DE20110764U1 - Drainage channel body, in particular made of polymer concrete - Google Patents
Drainage channel body, in particular made of polymer concreteInfo
- Publication number
- DE20110764U1 DE20110764U1 DE20110764U DE20110764U DE20110764U1 DE 20110764 U1 DE20110764 U1 DE 20110764U1 DE 20110764 U DE20110764 U DE 20110764U DE 20110764 U DE20110764 U DE 20110764U DE 20110764 U1 DE20110764 U1 DE 20110764U1
- Authority
- DE
- Germany
- Prior art keywords
- channel
- web
- groove
- channel body
- face
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000002986 polymer concrete Substances 0.000 title claims abstract description 6
- 230000007704 transition Effects 0.000 claims description 3
- 230000005484 gravity Effects 0.000 claims description 2
- 238000007789 sealing Methods 0.000 claims 1
- 230000008878 coupling Effects 0.000 abstract description 2
- 238000010168 coupling process Methods 0.000 abstract description 2
- 238000005859 coupling reaction Methods 0.000 abstract description 2
- 239000004567 concrete Substances 0.000 description 5
- 238000011065 in-situ storage Methods 0.000 description 5
- 238000009434 installation Methods 0.000 description 3
- 244000309464 bull Species 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000000565 sealant Substances 0.000 description 1
- 239000003566 sealing material Substances 0.000 description 1
- 238000011144 upstream manufacturing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/04—Pipes or fittings specially adapted to sewers
- E03F3/046—Open sewage channels
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Sewage (AREA)
- Orthopedics, Nursing, And Contraception (AREA)
- Addition Polymer Or Copolymer, Post-Treatments, Or Chemical Modifications (AREA)
- Compositions Of Macromolecular Compounds (AREA)
- Separation Of Suspended Particles By Flocculating Agents (AREA)
- Tires In General (AREA)
Abstract
Description
PATENT- UND RECHTSANWÄLTE MEINKE, DABRINGHAUS UND PARTNER GbRPATENT AND LAWYERS MEINKE, DABRINGHAUS AND PARTNER GbR
ZUGELASSEN BEIM EUROPÄISCHEN PATENTAMT UND GEMEINSCHAFTSMARKENAMT EUROPEAN PATENT AND TRADEMARK ATTORNEYS*ADMISSIONED AT THE EUROPEAN PATENT AND TRADEMARK OFFICE EUROPEAN PATENT AND TRADEMARK ATTORNEYS*
PATENTANWÄLTE'PATENT ATTORNEYS'
JULIUS MEINKE, dipl.-ing. WALTER DABRINGHAUS, dipl.-ing. JOCHEN MEINKE, dipl.-ing.JULIUS MEINKE, dipl.-ing. WALTER DABRINGHAUS, dipl.-ing. JOCHEN MEINKE, dipl.-ing.
RECHTSANWALTLAWYER
THOMAS MEINKETHOMAS MEINKE
ROSA-LUXEMBURG-STRASSE 44141 DORTMUNDROSA-LUXEMBURG-STRASSE 44141 DORTMUND
TELEFON (0231)58 41 90 TELEFAX (0231) 14 76 70 info @ patent-recht.cteTELEPHONE (0231)58 41 90 TELEPHONE (0231) 14 76 70 info @ patent-recht.cte
POSTFACH 10 46 45PO BOX 10 46 45
44046 Dortmund, 28. Juni 200144046 Dortmund, 28 June 2001
DRESDNER BANK AG DTMD, Kto.-Nr. 1 148 047 (BLZ 440 800 50) POSTBANK DORTMUND, Kto.-Nr. 542 02-463 (BLZ 440 100 46)DRESDNER BANK AG DTMD, Account No. 1 148 047 (bank code 440 800 50) POSTBANK DORTMUND, Account No. 542 02-463 (bank code 440 100 46)
AKTEN-NR. 13/16480 D/Dr swFILE NO. 13/16480 D/Dr sw
Anmelderin: Rita BroermannApplicant: Rita Broermann
'Drainaae-Rinnenkörper, insbesondere aus Polvmerbeton"'Drainage channel bodies, in particular made of polymer concrete'
I :&Ggr;":·: : &iacgr;I :&Ggr;":·: : &iacgr;
'Drainaqe-Rinnenkörper, insbesondere aus Polvmerbeton' ' Drainage channel bodies, in particular made of polymer concrete'
Die Erfindung richtet sich auf einen Drainage-Rinnenkörper, insbesondere aus Polymerbeton, als Kastenrinne oder Schlitzrinne mit wahlweise eingebautem Sohlengefälle in der Rinneninnensohle als Teilelement eines Drainagesystemes.The invention relates to a drainage channel body, in particular made of polymer concrete, as a box channel or slot channel with optionally built-in sole gradient in the channel inner sole as a partial element of a drainage system.
Derartige Drainage-Rinnenkörper gibt es in unterschiedlicher Gestaltung, lediglich als Beispiel sei hier auf die DE-84 35 101-Ul, DE-35 15 917-Al, DE-40 07 296-C2, DE-44 36 460-Al oder die europäischen Patentanmeldungen 0 112 287, 0 380 901 oder 0 758 038 verwiesen. Dabei ist es auch bekannt, derartige Rinnen zum gesamten Entwässerungssystem zusammenzustellen, wobei dem Benutzer Rinnensegmente bzw. Rinnenabschnitte zur Verfügung gestellt werden mit eingebautem Gefälle. Um hier die richtige Reihenfolge zu treffen, wird in der Regel in die Außenwand nicht nur ein Pfeil in Fließrichtung eingebracht, sondern auch Nummern, um aus einem Bausatz die Rinnenabschnitte in der richtigen Reihenfolge zusammensetzen zu können, wobei die Montage in der Regel bei der höchsten Ziffer beginnt, die auch gleichzeitig die tiefste Stelle des Rinnenabschnittes bedeutet zurück zur kleinsten Nummer, etwa von Rinne Nr. 9 ausgehend zurück Nr. 8 auf die Nr. 9, Nr. 7 auf die Nr. 8 usw.Such drainage channel bodies are available in different designs; just as an example, reference is made to DE-84 35 101-Ul, DE-35 15 917-Al, DE-40 07 296-C2, DE-44 36 460-Al or the European patent applications 0 112 287, 0 380 901 or 0 758 038. It is also known to put such channels together to form a complete drainage system, whereby the user is provided with channel segments or channel sections with a built-in gradient. In order to ensure the correct sequence, not only an arrow in the direction of flow is usually inserted into the outer wall, but also numbers so that the gutter sections can be assembled in the correct order from a kit. Assembly usually begins with the highest number, which also means the lowest point of the gutter section, back to the smallest number, for example starting from gutter No. 9, back to No. 8 to No. 9, No. 7 to No. 8, etc.
Beim Verlegen beginnt man also am Abfluß und arbeitet sichWhen laying, you start at the drain and work your way
dann "stromaufwärts" weiter. Wird diese Technik angewandt, ist es möglich, zunächst z.B. auf einem Ortbeton ein Rinnenstück zu setzen, das dann auf der Stirnseite mit einer eingeformten vorspringenden Auflagehalbnut ausgerüstet ist. Die nachfolgende Rinne kann von oben mit ihrem entsprechenden Vorsprung eingesetzt werden. Es gibt aber auch Halbrinnen, die rechts und links außen Anschlußöffnungen über Sollbruchstellen aufweisen, wobei in diesen Bereichen auch entsprechende Halbnuten vorgesehen sind, um rechtwinklig verlaufende Zuläufe zum Rinnensystem zu ermöglichen.then continue "upstream". If this technique is used, it is possible to first place a section of channel on, for example, in-situ concrete, which is then equipped with a molded, protruding support half-groove on the front side. The subsequent channel can be inserted from above with its corresponding projection. However, there are also half-channels that have connection openings on the right and left outside via predetermined breaking points, whereby corresponding half-grooves are also provided in these areas to enable right-angled inlets to the channel system.
Ein Nachteil der bekannten Lösungen besteht u.a. darin, daß ein Verlegen der Rinnenelemente in einem Strang mit wechselnden Gefällerichtungen auf Probleme stößt, insbesondere an den mittleren Hochpunktlagen des Stranges, da dort Rinnensegmente zusammenstoßen, deren stirnseitige Ausbildung nicht miteinander koppelbar ist.One disadvantage of the known solutions is that laying the gutter elements in a line with changing gradient directions encounters problems, especially at the middle high point positions of the line, since there gutter segments collide whose frontal design cannot be coupled with each other.
Da hierbei Teile des Rinnenstranges entgegen der zugedachten Einbaurichtung verlegt werden, entsteht hier eine Erschwernis beim Einbau.Since parts of the gutter line are laid against the intended installation direction, this makes installation more difficult.
