 7300 Ejölingon |N»Aor), Hindgnburgntroflo 44 22. Sept. 1-9Ö1 Ey P 673B 121. 619 F Mannesr.ann-Rexroth GmbH, Jahnstraße 3-5, 8770 Lohr/Main Ansprüche-Γ:;. 3U6267 DJPL-JNG. Kl »PQEiOK PATENTANWALT · D 7300 ESSUNGEN NEAR STUTTGART ■ HtNDENBURGSTRASSE Patoiianwoll PI N K. D 7300 Ejölingon | N »Aor), Hindgnburgntroflo 44 22 Sept. 1-9Ö1 Ey P 673B 121.619 F Mannesr.ann-Rexroth GmbH, Jahnstrasse 3-5, 8770 Lohr / Main claims 1. / Verfahren zun Verhindern des Ausströmens von1. / Method of Preventing Leakage of Verunreinigungen, insbesondere Schlacke, zusammen nit schraelzflüssigem Gut, insbesondere Metall, aus einer Gießöffnung (22) eines Warmhalteofens, dadurch gekennzeichnet , daß die Gießöffnung vor dem Füllen des Warmhalteofens mit schmelzflüssigen Gut mittels einer durch das in den V.'arnihaltecfen eingefüllte schmelzflüssige Gut in vorbestirr.mter Zeit mindestens teilweise schmelzbaren Schmelzplatte (25) abgeschlossen wird.Impurities, especially slag, together with molten material, especially metal a pouring opening (22) of a holding furnace, characterized in that the pouring opening before filling the holding furnace with molten liquid Well by means of a molten material poured into the V.'arnihaltecfen in predetermined time at least partially fusible Melting plate (25) is completed. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet , daß die Schmelzplatte (25) mit einer ihre Dicke vermindernden Sollschmelzstelle (26) versehen ist, die von den im Warmhalteofen befindlichen schmelzflüssifc-,en Gut vor dem übrigen Teil der Schnelzplatte geschmolzen wird und die in durchgeschmolzenem Zustand einen wesentlich geringeren Durchschnittsquerschnitt für aas schmelzflüssige Gut als die geschmolzene Schmelzplatte ■aufweist.2. The method according to claim 1, characterized in that the melting plate (25) with a their thickness reducing predetermined melting point (26) is provided, which is located in the holding furnace schmelziquidifc-, en good is melted before the remaining part of the Schnelzplatte and the in melted state a much lower Average cross-section for as much molten material as the molten melting plate ■ has. -2--2- -2- 22. Sept. 1981 By-2- Sept. 22, 1981 By P 6738 121.619FP 6738 121.619F 3. Vorrichtung zur Durchführung des Verfahrens nach einem der vorhergehenden Ansprüche an einem Warmhalteofen für eine Stran^gußanla^.e, mit einer Gießöffnung (22) im üfenmantel (1), mit einer fest daran angebrachten Frontplatte (k) und mit einem von der Frontplatte nach Belieben lösbaren Zwischenflansch (5) zum Anbringen einer Kokille (6), gekennzeichnet durch eine bei leerem Warmhalteofen in die Gießöffnung eingesetzte und diese verschließende Schmelzplatte (25), die durch das in den Warmhalteofen anschließend eingefülte schmelzflüssige Gut in vorbestimmter Zeit mindestens teilweise zum Schmelzen gebracht wird. 3. Device for performing the method according to one of the preceding claims on a holding furnace for a Stran ^ gußanla ^ .e, with a pouring opening (22) in the furnace jacket (1), with a front plate ( k ) firmly attached to it and with one of the Front plate at will, detachable intermediate flange (5) for attaching a mold (6), characterized by a melting plate (25) which is inserted into the pouring opening when the holding furnace is empty and which closes it and which is at least partially converted in a predetermined time by the molten material subsequently poured into the holding furnace Melting is brought about. ^. Vorrichtung nach Anspruch 3, dadurch gekennzeichnet , daß die Schmelzplatte (25) auf einer ihrer beiden großflächigen Seiten eine ihre ticke vermindernde Ausnehmung als Sollschmelzstelle (26) hat.^. Device according to claim 3, characterized in that the melting plate (25) on a On both of its large sides a recess that reduces its thickness as a predetermined melting point (26) Has. 5. Vorrichtung nach Anspruch Ü, dadurch gekennzeichnet , daß die Schmelzplatte (25) zwischen die von der Frontplatte (*J ) urgebene Mündung der Gießöffnung (22) und einen von dem Zwischenflansch (5) umgebenen Zuführtrichter (17) eingesetzt ist.5. Apparatus according to claim U, characterized in that the melting plate (25) is inserted between the mouth of the pouring opening (22) and a feed funnel (17) surrounded by the intermediate flange (5) from the front plate (* J). -3--3-
DE19813146267 1981-11-21 1981-11-21 "METHOD AND DEVICE FOR PREVENTING THE OUTFLOW OF IMPURITIES TOGETHER WITH MELT-LIQUID GOODS" Granted DE3146267A1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
DE19813146267 DE3146267A1 (en) 1981-11-21 1981-11-21 "METHOD AND DEVICE FOR PREVENTING THE OUTFLOW OF IMPURITIES TOGETHER WITH MELT-LIQUID GOODS"
EP82110138A EP0080087B1 (en) 1981-11-21 1982-11-04 Apparatus for preventing the outflow of impurities together with molten material
AT82110138T ATE13148T1 (en) 1981-11-21 1982-11-04 DEVICE FOR PREVENTING THE OUTLET OF CONTAMINANTS TOGETHER WITH MOLTEN PRODUCT.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19813146267 DE3146267A1 (en) 1981-11-21 1981-11-21 "METHOD AND DEVICE FOR PREVENTING THE OUTFLOW OF IMPURITIES TOGETHER WITH MELT-LIQUID GOODS"

Publications (2)

Publication Number Publication Date
DE3146267A1 true DE3146267A1 (en) 1983-05-26
DE3146267C2 DE3146267C2 (en) 1988-07-14

Family

ID=6146944

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19813146267 Granted DE3146267A1 (en) 1981-11-21 1981-11-21 "METHOD AND DEVICE FOR PREVENTING THE OUTFLOW OF IMPURITIES TOGETHER WITH MELT-LIQUID GOODS"

Country Status (3)

Country Link
EP (1) EP0080087B1 (en)
AT (1) ATE13148T1 (en)
DE (1) DE3146267A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06279813A (en) * 1993-03-26 1994-10-04 Mitsubishi Materials Corp Container for melting high-purity metal and production thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1145205B (en) * 1957-05-17 1963-03-14 Deutsche Edelstahlwerke Ag Tiltable metallurgical furnace, in particular large-capacity electric furnace, from which either molten steel or molten steel with molten slag are to be tapped
CH448396A (en) * 1965-12-20 1967-12-15 Concast Ag Method and device for the continuous casting of metals, in particular steel
CH474305A (en) * 1968-05-22 1969-06-30 Concast Ag Method and device for the continuous casting of steel
DE2632253A1 (en) * 1975-07-18 1977-01-20 Concast Ag METHOD AND DEVICE FOR CASTING ON A STRAND IN A CONTINUOUS CASTING PLANT
DE2707533A1 (en) * 1977-02-22 1978-08-24 Rexroth Gmbh G L Holding furnace for horizontal continuous casting plant - where horizontal row of moulds are rapidly changed via intermediate flange
DE2941720A1 (en) * 1979-10-15 1981-04-23 Gebr. Lüngen KG, 4006 Erkrath Consumable stopper for tundish in continuous casting plant - consists of plate covering tundish outlet nozzle and gradually destroyed by heat in molten metal
CH624321A5 (en) * 1977-12-05 1981-07-31 Concast Ag Method and apparatus for starting a strand in a continuous casting installation for steel with a plurality of strands

