DE2856474C2 - Wire mesh mat for pit construction, especially for route expansion in underground mining and tunnel construction - Google Patents
Wire mesh mat for pit construction, especially for route expansion in underground mining and tunnel constructionInfo
- Publication number
- DE2856474C2 DE2856474C2 DE19782856474 DE2856474A DE2856474C2 DE 2856474 C2 DE2856474 C2 DE 2856474C2 DE 19782856474 DE19782856474 DE 19782856474 DE 2856474 A DE2856474 A DE 2856474A DE 2856474 C2 DE2856474 C2 DE 2856474C2
- Authority
- DE
- Germany
- Prior art keywords
- wire
- longitudinal
- mat
- rods
- bars
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000005065 mining Methods 0.000 title claims description 5
- 238000010276 construction Methods 0.000 title claims 4
- 239000000463 material Substances 0.000 claims description 20
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 230000006378 damage Effects 0.000 claims description 2
- 108010084652 homeobox protein PITX1 Proteins 0.000 claims 4
- 239000004744 fabric Substances 0.000 claims 3
- 239000007788 liquid Substances 0.000 claims 3
- 230000000717 retained effect Effects 0.000 claims 2
- 101150049168 Nisch gene Proteins 0.000 claims 1
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 239000000428 dust Substances 0.000 claims 1
- 239000007789 gas Substances 0.000 claims 1
- 239000002245 particle Substances 0.000 claims 1
- 230000035699 permeability Effects 0.000 claims 1
- 238000003466 welding Methods 0.000 claims 1
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 208000011092 Hand injury Diseases 0.000 description 1
- 238000005253 cladding Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 239000003245 coal Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 239000000543 intermediate Substances 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 108090000623 proteins and genes Proteins 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/152—Laggings made of grids or nettings
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Building Environments (AREA)
- Revetment (AREA)
Description
Drahtnetz nicht mit allen Längsstäben verbunden ist, auch teilweise ineinander geschoben werden. Wegen der nur geringfügig vorstehenden von den Spitzen der Querstäbe gebildeten Haken sind Handverletzungen praktisch ausgeschlossen. Die von den Spitzen der Querstäbe gebildeten Haken sind so angeordnet, daß sie bei der eingebrachten Verzugmatte vom Gebirge weg zum Streckeninneren hin weisen. Beim mechanischen Einbringen von Hinterfüllmaterial liegen die Spitzen später außerhalb des Hinterfüllmaterials, während sie bei Verwendung der Verzugmatten bei einem Ausbau ohne Hinterfüllung im ungünstigsten Fall durch das Gebirge gegen das Stahlprofi1 gedrückt und somit weiter geschlossen werden. Zur Verbindung der Drahtverzugmatte mit dem Streckenausbau, d. h. mit den Streckenprofilsegmenten, ist es möglich, an den beiden Enden jeweils aus der Bahnebene vorstehende Haken vorzusehen, die zur teilweisen Umfassung der Ausbauprofile dienea Erfindungsgemäß ist jedoch vorgesehen, daß die einzelnen Matten jeweils ineinander gehängt werden und sich an den einzelnen Profilsegmenten jeweils nur abstützen. Dies hat den Vorteil, daß nach Auflegen der Drahtverzugmatten auf die Firstsegmente und entsprechender Verkeilung dieser Drahtverzugmatten alle anderen das Streckeninnere gegen die Stöße absichernden Drahtverzugmatten an diesen jeweils befestigt, d. h. in diese eingehängt werden können. Dazu ist es lediglich erforderlich, daß die jeweils äußeren Haken ein soweit geöffnetes Maul aufweisen, daß ein entsprechender Längsstab eingeführt werden kann.Wire mesh is not connected to all longitudinal rods, and can also be partially pushed into one another. Because of the only slightly protruding hooks formed by the tips of the cross bars, hand injuries are practically impossible. The hooks formed by the tips of the cross bars are arranged in such a way that they point away from the mountains towards the inside of the track when the warping mat is introduced. In the mechanical insertion of backing material, the tips are later outside of the backfill material, while being pressed when using the lagging mats in an expansion without backfill in the worst case through the mountains against the steel profile 1 and thus further closed. To connect the wire warping mat with the extension of the track, ie with the track profile segments, it is possible to provide hooks protruding from the plane of the track at the two ends, which serve to partially enclose the extension profiles only support themselves on the individual profile segments. This has the advantage that after placing the wire warping mats on the ridge segments and wedging these wire warping mats appropriately, all other wire warping mats securing the inside of the track against the impacts can be attached to them, ie can be hooked into them. For this it is only necessary that the respective outer hooks have a mouth that is open to the extent that a corresponding longitudinal rod can be inserted.
Eine Verletzung des feinmaschigen Drahtnetzes ist vollkommen ausgeschlossen, wenn wie erfindungsgemäß vorgeschlagen, das Drahtnetz jeweils über ein U-Profil an den äußeren Längsstab geklemmt bzw. punktweise mit Längsstab und U-Profü verschweißt ist In den übrigen Bereichen liegt das Drahtnetz dann nur lose auf den Längsstäben auf. Die Längsstäbe sind dabei so dicht angeordnet, da3 Ausbeulungen des feinmaschigen Drahtnetzes weitgehendst ausgeschlossen sind.Damage to the fine-meshed wire network is completely excluded if, as proposed according to the invention, the wire network is clamped to the outer longitudinal rod via a U-profile or welded pointwise to the longitudinal rod and U-profile In the remaining areas, the wire mesh then rests only loosely on the longitudinal rods. The longitudinal bars are so tight arranged so that bulges in the fine-meshed wire network are largely excluded.
Zur Vereinfachung des Transportes sowie zur besseren Abstützung des feinmaschigen Drahtnetzes ist erfindungsgemäß vorgesehen, daß das Drahtnetz abwechselnd ober- und unterhalb der Längsstäbe verlaufend angeordnet ist. Auch hier ist das Drahtnetz jeweils nur an den beiden Endlängsstäben angeklemmtTo simplify the transport and to better support the fine-meshed wire netting, the invention provides that the wire netting extends alternately above and below the longitudinal bars is arranged. Here, too, the wire mesh is only clamped to the two end longitudinal rods
Das Drahtnetz kann auch in Querrichtung nicht verrutschen, wenn es zwischen den Längsstäben und parallel dazu liegenden und mit diesen punktweise verbundenen Flachstäben angeordnet ist Dies ist insbesondere dann vorteilhaft, wenn aufgrund eines größeren Ausbruches die zu hinterfüllende Schicht besondes dick und damit ein größerer Druck zu erwarten istThe wire mesh cannot slip in the transverse direction either if it is arranged between the longitudinal rods and flat rods lying parallel to them and connected to them at points. This is particularly important advantageous if the layer to be backfilled is particularly thick and due to a larger breakout so that greater pressure can be expected
Die Flachstäbe sind so angeordnet, daß sie vom Hinterfüllmaterial eingebettet werden. Eine bessere Armierungswirkung wird erreicht, wenn wie erfindungsgemäß vorgesehen, parallel zu den Längsstäben Rundstäbe angeordnet sind, die mit ihren Rundstabenden gegen die Spitzen der Querstäbe stoßen. Damit ist gleichzeitig eine Verstärkung der Matte erreicht, zumal die Beweg-The flat bars are arranged so that they are embedded by the backfill material. A better reinforcement effect is achieved if, as in accordance with the invention provided, round bars are arranged parallel to the longitudinal bars, which with their round rod ends against the Push the tips of the crossbars. This means that the mat is reinforced at the same time, especially since the movement ■ T äno■ T äno
ctSka rviiAinArks4&·· im /"Λι·αμ j»*·. *»»* *»·.ctSka rviiAinArks4 & ·· im / "Λι · αμ j» * ·. * »» * * »·.
geführten Längsstab eine ausreichende Drehbeweglichkeit verbleibt Fertigungstechnisch weniger aufwendig ist es, wenn die Spitzen soweit auf die Querstäbe zugebogen werden, daß das entstehende Hakenmaul eine kleinere Öffnung aufweist, als der Hakenbogen. Hierdurch wird verhindert, daß der im Hakenbogen geführte Längsstab aus dem Haken herausgedrückt oder herausgezogen wird. Besonders vorteilhaft ist, daß die erfindungsgemäßeguided longitudinal rod sufficient rotational mobility remains less expensive from a manufacturing point of view it is when the tips are bent so far towards the cross bars that the resulting hook mouth a has a smaller opening than the arch of the hook. This prevents the out of the hook arch The longitudinal rod is pushed or pulled out of the hook. It is particularly advantageous that the inventive
ίο Drahtverzugmatte, sowohl in Strecken mit mechanischer Hinterfüllung, Hinterfüllung aus Handsteinen und Strecken ohne jede Hinterfüllung verwendet werden kann. Bei der Hinterfüllung mit Beton kann sowohl von der Ortsbrust her hinterfüllt werden als auch jeweils vonίο wire mesh, both in sections with mechanical backfilling, backfilling from hand stones and Stretch can be used without any backfilling. When backfilling with concrete, both of the working face are backfilled as well as each
is der Streckenmitte her. Bei Hinterfüllung von der Strekkenmitte aus, wird die Drahtverzugmatte jeweils soweit notwendig beiseite geschoben und nach Abschluß der Hinterfüllarbeiten in diesem Bereich wieder in ihre ursprüngliche Lage zurückgebracht Das feinmaschigeis the middle of the route. When backfilling from the middle of the stretch, the wire mesh mat is always so far necessary pushed aside and after the completion of the backfilling work in this area returned to its original position The fine-meshed Drahtnetz bleibt somit durch den eigentlichen Hinterfüllvorgang völlig unverletzt und kann seine Funktion voll erfüllen.The wire mesh remains completely undamaged by the actual backfilling process and can function fully meet.
Im Folgenden wird die Erfindung anhand der Zeich-· nung, in der ein bevorzugtes Ausführungsbeispiel mitIn the following, the invention is based on the drawing tion, in which a preferred embodiment with den dazu notwendigen Einzelheiten und Einzelteilen dargestellt ist, näher erläutert Es zeigtthe necessary details and individual parts is shown, explained in more detail It shows
Fig. la Drahtverzugmatte mit abwechselnd ober- und unterhalb der Längsstäbe verlegtem Drahtnetz, F i g. Ib Schnitt durch die Drahtverzugmatte,Fig. La wire warping mat with wire mesh alternately laid above and below the longitudinal bars, F i g. Ib section through the wire warping mat,
F i g. 2a Drahtverzugmatte mit Flachstäben, F i g. 2b Schnittzeichnung, F i g. 3a Drahtverzugmatte mit Rundstäben, F i g. 3b Schnittzeichnung, Fig.4 Streckenabschnitt mit eingebrachtem VerzugF i g. 2a wire mesh mat with flat bars, F i g. 2b sectional drawing, F i g. 3a wire mesh mat with round bars, F i g. 3b sectional drawing, Fig. 4 route section with introduced delay (Querschnitt) und(Cross section) and
F i g. 5 Streckenabschnitt mit eingebrachtem Verzug (Längsschnitt).F i g. 5 route section with introduced delay (Longitudinal section).
F i g. la und b zeigen einen Ausschnitt aus einer erfindungsgemäßen Drahtverzugmatte, die wie F i g. 5 zeigtF i g. la and b show a section of a wire warping mat according to the invention which, like FIG. 5 shows als Verzug 1 im untertägigen Bergbau eingesetzt werden kann. Die einzelnen Längsstäbe 21, 23, 26 sind jei weils an ihren Enden 22 und 23 umgebogen. Dadurch entstehen jeweils an den Enden die Querstäbe 28—31. Die Querstäbe 28—31 sind dabei geringfügig aus dercan be used as delay 1 in underground mining. The individual longitudinal bars 21, 23, 26 are jei Weil bent over at their ends 22 and 23. This creates the transverse rods 28-31 at each end. The cross bars 28-31 are slightly out of the Mattenebene nach unten gebogen und verlaufen vom Knickpunkt 27 aus geringfügig zur Mattenmitte hin. Die Spitzen 32,33 der Querstäbe 28—31 sind ebenfalls umgebogen, so daß ein Haken 35 entsteht, in den das Ende 22,23 des nächsten Längsstabes eingeführt ist DadurchThe mat level is bent down and run from the Kink point 27 from slightly towards the middle of the mat. the Tips 32,33 of the transverse rods 28-31 are also bent over, so that a hook 35 is created in which the end 22.23 of the next longitudinal rod is inserted thereby entsteht, wie insbesondere F i g. Ib zeigt, eine Art Kette an beiden Seiten der Drahtverzugmatte 20, wodurch diese die gewünschte Beweglichkeit erhält. Die öffnung des Hakenmauls 36 ist dabei kleiner als der Hakenbogen 37, der den Längsstab aufzunehmen hat Ein Her-arises, as in particular F i g. Ib shows a kind of chain on both sides of the wire warping mat 20, which gives it the desired mobility. The opening of the hook mouth 36 is smaller than the hook bow 37, which has to accommodate the longitudinal rod. ausrutschen des Längsstabes ist somit nicht mögliph. Durch die besondere Art der Biegung, insbesondere der Querstäbe, im Bereich der Enden 22,23 der Längsstabe 21,25,26 wird ein zu weites Vorstehen des Hakens 35 aus der Mattenebene verhindert Insbesondere wird da-Slipping of the longitudinal rod is therefore not possible. Due to the special type of bend, especially the Cross bars, in the region of the ends 22, 23 of the longitudinal bars 21,25,26 prevents the hook 35 from protruding too far from the plane of the mat.
richtung der Drahtverzugmatte begrenzt istdirection of the wire warping mat is limited
Die Querverschieblichkeit des feinmaschigen Drahtnetzes kann erfindungsgemäß auch dadurch begrenzt werden, daß die Spitzen der Querstäbe senkrecht zu den Längsstäben verlaufen.According to the invention, the transverse displaceability of the fine-mesh wire netting can also be limited thereby be that the tips of the cross bars are perpendicular to the longitudinal bars.
