DE1109075B - Method and stone clamp for removing the documents for shaped stones - Google Patents

Method and stone clamp for removing the documents for shaped stones

Info

Publication number
DE1109075B
DE1109075B DER25760A DER0025760A DE1109075B DE 1109075 B DE1109075 B DE 1109075B DE R25760 A DER25760 A DE R25760A DE R0025760 A DER0025760 A DE R0025760A DE 1109075 B DE1109075 B DE 1109075B
Authority
DE
Germany
Prior art keywords
documents
another
stones
clamp
gripper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
DER25760A
Other languages
German (de)
Inventor
Mathias Neises
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ruhr Intrans Hubstapler GmbH
Original Assignee
Ruhr Intrans Hubstapler GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ruhr Intrans Hubstapler GmbH filed Critical Ruhr Intrans Hubstapler GmbH
Priority to DER25760A priority Critical patent/DE1109075B/en
Publication of DE1109075B publication Critical patent/DE1109075B/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F9/00Devices for lifting or lowering bulky or heavy goods for loading or unloading purposes
    • B66F9/06Devices for lifting or lowering bulky or heavy goods for loading or unloading purposes movable, with their loads, on wheels or the like, e.g. fork-lift trucks
    • B66F9/075Constructional features or details
    • B66F9/12Platforms; Forks; Other load supporting or gripping members
    • B66F9/125Platforms; Forks; Other load supporting or gripping members rotatable about a longitudinal axis
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F9/00Devices for lifting or lowering bulky or heavy goods for loading or unloading purposes
    • B66F9/06Devices for lifting or lowering bulky or heavy goods for loading or unloading purposes movable, with their loads, on wheels or the like, e.g. fork-lift trucks
    • B66F9/075Constructional features or details
    • B66F9/12Platforms; Forks; Other load supporting or gripping members
    • B66F9/18Load gripping or retaining means
    • B66F9/183Coplanar side clamps

Landscapes

  • Engineering & Computer Science (AREA)
  • Transportation (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Description

Verfahren und Steinklammer zum Entfernen der Unterlagen für Formsteine Die Erfindung betrifft ein Verfahren und eine Steinklammer zum Entfernen der Unterlagen für Formsteine aus Beton, Bims, Kalksandstein u. dgl. aus Stapeln, in denen die Formsteine auf den Unterlagen liegend aufeinandergeschichtet sind.Method and stone clamp for removing the supports for shaped stones The invention relates to a method and a stone clip for removing the documents for shaped stones made of concrete, pumice, sand-lime brick and the like from stacks in which the Form stones are stacked on top of each other.

Die auf den Unterlagen, z. B. auf Brettern, Platten u. dgl., hergestellten Formsteine werden, besonders wenn sie getrocknet werden sollen, gewöhnlich zu vier Stück auf je einer Unterlage so angeordnet, daß je zwei Formsteine mit einer ihrer Schmalseiten aneinanderliegend und beide Steinpaare mit Abstand parallel zueinander auf der Unterlage ruhen. Das Trocknen oder zumindest das Antrocknen der Formsteine erfolgt in Stapeln, die aus vier oder fünf übereinandergeschichteten, in der vorbeschriebenen Weise auf den Unterlagen angeordneten Steinlagen bestehen. The on the documents, z. B. on boards, panels and the like., Manufactured Shaped bricks, especially if they are to be dried, usually turn into four Pieces arranged on a base so that two shaped bricks with one of their Narrow sides lying next to each other and both pairs of stones with a distance parallel to each other rest on the mat. The drying or at least the drying of the shaped stones takes place in stacks, consisting of four or five stacked one on top of the other, in the manner described above Way consist of stone layers arranged on the documents.

Zum Abbauen dieser Steinstapel müssen die Formsteine einzeln von Hand von den Unterlagen genommen und zu meist größeren, keine Unterlagen mehr aufweisenden Stapeln zusammengesetzt bzw. einem geeigneten Fördergerät übergeben werden, mit welchem die Formsteine dann erneut gestapelt werden.To dismantle this pile of stones, the shaped stones must be individually hand taken from the documents and mostly larger ones that no longer contain any documents Stacked together or transferred to a suitable conveyor device which the shaped bricks are then stacked again.

