DE19509315C1 - Concrete post-treatment during tunnel concretion - Google Patents

Concrete post-treatment during tunnel concretion

Info

Publication number
DE19509315C1
DE19509315C1 DE1995109315 DE19509315A DE19509315C1 DE 19509315 C1 DE19509315 C1 DE 19509315C1 DE 1995109315 DE1995109315 DE 1995109315 DE 19509315 A DE19509315 A DE 19509315A DE 19509315 C1 DE19509315 C1 DE 19509315C1
Authority
DE
Germany
Prior art keywords
concrete
aftertreatment
temperature
chambers
micro
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
DE1995109315
Other languages
German (de)
Inventor
Hermann Ing Grad Breucha
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE1995109315 priority Critical patent/DE19509315C1/en
Priority to EP96104190A priority patent/EP0732480A3/en
Application granted granted Critical
Publication of DE19509315C1 publication Critical patent/DE19509315C1/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

A process for post-treating concrete during setting, in a tunnel arch concretion operation, involves: (a) forming one or more series-connected conditioning chambers (3) at the inside of the concrete arch; (2) by means of one or more travelling post-treatment carriages (1); (b) introducing a pressurised temp.-controlled micro-mist of a medium into each chamber; (3) by means of micro-misting nozzles (10); (c) calculating, for each chamber (3), the relative humidity and temp. target values for the post-treatment; and (d) continuously or intermittently determining the temp. and relative humidity values, by means of temp. and humidity sensors (23,24) arranged in the chambers (3) or in the concrete, for adjustment according to the preset target values. Also claimed is equipment for carrying out the above process in which the or each carriage is covered with mesh-reinforced PVC foil and a closed-cellular polyethylene foil.

Description

Die Erfindung betrifft ein Verfahren für die Nachbehandlung von Beton beim Betonieren von Tunnelgewölben und eine Anlage zur Durchführung des Verfahrens gemäß den in den Ansprüchen 1 und 9 angegebenen Gattungen.The invention relates to a method for aftertreatment of concrete when concreting tunnel vaults and a plant for performing the method according to the genera specified in claims 1 and 9.

Erstarren und Erhärten des Betons sind chemische Vorgänge, und deshalb sehr abhängig von Temperatur und Feuchtigkeit. Durch die während des Erstarrungsvorganges entstehende Hydrationswärme wird die Betonmasse erwärmt. Ungleichmäßige oder zu schnelle Abkühlung kann thermische Spannungen sowie Rißbildung zur Folge haben. Zu hohe Temperaturen können die Ausbildung des Betongefüges stören und zu wesentlich niedri­ geren Festigkeitswerten führen. Unter Festigkeit sind vor allem Druck-, Zug- und Biegefestigkeit zu verstehen. Zu hoher Wassergehalt kann eine Entmischung, einen unzuver­ lässigen Zusammenhalt, eine verzögerte Erhärtung und damit eine Verminderung der Festigkeit des Betons bewirken. Neben besonderen Maßnahmen während des Mischens, dem Transport und Verdichten des Betons, ist die Nachbehandlung von großer Bedeutung.Solidification and hardening of the concrete are chemical processes, and therefore very dependent on temperature and humidity. By the arising during the solidification process Heat of hydration heats the concrete mass. Uneven or cooling too quickly can cause thermal stresses as well Result in cracking. Too high temperatures can Disrupt formation of the concrete structure and too low lower strength values. Under firmness are before all to understand compressive, tensile and flexural strength. To high water content can cause segregation casual cohesion, a delayed hardening and thus cause a reduction in the strength of the concrete. Next special measures during mixing, transport and compacting the concrete, the after-treatment is great Meaning.

Bekannt ist, (DE-Z.: Beton- und Stahlbetonbau 12/1983, S. 336 bis 341), daß die Bedeutung der Nachbehandlung für die Festigkeit des Betons und die Dauerhaftigkeit der Beton­ bauwerke zu allgemeinen Regeln und Vorschriften (DIN 1045) geführt hat, die aber meist für die praktische Ausführung einen weiten Spielraum lassen. Grund hierfür ist die Viel­ falt der Faktoren, wie Zementfestigkeitsklasse, Beanspru­ chung und Abmessung der Baukörper sowie Erhärtungsgeschwin­ digkeit und Austrocknungsbedingungen, die den Erstarrungspro­ zeß beeinflussen. Entsprechend vielfältig sind auch die Maßnahmen zur Nachbehandlung.Is known, (DE-Z .: concrete and reinforced concrete construction 12/1983, Pp. 336 to 341) that the importance of aftercare for the strength of the concrete and the durability of the concrete buildings to general rules and regulations (DIN 1045) has led, but mostly for the practical execution leave a wide margin. The reason for this is the much fold of factors such as cement strength class, stress The dimensions and dimensions of the structures as well as the hardening speed density and dehydration conditions that affect the solidification pro influence. They are correspondingly diverse Post-treatment measures.

In der Praxis sind folgende Methoden üblich: Abdecken mit feuchter Jute, Abdecken mit Folie, Belassen des Betons in der Schalung, zeitweiliges Besprühen mit Wasser, Lagern un­ ter Wasser und Anwendung von chemischen Nachbehandlungs­ mitteln.The following methods are common in practice: Cover with damp jute, covering with foil, leaving the concrete in the formwork, occasional spraying with water, storage and ter water and application of chemical aftertreatment average.

Die Mängel der vorbeschriebenen Maßnahmen bestehen darin, daß der Erstarrungsprozeß hinsichtlich Feuchtigkeit und Temperatur nicht koordiniert und meßbar beeinflußt wird.The shortcomings of the measures described above are that the solidification process with regard to moisture and Temperature is not coordinated and is measurably influenced.

Der Erfindung liegt die Aufgabe zugrunde, ein Verfahren so­ wie eine Vorrichtung zur Durchführung des Verfahrens der gattungsgemäßen Arten anzugeben, mit denen es möglich ist, den Erstarrungsprozeß des Betons zur Erzielung eines gleich­ mäßigen Gefüges und einer optimalen Festigkeitsentwicklung meßbar zu beeinflussen und bei denen auch äußere Einflüsse, wie Witterungsschwankungen oder interne Unregelmäßigkeiten beim Ablauf der chemischen Prozesse, mitberücksichtigt werden.The invention has for its object a method like this as an apparatus for performing the method of Specify generic species with which it is possible the solidification process of the concrete to achieve the same moderate structure and optimal strength development measurable influence and where also external influences, such as weather fluctuations or internal irregularities taken into account in the course of the chemical processes will.

Diese Aufgabe wird durch ein Verfahren sowie eine Anlage gemäß den kennzeichnenden Merkmalen der Ansprüche 1 und 9 gelöst. Zweckmäßige Ausführungsformen der Erfindung sind Gegenstand der Unteransprüche.This task is accomplished through a process as well as an attachment according to the characterizing features of claims 1 and 9 solved. Appropriate embodiments of the invention are Subject of the subclaims.

Die Vorteile der Erfindung bestehen in der meßbar kontrol­ lierten Nachbehandlung von Beton. Statt der bisher üblichen Maßnahmen wie Abdecken und unkontrolliertem Befeuchten des Betons, wird der Erstarrungsprozeß erfindungsgemäß hinsicht­ lich Temperatur, Feuchtigkeit und zeitlichem Ablauf ge­ steuert.The advantages of the invention lie in the measurable control after-treatment of concrete. Instead of the usual Measures such as covering and uncontrolled humidification of the Concrete, the solidification process according to the invention temperature, humidity and chronological sequence controls.

Es ist möglich, mittels Probewürfel von jeder Betoncharge die optimalen Soll-Werte zu bestimmen und den Prozeß chargenweise durch unterschiedliche Werte in den einzelnen Klimakammern zu führen. Hierdurch ist mit größerer Sicher­ heit ein gleichmäßiges Gefüge und damit höhere Festigkeit zu erzielen.It is possible to use test cubes from each batch of concrete to determine the optimal target values and the process in batches by different values in the individual To lead climatic chambers. This is more secure an even structure and thus higher strength to achieve.

Nachfolgend wird anhand schematischer Zeichnungen ein Aus­ führungsbeispiel der Erfindung beschrieben.Below is an off using schematic drawings leadership example of the invention described.

