CN2897956Y - Cable lifter against tilting for upright post of elevator - Google Patents

Cable lifter against tilting for upright post of elevator Download PDF

Info

Publication number
CN2897956Y
CN2897956Y CN 200620114271 CN200620114271U CN2897956Y CN 2897956 Y CN2897956 Y CN 2897956Y CN 200620114271 CN200620114271 CN 200620114271 CN 200620114271 U CN200620114271 U CN 200620114271U CN 2897956 Y CN2897956 Y CN 2897956Y
Authority
CN
China
Prior art keywords
pulley
cage
cable
fixed
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200620114271
Other languages
Chinese (zh)
Inventor
涂翼民
涂佳
涂斗岩
涂倩
涂卓民
胡立化
郑世霞
吴建平
苏则彪
骆平
Original Assignee
涂翼民
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 涂翼民 filed Critical 涂翼民
Priority to CN 200620114271 priority Critical patent/CN2897956Y/en
Application granted granted Critical
Publication of CN2897956Y publication Critical patent/CN2897956Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model relates to an elevator column anti-tilting and cable lifting device for building construction, industrial and mining enterprises, the device comprises: a beam, a guide rope, a heavy block, a pulley, a cable. The utility model is characterized in that the beam (10) exceeds two end heads of running track outside two suspension cages (5), is fixed on one end of two guide ropes (1) that form a group, the other end of two guide ropes (1) in the same group passes through slip ring (3) on both sides of heavy block (2) with a pulley (4) respectively, is tensioned and fixed on groundwork vertically in parallel; one end of hanging pipe (6) is arranged on suspension cage (5), the other end corresponds and approaches the running track on one side of the pulley (4) notch, one end of branch pipe (7) is arranged on middle height of the column (9), corresponds and approaches the other side of pulley (4) notch running track, the other end is fixed on wall body.

Description

Elevator column anti-dumping and cable jacking system
Technical field
The utility model belongs to the elevator column anti-dumping and the cable jacking system of a kind of building operation, mine vertical shaft, interior of building, the column anti-dumping and the cable jacking system of the two cage elevators of particularly a kind of single column.
Background technology
In the prior art, existing elevator, SS100 * 100 building hoists of the two cages of producing as Nanchang science-star's vehicle for construction limited liability company of single column, its structure is that the column top is provided with a day beam, cage is installed at the two ends of the corresponding day beam in column both sides respectively.Hoisting rope one end is connected on the cage, after the other end is walked around pulley on day beam, is mounted on traction cage lifting on the ground-surface winch down.Difference captive joint cable one end on every cage, the other end of cable is connected on the ground-surface electric appliance box.During work, when a cage is parked in ground, when the fully loaded weight of another cage was raised the rope traction and upwards moves, at this moment a column and a day beam out-of-balance condition occurred tiltedly to the inclination of load-carrying cage, and tilt quantity will have an accident above permissible value.The cable that one end is connected on the cage also rises disorderly arbitrarily or lands with cage is lax, causes lifting meeting in service to be colluded to hang or landed cage by other protrusions and pushes down accident.
Summary of the invention
The purpose of this utility model is to overcome above-mentioned the deficiencies in the prior art part, provides a kind of elevator column anti-dumping scientific and reasonable for structure, safe and reliable, easy to install and cable with the cage jacking system.
The technical solution of the utility model is: installing two on pouring weight top coorespondingly has an axis hole back plate, and pulley is installed in two rotating shafts between the back plate, and slip ring is installed in the pouring weight both sides.The middle part of it beam is installed in column top, and a cage is respectively installed in the two sides at the corresponding Tian Liang of column two ends.The length of it beam exceeds two cage outside running orbits, fixing two on the termination, Tian Liang two ends separately respectively is one group guide rope one end, two guide rope other ends pass the slip ring of the pouring weight both sides of pulley when top respectively on the same group, are fixed on the basis, ground after the vertical parallel tension.Outstanding Guan Yiduan is installed on the cage, and the corresponding and close pulley notch of the other end is running orbit on one side.Cage is when ground, and cable one end is fixed on connecting circuit on the cage after penetrating outstanding pipe, after the cable other end is walked around suspended pouring weight built on stilts, fixedly is connected on the electric appliance box after penetrating arm, and cable is stressed linearity under the effect of unsettled pouring weight.Arm one end is installed in the corresponding and close pulley notch running orbit another side in middle part of column height, and the other end is fixed on the body of wall.
Description of drawings
Accompanying drawing is an example structure scheme drawing of the present utility model.
The specific embodiment
Embodiment: installing two on pouring weight 2 tops coorespondingly has an axis hole back plate 13, and pulley 4 is installed in two rotating shafts 12 between the back plate 13, and slip ring 3 is installed in pouring weight 2 both sides.The middle part of it beam 10 is installed in column 9 tops, and column 9 corresponding day beam 10 side faces at both ends are installed two cages 5 respectively, and the length of day beam 10 exceeds two cages, 5 outside running orbits.Fixing two on it termination, beam 10 two ends separately respectively is one group of guide rope 1 one end, and two guide rope 1 other ends are fixed on the basis, ground after passing the slip ring 3 vertical parallel tension of pouring weight 2 both sides respectively on the same group.Outstanding pipe 6 one ends are installed on the cage 5, corresponding and close pulley 4 notches of the other end are running orbit on one side, cable 14 1 ends penetrated and enter cage 5 fixing backs behind the outstanding pipe 6 and join with electrical equipment when cage 5 landed, cable 14 other ends are walked around pulley 4 backs and are hung pouring weight 2 built on stilts, penetrate arm 7 backs and fixedly be connected in the ground-surface electric appliance box, cable 14 is stressed linearity under the effect of hanging pouring weight 2.Arm 7 one ends are installed in the middle part of column 9 height, corresponding and close pulley 4 notch running orbit another sides, and the other end is fixed on the building.Its process was when the utility model used in reality: when two cages 5 of elevator were stopped ground, its column 9 and a day beam 10 were state of equilibrium.When a cage 5 rests in ground, another cage 5 fully loaded weights, at the hoisting rope 8 of walking around the head sheave 15 on day beam 10 be installed under the traction of ground winch 11 when rising, the right stress destruction of one distal process of the column 9 of elevator and day beam 10 state of equilibrium, under gravitate, they beam 10 1 ends are downward, and column 9 takes place to tilt in the allowed band.Uptrending appears in they beam 10 other ends, but two guide ropes having been strained 1 hold and can't rise, the relative equilibrium after having kept day beam 10 1 distal process right stressed, and the bending resistance of column 9 is stressed, and to become resistance to compression stressed, controls the further inclination of column 9.Same framing member pressure resistance has improved the safety of elevator column 9 greater than resistance to bending.Cable 14 makes progress, moves downwards by the guide rope 1 of the slip ring 3 of pulley 4 on rotating shaft 12 rotation pulling pouring weights 2 along two vertical parallel along with the outstanding pipe on the cage 56 makes progress, moves downwards.Cable 14 is stressed linearity under the effect of pouring weight 2, overcome cable 14 and colluded to hang by other protrusions and break by the moving range of operation that departs from of wind, and cable 14 is lowered by when landing and lands cage 5 and push down and cause the accident.The alleged cage of the utility model can also be the car of elevator, the cage of mine vertical shaft.
The utility model compared with prior art, have characteristics such as scientific and reasonable for structure, easy to install, safe and practical, be existing building construction, mine, the novel column anti-dumping of industrial elevator and cable jacking system.