Mit dem erfindungsgemäßen Verfahren werden die vorbeschriebenen Arbeitsgänge dadurch wesentlich vereinfacht, daß der Steinstapel zunächst vom Boden aufgenommen wird, worauf die Steinlagen zur Bildung von Zwischenräumen voneinander abgehoben, sodann zum Herausfallen der Unterlagen um etwa 80° zur Waagerechten geneigt und anschließend in die waagerechte Lage zurückgebracht und aufeinanderliegend abgesetzt bzw. zu größeren Steinstapeln zusammengesetzt werden. Auf diese Weise wird die bislang erforderlich gewesene mühevolle, zeitraubende und Kosten verursachende Handarbeit eingespart. The above-described operations are carried out with the method according to the invention significantly simplified by the fact that the stack of stones was initially taken from the ground whereupon the stone layers are lifted from one another to form gaps, then inclined by about 80 ° to the horizontal for the documents to fall out then brought back into the horizontal position and placed on top of each other or put together to form larger stacks of stones. In this way, the so far laborious, time-consuming and costly manual labor that has been required saved.

Um das Herausgleiten der Unterlagen zwischen den Formsteinen erforderlichenfalls zu erleichtern und zu beschleunigen, wird das Verfahren dahingehend ausgestaltet, daß beim Erfassen der Formsteine die Unterlagen zum Lösen von den Formsteinen seitlich verschoben werden. Die möglicherweise an den Formsteinen noch etwas anhaftenden Unterlagen werden somit durch eine Relativbewegung gegenüber den Formsteinen von diesen gelöst. To allow the documents to slide out between the shaped stones if necessary To facilitate and accelerate, the procedure is designed in such a way that that when grasping the shaped stones, the documents for loosening the shaped stones laterally be moved. The ones that may still be stuck to the shaped stones Documents are thus by a relative movement with respect to the shaped stones of solved this.

Zum Durchführen des Verfahrens wird zweckmäßig eine Klammer für Fördergeräte, insbesondere eine Steinklammer für Gabelstapler verwendet, die um eine waagerechte Achse drehbar an einem Drehgerät angeordnet ist, das seinerseits an einem Hubgerüst heb- und senkbar geführt ist. Diese Klammer besteht erfindungsgemäß aus mehreren übereinanderliegenden, zueinander und voneinander verschiebbaren Greifern, die durch Verbindungsglieder, wie Ketten, Seile, Kabel od. dgl. miteinander verbunden und mittels eines am oberen Greifer befestigten Zugseiles od. dgl. an eine Heb- und Senkeinrichtung angeschlossen sind, mit welcher die Greifer aufeinanderliegend abzusenken und zu vergrößerten Abständen voneinander abzuheben sind. Die Anzahl der an der Klammer vorgesehenen Greifer richtet sich nach der Anzahl der in einem Steinstapel befindlichen Steinlagen, so daß jeweils ein Steinstapel in einemArbeitsgang aufgenommen und nach dem Entfernen der Unterlagen an seinem Bestimmungsort abgesetzt bzw. dort in größeren Steinstapeln aufgeschichtet werden kann. To carry out the process, it is advisable to use a clamp for conveyors, in particular a stone clamp used for forklift trucks that need to be horizontal Axis is rotatably arranged on a rotating device, which in turn on a lifting frame is raised and lowered. According to the invention, this bracket consists of several superimposed, mutually and mutually displaceable grippers, which by Connecting links, such as chains, Ropes, cables or the like. Interconnected and by means of a pull rope attached to the upper gripper or the like to a lifting and lowering device are connected, with which the grippers are lowered and closed on top of one another increased distances from each other. The number of on the bracket provided gripper depends on the number of stones in a stack of stones Stone layers, so that a stack of stones is picked up in one work cycle and after the removal of the documents at its destination or there in larger Stacking stones can be piled up.