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1383914A (en) * 1971-10-12 1974-02-12 Foseco Int Molten metal casting
WO1980000546A1 (en) * 1978-09-15 1980-04-03 Ssab Svenskt Stal Ab Method for opening the tundish nozzle in continuous casting of steel

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1145205B (en) * 1957-05-17 1963-03-14 Deutsche Edelstahlwerke Ag Tiltable metallurgical furnace, in particular large-capacity electric furnace, from which either molten steel or molten steel with molten slag are to be tapped
CH448396A (en) * 1965-12-20 1967-12-15 Concast Ag Method and device for the continuous casting of metals, in particular steel
CH474305A (en) * 1968-05-22 1969-06-30 Concast Ag Method and device for the continuous casting of steel
DE2632253A1 (en) * 1975-07-18 1977-01-20 Concast Ag METHOD AND DEVICE FOR CASTING ON A STRAND IN A CONTINUOUS CASTING PLANT
DE2707533A1 (en) * 1977-02-22 1978-08-24 Rexroth Gmbh G L Holding furnace for horizontal continuous casting plant - where horizontal row of moulds are rapidly changed via intermediate flange
CH624321A5 (en) * 1977-12-05 1981-07-31 Concast Ag Method and apparatus for starting a strand in a continuous casting installation for steel with a plurality of strands
DE2941720A1 (en) * 1979-10-15 1981-04-23 Gebr. Lüngen KG, 4006 Erkrath Consumable stopper for tundish in continuous casting plant - consists of plate covering tundish outlet nozzle and gradually destroyed by heat in molten metal

Also Published As

Publication number Publication date
EP0080087A1 (en) 1983-06-01
EP0080087B1 (en) 1985-05-08
ATE13148T1 (en) 1985-05-15
DE3146267C2 (en) 1988-07-14

Similar Documents

Publication Publication Date Title
DE2734388C2 (en) Method and device for continuous casting
DE69515164T2 (en) Process for producing slurry-like molten metal for casting
DE2919880A1 (en) PIPE
DE69503643T2 (en) ARRANGEMENT FOR THE FLOW CONTROL OF A POUR IN A METALLURGICAL CONTAINER
DE3424255C2 (en) Pouring device for intermediate containers in continuous casting plants
DE3146267A1 (en) "METHOD AND DEVICE FOR PREVENTING THE OUTFLOW OF IMPURITIES TOGETHER WITH MELT-LIQUID GOODS"
DE3334733C2 (en) Process and plant for the production of high-purity alloys
CH685332A5 (en) Continuous casting.
DE2913024A1 (en) PROCESS FOR COOLING AN OSCILLATING CONTINUOUS STEEL COLLAR
EP0367800B1 (en) Process and outlet sleeve for introducing gas into the outlet of a molten bath, in particular of a receptacle containing molten steel
EP0433419B2 (en) Device for slag-free casting on in continuous casting installations
DE2632253B2 (en) Method and device for casting a strand in a continuous caster
DE8233113U1 (en) FLOAT FOR METAL MELTING
DE4311031C2 (en) Device for the continuous continuous casting of metals
DE2361344B2 (en) Process for pouring metal into a continuous casting mold
DE1925862A1 (en) Process for the production of strands in the continuous casting process and device for carrying out the process
AT282854B (en) Method and device for the continuous casting of steel
DE2113870A1 (en) Mold
DE1945141A1 (en) Continuous metal casting machine
DE3641035C1 (en) Casting ladle for holding molten steel
DE3037091C2 (en)
DE3101773A1 (en) DEVICE FOR POURING LIQUID STEEL
DE2166230A1 (en) Continuous casting - using closed bottom melt feed funnel
DE1483637A1 (en) Method and device for pouring overheated metal melts
DE3909228C1 (en) Starting aid for continuous casting installations

Legal Events

Date Code Title Description
8110 Request for examination paragraph 44
8125 Change of the main classification

Ipc: F27D 3/15

D2 Grant after examination
8364 No opposition during term of opposition
8339 Ceased/non-payment of the annual fee