Der von den Querstäben und den Querstabspitzen gebildete Haken ist erfindungsgemäß als öse ausgeführt. Dadurch ist gewährleistet daß dem in dem HakenAccording to the invention, the hook formed by the cross bars and the tips of the cross bars is designed as an eyelet. This ensures that that in the hook
6565 11, UUI UlC GIU^GIUCII LiOUgSaiaUC JEt, 4t—iD11, UUI UlC GIU ^ GIUCII LiOUgSaiaUC JEt, 4t — iD
eine Ebene bilden. Wie Fig. la und b zeigen, ist das Drahtnetz 40 jeweils abwechselnd ober- und unterhalb der Längsstäbe 21,24—26 verlaufend angeordnet, Dadurch wird ein zu großes Ausbeulen des Drahtnetzes 4Q verhindertform a level. As Fig. La and b show, that is Wire mesh 40 is arranged to run alternately above and below the longitudinal bars 21, 24-26. This results in excessive bulging of the wire mesh 4Q prevented
Das Drahtnetz 40 ist jeweils an den äußeren Längsstäben 21,24 über ein U-Profil 41 mit den Längsstäben verbunden. Dabei ist es möglich, die Verbindung rlnrrhThe wire mesh 40 is in each case on the outer longitudinal rods 21, 24 via a U-profile 41 with the longitudinal rods tied together. It is possible to use the connection rlnrrh
5 65 6
Schweißungen 42 zu verbessern. Wie dargestellt, profilen 2—4 erreicht werden.Welds 42 to improve. As shown, profiles 2-4 can be achieved.
kommt hierfür insbesondere eine Punktschweißung in Das Hinterfüllmaterial 18 wird z. B. mit Hilfe von Be-For this purpose, in particular, a spot weld comes in. The backfill material 18 is z. B. with the help of
Frage. tonpumpen entweder von der Ortsbrust 14 aus oder ausQuestion. clay pumps either from the face 14 or from
Die F i g. 2,3a und b zeigen den gleichen Gegenstand, der Streckenmitte 12 heraus in den Hohlraum 17 ge-The F i g. 2,3a and b show the same object, the middle of the route 12 out into the cavity 17
wobei lediglich parallel zu den Längsstäben 21,24—26 5 pumpt. Beim Einbringen des Hinterfüllmaterials 18 vononly pumping parallel to the longitudinal rods 21, 24-26 5. When introducing the backfill material 18 from
Flachstäbe 43 bzw. Rundstäbe 44 angeordnet sind. Die der Streckenmitte 12 aus, kann die DrahtverzugmatteFlat bars 43 or round bars 44 are arranged. The middle of the route 12 can be the wire mesh mat
Flachstäbe 43 bzw. Rundstäbe 44 sind über Punkt- 20 jeweils in dem notwendigen Bereich so verschobenFlat bars 43 or round bars 44 are shifted over point 20 in each case in the required area
schweißung 46 mit den Längsstäben 21,24—26 verbun- werden, daß die Spritze der Betonpumpe z. B. zwischenweld 46 with the longitudinal rods 21,24-26 are connected so that the syringe of the concrete pump z. B. between
dea Zwischen den Längsstäben 21, 24—26 und den den Querstäben 28—41 und dem Stoßsegment 5,6 hin-dea Between the longitudinal bars 21, 24-26 and the cross bars 28-41 and the joint segment 5,6 back
Flachstäben 43 bzw. Rundstäben 44 ist das Drahtnetz 40 10 durchgeführt werden kann. Insbesondere bei den mitFlat bars 43 or round bars 44 is the wire mesh 40 10 can be carried out. Especially with those with
angeordnet, so daß es durch die Verbindung der Längs- Rundstäben 44 ausgerüsteten Drahtverzugmatten 20arranged so that it is equipped by the connection of the longitudinal rods 44 wire warping mats 20
stäbe 21,24—26 und der Flachstäbe 43 bzw. Rundstäbe wird die Außenhaut der Hinterfüllung zusätzlich durchrods 21, 24-26 and the flat rods 43 or round rods, the outer skin of the backfill is additionally penetrated
44 gleichzeitig fixiert ist Die Stabilität der Drahtverzug- die Rundstäbe 44 armiert44 is fixed at the same time. The stability of the wire warpage - the round rods 44 are reinforced
matte 20 wird dadurch erhöht, wobei die Rundstaben- Bei Handverzug, d. h. bei Einbringen des Hinterfüll-matte 20 is increased thereby, with the round rods. H. when introducing the backfill
den 45 jeweils wie F i g. 3 zeigt, vor die Spitzen 32, 33 15 materials in Form von Handsteinen, kann im wesentii-the 45 as shown in FIG. 3 shows, in front of the tips 32, 33, 15 material in the form of hand stones, can essentially
der Querstäbe 28—31 stoßen. chen in der gleichen Art vorgegangen werden. Nachthe cross bars 28-31 butt. proceed in the same way. To
Die Einbringung des erfindungsgemäßen Verzuges 1 Herstellen des Kappenschirms aus den Kappen 7, denThe introduction of the delay 1 according to the invention manufacturing the canopy from the caps 7, the
wird mit Hilfe der Fig.4 und 5 erläutert Nach dem nicht dargestellten Abstandshaltern bzw. Bolzen undis explained with the help of FIGS. 4 and 5 After the spacers or bolts and not shown
Abtun der Schüsse werden zunächst die aus einem oder den Drahtverzugmatten 20 wird die zur AbsicherungThe shots are first removed from one or the wire warping mats 20 for protection
mehreren Segmenten bestehenden Kappen 7 als bereits 20 des Stoßes vorgesehene Hinterfüllmatte entweder inseveral segments existing caps 7 as already 20 of the joint provided backfill mat either in
vorher fertiggestellter Schirm oder einzeln mit Hilfe einer Bahn oder aus mehreren einzelnen Matten beste-previously completed umbrella or individually with the help of a sheet or composed of several individual mats
von Vorpfändschienen unter der Firste 15 angeordnet hend an den letzten Längsstab der an der Firste fixiertenarranged by pre-pledging rails under the roof 15 starting to the last longitudinal bar of the fixed to the roof
Der Abstand der Streckenprofile 2—4 wird über Ab- Drahtverzugmatte 20 angebracht und während des ,iThe distance between the section profiles 2-4 is attached via a wire-warping mat 20 and during the, i
standseisen bzw. Bolzen sichergestellt Die Zwischen- Wegladens des Haufwerkes in geeigneter Weise abge- i*.;was iron or bolt ensures the intermediates Wegladens off the pile material suitably * i .;
räume zwischen den Streckenprofilen 2—4 bzw. deren 25 stützt, um dann endgültig hinter den Stoßsegmenten ;jspaces between the route profiles 2-4 or their 25 supports, to then finally behind the joint segments ; j
Kappen 7 sind mit Drahtverzugmatten 20 abgedeckt 5—6 angeordnet zu werden. Danach werden die Hand- iiCaps 7 are covered with wire mesh mats 20 to be arranged 5-6. Then the hand ii
Die Drahtverzugmatten 20 sind mit dem Gebirge ver- steine jeweils eingebracht indem die Drahtverzugmatte νThe wire warping mats 20 are each introduced with the rock in that the wire warping mat ν
keilt oder durch entsprechende Hakenanordnungen mit 20 in dem erforderlichen Bereich und soweit nötig bei- >,wedges or by corresponding hook arrangements with 20 in the required area and if necessary with->,
den Kappen fest verbunden. Die Verkeilung mit dem seite geschoben wird. Dies geschieht von der Sohle 16 |;firmly connected to the caps. The wedging with the side is pushed. This is done from the sole 16 |;
Gebirge kann auch dadurch erreicht werden, daß be- 30 beginnend in Richtung Firste 15. :&■Mountains can also be reached by starting in the direction of Firste 15.: & ■
reits in diesem Bereich Hinterfüllmaterial 18 einge- Noch einfacher ist die Verwendung der erfindungsge- |§backfill material 18 has already been included in this area. It is even easier to use the inventive | §
bracht wird. Danach wird das losgeschossene Bergema- mäßen Drahtverzugmatte 20 dann, wenn überhaupt §kis brought. Thereafter, the released mountain-sized wire warping mat 20 is then, if at all, §k
terial oder Kohle/Bergegemisch geladen. Um die Aufla- kein Hinterfüllmaterial eingebracht werden muß, da ?fmaterial or coal / recovery mixture loaded. No backfill material has to be introduced around the top, so that
gen der Bergbehörde zur Sicherung der Stöße 13 zu dann bereits mit dem Anbringen der Stoßsegmente 5,6 ;;,.gene of the mining authority to secure the joints 13 to then already with the attachment of the joint segments 5,6; ; ,.
erfüllen, können mehrere erfindungsgemäße Drahtver- 35 die notwendige Verbindung zwischen Gebirge 11, S*meet, several wire connections according to the invention can provide the necessary connection between mountains 11, S *
zugmatten an die über die Kappen fixierten Drahtver- Drahtverzugmatte 20 und Streckenprofil 2—4 bzw. ptension mats to the wire mesh wire mesh mat 20 and section profile 2—4 or p, which are fixed over the caps
zugmatten 20 angehängt werden. Dazu sind jeweils die 2—6 erreicht wird. Insbesondere bei der zuletzt genann- 11Zugmatten 20 are attached. For this purpose, the 2-6 is reached in each case. Especially with the last mentioned 11
Hakenmäuler 36 der Endhaken soweit geöffnet, daß sie ten Verwendung der erfindungsgemäßen Drahtverzug- ig Hook mouths 36 of the end hook opened so as to th use of the invention Drahtverzug- ig
über die Längsstäbe der fixierten Matten geschoben matten ist es ausreichend, wenn das feinmaschige gmats pushed over the longitudinal bars of the fixed mats, it is sufficient if the fine-meshed g
werden können. Dabei ist es besonders vorteilhaft, eine 40 Drahtnetz jeweils nur an den äußeren Längsstäben 21, Acan be. It is particularly advantageous to use a wire mesh only on the outer longitudinal rods 21, A
von den üblichen Mattengrößen abweichende Matte 24 Fixiert ist und im übrigen abwechselnd ober- und ~g Mat 24, which differs from the usual mat sizes, is fixed and otherwise alternately above and ~ g
vorzusehen, die z. B. den gesamten Bereich zwischen unterhalb der Längsstäbe 21 und 24—26 verlaufend an- ||provide the z. B. the entire area between below the longitudinal bars 21 and 24-26 extending to ||
der letzten über die Kappe fixierten Drahtverzugmatte geordnet ist Ein Verrutschen in Querrichtung wird da- öthe last wire mesh mat fixed over the cap is in order. Slipping in the transverse direction will result
bis zur Sohle 16 reicht Um ein Hereinhängen der bei weitgehendst dadurch verhindert, daß die Spitzen ρup to the sole 16 is enough to hang in the largely prevented by the fact that the peaks ρ
Drahtverzugmatte 20 in die Streckenmitte zu verhin- 45 32,33 der Querstäbe 28—31 senkrecht zu den Längsstä- feWire warping mat 20 in the middle of the route 45, 32, 33 of the transverse bars 28-31 perpendicular to the longitudinal bars
dem, kann die Drahtverzugmatte 20 jeweils über Kurz- ben 21 und 24—26 verlaufen. Die Außenkanten 47 des λThat is, the wire mesh mat 20 can run over abbreviations 21 and 24-26, respectively. The outer edges 47 of the λ
anker, Keile o. ä. mit dem Gebirge verbunden oder aber feinmaschigen Drahtnetzes 40 stoßen dabei jeweils ge- ^Anchors, wedges or the like connected to the rock or fine-meshed wire netting 40 each come up against it
mit Hilfe von Stützen abgestützt werden. Nach dem gen die Spitzen 32,33 der Querstäbe 28—31. fi be supported with the help of supports. After that the tips 32,33 of the cross bars 28-31. fi
Wegladen des gesamten Haufwerks werden dann die ;Downloading the entire heap will then be the;
Stoßsegmente 5,6 eingebracht, die über Laschen 8 mit 50 Hierzu 3 Blatt ZeichnungenJoint segments 5, 6 introduced, which are connected via tabs 8 with 50. 3 sheets of drawings
den Kappen 7 verbunden werden. Die Stoßsegmente 5, the caps 7 are connected. The joint segments 5,
6 halten dann die Drahtverzugmatte in dem Abstand6 then hold the wire warping mat at the distance
vom Gebirge 11, daß anschließend das Hinterfüllmateri- ^from the mountains 11, that then the back-filling material ^
al 18 in den Hohlraum 17 eingebracht werden kann. Die g|Al 18 can be introduced into the cavity 17. The g |
Drahtverzugmatten 20 sind somit jeweils auf der Au- 55 ffWire warping mats 20 are thus each on the Au- 55 ff
ßenseite 10 der Streckenprofile 2—4 angeordnet, wäh- ||Outside 10 of the route profiles 2-4 arranged, wäh- ||
rend eventuelle Befestigungshaken 39 über die Innen- Jwrend possible fastening hooks 39 over the inner Jw
seite 9 hinweg hinter das jeweilige Profil greifen. ||page 9 reach behind the respective profile. ||
Wie F i g. 5 insbesondere zeigt, liegt die Drahtverzug- £fLike F i g. 5 shows in particular that the wire warpage is £ f
matte 20 nahezu in Form eines Kettenhemdes hinter ω ||matte 20 almost in the form of a chain mail behind ω ||
den Streckenprofilen 3—4, wobei das dargestellte fein- Hthe route profiles 3–4, with the fine H
maschige Drahtnetz 40 als Verschalung wirkt bzw. den §*meshed wire mesh 40 acts as cladding or the § *
Streckenhohlraum gegen Steinfall aus dem Stoß sichert ©Section cavity protects against falling stones from the joint ©
Die Enden 22,23 benachbarter Matten sind so angeord- §5The ends 22, 23 of adjacent mats are arranged in this way
net, daß sie sich überlappen. Werden Glockenprofile 65 Ilnot that they overlap. If bell profiles 65 Il
oder diesen gleiche verwendet so kann durch die beson- *5or this same can be used by the special * 5
dere Biegung im Bereich der Enden 22, 23 sogar ein Ig their bend in the area of the ends 22, 23 even an Ig
Verhaken der Drahtverzugmatte 20 mit den Strecken- %?Does the wire warping mat 20 get caught in the route%?
Claims (7)
Drahtnetz aus dünnerem Draht aufweist, wobei die Unter besonderen Voraussetzungen und bei Erfül-Maschenweite des Drahtnetzes so gewählt ist, daß lung von Auflagen der Aufsichtsbehörden können derdas zurückzuhaltende HinterfüUmaterial nicht das 10 artige Strecken auch ohne Hinterfüllung mit mecha-Drahtnetz durchdringen kann, dadurch ge- nisch eingebrachtem HinterfüUmaterial oder mit Handkennzeichnet, daß die Querstäbe (28—31) steinen aufgefahren werden. Das feinmaschige Drahtdurch Umbiegen im wesentlichen in der Mattenebe- netz verhindert dabei ein Durchrieseln oder Durchdrinne aus den beiden Enden (22,23) der Längsstäbe (21 gen feinkörniger Bergeteilchen.1. Wire warping mat for the trench, in particular the task of supporting the liquid state of the line expansion in the underground mining and backfoot material for so long and of holding back tunnel construction, the several parallel longitudinal bars and until it has hardened at the same time serves these vertically running cross bars as well as a kind of reinforcement for the backfoot material.
Has wire mesh made of thinner wire, whereby the under special conditions and when the mesh size of the wire mesh is met, the backfoot material to be retained cannot penetrate the 10-like stretch even without backfilling with mecha wire mesh. Nisch introduced backfoot material or with hand marks that the cross bars (28-31) stones are driven up. The fine-meshed wire, which is essentially bent over in the mat net, prevents fine-grained mountain particles from trickling through or through from the two ends (22, 23) of the longitudinal rods (21).
durch gekennzeichnet, daß das Drahtnetz (40) ab- Es ist ferner bekannt, ein zwischen den Längs- und wechselnd ober- und unterhalb der Längsstäbe (21 Querstäben einer solchen Matte angeordnetes Draht- und 24—26) verlaufend angeordnet ist 30 netz als Armierungsnetz für ein sehr engmaschiges oder3. Wire warping mat according to spoke 1 and 2, that the dust or backing material can escape,
It is also known that a wire mesh and 24-26 arranged between the longitudinal rods and alternately above and below the longitudinal rods (21 transverse rods of such a mat and 24-26) is arranged as a reinforcement mesh for a very close-knit or
gigen Berg- und Tunnelbau, die mehrere, parallele Gemäß der Erfindung wird diese Aufgabe dadurch Längsstäbe und zu diesen senkrecht verlaufende Quer- gelöst, daß die Querstäbe durch Umbiegen im wesentlistäbe sowie ein Drahtnetz aus dünnerem Draht auf- chen in der Mattenebene aus den beiden Enden der weist, wobei die Maschenweite des Drahtnetzes so ge- Längsstäbe gebildet sind, daß die Spitzen der Querstäbe wählt ist, daß das zurückzuhaltende Hinterfüllmaterial 60 die Enden des jeweils nächsten Längsstabes umfassend nicht das Drahtnetz durchdringen kann. und unter Bildung eines Hakens wiederum umgebogen Derartige Drahtverzugmatten werden im untertäti- sind und daß das zwischen den beiden äußeren Längsgen Berg- und Tunnelbau, insbesondere in den Berei- stäben verspannte Drahtnetz nur durch die Längsstäbe chen zusammen mit Stahlprofilbögen eingesetzt, in de- gestützt ist.The invention relates to a wire warping mat for which rigidity is easy to transport, easy to bring in and trench, in particular route expansion, can also be used as a temporary warpage.
According to the invention, this object is achieved by longitudinal bars and transverse bars running perpendicular to them, in that the cross bars are essentially bent over and a wire mesh of thinner wire is opened in the mat plane from the two ends which has, the mesh size of the wire netting being formed in such a way that the tips of the transverse bars are chosen so that the backfill material 60 to be retained cannot penetrate the wire netting including the ends of the next longitudinal bar. and again bent over to form a hook. Such wire mesh mats are in the underside and that the wire mesh tensioned between the two outer longitudinal lines of mining and tunnel construction, especially in the areas, is only inserted through the longitudinal rods together with steel profile arches .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19782856474 DE2856474C2 (en) | 1978-12-28 | 1978-12-28 | Wire mesh mat for pit construction, especially for route expansion in underground mining and tunnel construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19782856474 DE2856474C2 (en) | 1978-12-28 | 1978-12-28 | Wire mesh mat for pit construction, especially for route expansion in underground mining and tunnel construction |
Publications (2)
Publication Number | Publication Date |
---|---|
DE2856474A1 DE2856474A1 (en) | 1980-07-10 |
DE2856474C2 true DE2856474C2 (en) | 1986-10-09 |
Family
ID=6058570
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19782856474 Expired DE2856474C2 (en) | 1978-12-28 | 1978-12-28 | Wire mesh mat for pit construction, especially for route expansion in underground mining and tunnel construction |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE2856474C2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108194108B (en) * | 2018-03-05 | 2023-10-20 | 霍州煤电集团有限责任公司 | Electric portable metal net automatic connecting device for coal mine tunnel |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2437323C2 (en) * | 1974-08-02 | 1983-09-08 | Drahtwerke Rösler Soest GmbH & Co KG, 4770 Soest | Roll-out warp mat web for route expansion in mining and tunnel construction |
DE2825160A1 (en) * | 1978-06-08 | 1979-12-13 | Ruhrkohle Ag | Mine type backfilling concrete reinforcing mat - has longitudinal bars on ridge side with ends bent towards ridge |
-
1978
- 1978-12-28 DE DE19782856474 patent/DE2856474C2/en not_active Expired
Also Published As
Publication number | Publication date |
---|---|
DE2856474A1 (en) | 1980-07-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2734717A1 (en) | METHOD AND DEVICE FOR REMOVING AN UNDERGROUND ROUTE OR TUNNEL | |
DE2856474C2 (en) | Wire mesh mat for pit construction, especially for route expansion in underground mining and tunnel construction | |
DE3027661C2 (en) | Extension of the line to intercept the layers of the slope and to secure the line edge in the stretches of underground mining | |
DE3601587C2 (en) | ||
DE2503014C3 (en) | Wire mesh mat for routes in mining and tunnel construction | |
AT402534B (en) | METHOD FOR DRIVING A TUNNEL OR THE LIKE AND REMOVAL REINFORCEMENT FOR IMPLEMENTING THE METHOD | |
DE2825160A1 (en) | Mine type backfilling concrete reinforcing mat - has longitudinal bars on ridge side with ends bent towards ridge | |
DE4104298C2 (en) | Profile reinforcement mat | |
DE2854579A1 (en) | Mine gallery or tunnel reinforcement roll=up mat - has regularly ascending wire spirals enclosing longitudinal bars | |
DE2408038C3 (en) | Process to reduce subsidence in the expansion of multi-part underground cavities | |
DE2923016C2 (en) | Composition consisting of flexible shells that can be connected to one another and filled with material capable of binding to fill in cavities, in particular cavities in mining | |
DE2159486C3 (en) | Process and devices for the production of underground structures in hydraulic jacking | |
DE2842441A1 (en) | Steel support mesh for mine or tunnel gallery - has longitudinally extending bars and narrower woven reinforcement in integrated framework | |
DE2616970C3 (en) | Method and shuttering element for the production of a diaphragm wall in a prefabricated composite construction | |
DE3208177C2 (en) | ||
DE3326430A1 (en) | Reusable formwork for the composite supports and back-filling method | |
DE3336153A1 (en) | Construction-material body | |
DE2721155A1 (en) | Tunnel lining quick hardening cement application - uses plastics sheet receiving foam layer before injecting quick hardening layer | |
DE2734874B2 (en) | Process for introducing delay in the expansion of the mining and tunnel construction and delay mat for carrying out the process | |
DE3815674C2 (en) | ||
DE3241848C2 (en) | ||
DE2215522C3 (en) | Process for lining underground cavities, especially in mining and tunnel construction, with reinforced shotcrete and reinforcement for carrying out the process | |
DE2949859C2 (en) | Process for the production of crates transversely to the route axis | |
CH674535A5 (en) | Concrete-wall formation method against rock face - involves installing reinforcing members protruding from shuttering after delivery to site | |
DE2949963A1 (en) | Mine or tunnel gallery composite support reinforcement - involves stretching new warping mats in close tiers across support profiles front |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8110 | Request for examination paragraph 44 | ||
D2 | Grant after examination | ||
8364 | No opposition during term of opposition | ||
8339 | Ceased/non-payment of the annual fee |