Für das Befördern von Ziegelsteinen ist ein an einem Kran aufhängbarer Förderrahmen bekannt, der zum Festklemmen von unmittelbar aufeinandergestapelten Ziegeln mehrere mit unveränderbaren Abständen übereinander angeordnete Klemmplattenpaare aufweist. Die Klemmplatten sind an Kipphebeln und -wellen gelagert und werden durch Drehen einer Spindel in die Klemmstellung gebracht bzw. nach dem Absetzen des Stapels- von den Ziegeln gelöst. Mit dieser Einrichtung können keine Unterlagen von gestapelten Formsteinen entfernt werden. For moving bricks there is one that can be suspended from a crane Conveyor frame known that for clamping directly stacked one on top of the other Bricks several pairs of clamping plates arranged one above the other with unchangeable distances having. The clamping plates are mounted on rocker arms and shafts and are operated by Turning a spindle brought into the clamping position or after the stacking detached from the bricks. With this facility, no documents can be stacked Form stones are removed.

Eine Weiterbildung der Erfindung besteht darin, daß die Greifer je einen feststehenden und einen beweglichen Klemmarm aufweisen, wobei an der Unterseite der feststehenden Klemmarme eine in deren Längsrichtung liegende Anschlagleiste vorgesehen und die Klammer in Richtung der beweglichen Klemmarme drehbar ist. Dies hat den Vorteil, daß beim Erfassen der Formsteine die in Richtung der feststehenden Klemmarme verschwenkten beweglichen Klemmarme, infolge der an den Anschlagleisten anliegenden und über die Außenflächen der Formsteine etwas überstehenden Unterlagen, die Form steine relativ zu den Unterlagen verschieben. A further development of the invention is that the gripper each have a fixed and a movable clamp arm, on the underside of the fixed clamping arms a stop strip lying in their longitudinal direction intended and the clamp in the direction of the movable clamp arms is rotatable. This has the advantage that when you grasp the shaped blocks in the direction the fixed clamping arms pivoted movable clamping arms, as a result of the resting against the stop strips and protruding slightly over the outer surfaces of the shaped stones Documents that move the shape stones relative to the documents.

Hierdurch werden in vorteilhafter Weise die Unterlagen von den Form steinen gelöst und gleiten nach dem Auseinanderziehen der Steinlagen und Schwenken derselben aus der Waagerechten ungehindert von den Form steinen.This advantageously removes the documents from the form stones loosened and slide after pulling apart the stone layers and pivoting the same from the horizontal unhindered by the shape stones.

Es ist eine Ziegelzange mit einem feststehenden und einem beweglichen Klemmarm bekannt, die zum Befördern einiger Ziegel von Hand getragen wird. It is a brick tong with one fixed and one movable Clamp arm known, which is carried by hand to move some bricks.

Der bewegliche Klemmarm ist mit einem abgewinkelten Handgriff ausgestattet, so daß der Klemmarm beim Tragen der Ziegelzange durch das Eigengewicht der Ziegel in die Klemmstellung bewegt wird und dabei die aneinanderliegenden Ziegel festklemmt. Diese Vorrichtung kann nicht zum Befördern von aufeinandergestapelten Formsteinen mittels eines Flurfördergerätes verwendet werden.The movable clamp arm is equipped with an angled handle, so that the clamping arm when carrying the brick tongs by the weight of the brick is moved into the clamping position and thereby clamps the adjoining bricks. This device cannot be used to convey shaped blocks that are stacked on top of one another be used by means of an industrial truck.

Die Erfindung ist nachfolgend an Hand eines auf der Zeichnung veranschaulichten Ausführungsbeispiels beschrieben. Es zeigt Abb. 1 die Seitenansicht einer Klammer, Abb. 2 eine Draufsicht auf die Klammer nach Abb. 1, Abb. 3 einen senkrechten Längsschnitt durch die Klammer nach der Linie III-III in Abb. 2, Abb. 4 die Vorderansicht eines Greifers, Abb. 5 eine Vorderansicht eines Steinstapels beim Entfernen der Unterlagen. The invention is illustrated below with reference to one of the drawings Embodiment described. It shows Fig. 1 the side view of a clip, Fig. 2 is a plan view of the clip according to Fig. 1, Fig. 3 is a vertical longitudinal section through the bracket after the line III-III in Fig. 2, Fig. 4 the front view of a Gripper, Fig. 5 is a front view of a stack of stones removing the documents.

An dem senkrechten Hubgerüst 1 eines Gabelstaplers ist ein eine Quertraverse2 aufweisender, heb-und senkbarer Hubschlitten 3 angeordnet, der ein Drehgerät 4 trägt. Dieses Drehgerät ist mit einer hydraulischen Schwenkvorrichtung 5 ausgerüstet, die mittels eines Bolzens 6 drehbeweglich gelagert ist. Mit der Schwenkvorrichtung 5 kann das Drehgerät 4 um eine waagerechte Achse 7 in der Pfeilrichtung a (Abb. 2 und 5) bis zu etwa 900 aus der Waagerechten geschwenkt werden. On the vertical mast 1 of a forklift is a cross member 2 arranged having, liftable and lowerable lifting carriage 3, which carries a rotating device 4. This rotating device is equipped with a hydraulic swivel device 5, which is rotatably mounted by means of a bolt 6. With the swivel device 5 the rotating device 4 can be rotated about a horizontal axis 7 in the direction of the arrow a (Fig. 2 and 5) can be swiveled up to about 900 from the horizontal.

Am Drehgerät 4 ist eine Klammer 8 befestigt, die aus vier übereinanderliegenden Greifern 9 besteht. A bracket 8 is attached to the rotating device 4, which consists of four superimposed Grippers 9 consists.

Diese Greifer haben je einen feststehenden und einen beweglichen Klemmarm 10 bzw. 11. Der bewegliche Klemmarm 11 kann mittels einer Hydraulikeinrichtung 12 verschwenkt werden, die an einem Zapfen 13 des Greifers drehbar gelagert ist und mit einer Schubstange 14 und einem Bolzen 15 an dem inneren Ende des Klemmarmes 11 drehbeweglich angelenkt ist. Der Klemmarm 11 ist als zweiarmiger Hebel ausgebildet, welcher mittels eines am Greifer gelagerten Drehzapfens 16 gehalten wird und an seinem äußeren Ende einen Bolzen 17 für die drehbewegliche Lagerung einer gleichfalls als zweiarmiger Hebel ausgebildeten Klemmbacke 18 trägt. Diese Klemmbacke ist mit zwei Anlageflächen 19, 20 ausgestattet, die zwei entsprechenden Anlageflächen 21, 22 des feststehenden Klemmarmes 10 gegenüberliegen. Durch die drehbewegliche Lagerung der Klemmbacke 18 können Längenunterschiede der Formsteine 23 ausgeglichen werden und ist eine rutschsichere Anlage der Außen flächen 19, 20, 21, 22 an den Formsteinen 23 gewährleistet, An der Unterseite der feststehenden Klemmarme 10 befindet sich eine in deren Längsrichtung liegende Anschlagleiste 24, die beim Ausführungsbeispiel aus einem Winkelstahl besteht.These grippers each have a fixed and a movable clamp arm 10 or 11. The movable clamping arm 11 can be operated by means of a hydraulic device 12 are pivoted, which is rotatably mounted on a pin 13 of the gripper and with a push rod 14 and a bolt 15 at the inner end of the clamp arm 11 is rotatably articulated. The clamping arm 11 is designed as a two-armed lever, which is held by means of a pivot pin 16 mounted on the gripper and on its outer end a bolt 17 for the rotatable mounting of a likewise designed as a two-armed lever clamping jaw 18 carries. This jaw is with two contact surfaces 19, 20, the two corresponding contact surfaces 21, 22 of the fixed clamp arm 10 are opposite. Due to the rotatable bearing of the clamping jaw 18, differences in length of the shaped blocks 23 can be compensated for and is a non-slip system of the outer surfaces 19, 20, 21, 22 on the shaped stones 23 guaranteed, at the bottom of the fixed Clamp arms 10 is located a stop strip 24 lying in the longitudinal direction thereof, which in the exemplary embodiment consists of an angle steel.

Die Greifer 9 sind mittels Führungsrollen 25 in Führungsschienen 26 der Klammer 8 zueinander und voneinander verschiebbar gelagert. Die unteren Enden der Führungsschienen sind durch Platten 34 verschlossen, auf denen die unteren Führungsrollen25 des in abgesenktem Zustand befindlichen untersten Greifers 9 aufliegen. Zwischen den Führungsschiener 26 ist an der Klammer eine hydraulische Heb- und Senkeinrichtung 27 befestigt. Die Kolbenstange 28 dieser Heb- und Senkeinrichtung trägt an ihrem äußeren Ende ein Umlenkrad 29 für ein Zugseil 30, welches mit dem einen Ende an der Klammer 8 und dem anderen Ende am obersten Greifer 9 angeschlossen ist. Zwischen den Greifern befinden sich als Verbindungsglieder dienende Ketten 31. Die Länge der die Greifer 9 verbindenden Ketten 31 richtet sich nach der jeweiligen Höhe der Formsteine 23 und dem beim nachfolgend beschriebenen Auseinanderziehen der Steinlagen gewünschten Zwischenraum. Dieser Zwischenraum wird zweckmäßig etwa 50 mm groß gewählt. An Stelle der Ketten 31 können in gleicher Weise Seile oder Kabel verwendet werden. The grippers 9 are in guide rails by means of guide rollers 25 26 of the clamp 8 are mounted to be displaceable to one another and to one another. The lower ends of the guide rails are closed by plates 34 on which the lower guide rollers 25 of the lowermost gripper 9, which is in the lowered state, rest. Between the guide rail 26 is a hydraulic lifting and lowering device on the clamp 27 attached. The piston rod 28 of this lifting and lowering device carries on its outer end of a pulley 29 for a pull rope 30, which one end to the clamp 8 and the other end to the uppermost gripper 9 is connected. Between the grippers are chains 31 serving as connecting links. The length the chains 31 connecting the grippers 9 depends on the respective height of the Molded stones 23 and the pulling apart of the stone layers described below desired space. This gap is expediently chosen to be about 50 mm. Instead of the chains 31, ropes or cables can be used in the same way.

Innerhalb der Führungsschienen 26 befinden sich an der Unterseite jedes Greifers Abstandstücke 32, die den Greifern in abgesenktem, aufeinanderliegendem Zustand einen der Höhe der Formsteine 23 entsprechenden senkrechten Abstand voneinander erteilen. Auf der Abb. 1 sind die Greifer 9 abgesenkt und aufeinanderliegend dargestellt. Bei sich ändernder Steinhöhe wird die Länge der Abstandstücke 32 und - wie bereits erwähnt - die Länge der Ketten 31 entsprechend verändert. Es besteht mit der Erfindung auch die Möglichkeit, die Abstandstücke 32 fortzulassen und in einem solchen Falle die Greifer 9 mit der Heb- und Senkeinrichtung 27 vor dem Klammern der Formsteine einzeln, mit dem untersten Greifer beginnend, in die gewünschte Höhenlage zu bringen und sodann die Formsteine zu klammern. Inside the guide rails 26 are located on the underside each gripper spacers 32, which the grippers in lowered, one on top of the other State a vertical distance from one another corresponding to the height of the shaped blocks 23 To give. In Fig. 1, the grippers 9 are shown lowered and lying on top of one another. When the stone height changes, the length of the spacers 32 and - as already mentioned - the length of the chains 31 changed accordingly. It exists with the invention also the possibility of omitting the spacers 32 and in such a case the gripper 9 with the lifting and lowering device 27 before clamping the shaped blocks individually, starting with the lowest gripper, to the desired height and then to clamp the shaped bricks.