Darüber hinaus ist es bekannt, in einer Stirnwandseite ein Loch und in der korrespondierenden einen Zapfen vorzusehen, um das Ausfluchten der Rinnenstücke beim Verlegen zu erleichtern, die beiden Elemente können dann ineinander ein-In addition, it is known to provide a hole in one end wall and a tenon in the corresponding one to facilitate the alignment of the gutter pieces during installation, the two elements can then be inserted into each other.
: &igr;: &igr;
geschoben werden. Ein Nachteil besteht allerdings darin, daß bei neu zu verlegenden Rinnenstücken das neue Stück auf das bereits verlegte Stück zugeschoben werden muß, so daß sich beim Zusammenschieben in der Fugenebene Material anhäufen kann, derart, daß die Trennfuge nicht mehr zum Schließen gebracht werden kann, ein besonderes Problem bildet sich bei der Verlegung auf frischem Ortbeton.A disadvantage, however, is that when new gutter sections are to be laid, the new section must be pushed onto the section already laid, so that when pushed together, material can build up in the joint plane to such an extent that the separating joint can no longer be closed; a particular problem arises when laying on fresh in-situ concrete.
Aufgabe der Erfindung ist die Schaffung einer Stirnseitengestaltung derartiger Rinnenteilstücke, die sowohl ein Koppeln und ein genaues Fluchten der Rinnenstücke ermöglicht, gleichzeitig aber auch das Zusammenschieben auf bereits aufgebrachtem Ortbeton oder einer entsprechend vorbereiteten Oberfläche vermeidet, d.h. trotz Fluchten ein Einsetzen von oben möglich macht.The object of the invention is to create a front side design of such gutter sections which enables both coupling and precise alignment of the gutter sections, but at the same time also avoids pushing them together on already applied in-situ concrete or a correspondingly prepared surface, i.e. makes insertion from above possible despite alignment.
Bei einem Drainage-Rinnenkörper der eingangs bezeichneten Art wird diese Aufgabe gemäß der Erfindung dadurch gelöst, daß stirnseitig in einem der beiden U-Schenkel ein in der Gebrauchslage im wesentlichen senkrecht verlaufender, nach außen weisender Steg und in dem anderen U-Schenkel eine in der Gebrauchslage im wesentlichen senkrechte Nut zum Eingriff des Steges einer Nachbarrinne vorgesehen ist, wobei die Länge der jeweiligen Nut in der senkrechten Ausdehnung sowohl nach oben wie auch nach unten größer ist als die Längenausdehnung des entsprechenden Steges.In a drainage channel body of the type described at the outset, this object is achieved according to the invention in that a web which runs essentially vertically and points outwards in the position of use is provided on the front side in one of the two U-legs and a groove which runs essentially vertically in the position of use for engagement with the web of a neighboring channel is provided in the other U-leg, the length of the respective groove in the vertical extension both upwards and downwards being greater than the length of the corresponding web.
Dadurch, daß die Nut in ihrer Längserstreckung größer ist als der einzusetzende Steg, ist es möglich, ein neu zu verlegendes Rinnenstück zunächst oberhalb der vorbereiteten Auflagefläche, z.B. oberhalb des Ortbetons, an das bereits verlegte Stück heranzuführen, die Nut und die Feder zusammenzuschieben und dann das Rinnenelement abzusenken, und zwar geführt in der jeweiligen Nut durch Eingriff der etwas kürzeren Feder, die damit die Absenkung möglich macht.Because the groove is longer than the web to be used, it is possible to first guide a new piece of gutter to be laid above the prepared support surface, e.g. above the in-situ concrete, to the piece already laid, push the groove and the tongue together and then lower the gutter element, guided in the respective groove by the engagement of the slightly shorter tongue, which thus makes the lowering possible.
Ausgestaltungen der Erfindung ergeben sich aus den Unteransprüchen, wobei vorgesehen sein kann, die Anordnung des Steges bzw. der Nut in der gegenüberliegenden Stirnfläche des Rinnenkörpers umschlagsymmetrisch zu vertauschen, derart, daß eine Rinnenseite auf der einen Seite über einen Steg und auf der anderen Seite über eine Nut verfügt.Embodiments of the invention emerge from the subclaims, wherein it can be provided that the arrangement of the web or the groove in the opposite end face of the channel body is exchanged in a symmetrical manner, such that one channel side has a web on one side and a groove on the other side.
Jede der beiden stirnseitigen Enden kann im Bereich der Rinneninnenseite eine entsprechende Halbnut bzw. Ausfräsung aufweisen, derart, daß beim Zusammenbau zweier Rinnenkörper eine im wesentlichen U-förmige Nut zur Einbringung eines Dichtmittels entsteht.Each of the two front ends can have a corresponding half-groove or milled recess in the area of the inside of the gutter, such that when two gutter bodies are assembled, a substantially U-shaped groove is created for the introduction of a sealant.
Nach der Erfindung kann auch vorgesehen sein, daß in jedem Übergangsbereich der beiden U-Schenkel zum die Rinnensohle bereitstellenden U-Steg auf einer der Stirnseiten je eine in Schwerkraftrichtung eine untere Auflagefläche ausbilden-According to the invention, it can also be provided that in each transition area of the two U-legs to the U-web providing the channel bottom, on one of the front sides, a lower support surface is formed in the direction of gravity.
• &igr;» a m·a ·♦ «· *•&igr;» a m a ♦ « *
aaa mi ·«*· ·· ··aaa mi ·«*· ·· ··
a · aa · a
a aa a
« a« a
a a a a a a aa a a a a a a
de nischenförinige Eingrif fsausnehmung und auf der anderen stirnseitigen Rinnenfläche zwei nach außen weisende, eine Auflagefläche bildende Nocken ausgebildet sind, wobei in der Gebrauchslage sich die Nocken der einen Rinnenstirnseite auf die Auflagefläche der Ausnehmungen in der anderen Stirnseite auflegen.the niche-shaped engagement recess and on the other front surface of the channel two outward-facing cams forming a support surface are formed, wherein in the position of use the cams of one front side of the channel rest on the support surface of the recesses in the other front side.
Das Bereitstellen zweier Auflageflächen auf eine Stirnseite eines Rinnenkörpers einerseits und das Vorsehen zweier Nocken andererseits, die korrespondierende Auflageflächen aufweisen, in der anderen Stirnseite des Rinnenkörpers ermöglicht ein Auflegen des einen Rinnenelementes auf das andere bei der Montage.The provision of two support surfaces on one end face of a gutter body on the one hand and the provision of two cams on the other end face of the gutter body, which have corresponding support surfaces, enables one gutter element to be placed on the other during assembly.
Auch hier ist vorgesehen, daß die Höhe der nischenförmigen Eingriffsausnehmung größer ist als die Erstreckung der Eingrif fsnocken in der Senkrechten, derart, daß die Einschub- und Absenkbewegung, wie oben schon näher beschrieben wurde, auch hier möglich gemacht wird, d.h. der neu zu verlegende Rinnenkörper kann zunächst oberhalb der Auflagefläche in den bereits verlegten Rinnenkörper eingesetzt bzw. eingeschoben und dann an seine Position abgesenkt werden.Here too, it is intended that the height of the niche-shaped engagement recess is greater than the vertical extension of the engagement cams, in such a way that the insertion and lowering movement, as described in more detail above, is also made possible here, i.e. the new gutter body to be laid can first be inserted or pushed into the already laid gutter body above the support surface and then lowered into its position.
Um die Nachteile bei der weiter oben schon erwähnten Verlegung eines Stranges mit wechselnden Gefällerichtungen zu beheben, ist nach der Erfindung vorgesehen, daß die Aufla-In order to eliminate the disadvantages of laying a line with changing gradient directions as mentioned above, the invention provides that the support
genocken selbst ebenfalls in Nischen der Stirnseiten zur Bildung von Sollbruchstellen nach außen ragend ausgebildet sind, d.h. sie können beispielsweise durch ein einfaches Aufschlagen mit einein Hammer abgebrochen werden und stören dann nicht mehr bei einem Zusammenbau zweier gleich gestalteter Stirnflächen im oberen oder unteren Rinnenscheitelpunkt .The cams themselves are also designed to protrude outwards in niches in the front sides to form predetermined breaking points, i.e. they can be broken off by simply hitting them with a hammer, for example, and then no longer interfere with the assembly of two similarly designed front surfaces at the upper or lower gutter apex.
Weitere Merkmale, Einzelheiten und Vorteile der Erfindung ergeben sich aufgrund der nachfolgenden Beschreibung sowie anhand der Zeichnung. Diese zeigt inFurther features, details and advantages of the invention will become apparent from the following description and the drawing. This shows in
Fig. 1Fig.1
eine stirnseitige Aufsicht auf einen Rinnenkörper nach der Erfindung,a front view of a gutter body according to the invention,
Fig. 2Fig. 2
einen Schnitt gemäß Linie II-II in Fig. 1 im Fugenbereich zweier benachbarter Rinnenkörper, a section along line II-II in Fig. 1 in the joint area of two adjacent gutter bodies,
Fig. 3 und 4 Schnitte gemäß Linien III bzw. IV in Fig. 2,Fig. 3 and 4 sections according to lines III and IV in Fig. 2,
Fig. 5 und 6 stirnseitige Aufsichten auf die beiden unterschiedlichen Seiten eines Rinnenkörpers in einem weiteren Ausführungsbeispiel sowie in denFig. 5 and 6 frontal views of the two different sides of a channel body in a further embodiment and in the
• ·· &igr;• ·· &igr;
Fig. 7,8 und 9 jeweils Schnitte durch den Fugenbereich gemäß der Linien VII, VIII bzw. IX in Fig. 6 bzw. 7,Fig. 7,8 and 9 are sections through the joint area according to lines VII, VIII and IX in Fig. 6 and 7 respectively,
In den Figuren ist mit 1 allgemein der Drainage-Rinnenkörper nach der Erfindung bezeichnet, wobei auf die vollständige Darstellung eines Rinnenkörpers hier verzichtet wurde, da es erfindungsgemäß im wesentlichen auf die Ausbildung der Stirnflächen und des sich beim Zusammensetzen dadurch ergebenden Fugenbereiches ankommt.In the figures, 1 generally designates the drainage channel body according to the invention, whereby the complete representation of a channel body has been omitted here, since the invention essentially depends on the formation of the end faces and the joint area resulting from the assembly.
Beim Ausführungsbeispiel nach den Fig. 1 bis 4 weist jede mit 2 bezeichnete Stirnseite des querschnittlich U-förmigen Rinnenkörpers 1 in einem U-Schenkel 2a einen nach außen ragenden Steg 3 auf, in dem anderen U-Schenkel 2b eine Nut 4, derart, daß der Steg 3 und eine Stirnseite eines Rinnenkörpers 1 in die Nut 4 des Nachbarrinnenkörpers la eingreifen kann.In the embodiment according to Figs. 1 to 4, each end face designated 2 of the cross-sectionally U-shaped gutter body 1 has an outwardly projecting web 3 in one U-leg 2a and a groove 4 in the other U-leg 2b, such that the web 3 and an end face of a gutter body 1 can engage in the groove 4 of the neighboring gutter body 1a.
Wie sich insbesondere aus Fig. 3 bzw. Fig. 4 ergibt, ist die Längsausdehnung der Nut 4 insbesondere nach oben länger als die Längsausdehnung des Steges 3, so daß es möglich ist, nach Verlegen eines Rinnenkörpers 1 den Nachbarrinnenkörper la zunächst über der Auflagefläche stirnseitig zu koppeln und dann abzusenken, so daß der Steg 3 in der Nut 4a des Nachbarkörpers eingreifen kann, während der Steg 3aAs can be seen in particular from Fig. 3 and Fig. 4, the longitudinal extension of the groove 4 is longer, in particular upwards, than the longitudinal extension of the web 3, so that after laying a gutter body 1, it is possible to first couple the adjacent gutter body 1a above the support surface at the front and then lower it so that the web 3 can engage in the groove 4a of the adjacent body, while the web 3a
des Nachbarkörpers in der Nut 4 des bereits verlegten Rinnenelementes eingreifen und darin abgesenkt werden kann.of the neighbouring body can engage in the groove 4 of the already laid gutter element and be lowered into it.
Die Fig. 5 bis 8 zeigen eine abgewandelte Gestaltung eines Drainage-Rinnenkörpers, hier sind die Elemente 1 bis 4 mit 11 bis 14 bezeichnet.Fig. 5 to 8 show a modified design of a drainage channel body, here the elements 1 to 4 are designated 11 to 14.
Im Übergangsbereich zwischen den U-Schenkeln 12a und 12b zum mit 12c bezeichneten U-Schenkel sind hier auf einer Seite des Rinnenkörpers 11 nischenförmige Eingriffsausnehmungen 5 eingebracht, die eine zum Boden ausgerichtete gerade Auflagefläche 6 ausbilden, während in der anderen Stirnseite aus Nischen 7 nach außen weisende, die Kontur überragende Nocken 8 vorgesehen sind, die eine nach unten weisende gerade Auflagefläche 9 ausbilden.In the transition area between the U-legs 12a and 12b to the U-leg designated 12c, niche-shaped engagement recesses 5 are introduced on one side of the channel body 11, which form a straight support surface 6 aligned with the ground, while in the other end face, cams 8 are provided from niches 7 that point outwards and protrude beyond the contour, forming a straight support surface 9 pointing downwards.
Da die Höhe der Nischen 5 größer ist als die nach oben weisende Dicke der Nocken 8 kann die oben beschriebene Einhubbewegung in die Stirnseiten auch bei dieser Ausbildung ausgeführt werden. Wird der benachbarte Rinnenkörper zunächst in einer leicht angehobenen Stellung über den z.B. Ortbeton an die Stirnseite herangeführt, kann der Nocken 8 in die Nische 7 oben eingreifen. Wird dann das Rinnenelement abgesenkt, kontaktieren sich die Auflageflächen 6 und 9, wie dies in Fig. 9 angedeutet ist.Since the height of the niches 5 is greater than the upward thickness of the cams 8, the lifting movement into the front sides described above can also be carried out with this design. If the adjacent channel body is initially brought to the front side in a slightly raised position over the in-situ concrete, for example, the cam 8 can engage in the niche 7 at the top. If the channel element is then lowered, the support surfaces 6 and 9 come into contact, as is indicated in Fig. 9.
Wie sich insbesondere aus Fig. 7 ergibt, ist eine Zusammenfügung stirnseitig identischer Rinnenkörper etwa im Hochpunkt eines Rinnenstranges mit wechselnder Gefällerichtung problemlos möglich, da die nach außen, die Fugenfläche überragenden Nocken 8 etwa durch einen Aufschlag mittels eines Hammers abgebrochen werden können, die Reststümpfe, in Fig. 7 an einer Stelle mit 8a bezeichnet, treten dann soweit hinter die stirnseitige Fläche zurück, daß ein Zusammenfügen problemlos möglich ist.As can be seen in particular from Fig. 7, joining of gutter bodies that are identical on the front side is possible without any problems, for example at the highest point of a gutter line with a changing gradient direction, since the cams 8 that protrude outwards beyond the joint surface can be broken off by an impact using a hammer, for example, the remaining stumps, designated at one point in Fig. 7 with 8a, then recede far enough behind the front surface that joining is possible without any problems.
Wie sich dies aus den Figuren ergibt, weist jeder Rinnenkörper 1 bzw. 11 stirnseitig eine der Kontur der Rinne folgende Halbnut 10 bzw. 10a auf, derart, daß sich beim Zusammenschieben zweier Rinnenkörper 1 und la eine U-förmige Vollnut ergibt, die mit Dichtmaterial 15 ausgefüllt werden kann, was in Fig. 2 angedeutet ist.As can be seen from the figures, each gutter body 1 or 11 has a half-groove 10 or 10a on the front side which follows the contour of the gutter, such that when two gutter bodies 1 and 1a are pushed together, a U-shaped full groove is formed which can be filled with sealing material 15, as is indicated in Fig. 2.
Natürlich sind die beschriebenen Ausführungsbeispiele der Erfindung noch in vielfacher Hinsicht abzuändern, ohne den Grundgedanken zu verlassen. So kann etwa die Position der nischenförmigen Eingriffsausnehmungen bzw. der Nischen mit den Nocken näher an die Nut 14 bzw. zum Steg 13 gerückt sein oder derart, daß diese Elemente ineinander übergehen u. dgl. mehr.Of course, the described embodiments of the invention can be modified in many ways without deviating from the basic idea. For example, the position of the niche-shaped engagement recesses or the niches with the cams can be moved closer to the groove 14 or to the web 13 or in such a way that these elements merge into one another, etc.
• ··
• ··
• ··
• ··
Claims (6)
Priority Applications (8)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE20110764U DE20110764U1 (en) | 2001-06-29 | 2001-06-29 | Drainage channel body, in particular made of polymer concrete |
PCT/EP2002/006982 WO2003002825A1 (en) | 2001-06-29 | 2002-06-25 | Drainage channel base, especially from polymer concrete |
PL359151A PL199457B1 (en) | 2001-06-29 | 2002-06-25 | Drainage channel base, especially from polymer concrete |
EP02751068A EP1399627B1 (en) | 2001-06-29 | 2002-06-25 | Drainage channel base, especially from polymer concrete |
CZ20024060A CZ301354B6 (en) | 2001-06-29 | 2002-06-25 | Drainage channel base, especially from polymer concrete |
AT02751068T ATE430225T1 (en) | 2001-06-29 | 2002-06-25 | DRAINAGE GUTTER BODY, ESPECIALLY MADE OF POLYMER CONCRETE |
ES02751068T ES2324703T3 (en) | 2001-06-29 | 2002-06-25 | DRAIN CHANNEL BODY, IN PARTICULAR POLYMER CONCRETE. |
DE50213502T DE50213502D1 (en) | 2001-06-29 | 2002-06-25 | DRAINAGE CORNERS, PARTICULARLY OF POLYMER BEETON |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE20110764U DE20110764U1 (en) | 2001-06-29 | 2001-06-29 | Drainage channel body, in particular made of polymer concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
DE20110764U1 true DE20110764U1 (en) | 2001-08-30 |
Family
ID=7958688
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE20110764U Expired - Lifetime DE20110764U1 (en) | 2001-06-29 | 2001-06-29 | Drainage channel body, in particular made of polymer concrete |
DE50213502T Expired - Lifetime DE50213502D1 (en) | 2001-06-29 | 2002-06-25 | DRAINAGE CORNERS, PARTICULARLY OF POLYMER BEETON |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE50213502T Expired - Lifetime DE50213502D1 (en) | 2001-06-29 | 2002-06-25 | DRAINAGE CORNERS, PARTICULARLY OF POLYMER BEETON |
Country Status (7)
Country | Link |
---|---|
EP (1) | EP1399627B1 (en) |
AT (1) | ATE430225T1 (en) |
CZ (1) | CZ301354B6 (en) |
DE (2) | DE20110764U1 (en) |
ES (1) | ES2324703T3 (en) |
PL (1) | PL199457B1 (en) |
WO (1) | WO2003002825A1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10353080B3 (en) * | 2003-11-13 | 2005-08-25 | Aco Severin Ahlmann Gmbh & Co. Kg | Cast roadway drainage channel has cast concrete base with cast in tapering channel |
US7458745B2 (en) | 2004-10-18 | 2008-12-02 | Aco Severin Ahlmann Gmbh & Co. Kg | Drainage channel |
FR2959250A1 (en) * | 2010-04-23 | 2011-10-28 | Hauraton France | Modular element for e.g. beam gutter, has female formations whose dimensions are slightly higher than that of male formations, so that interstices are formed between end faces with respect to formations mutually stacked with bodies |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2402152B (en) * | 2003-05-30 | 2005-08-17 | Aco Technologies Plc | Drain sealing |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE8333233U1 (en) | 1982-11-23 | 1984-02-16 | Poly Bauelemente AG, Adliswil | DRAINAGE GUTTER |
GB2138873B (en) * | 1983-04-29 | 1986-05-08 | Maeta Concrete Works Ltd | U-shaped drainage channel block |
DE8435101U1 (en) | 1984-11-30 | 1985-03-28 | ACO Severin Ahlmann GmbH & Co KG, 2370 Rendsburg | DRAINAGE GUTTER |
DE3515917A1 (en) | 1985-05-03 | 1986-11-06 | Passavant-Werke AG & Co KG, 6209 Aarbergen | Drainage channel |
EP0380901B1 (en) | 1989-01-31 | 1992-08-12 | Poly-Bauelemente AG | Gutter |
KR930006051B1 (en) | 1989-03-08 | 1993-07-03 | 미쯔비시 덴끼 가부시끼가이샤 | Idle rotation frequency control device of engine |
DE4436460C2 (en) | 1994-10-12 | 1998-06-10 | Ahlmann Aco Severin | Drainage channel |
CH690132A5 (en) | 1995-08-08 | 2000-05-15 | Poly Bauelemente Ag | Drainage channel. |
US5653553A (en) * | 1995-12-06 | 1997-08-05 | Abt, Inc. | Drainage channel and associated method |
IT242332Y1 (en) * | 1996-02-09 | 2001-06-14 | Edil Plast Srl | MODULAR AND MODULAR CHANNEL FOR THE FORMATION OF SCHOOL CHANNELS WITH WALKABLE AND / OR DRIVEABLE GRID. |
-
2001
- 2001-06-29 DE DE20110764U patent/DE20110764U1/en not_active Expired - Lifetime
-
2002
- 2002-06-25 ES ES02751068T patent/ES2324703T3/en not_active Expired - Lifetime
- 2002-06-25 AT AT02751068T patent/ATE430225T1/en active
- 2002-06-25 WO PCT/EP2002/006982 patent/WO2003002825A1/en not_active Application Discontinuation
- 2002-06-25 DE DE50213502T patent/DE50213502D1/en not_active Expired - Lifetime
- 2002-06-25 PL PL359151A patent/PL199457B1/en unknown
- 2002-06-25 CZ CZ20024060A patent/CZ301354B6/en not_active IP Right Cessation
- 2002-06-25 EP EP02751068A patent/EP1399627B1/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10353080B3 (en) * | 2003-11-13 | 2005-08-25 | Aco Severin Ahlmann Gmbh & Co. Kg | Cast roadway drainage channel has cast concrete base with cast in tapering channel |
US7458745B2 (en) | 2004-10-18 | 2008-12-02 | Aco Severin Ahlmann Gmbh & Co. Kg | Drainage channel |
FR2959250A1 (en) * | 2010-04-23 | 2011-10-28 | Hauraton France | Modular element for e.g. beam gutter, has female formations whose dimensions are slightly higher than that of male formations, so that interstices are formed between end faces with respect to formations mutually stacked with bodies |
Also Published As
Publication number | Publication date |
---|---|
CZ301354B6 (en) | 2010-01-27 |
PL359151A1 (en) | 2004-08-23 |
DE50213502D1 (en) | 2009-06-10 |
PL199457B1 (en) | 2008-09-30 |
CZ20024060A3 (en) | 2003-05-14 |
EP1399627A1 (en) | 2004-03-24 |
ATE430225T1 (en) | 2009-05-15 |
EP1399627B1 (en) | 2009-04-29 |
WO2003002825A1 (en) | 2003-01-09 |
ES2324703T3 (en) | 2009-08-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2134916B1 (en) | Plug-in connector | |
EP1224365A1 (en) | Panel element | |
WO2001094703A1 (en) | Cast stone for fixing exterior traffic surfaces | |
EP1644595B1 (en) | Formwork with hookable turnbuckle device | |
DE102009011504B4 (en) | Vehicle restraint system made of sheet steel | |
DE202004004933U1 (en) | Rectilinear plug connector for hollow profiles for insulation glass has U-shaped cross section with centre web and with recesses along free edges of side webs for easier alignment | |
DE102009005793B3 (en) | Flooring made of a composite panel | |
DE20110764U1 (en) | Drainage channel body, in particular made of polymer concrete | |
EP3221599B1 (en) | Plug connector and plug connection | |
EP0571357A2 (en) | Fastening arrangement for sliding inserts | |
DE102021100406B4 (en) | MOLDED PART FOR ESTABLISHING A SLOPE FORTIFICATION, A FASTENING WALL ETC. | |
EP1024226A1 (en) | Artificial stone for pavings | |
EP3561213B1 (en) | Linear connector | |
DE102006040692A1 (en) | Kit for the limitation of beds, green areas, paths or other surfaces by means of boundary stones | |
DE69613744T2 (en) | Protective device for preventing water from entering a wall and for improving the drainage of water from a wall | |
DE102018132064A1 (en) | linear connector | |
EP2191083B1 (en) | Connection for floor panels | |
DE2213777A1 (en) | SOUND BARRIER | |
DE4320587C2 (en) | Reusable guide tool that does not remain in the component | |
DE29714539U1 (en) | Lattice board for fences, corresponding fence post and corresponding fence | |
DE20313254U1 (en) | Shaped brick system | |
DE202005015182U1 (en) | Glass brick wall is erected with a support structure of longitudinal and lateral wood profiles, locked together in a positive fit, without mortar between the bricks | |
DE7131525U (en) | Multi-part panel element for prefabricated house constructions | |
DE2207463A1 (en) | KIT FOR PRODUCTION OR ASSEMBLY OF A BALCONY RAILING | |
AT501830B1 (en) | CLOSING CYLINDER WITH CENTRAL LENS FOR CENTERING THE KEY TIP |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R207 | Utility model specification |
Effective date: 20011004 |
|
R150 | Utility model maintained after payment of first maintenance fee after three years |
Effective date: 20040512 |
|
R151 | Utility model maintained after payment of second maintenance fee after six years |
Effective date: 20070503 |
|
R152 | Utility model maintained after payment of third maintenance fee after eight years |
Effective date: 20090506 |
|
R071 | Expiry of right | ||
R071 | Expiry of right |