Es zeigenShow it

Fig. 1 einen Querschnitt durch ein Tunnelprofil und einen Nachbehandlungswagen, Fig. 1 shows a cross section through a tunnel profile, and a post-treatment cart,

Fig. 2 den Längsschnitt durch einen Nachbehandlungswagen, Fig. 2 is a longitudinal section through a post-treatment cart,

Fig. 3 eine Seitenansicht eines Nachbehandlungswagens mit der Anordnung der Mikro-Vernebelungsdüsen, Fig. 3 is a side view of a post-treatment vehicle with the arrangement of the micro-atomizing nozzles,

Fig. 4 eine Darstellung der Metall-Systemelemente, Fig. 4 is an illustration of the metal-system elements,

Fig. 5 die Anpassungsmöglichkeit an das Tunnelprofil, Fig. 5, the adaptability to the tunnel profile,

Fig. 6 die Außenverkleidung der Nachbehandlungswagen. Fig. 6, the outer lining of the aftertreatment trolley.

Wie aus Fig. 1 zu ersehen, ist der Nachbehandlungswagen (1) mit seinem Außenprofil der Innenseite des Betongewöl­ bes (2) so angepaßt, daß ein Zwischenraum entsteht, der zur Nachbehandlung des Betons als Klimakammer (3) verwendet wird.As can be seen from Fig. 1, the aftertreatment trolley ( 1 ) with its outer profile of the inside of the concrete vault bes ( 2 ) is adapted so that an intermediate space is created which is used for the aftertreatment of the concrete as a climatic chamber ( 3 ).

Die Außenseite (6) der Nachbehandlungswagen (1) ist gemäß Fig. 6 mit gitterverstärkter PVC-Folie (7) bespannt. Die jeweils zwischen zwei Wagen bestehenden Zwischenräume sind ebenfalls mit PVC-Folie abgeschirmt.The outside ( 6 ) of the aftertreatment trolley ( 1 ) is covered with grid-reinforced PVC film ( 7 ) according to FIG. 6. The gaps between two cars are also shielded with PVC film.

Beim ersten hinter dem Schalwagen folgenden Nachbehandlungs­ wagen (1) ist zur Vermeidung eines Kälteschocks unter der PVC-Folie (7) noch eine geschlossenzellige Polyethylen- Folie (8) als Wärmeisolation angebracht. Die beiden ersten Nachbehandlungswagen (1) sind zusätzlich außen mit einem Filzbelag (9) versehen.In the first aftertreatment carriage ( 1 ) behind the formwork carriage, a closed-cell polyethylene film ( 8 ) is attached as thermal insulation to avoid a cold shock under the PVC film ( 7 ). The first two post-treatment trolleys ( 1 ) are additionally provided with a felt covering ( 9 ) on the outside.

Die Abdichtung der Klimakammern (3) zur Tunnelsohle und an den Stirnseiten der Nachbehandlungswagen (1) zum Tunnelge­ wölbe erfolgt gemäß Fig. 1 und 2 durch aufblasbare Schläu­ che (4) und (5).The sealing of the climatic chambers ( 3 ) to the tunnel sole and on the end faces of the aftertreatment trolley ( 1 ) to the tunnel vault takes place according to FIGS . 1 and 2 by inflatable hoses ( 4 ) and ( 5 ).

Die Steuerung und Versorgung mit dem zu vernebelnden Medium und der Druckluft erfolgt mittels der Steuer- und Versor­ gungseinheit (13).The control and supply with the medium to be atomized and the compressed air takes place by means of the control and supply unit ( 13 ).

Gemäß Fig. 1, 2 und 4 sind die Nachbehandlungswagen (1) aus den zusammensteckbaren Metall-Systemelementen (14), (15) und (16) aufgebaut, wobei diese nach Fig. 2 mittels Längsverbin­ dungen (17) und Diagonalverstrebungen (18) miteinander ver­ bunden sind. Die Metall-Systemelemente (14), (15) und (16) sind nach Fig. 1 und 2 auf beiderseits angeordneten Basis­ trägern (19) montiert, die ihrerseits an beiden Enden tele­ skopartig ausziehbar und auf der Unterseite mit Lauf­ rollen (20) versehen sind.According to Fig. 1, 2 and 4, the post-treatment cart (1) from the matable metal system members (14), (15) and (16) are constructed, these compounds according to Fig. 2 by means of Längsverbin (17) and diagonal struts (18) are connected with each other. The metal system elements ( 14 ), ( 15 ) and ( 16 ) are mounted according to FIGS. 1 and 2 on both sides arranged base carriers ( 19 ), which in turn telescopically extendable at both ends and roll on the underside with barrel ( 20 ) are provided.

Die Möglichkeit der Anpassung an das Tunnelprofil ist aus Fig. 5 ersichtlich. Der schwenkbare Haltebügel (21) des Metall-Systemelementes (15) nimmt das segmentartig geformte Metall-Systemelement (16) in der erforderlichen Winkelnei­ gung auf. Die Verbindung der beiden jeweils zugehörigen Metall-Systemelemente (16) erfolgt durch Anpaßstücke (22), die entsprechend der Winkelneigung und der Tunnelbreite aus gebildet sind.The possibility of adapting to the tunnel profile can be seen in FIG. 5. The pivotable bracket ( 21 ) of the metal system element ( 15 ) takes the segment-shaped metal system element ( 16 ) in the required Winkelnei supply. The connection of the two respective associated metal system elements ( 16 ) is carried out by adapter pieces ( 22 ) which are formed in accordance with the angular inclination and the tunnel width.

Fig. 1 und 3 zeigen die in den Klimakammern (3) angeord­ neten und die in das Betongewölbe (2) eingegossenen Sen­ soren für Temperatur (23) und relative Luftfeuchte (24). Fig. 1 and 3 show the angeord Neten in the air chambers (3) and the cast concrete into the vault (2) Sen sensors for temperature (23) and relative humidity (24).

Claims (21)

1. Verfahren für die Nachbehandlung von Beton beim Betonieren von Tunnelgewölben während des Erstarrungsvorganges zur Erzielung eines gleichmäßigen Gefüges und der Verbesserung der Festigkeit, bei dem die Innenseite des Betongewölbes hinsichtlich Temperatur und Feuchtigkeit beeinflußt wird, dadurch gekennzeichnet, daß mittels zumindest eines verfahrbaren Nachbehandlungs­ wagens (1) an der Innenseite des Betongewölbes (2) eine oder mehrere hintereinander geschaltete Klimakammern (3) gebildet werden und mittels Mikro-Vernebelungsdüsen (10) in jede Klimakammer (3) ein unter Druck stehender tempe­ rierter Mikronebel eines Mediums eingebracht wird, daß die für den Nachbehandlungsprozeß vorzugebenden Sollwerte der relativen Luftfeuchte und Temperatur für jede Klimakam­ mer (3) errechnet werden, und daß über in den Klimakam­ mern (3) oder im Beton angeordnete Temperatur- und Feuch­ tigkeitssensoren (23) (24) die Temperatur und die rela­ tiven Luftfeuchtewerte kontinuierlich oder intermittierend erfaßt und die vorgegebenen Sollwerte angesteuert werden.1. A method for the post-treatment of concrete when concreting tunnel vaults during the solidification process to achieve a uniform structure and improvement in strength, in which the inside of the concrete vault is influenced in terms of temperature and humidity, characterized in that by means of at least one movable post-treatment trolley ( 1 ) on the inside of the concrete vault ( 2 ) one or more climate chambers ( 3 ) connected in series are formed and by means of micro-atomizing nozzles ( 10 ) in each climate chamber ( 3 ) a pressurized temperature-controlled micro mist of a medium is introduced that the for the post-treatment process predetermined setpoints of the relative humidity and temperature for each climate chamber ( 3 ) are calculated, and that temperature and humidity sensors ( 23 ) ( 24 ) arranged in the climate chambers ( 3 ) or in the concrete, the temperature and the rela tive Humidity values cont recorded continuously or intermittently and the specified setpoints are controlled. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, daß die relative Luftfeuchte und Temperatur in jeder Klimakam­ mer (3) automatisch oder manuell gesteuert werden.2. The method according to claim 1, characterized in that the relative humidity and temperature in each Klimakam mer ( 3 ) are controlled automatically or manually. 3. Verfahren nach Anspruch 1 oder 2, dadurch gekennzeich­ net, daß die relative Luftfeuchte und Temperatur in jeder Klimakammer (3) zwischen zwei vorgegebenen Grenzwerten gesteuert werden.3. The method according to claim 1 or 2, characterized in that the relative humidity and temperature in each climatic chamber ( 3 ) are controlled between two predetermined limit values. 4. Verfahren nach einem der Ansprüche 1 bis 3, dadurch ge­ kennzeichnet, daß dem Mikronebelmedium chemische Zusätze zugegeben werden. 4. The method according to any one of claims 1 to 3, characterized ge indicates that the micro fog medium contains chemical additives be added.   5. Verfahren nach einem der Ansprüche 1 bis 4, dadurch ge­ kennzeichnet, daß jede Klimakammer (3) unabhängig von den anderen steuerbar ist.5. The method according to any one of claims 1 to 4, characterized in that each climate chamber ( 3 ) is controllable independently of the others. 6. Verfahren nach einem der Ansprüche 1 bis 5, dadurch ge­ kennzeichnet, daß die gesamte Anlage von einer Zentral­ einheit (13) steuerbar ist.6. The method according to any one of claims 1 to 5, characterized in that the entire system from a central unit ( 13 ) is controllable. 7. Verfahren nach einem der Ansprüche 1 bis 6, dadurch ge­ kennzeichnet, daß die von den Feuchte- und Temperatur­ sensoren (23) (24) gemessenen Istwerte gespeichert und angezeigt oder protokolliert werden.7. The method according to any one of claims 1 to 6, characterized in that the actual values measured by the humidity and temperature sensors ( 23 ) ( 24 ) are stored and displayed or logged. 8. Verfahren nach einem der Ansprüche 1 bis 7 dadurch ge­ kennzeichnet, daß der zeitliche Ablauf der Nachbehand­ lung durch die Verfahrzyklen und Stillstandszeiten der Klimakammern (3) beeinflußt wird.8. The method according to any one of claims 1 to 7, characterized in that the timing of the after-treatment is influenced by the travel cycles and downtimes of the climatic chambers ( 3 ). 9. Anlage für die Nachbehandlung von Beton beim Betonieren von Tunnelgewölben während des Erstarrungsvorganges zur Erzielung eines gleichmäßigen Gefüges und der Verbesse­ rung der Festigkeit, die Einrichtungen zur Beeinflussung der Innenseite des Betongewölbes hinsichtlich Tempe­ ratur und Feuchtigkeit aufweist, zur Durchführung des Verfahrens nach Anspruch 1, dadurch gekennzeichnet, daß zumindest ein aus Metall-Systemelementen aufgebauter Nachbehandlungswagen (1) mit einem dem Tunnelprofil mit Abstand angepaßten Aufbau vorgesehen ist, der gegenüber der Innenseite des Betongewölbes (2) an den Stirnseiten und zur Tunnelsohle hin abdichtbar ist und eine oder mehrere hintereinandergeschaltete Klimakammern (3) bildet, daß jeder Klimakammer (3) mehrere Mikro-Vernebelungs­ düsen (10) zum Einbringen von unter Druck stehendem, temperierten Mikronebel eines Mediums zugeordnet sind, daß in den Klimakammern (3) oder im Beton Temperatur-und Luft­ feuchtesensoren (23)(24) angeordnet sind, und daß eine elektronische Steuereinrichtung (13) zum Steuern der rela­ tiven Luftfeuchte und Temperatur in den Klimakammern (3) in Abhängigkeit von vorgegebenen Sollwerten vorgesehen ist.9. Plant for the post-treatment of concrete when concreting tunnel vaults during the solidification process to achieve a uniform structure and the improvement of the strength, which has devices for influencing the inside of the concrete vault with regard to temperature and moisture, for carrying out the method according to claim 1, characterized in that at least one aftertreatment trolley ( 1 ) made of metal system elements is provided with a structure which is adapted to the tunnel profile at a distance and which can be sealed against the inside of the concrete arch ( 2 ) on the front sides and towards the tunnel sole and one or more climate chambers connected in series (3), in that each air chamber (3) a plurality of micro-nebulization nozzles (10) are assigned for the introduction of pressurized, tempered micro-mist of a medium, that in the air chambers (3) or in the concrete temperature and air humidity sensors (23 ) ( 24 ) are arranged, and that an electronic control device ( 13 ) for controlling the rela tive air humidity and temperature in the climatic chambers ( 3 ) is provided as a function of predetermined setpoints. 10. Anlage nach Anspruch 9, dadurch gekennzeichnet, daß die Aufbauten der Nachbehandlungswagen mit gitterverstärkter PVC-Folie (7) bespannt sind.10. Plant according to claim 9, characterized in that the structures of the aftertreatment trolley are covered with lattice-reinforced PVC film ( 7 ). 11. Anlage nach Anspruch 9 oder 10, dadurch gekennzeichnet, daß mindestens der erste Nachbehandlungswagen (3) auf der Außenseite des Aufbaues mit einer geschlossenzel­ ligen Polyethylen-Folie (8) gegen extremen Temperaturab­ fall ausgekleidet ist.11. Plant according to claim 9 or 10, characterized in that at least the first aftertreatment trolley ( 3 ) on the outside of the structure is lined with a closed-cell polyethylene film ( 8 ) against extreme Temperaturab fall. 12. Anlage nach einem der Ansprüche 9 bis 11, dadurch ge­ kennzeichnet, daß der erste und zweite Nachbehandlungs­ wagen (3) mit Filz (9) zur Aufnahme des überflüssigen Mikronebels und gleichmäßigen Verteilung der Feuchtigkeit, unter Wegfall von zusätzlichen Auffangrinnen belegt ist.12. Plant according to one of claims 9 to 11, characterized in that the first and second aftertreatment carriage ( 3 ) with felt ( 9 ) for receiving the superfluous micro-fog and even distribution of moisture is occupied, with the omission of additional collecting channels. 13. Anlage nach einem der Ansprüche 9 bis 12, dadurch ge­ kennzeichnet, daß an den Stirnseiten jedes Nachbehand­ lungswagens (1) sich dem Tunnelprofil stetig anpassende Abdichtungen (5) der Klimakammern (3) zum Tunnelgewölbe vorgesehen sind.13. Plant according to one of claims 9 to 12, characterized in that the tunnel profile continuously adapting seals ( 5 ) of the climatic chambers ( 3 ) to the tunnel vault are provided on the end faces of each aftertreatment wagon ( 1 ). 14. Anlage nach einem der Ansprüche 9 bis 13 dadurch ge­ kennzeichnet, daß an beiden Längsseiten jedes Nachbe­ handlungswagens (1) sich stetig anpassende Abdich­ tungen (4) zur Tunnelsohle vorgesehen sind.14. Plant according to one of claims 9 to 13, characterized in that on both long sides of each Nachbe trolley ( 1 ) continuously adapting seals lines ( 4 ) are provided for the tunnel bottom. 15. Anlage nach einem der Ansprüche 13 oder 14, dadurch ge­ kennzeichnet, daß die stirn- und längsseitigen Abdich­ tungen (4) (5) der Klimakammern (3) als aufblasbare Schläuche aus elastischem Werkstoff oder gewebeverstärk­ tem, silikonisiertem Nylongewebe ausgeführt sind.15. Plant according to one of claims 13 or 14, characterized in that the end and longitudinal sealing lines ( 4 ) ( 5 ) of the climatic chambers ( 3 ) are designed as inflatable tubes made of elastic material or tissue-reinforced, siliconized nylon fabric. 16. Anlage nach einem der Ansprüche 13 bis 15, dadurch ge­ kennzeichnet, daß der Luftdruck in den Abdichtungs­ schläuchen (4) (5) beim Verfahren der Nachbehandlungs­ wagen (1) absenkbar ist.16. Plant according to one of claims 13 to 15, characterized in that the air pressure in the sealing tubes ( 4 ) ( 5 ) in the process of the aftertreatment carriage ( 1 ) can be lowered. 17. Anlage nach einem der Ansprüche 9 bis 16, dadurch ge­ kennzeichnet, daß die Nachbehandlungswagen (1) mit min­ destens je vier Laufrollen (20) versehen sind, die auf Schienen laufen und auch bei Kurvenfahrt die Einhaltung der Geometrie der Klimakammern (1) sichergestellt ist.17. Plant according to one of claims 9 to 16, characterized in that the aftertreatment trolley ( 1 ) with at least four rollers ( 20 ) are provided, which run on rails and even when cornering, the compliance with the geometry of the climatic chambers ( 1 ) is ensured. 18. Anlage nach einem der Ansprüche 9 bis 17, dadurch ge­ kennzeichnet, daß die Nachbehandlungswagen (1) aneinander­ kuppelbar sind, wobei Kurven unter Erhaltung der Abdich­ tung der Klimakammern (3) fahrbar sind.18. Plant according to one of claims 9 to 17, characterized in that the aftertreatment trolley ( 1 ) can be coupled to one another, curves while maintaining the sealing device of the climatic chambers ( 3 ) are mobile. 19. Anlage nach einem der Ansprüche 9 bis 18, dadurch ge­ kennzeichnet, daß auf der Außenseite der Nachbehandlungs­ wagen (1) die Mikro-Vernebelungsdüsen (10) angebracht sind.19. Plant according to one of claims 9 to 18, characterized in that on the outside of the aftertreatment carriage ( 1 ) the micro-atomizing nozzles ( 10 ) are attached. 20. Anlage nach einem der Ansprüche 9 bis 19, dadurch ge­ kennzeichnet, daß die Mikro-Vernebelungsdüsen (10) ein­ zeln nach Menge des in die Klimakammern (3) einzubringen­ den Mediums steuer- und abschaltbar sind.20. System according to one of claims 9 to 19, characterized in that the micro-atomizing nozzles ( 10 ) a single according to the amount of the medium to be introduced into the climatic chambers ( 3 ) can be controlled and switched off. 21. Anlage nach einem der Ansprüche 9 bis 20, dadurch ge­ kennzeichnet, daß die Nachbehandlungswagen (1) an den Schalwagen ankuppelbar oder mit eigenem Antrieb versehen sind.21. Plant according to one of claims 9 to 20, characterized in that the aftertreatment carriage ( 1 ) can be coupled to the formwork carriage or provided with its own drive.
DE1995109315 1995-03-15 1995-03-15 Concrete post-treatment during tunnel concretion Expired - Fee Related DE19509315C1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
DE1995109315 DE19509315C1 (en) 1995-03-15 1995-03-15 Concrete post-treatment during tunnel concretion
EP96104190A EP0732480A3 (en) 1995-03-15 1996-03-15 Method and installation for the post-treatment of concrete, in particular for casting a tunnel vault

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE1995109315 DE19509315C1 (en) 1995-03-15 1995-03-15 Concrete post-treatment during tunnel concretion

Publications (1)

Publication Number Publication Date
DE19509315C1 true DE19509315C1 (en) 1996-05-09

Family

ID=7756702

Family Applications (1)

Application Number Title Priority Date Filing Date
DE1995109315 Expired - Fee Related DE19509315C1 (en) 1995-03-15 1995-03-15 Concrete post-treatment during tunnel concretion

Country Status (2)

Country Link
EP (1) EP0732480A3 (en)
DE (1) DE19509315C1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2752013A1 (en) * 1996-07-30 1998-02-06 Parra Robert Curved coffering ring for tunnel
EP0863294A1 (en) * 1997-03-07 1998-09-09 Ed. Züblin Ag Method and device for the industrial construction of reinforced ceiling structures
CN104695979A (en) * 2015-02-16 2015-06-10 中交一航局第一工程有限公司 Method for integrally and transversely moving high and large formwork through high and large trolley
CN108533291A (en) * 2018-06-15 2018-09-14 中铁工程设计咨询集团有限公司 The concrete curing equipment that can be kept the temperature and maintenance process
CN115478517A (en) * 2022-09-19 2022-12-16 河南黄河河务局工程建设中心 Support protection device for hydraulic engineering construction and use method thereof

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704952B (en) * 2012-06-28 2014-12-10 中国水利水电第七工程局成都水电建设工程有限公司 Self-propelled tunnel grouting trolley
JP2014152527A (en) * 2013-02-08 2014-08-25 Mashino:Kk Curing water supply system for concrete curing facility and the like
CN104389622A (en) * 2014-09-26 2015-03-04 甘肃万泰建设工程有限公司 Construction method of arched steel lifting molds of tunnel secondary lining arch foot curved wall
CN104500098B (en) * 2014-11-25 2017-02-01 中铁十八局集团有限公司 Method for increasing construction space under invert trestle of single track railway tunnel
CN106065778B (en) * 2016-06-03 2018-04-20 江苏中路工程检测有限公司 A kind of tunnel steel arch frame apparatus for placing
CN108004888B (en) * 2017-12-12 2019-11-26 中交机电工程局有限公司 A kind of road traffic splash guard installation trolley
CN110617070B (en) * 2019-10-15 2020-12-11 中铁五局集团第一工程有限责任公司 Tunnel construction method
CN110645019B (en) * 2019-10-15 2021-02-26 中铁五局集团第一工程有限责任公司 Integrated form tunnel construction equipment
CN110645020B (en) * 2019-10-15 2021-02-26 中铁五局集团第一工程有限责任公司 Construction equipment walking method
CN110656958B (en) * 2019-10-15 2021-02-26 中铁五局集团第一工程有限责任公司 Steady formula construction equipment

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3826521A1 (en) * 1988-08-04 1990-02-08 Kloeckner Becorit Ind Device for wetting pack construction materials
US5089198A (en) * 1989-02-17 1992-02-18 Cam Sales, Inc. Method for curing concrete articles

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
DE-Z: Beton- und Stahlbetonbau 12/1983, S. 336-341 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2752013A1 (en) * 1996-07-30 1998-02-06 Parra Robert Curved coffering ring for tunnel
EP0863294A1 (en) * 1997-03-07 1998-09-09 Ed. Züblin Ag Method and device for the industrial construction of reinforced ceiling structures
CN104695979A (en) * 2015-02-16 2015-06-10 中交一航局第一工程有限公司 Method for integrally and transversely moving high and large formwork through high and large trolley
CN108533291A (en) * 2018-06-15 2018-09-14 中铁工程设计咨询集团有限公司 The concrete curing equipment that can be kept the temperature and maintenance process
CN115478517A (en) * 2022-09-19 2022-12-16 河南黄河河务局工程建设中心 Support protection device for hydraulic engineering construction and use method thereof
CN115478517B (en) * 2022-09-19 2024-01-26 河南黄河河务局工程建设中心 Support protection device for hydraulic engineering construction and application method thereof

Also Published As

Publication number Publication date
EP0732480A3 (en) 1998-08-12
EP0732480A2 (en) 1996-09-18

Similar Documents

Publication Publication Date Title
DE19509315C1 (en) Concrete post-treatment during tunnel concretion
EP2514871B1 (en) Method for laying and compacting an asphalt layer
DE69728549T2 (en) METHOD FOR COMPRESSING ASPHALT AND COMPRESSOR DEVICE
EP2227598B1 (en) Method for compacting a ballast bed and device for carrying out the method
EP3738800B1 (en) Apparatus for dispensing multicomponent adhesives onto a granular mixture, and method of dispensing and using the apparatus
DE4229534C2 (en) Process for renewing a track and machine arrangement for carrying out the process
DE102015013131A1 (en) Apparatus and method for the production of moldings consisting of a particle foam
DE102010036633A1 (en) Arrangement for humidification of concrete structure i.e. road, embedded into ground, has yield device arranged between wall and concrete surface in interspace part and yielding water mists that are directed parallel to concrete surface
EP3300486A1 (en) Method and device for cooling extruded profiles
DE4409829A1 (en) Method and device for producing walls and walls, in particular for buildings
EP0024520B1 (en) Process for producing thermally insulated composite profiles
CH667119A5 (en) CONTINUOUSLY TRAVELABLE TRACK LEVELING AND LEVELING MACHINE.
EP1785581B1 (en) Device for sealing the walls of underground tunnels
DE3236722A1 (en) METHOD FOR INFLATING BED MATERIAL BY MEANS OF A TRACK CORRECTION MACHINE
AT390288B (en) DEVICE AND METHOD FOR CORRECTING THE POSITION OF A TRACK STRUCTURE POSSIBLE ON A LENGTH CONCRETE TAPE
DE202006010504U1 (en) Device for pressure impacting (sic) of core sand in closing machine with pressurized gas storage container generally useful in casting operations, etc
DE202015101695U1 (en) Apparatus for treating cracks in surfaces of traffic areas
DE102015105208A1 (en) Apparatus for treating cracks in surfaces of traffic areas
DE3030497C2 (en) Method and device for cooling cast parts
DE102004042855B3 (en) Cooling device used in the manufacture of vehicle chasses comprises a cooling zone with a delimiting wall having a surface which is tempered
DE1945611A1 (en) Device for laying sheets of sealing and / or cladding material on tunnel walls
AT391103B (en) METHOD AND SYSTEM FOR TEMPERATURE CONTROL IN THE PRODUCTION OF BUILDING MATERIAL MIXTURES
CH641518A5 (en) Process for producing an anchoring used as a reinforced-concrete connection
DE2338998C2 (en)
DE2515999B2 (en) Device for applying a layer of malleable, compressible material to the walls of the tapping channels of blast furnaces

Legal Events

Date Code Title Description
8100 Publication of the examined application without publication of unexamined application
D1 Grant (no unexamined application published) patent law 81
8322 Nonbinding interest in granting licenses declared
8363 Opposition against the patent
8339 Ceased/non-payment of the annual fee