CS211437B1 - Frame supporting system particularly for shuttering the balk construction bodies - Google Patents

Frame supporting system particularly for shuttering the balk construction bodies Download PDF

Info

Publication number
CS211437B1
CS211437B1 CS414274A CS414274A CS211437B1 CS 211437 B1 CS211437 B1 CS 211437B1 CS 414274 A CS414274 A CS 414274A CS 414274 A CS414274 A CS 414274A CS 211437 B1 CS211437 B1 CS 211437B1
Authority
CS
Czechoslovakia
Prior art keywords
formwork
bars
horizontal
support system
frame
Prior art date
Application number
CS414274A
Other languages
Czech (cs)
Inventor
Hilmar Hopfe
Fritz Kluge
Original Assignee
Hilmar Hopfe
Fritz Kluge
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hilmar Hopfe, Fritz Kluge filed Critical Hilmar Hopfe
Publication of CS211437B1 publication Critical patent/CS211437B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/14Bracing or strutting arrangements for formwalls; Devices for aligning forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Úkolem vynálezu je vytvořit rámový opěrný systém pro bednění, který by byl tužší a lehčý, než systémy dosavadní, snadno se přemístoval jako celek jeřábem a byl snadno přizpůsobitelný menším změnám rozměrů . . Úloha je řešena vytvořením rámového podpěrného systému, jehož svislé nosiče, tvořené vždy dvojicí profilových tyčí o profilu U, jsou podepřeny vodorovnými nosnými rámy, složenými z dvojic profilových tyčí o.profilu U, do nichž jsou Zasunuty čtyřhranné duté tyče. Jednotlivé prvky vodorovného nosného rému jsou vzájemně spojeny čepovými spoji. Vodorovný nosný rám je zpevněn výztužnou konstrukcí, na níž je případně uspořádáno pracovní lešení.The object of the invention is to provide a frame a support system for formwork that is stiffer and lighter than previous systems, easily he moved as a whole by crane and was easily adaptable to smaller dimensional changes . . The task is solved by creating a frame supporting system, whose vertical carriers, formed by a pair of profile profile bars U, are supported by horizontal carriers frames, composed of pairs of profile bars O.profile U, into which the square is inserted hollow bars. Individual horizontal elements they are connected to each other pin joints. The horizontal support frame is reinforced by the reinforcement structure on which it is a scaffolding is optionally arranged.

Description

Vynález sě vztahuje na rámový podpěrný systém, zejména pro bednění hranolových stavebních těles, s nosiči, tvořenými dvojicí profilových tyčí profilu U a čtyřhrannými dutými tyčemi, případně s výztužnou konstrukcí.The invention also relates to a frame support system, in particular for the formwork of prismatic building bodies, with supports comprising a pair of U-shaped profile bars and square hollow bars, optionally with a reinforcing structure.

Jsou známa bednění pro hranolové stavební dílce, jež jsou podepírána vodorovně uspořádanými nosnými rámy, přičemž bednicí desky přímo doléhají ná nosné rámy. Tyto nosné rámy jsou trubkovými spojkami spojeny se svislými lešeňovými trubkami, které udržují nosné rámy ve stanovené vzájemné vzdálenosti.Formwork for prismatic components is known, which are supported by horizontally arranged support frames, the formwork plates directly abutting the support frames. These support frames are connected by pipe connectors to vertical scaffold tubes which keep the support frames at a specified distance from each other.

Počet vodorovných nosných rámů vyplývá z nosnosti bednících desek. V úrovni vodorovných stykových spár mezi bednícími deskami je nutno uspořádat vždy dalěi vodorovný nosný rám. Pokud rozměry bednění není možno sestavit ze sady bednících desek o normovaných rozměrech, je nutno bedtíění doplňovat individuálně vyrobenými bednícími deskami. Pracovní ležení je umístěno samostatně vedle bednění na svislých lešeňových trubkách.The number of horizontal support frames results from the load-bearing capacity of the formwork boards. At the level of the horizontal joints between the shuttering boards, an additional horizontal support frame must always be provided. If the shuttering dimensions cannot be assembled from a set of shuttering boards of standard dimensions, the shuttering must be completed with individually produced shuttering boards. The working scaffolding is placed separately next to the formwork on vertical scaffold tubes.

Bednění je při montáži drženo šikmými vzpěrami. Když je hranolový stavební dílec odstupňován, pak je nutno bednění horního menšího hranolu usadit na rošt z dřevěných trámů. Při větších rozměrech stavebního dílce je nutno nejprve vybetonovat spodní větší hranol a teprve po zatvrdnutí betonu postavit na něj bednění pro vrchní menší hranol.The formwork is held by inclined struts during assembly. If the prismatic component is graduated, then the formwork of the upper smaller prism must be placed on a wooden beam grid. In the case of larger dimensions of the building part, it is necessary to concret the lower larger prism first and only after the concrete has hardened the formwork for the upper smaller prism must be placed on it.

Při přemisťování a usazování sestaveného bednění pomocí jeřábů je nutno uspořádat svislé lešeňóvé trubky v malých vzdálenostech od sebe, aby se zatížení tíhou bednění rozložilo rovnoměrně. Protože nosnost bednících desek je poměrně malé, jsou vodorovné nosné rámy uspořádány poměrně hustě vedle sebe, takže jejich skutečná pevnost není využita, což platí zejména při uspořádání dalších vodorovných nosných rámů v oblasti vodorovných stykových spár mezi bednícími deskami.When moving and setting up the assembled formwork using cranes, it is necessary to arrange the vertical scaffold tubes at small distances from each other in order to distribute the weight of the formwork evenly. Since the load-bearing capacity of the formwork panels is relatively small, the horizontal support frames are arranged relatively densely side-by-side, so that their true strength is not utilized, especially when arranging other horizontal support frames in the region of horizontal joints between the formwork boards.

Vzájemné spojení vodorovných nosných rámů pomocí svislých lešeňových trubek není obvykle dosti tuhé, takže po několikerém přemístění bednění jeřábem se vodorovné nosné rámy posunou, bednicí desky se uvolní. Bednění je nutno opravovat a upravovat, ěímž vznikají přídavné náklady a průtahy v práci.The interconnection of the horizontal supporting frames by means of vertical scaffold tubes is not usually quite rigid, so that after the crane shuttering has been moved several times by crane, the horizontal supporting frames are displaced, the formwork plates are released. The formwork needs to be repaired and modified, resulting in additional costs and delays at work.

Pokud potřebné rozměry bedněni hranolového stavebního tělesa nelze sestavit z bednících desek normovaných rozměrů, nutno je doplnit bednícími deskami vyráběnými individuálně, protože známé vodorovné nosné rámy neumožňují žádné rozměrové přizpůsobení.If the required formwork dimensions of the prismatic building body cannot be assembled from formwork boards of standard dimensions, they must be completed with formwork boards manufactured individually because the known horizontal support frames do not allow any dimensional adjustment.

Vyztužení jednotlivých stěn bednění šikmými vzpěrami není ve všech případech dostatečně spolehlivé, takže bednění je nutno dodatečně upravovat, což způsobuje nemalé těžkosti.The reinforcement of the individual formwork walls by inclined struts is not always sufficiently reliable, so that the formwork needs to be retrofitted, which causes considerable difficulties.

Rovněž zhotovováni odstupňovaných hranolových stavebních těles ve dvou fázích, při němž se nejprve betonuje spodní kvádr, načež se musí čekat na jeho zatvrdnutí a teprve potom budovat bednění pro horní menší kvádr, způsobuje časovou ztrátu a zvýšené náklady. Přemisťování hotového bednění pomocí jeřábu je možné pouze tehdy, když vodorovné nosné rámy a svislé lešeňóvé trubky jsou uspořádány zvláště hustě, což zvyšuje náklady, hmotnost podpěrného systému a způsobuje manipulační potíže.Also, the production of staggered prismatic building bodies in two phases, in which the bottom block is first concreted, then it has to wait for its hardening before building the formwork for the smaller smaller block, results in time loss and increased costs. Transporting the finished formwork by crane is only possible when the horizontal support frames and vertical scaffold tubes are arranged particularly densely, which increases the cost, weight of the support system and causes handling difficulties.

Problém je řešen vytvořením rámového podpěrného systému, zejména pro bednění hranolových stavebních těles, s nosiči, tvořenými dvojicí profilových tyčí profilu U a čtyřhrannými dutými tyčemi,· případně s výztužnou konstrukcí, jež se od známých řešení liší tím, že svislé nosiče, tvořené dvojicí profilových tyčí profilu U, jež jsou upevněny na bednících deskách, jsou podepřeny vodorovnými nosnými rámy, vytvořenými z profilových tyčí profilu U a čtyřhranných dutých tyčí.The problem is solved by providing a frame support system, in particular for the formwork of prismatic building bodies, with supports formed by a pair of U-shaped profile bars and square hollow bars, possibly with a reinforcing structure which differs from known solutions in that vertical supports formed by a pair of The U-shaped bars, which are fastened to the formwork plates, are supported by horizontal support frames made of U-shaped profile bars and square hollow bars.

Pro zvýšení tuhosti podpěrného systému jsou podle vynálezu, zejména vodorovné nosné rámy opatřeny výztužnou konstrukcí.In order to increase the stiffness of the support system, according to the invention, in particular horizontal support frames, they are provided with a reinforcing structure.

Rozměrová přizpůsobivost podpěrného systému je podle vynálezu zajištěna tím, že čtyřhranné duté tyče jsou přestavitelné zasunuty do dvojic profilových tyčí profilu U i u svislých nosičů. Pro týž účel je podle vynálezu každý vodorovný nosný rám větší, než.úhrnná dálka nebo šířka bednících desek.According to the invention, the dimensional flexibility of the support system is ensured by the fact that the square hollow bars are adjustable in the pairs of U-shaped profile bars even in vertical supports. For the same purpose, according to the invention, each horizontal support frame is larger than the overall distance or width of the formwork panels.

Aby se uspořilo budování samostatného pracovního lešení, jsou podle vynálezu jednotlivé výztužné konstrukce jednotlivých vodorovných nosných rámů vzájemně spojeny svislými trubkami, na nichž jsou upevněny vodorovné trubky.In order to save the construction of a separate working scaffold, according to the invention, the individual reinforcing structures of the individual horizontal supporting frames are connected to each other by vertical tubes on which horizontal tubes are fixed.

Rámový podpěrný systém, vytvořený podle vynálezu, mé četné výhody. Především je to jeho vysoká tuhost při poměrně malé hmotnosti. Nepotřebuje samostatné pracovní lešení, které je součástí podpěrného systému. Rozměry podpěrného systému lze ve značném rozsahu přizpůsobovat dálce, šířce a výšce hranolového stavebního tělesa, přičemž se převážně vystačí s bednícími deskami normalizovaných rozměrů. Bednění odstupňovaných hranolových Stavebních těles lze montovat najednou a tudíž i najednou betonovat. Smontovaný opěrný systém i s bednícími deskami lze spolehlivě přenášet jeřábem, bez nebezpečí, že se bednění zdeformuje.The frame support system constructed according to the invention has my numerous advantages. First of all it is its high stiffness at relatively low weight. It does not need a separate working scaffold, which is part of the support system. The dimensions of the support system can be adapted to a large extent to the distance, width and height of the prismatic building body, using mostly standardized formwork panels. The shuttering of graduated prismatic building bodies can be assembled at the same time and therefore at once. The assembled support system, including the shuttering boards, can be reliably transported by crane, without the risk of the shuttering deforming.

To vše přináší úspory na nákladech, přispívá k vyšší produktivitě práce a ke zkráceni průběžných stavebních dob.All this brings savings in costs, contributes to higher labor productivity and shortening of continuous construction times.

Příklad provedeni rámového podpěrného systému, vytvořeného podle vynálezu, je uveden na připojených, výkresech, kde na obr. I je v axonometrickém pohledu zobrazen rámový podpěrný systém pro odstupňovaný základ, tvořený dvěma na sobě uspořádanými hranoly, a na obr. 2 pohled shora na roh bednění.An exemplary embodiment of a frame support system constructed in accordance with the invention is shown in the accompanying drawings, in which Fig. 1 is a perspective view of a frame support system for a graduated base formed by two prisms arranged one upon another, and Fig. 2 formwork.

Rámový podpěrný systém bednění jak pro větší dolní hranolovou část základu, tak i pro jeho horní meněí .část, je složen jednak ze svislých nosičů 1, jednak z vodorovných nosných rámů χ. Svislé nosiče X, na nichž jsou upevněny předem zhotovené bednící desky £, jsou tvořeny dvojicemi £ profilových tyčí profilu U. Výška rámového opěrného systému se přizpůsobuje výšce hranolového stavebního dílu £ tím, že do mezery ve dvojici £ profilových tyčí profilu U se zasune čtyřhranná dutá tyč £. Vodorovné nosné rámy X jsou tvořeny jednak dvojicemi £ profilových tyčí profilu U, jednak čtyřhrannými dutými tyčemi £, přičemž čtyřhranná dutá tyč 2 je vždy svým koncem částečně zasunuta do mezery mezi dvojicí £ profilových tyčí o profilu U. Vodorovné nosné rámy X jsou na svých dalších stranách zpevněny výztužnou konstrukcí 6. ' Svislé nosiče 1 bednících desek £ jsou spojeny s vodorovnými nosnými rámy X v místech vzájemného křížení pomocí třmenů 8 a dřevěných klínů J. Vodorovné nosná rámy X jsou z dvojic £ profilových tyčí profilu U a čtyřhranných dutých tyčí 2 složeny tak, že jedna strana vodorovného nosného rámu X končí dvojicí £ profilových tyčí o profilu U, kdežto křižující druhá strana vodorovného nosného rámu X končí čtyřhrannou dutou tyčí £, která je zasunuta do mezery mezi dvojicí £ profilových tyčí o profilu U. Obš strany vodorovného nosného rámu χ jsou vzájemně spojeny čepem 10.The frame formwork support system for both the lower prismatic base part and its lower part is composed of both vertical supports 1 and horizontal supporting frames χ. The vertical supports X on which the preformed formwork plates 4 are fixed consist of pairs of U-shaped profile bars. The height of the frame support system adapts to the height of the prismatic component 4 by inserting a rectangular hollow section into the gap. rod £. The horizontal support frames X consist of both pairs of U-shaped profile bars 4 and square hollow bars 4, the square hollow bar 2 being partially inserted into the gap between the pair of U-shaped profile bars 7 at each end. The vertical support frames 1 are connected to the horizontal support frames X at the cross-over points by means of yokes 8 and wooden wedges J. The horizontal support frames X are composed of pairs of U-shaped section bars and square hollow bars 2 composed of: such that one side of the horizontal support frame X terminates in a pair of U-shaped profile bars, while the intersecting second side of the horizontal support frame X ends in a rectangular hollow bar 6 which is inserted into the gap between the pair of U-shaped profile bars. frame χ are mutually interconnected by pin 10.

Protože v rozích bednění pro hranolový stavební díl £ vždy jedna ze vzájemně se stýkajících bednících desek £ překrývá okraj druhá, může se rámový podpěrný systém přizpůsobovat rozměrům hranolového stavebního dílu £ v rozpětí JJ., které je totožné s výškou stojiny profilové tyče profilu U svislého nosiče 1, bez použiti bednících desek £ individuálních, nenórmalizovaných rozměrů.Since in the formwork corners for the prismatic component 4, one of the interlocking formwork panels 4 always overlaps the edge of the other, the frame support system can adapt to the dimensions of the prismatic component 8 within a span 11 which is identical to the web height of the U-shaped section 1, without the use of formwork panels of individual, non-standardized dimensions.

Na svislých nosičích J. jsou upevněny konzoly 12. určené pro několik účelů. Upevněný na dolních koncích svislých nosičů J stabilizují jejich polohu a pomocí podpěrných patekBrackets 12 for several purposes are mounted on the vertical supports. Mounted at the lower ends of the vertical carriers, they stabilize their position and by means of support feet

13. jež jsou stavitelná, vyrovnávají svislé nosiče J. do přesné svislé polohy. Dále umožňují posadit rámový podpěrný systém pro horní menší hranol základu na rámový podpěrný systém ' pro dolní větší hranol základu. Konečně mohou být 1 opěrou pro pracovní lešení.13, which are adjustable, align the vertical supports J to a precise vertical position. In addition, they allow the frame support system for the upper minor prism base to be fitted on the frame support system for the lower larger prism base. Finally, they can be 1 support for working scaffolding.

Výztužná konstrukce 6 je zároveň nosným systémem pro podlahu Ť5 pracovního lešení. Přitom je přídavně podepírána svislými trubkami 14·. na nichž jsou dále upevněny vodorovné trubky 16 jako zábradlí.The reinforcing structure 6 is also the supporting system for the floor 5 of the scaffolding. It is additionally supported by vertical tubes 14. on which the horizontal tubes 16 are further fastened as railings.

Claims (5)

1. Rámový podpěrný systém, zejména pro bednění hranolových stavebních těles, s nosiči, tvořenými dvojicí profilových tyčí profilu U a čtyřhrannými dutými tyčemi, případně s výztužnou konstrukcí, vyznačený tím, že dvojice (2) profilových tyčí profilu lí, jež jsou upevněny na bednících deskách (3), jsou podepřeny vodorovnými nosnými rámy (4), vytvořenými z dvojic (2) profilových tyči profilu U a čtyřhranných dutých tyčí (5).Frame support system, in particular for the formwork of prismatic building bodies, with supports consisting of a pair of U-shaped profile bars and square hollow bars, possibly with a reinforcing structure, characterized in that a pair (2) of profile profile bars 11a fixed to the formwork The plates (3) are supported by horizontal support frames (4) formed of pairs (2) of U-shaped profile bars and square hollow bars (5). 2. Rámový podpěrný systém podle bodu 1, vyznačený tím, že vodorovné nosné rámy (4) jsou opatřeny výztužnou konstrukcí (6).Frame support system according to claim 1, characterized in that the horizontal supporting frames (4) are provided with a reinforcing structure (6). 3. Rámový podpěrný systém podle bodů 1 a 2, vyznačený tím, že čtyřhranné duté tyče (5) jsou zasunuty do dvojic (2) profilových tyči profilu U a v nich přestavitelné upevněny.Frame support system according to Claims 1 and 2, characterized in that the rectangular hollow bars (5) are inserted into and adjustable in pairs (2) of the U-shaped profile bars. 4. Rámový podpěrný systém podle bodu 1 až 3, vyznačený tím, že vodorovné nosné rámy (4) jsou delší než celková délka, případně šířka bednících desek (3).Frame support system according to Claims 1 to 3, characterized in that the horizontal support frames (4) are longer than the overall length or width of the formwork panels (3). 5. Rámový podpěrný systém podle bodů 2 až 4, vyznačený tím, Že na výztužné konstrukci (6) vodorovných nosných rámů (4) jsou upevněny svislé trubky (14), přičemž na výztužné konstrukci (6) je položena podlaha (15) a na svislých trubkách (14) jsou upevněny vodorovné trubky (16).Frame support system according to Claims 2 to 4, characterized in that vertical pipes (14) are fixed to the reinforcing structure (6) of the horizontal supporting frames (4), the floor (15) being laid on the reinforcing structure (6) and horizontal tubes (16) are fastened to the vertical tubes (14).
CS414274A 1973-06-12 1974-06-11 Frame supporting system particularly for shuttering the balk construction bodies CS211437B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DD17146473A DD107506A2 (en) 1973-06-12 1973-06-12

Publications (1)

Publication Number Publication Date
CS211437B1 true CS211437B1 (en) 1982-02-26

Family

ID=5491599

Family Applications (1)

Application Number Title Priority Date Filing Date
CS414274A CS211437B1 (en) 1973-06-12 1974-06-11 Frame supporting system particularly for shuttering the balk construction bodies

Country Status (3)

Country Link
CS (1) CS211437B1 (en)
DD (1) DD107506A2 (en)
DE (1) DE2426999A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007047438B4 (en) * 2007-10-04 2022-11-24 Doka Gmbh Formwork arrangement for the cantilever construction of bridges
DE102007047439A1 (en) * 2007-10-04 2009-04-16 Doka Industrie Gmbh Formwork routing for the cantilever construction of bridges
IT201600131088A1 (en) * 2016-12-27 2018-06-27 Gran Building S R L System for the construction of a walkable raised surface in formwork

Also Published As

Publication number Publication date
DE2426999A1 (en) 1975-01-09
DD107506A2 (en) 1974-08-12

Similar Documents

Publication Publication Date Title
CN104264895A (en) Prestressed concrete F slab and frame structure system
JP6752160B2 (en) Mobile work vehicle
CN108625486A (en) A kind of across frame structure edge support node structure of steel bar girder plate
US3302360A (en) Method of reinforcing concrete floors and the like, and a reinforcing element therefor
CN103194982A (en) Construction method for short cantilever support at bridge side span cast-in-situ segment
US3482005A (en) Method of constructing concrete buildings
WO2020214086A1 (en) Precast building
CS211437B1 (en) Frame supporting system particularly for shuttering the balk construction bodies
WO2015196264A1 (en) Connection set for formwork beams
US1957026A (en) Concrete building construction
JPH11158813A (en) Concrete pier constructing method
KR100612662B1 (en) Steel-frame assembly body production method of ferroconcrete infrastructure
US1865500A (en) Wall construction
US3349539A (en) Construction of two-way composite building system
JPH0681463A (en) Building method for stair
CN215330933U (en) Steel skeleton beam structure and steel structure building
JP6961408B2 (en) Precast concrete boards and concrete structural slabs
CN212561569U (en) Slope concrete lattice template
RU2000133028A (en) CONSTRUCTIVE SYSTEM OF A MULTI-STOREY BUILDING AND METHOD OF ITS BUILDING (OPTIONS)
EP0441474A2 (en) Structural cladding members
RU2632592C1 (en) Reinforced formwork block and building structure
JP6854652B2 (en) Reinforcing bar assembly method and rebar assembly jig
US1927908A (en) Scaffold
CN114016731A (en) Basement ceiling template structure and basement template system
RU148788U1 (en) FRAMEWORK CONSTRUCTION OF REINFORCED CONCRETE BUILDING FRAME