Die Wirkungsweise der Erfindung ist folgende: Die auf ihren Unterlagen 33 in der eingangs beschriebenen Weise ruhenden und zu einem Steinstapel aufgeschichteten Formsteine 23 werden nach dem Heranfahren des Gabelstaplers in Pfeilrichtung b von den gemäß Abb. 1 aufeinanderliegenden Greifern 9 (Abb. 2) durch Andrücken der Klemmarme 18 mit den Anlageflächen 19, 20, 21, 22 erfaßt. Danach wird der gesamte Steinstapel durch Aufwärtsbewegen des Drehgerätes 4 am Hubgerüst 1 vom Boden aufgenommen und zu seinem Bestimmungsort gefahren. The mode of operation of the invention is as follows: The one on your documents 33 resting in the manner described above and piled up to form a stack of stones Shaped blocks 23 are after the forklift has approached in the direction of arrow b from the grippers 9 lying on top of one another according to Fig. 1 (Fig. 2) by pressing the clamping arms 18 with the contact surfaces 19, 20, 21, 22 detected. After that, the entire stone pile taken up by moving the rotating device 4 on the mast 1 from the ground and driven to its destination.

Dort werden die Steinlagen zur Bildung von Zwischenräumen (Abb. 5) durch entsprechendes Betätigen der Heb- und Senkeinrichtung 27 mittels des Zugseiles 30 und der zwischen den Greifern 9 befindlichen Ketten 31 voneinander abgehoben. Sodann werden die Steinlagen zum Herausfallen der Unterlagen 33 um etwa 800 (Abb. 5) zur Waagerechten in Richtung der beweglichen Klemmarme 18 geneigt, wobei die Unterlagen 33 von den Formsteinen 23 gleiten und aus dem Steinstapel herausfallen. Anschließend werden die Greifer in die waagerechte Lage zurückgebracht und wird die Heb- und Senkeinrichtung im Sinne eines Absenkens der Greifer betätigt, so daß die Steinlagen unmittelbar aufeinanderliegen und nach dem Absenken des Drehgerätes 4 am Hubgerüst 1 auf dem Boden abgesetzt werden können. Es besteht auch die Möglichkeit, nach dem Entfernen der Unterlagen die Formsteine zu größeren Steinstapeln zusammenzusetzen.There the stone layers are used to form gaps (Fig. 5) by appropriately actuating the lifting and lowering device 27 by means of the pull rope 30 and the chains 31 located between the grippers 9 are lifted from one another. Then the stone layers for the supports 33 to fall out are about 800 (Fig. 5) inclined to the horizontal in the direction of the movable clamping arms 18, the Slides 33 slide from the shaped stones 23 and fall out of the stone stack. Then the grippers are brought back into the horizontal position and is the lifting and lowering device actuated in the sense of lowering the gripper, so that the stone layers are directly on top of each other and after lowering the rotating device 4 set down on the mast 1 on the ground can be. It exists also the possibility of making the shaped stones larger after removing the documents Assemble stacks of stones.

Wie die Abb. 4 erkennen läßt, liegen beim Einfahren der Greifer 9 die Anschlagleisten 24 der festen Klemmarme 10 in Höhe der über die Außenflächen der Formsteine etwas überstehenden Unterlagen 33, so daß der sich anschließend in Pfeilrichtung d bewegende bewegliche Klemmarm 18 die Formsteine auf der an der Anschlagleiste 24 anliegenden Unterlage 33 verschiebt. Auf diese Weise wird das Lösen der Unterlagen von den Formsteinen vorteilhaft erleichtert und erforderlichenfalls beschleunigt, so daß beim nachfolgenden Auseinanderziehen der Steinlagen und Neigen derselben die Unterlagen leicht und schnell herausfallen. As can be seen in Fig. 4, the grippers 9 are positioned when they are retracted the stop bars 24 of the fixed clamping arms 10 at the level of the over the outer surfaces the molded blocks slightly protruding documents 33, so that the then in Arrow direction d moving movable clamping arm 18 the shaped stones on the on the stop bar 24 adjacent pad 33 moves. This way the paperwork will be loosened advantageously facilitated by the shaped bricks and, if necessary, accelerated, so that when the stone layers are subsequently pulled apart and inclined the documents fall out easily and quickly.

Abweichend von dem auf der Zeichnung dargestellten Ausführungsbeispiel kann die Erfindung auch bei Formsteinen angewendet werden, die eine andere Gestalt oder Größe aufweisen bzw. in anderer Anordnung auf den Unterlagen liegend zu Steinstapeln aufgeschichtet sind. In einem solchen Fall werden die Greifer der Klammer entsprechend ausgebildet. Deviating from the embodiment shown in the drawing the invention can also be applied to shaped bricks that have a different shape or size or in a different arrangement lying on the documents to form stone stacks are piled up. In such a case, the grippers of the clamp will be appropriately educated.

Claims (4)

PATENTANSPRÜCHE: 1. Verfahren zum Entfernen der Unterlagen für Formsteine aus Beton, Bims, Kalksandstein u. dgl. aus Stapeln, in denen die Formsteine auf den Unterlagen liegend aufeinandergeschichtet sind, dadurch gekennzeichnet, daß der Steinstapel zunächst vom Boden aufgenommen wird, worauf die Steinlagen zur Bildung von Zwischenräumen voneinander abgehoben, sodann zum Herausfallen der Unterlagen um etwa 80u zur Waage- rechten geneigt und anschließend in die waagerechte Lage zurückgebracht und aufeinanderliegend abgesetzt bzw. zu größeren Steinstapeln zusammengesetzt werden. PATENT CLAIMS: 1. Procedure for removing the underlays for shaped stones Made of concrete, pumice, sand-lime brick and the like. From stacks in which the shaped stones are placed the documents are stacked lying on top of one another, characterized in that the stone pile is first picked up from the ground, whereupon the stone layers to form lifted from each other by gaps, then for the documents to fall out around 80u to the balance right inclined and then brought back into the horizontal position and placed on top of one another or put together to form larger stacks of stones. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, daß beim Erfassen der Formsteine die Unterlagen zum Lösen von den Formsteinen seitlich verschoben werden. 2. The method according to claim 1, characterized in that when detecting of the shaped stones moved the documents to the side to loosen them from the shaped stones will. 3. Klammer für Fördergeräte zur Ausführung des Verfahrens nach Anspruch 1 und 2, insbesondere Steinklammer für Gabelstapler, die um eine waagerechte Achse drehbar an einem Drehgerät angeordnet ist, das seinerseits an einem Hubgerüst heb- und senkbar geführt ist, dadurch gekennzeichnet, daß die Klammer (8) aus mehreren übereinanderliegenden, zueinander und voneinander verschiebbaren Greifern (9) besteht, die durch Verbindungsglieder (31), wie Ketten, Seile, Kabel od. dgl., miteinander verbunden und mittels eines am obersten Greifer(9) befestigten Zugseiles (30) od. dgl. an eine Heb- und Senkeinrichtung (27) angeschlossen sind, mit welcher die Greifer (9) aufeinanderliegend abzusenken und zu vergrößerten Abständen voneinander abzuheben sind. 3. Clamp for conveyors for carrying out the method according to claim 1 and 2, in particular stone clamps for forklifts, which are about a horizontal axis is rotatably arranged on a rotating device, which in turn lifts on a lifting frame and is guided so that it can be lowered, characterized in that the clamp (8) consists of several grippers (9) lying one above the other and displaceable to one another and from one another, by connecting links (31), such as chains, ropes, cables or the like., With each other connected and by means of a pull rope (30) attached to the uppermost gripper (9) od. Like. Are connected to a lifting and lowering device (27) with which the gripper (9) to be lowered on top of one another and lifted off from one another at increased distances are. 4. Klammer nach Anspruch 3, dadurch gekennzeichnet, daß die Greifer (9) je einen feststehenden und einen beweglichen Klemmarm (10 bzw. 4. Clip according to claim 3, characterized in that the gripper (9) one fixed and one movable clamp arm (10 resp. 11) aufweisen, wobei an der Unterseite der feststehenden Klemmarme (10) eine in deren Längsrichtung liegende Anschlagleiste (24) vorgesehen und die Klammer (8) in Richtung der beweglichen Klemmarme (11) drehbar ist. 11), with the fixed clamp arms on the underside (10) a stop strip (24) lying in the longitudinal direction thereof is provided and the Clamp (8) is rotatable in the direction of the movable clamping arms (11). In Betracht gezogene Druckschriften: USA.-Patentschriften Nr. 954 584, 1 153 269. References considered: U.S. Patent No. 954 584, 1 153 269.
DER25760A 1959-06-18 1959-06-18 Method and stone clamp for removing the documents for shaped stones Pending DE1109075B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DER25760A DE1109075B (en) 1959-06-18 1959-06-18 Method and stone clamp for removing the documents for shaped stones

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DER25760A DE1109075B (en) 1959-06-18 1959-06-18 Method and stone clamp for removing the documents for shaped stones

Publications (1)

Publication Number Publication Date
DE1109075B true DE1109075B (en) 1961-06-15

Family

ID=7401997

Family Applications (1)

Application Number Title Priority Date Filing Date
DER25760A Pending DE1109075B (en) 1959-06-18 1959-06-18 Method and stone clamp for removing the documents for shaped stones

Country Status (1)

Country Link
DE (1) DE1109075B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0045553A1 (en) * 1980-08-04 1982-02-10 Stork Services B.V. Apparatus for displacing part by part a stack of cages, cases or boxes

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US954584A (en) * 1908-11-06 1910-04-12 Raymond C Penfield Machine for handling bricks.
US1153269A (en) * 1914-09-18 1915-09-14 William Sturm Sr Brick-handling tongs.

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US954584A (en) * 1908-11-06 1910-04-12 Raymond C Penfield Machine for handling bricks.
US1153269A (en) * 1914-09-18 1915-09-14 William Sturm Sr Brick-handling tongs.

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0045553A1 (en) * 1980-08-04 1982-02-10 Stork Services B.V. Apparatus for displacing part by part a stack of cages, cases or boxes

Similar Documents

Publication Publication Date Title
DE3417876C2 (en) Device for stacking objects
DE3339115A1 (en) DEVICE FOR LAYING PAVING STONES
DE1109075B (en) Method and stone clamp for removing the documents for shaped stones
DE3507282C2 (en)
DE2545186A1 (en) Pallet loading machine for containers - has separate transport tracks for containers and pallets and vertically and horizontally movable frame grab
DE2434060A1 (en) Profilated brick blanks handling and stacking machine - has grabs for blanks and supports forming combined mechanism
DE3601404C2 (en)
DE4241165C2 (en) Device for picking up a layer of packs
DE3139418C2 (en) "Device for loading pipes"
DE1208691B (en) Method and device for dividing stacks of hardened or calcined artificial stone
DE824500C (en) Device for pulling and conveying steel blocks
DE1201769B (en) Method and apparatus for dividing stacks of hardened or calcined stones
DE2025203A1 (en) Device for stacking or removing plate-shaped objects
DE1555717C (en) Vehicle for transporting stones stacked in blocks
DE1219400B (en) Method and device for stacking molded bodies, in particular concrete blocks, to form blocks with a square cross-section
DE1280735B (en) Device for destacking shaped blocks lying on production boards
DD219453A1 (en) APPARATUS FOR ASSEMBLING BARRELED ROLLING GOODS, ESPECIALLY REINFORCING BOARDS
DE2611569C3 (en) Device for the mechanical installation of track expansion frames
DE8212936U1 (en) LOADING CROSS FOR CRANES
DE1584499C (en) Method and device for the mechanical occupation of kiln cars with clay moldings in the brick industry
DE1952369U (en) DEVICE FOR STACKING MOLDED BLOCKS LYING ON BASE BOARD.
DE1216201B (en) Device for storing and keeping items
DE2535208A1 (en) LATERAL FORKLIFT
DE1003420B (en) Loading system, e.g. B. for cement-bound shaped stones
DE1231162B (en) Device for removing fresh concrete blocks or the like. Molded bodies that are easy to damage from production boards transported on a conveyor