Claims (3)

1, a kind of elevator column anti-dumping and cable jacking system, it is characterized in that a day beam (10) exceeds on the termination, two ends of two cages (5) outside running orbit, fixing two respectively is one group guide rope (1) one end, two guide ropes (1) other end on the same group passes pouring weight (2) the both sides slip rings (3) that pulley (4) are housed respectively, and vertical parallel is strained and fixed on ground; Outstanding pipe (6) one ends are installed on the cage (5), and corresponding and close pulley (4) notch of the other end is running orbit on one side; Arm (7) one ends are installed in the another side of corresponding and close pulley (4) the notch running orbit in middle part of column (9) height, and the other end is fixed on the body of wall.
2, elevator column anti-dumping according to claim 1 and cable jacking system is characterized in that pouring weight (2) go up to install two back plate (13), the pulley (4) that axis hole should be arranged be installed in the rotating shaft (12) between two back plates (13).
3, elevator column anti-dumping according to claim 1 and 2 and cable jacking system, it is characterized in that cage (5) is when ground, cable (14) one ends penetrate outstanding pipe (6) and are fixed on upward connecting circuit of cage (5), the other end is walked around pulley (4) and is hung pouring weight (2) built on stilts, penetrates the fixing connecting circuit case again of arm (7).
CN 200620114271 2006-04-16 2006-04-16 Cable lifter against tilting for upright post of elevator Expired - Fee Related CN2897956Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620114271 CN2897956Y (en) 2006-04-16 2006-04-16 Cable lifter against tilting for upright post of elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620114271 CN2897956Y (en) 2006-04-16 2006-04-16 Cable lifter against tilting for upright post of elevator

Publications (1)

Publication Number Publication Date
CN2897956Y true CN2897956Y (en) 2007-05-09

Family

ID=38073292

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620114271 Expired - Fee Related CN2897956Y (en) 2006-04-16 2006-04-16 Cable lifter against tilting for upright post of elevator

Country Status (1)

Country Link
CN (1) CN2897956Y (en)

Similar Documents

Publication Publication Date Title
CN102229395B (en) Multi-functional simulation experiment system for mining elevator
CN101786570B (en) Process for replacing hoisting ropes
CN209758971U (en) Lifting anti-falling device for building construction
CN101537976A (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN110228743A (en) Two-to-one suspension is set in elevator traction than building hoist and its operational method
CN201376848Y (en) Large-scale double-tower automatic-elevation hoisting equipment
CN2923635Y (en) Single-column towing type elevator
CN216341336U (en) Adjustable inverted frame structure of 750 x 750mm cross-section holding rod system
CN101863423B (en) Steel box beam cable carrying lifter for construction of suspension bridge
CN201132717Y (en) Single-column and single-cage elevator driven by drawing
CN202148109U (en) Multifunctional simulation test system for mining elevators
CN105645275B (en) Cable hoist and its construction method
CN111847267A (en) Cantilever crane
CN204531348U (en) Electronic independent-lifting discharging platform
CN2897956Y (en) Cable lifter against tilting for upright post of elevator
CN214364873U (en) Lifting and hanging device of climbing frame for building
CN204530513U (en) The manned maintenance Hanging Basket of suspension cable
CN210049875U (en) Hydraulic oil pumping unit
CN2154250Y (en) Mini-tower hoist
CN2184684Y (en) Self lifting high speed derrick lift
CN2301428Y (en) Lower extension attached portal building lifter
CN2775016Y (en) Headframe type two purpose construction lift for person and goods
CN218520918U (en) Real abdomen formula steel crane roof beam installation device
CN101672101A (en) One-drive multi-hoisting-point hoisting system
CN201857225U (en) Hoisting device for bridge crane frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee