CN2549391Y - High-performance continuous water supplying boiler - Google Patents
High-performance continuous water supplying boiler Download PDFInfo
- Publication number
- CN2549391Y CN2549391Y CN 02267408 CN02267408U CN2549391Y CN 2549391 Y CN2549391 Y CN 2549391Y CN 02267408 CN02267408 CN 02267408 CN 02267408 U CN02267408 U CN 02267408U CN 2549391 Y CN2549391 Y CN 2549391Y
- Authority
- CN
- China
- Prior art keywords
- water chamber
- water
- chamber
- communicated
- warm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Heat-Pump Type And Storage Water Heaters (AREA)
Abstract
The utility model discloses a high-performance continuous water supplying boiler which belongs to the stove field, and comprises a water chamber, and an inlet pipe and an outlet pipe both communicated with the water chamber. The utility model is characterized in that: a cold water chamber, a warm water chamber which is communicated with the cold water chamber through pipelines and a check valve, and a hot water chamber communicated with the warm water chamber through pipelines and a check valve are arranged in the water chamber from top to bottom, wherein, the hot water chamber is communicated with the outlet pipe, and the cold water chamber is communicated with the inlet pipe. As the inside of the cavity is provided with the cold water chamber, the warm water chamber and the hot water chamber from top to bottom, the heat energy in the upper part of chimney can be absorbed and utilized fully by the water in the cold water chamber, which has high thermal efficiency; as the water in the warm water chamber can be supplied for the hot water chamber continuously, the time that the water in the hot water chamber is heated to some given temperature is short, realizing the continuous supply of hot water wholly.
Description
Technical field
The utility model belongs to the cooking stove field, is specifically related to a kind of water heating boiler that has a plurality of sleeves.
Background technology
The boiler that being used for of prior art supplies water in the bathing pool is generally by water tank, form by flue and a combustion chamber of water tank, and the combustion chamber is connected with flue.Coal produces hot gas when the internal combustion of combustion chamber, hot gas is discharged through behind the flue, and then the water between flue and the water tank is heated.Because generally have only a water tank in the housing of existing boiler, water inlet pipe is arranged on the bottom of water tank, outlet pipe is arranged on the top in the water tank, and discharge from outlet pipe on the top that rises to water tank after water is heated.Because the temperature contrast of the temperature on flue top and the water of water tank upper is less, therefore, the heat energy on flue top can not fully be absorbed, thereby the thermal efficiency is low.
Summary of the invention
For the low drawback of boiler thermal output that overcomes prior art, the utility model provides a kind of high-efficiency and continuous water supply boiler, this boiler can not only hot water without interruption and also the thermal efficiency also very high.
The technical scheme that its technical problem that solves this real the utility model adopts is: design a kind of high-efficiency and continuous water supply boiler, comprise the chamber that is filled with water, the water inlet pipe that is connected with the chamber of being filled with water and outlet pipe, the hot hydroecium that it is characterized in that being filled with water the indoor warm water chamber that sets gradually cold water chamber from top to bottom, is connected with cold water chamber by pipeline and check valve, is connected by pipeline and check valve with warm water chamber, hot hydroecium is communicated with outlet pipe, and cold water chamber is communicated with water inlet pipe.
The utility model is at the epimere of flue, stage casing, the hypomere water pipe that is connected with cold water chamber, warm water chamber, hot hydroecium of setting respectively.Heat-insulation layer is set respectively between cold water chamber and hot hydroecium, warm water chamber and the hot hydroecium.
The beneficial effects of the utility model are: owing in cavity, set gradually cold water chamber, warm water chamber, hot hydroecium from top to bottom, thereby the heat energy on flue top can fully be absorbed thermal efficiency height by the water in the cold water chamber; Because the water in the warm water chamber can constantly replenish,, can realize the without interruption of hot water on the whole so the water in the hot hydroecium is heated to both time weak points of fixed temperature in hot hydroecium.
Description of drawings
Fig. 1 is the structural representation of the utility model embodiment.
The specific embodiment
As shown in Figure 1: 1: pipeline 2: water inlet pipe 3: flue 4: water pipe 5: cold water chamber 6: outlet pipe 7: warm water chamber 8: hot hydroecium 9: main chamber 10: water pipe 11: subsidiary combustion chamber 12: check valve 13: pipeline 14: check valve 15: housing 16: water pipe 17: heat-insulation layer.
Indoor cold water chamber 5, warm water chamber 7, the hot hydroecium 8 of setting gradually from top to bottom that be filled with water that housing 15 surrounds.Be communicated with by pipeline 1 and check valve 14 between cold water chamber 5 and the warm water chamber 7, guaranteed that water can only flow to warm water chamber by cold water chamber; Be communicated with by pipeline 13 and check valve 12 between warm water chamber 7 and the hot hydroecium 8, guaranteed that water can only flow to hot hydroecium 8 by warm water chamber 7.Cold water enters cold water chamber 5 by water inlet pipe 2, and hot water is discharged by outlet pipe 6.
Coal is ignition combustion in main chamber 9.Owing to be subjected to the influence of rising thermal current in the flue 3, flame burns downwards, and the cinder that does not burn is fallen into the generation thermal current that burns away in the subsidiary combustion chamber 11, and thermal current is earlier to the heating of the water in the hot hydroecium 8, then to the heating of the water in the warm water chamber 7, at last to the heating of the water in the cold water chamber 5.Because the water temperature in cold water chamber 5 and the warm water chamber 7 is lower, thereby can distinguish the heat energy that fully effectively absorbs flue 3 tops and middle part.Hot water is discharged from outlet pipe 6, and the water in the warm water chamber 7 flow in the hot hydroecium 8 through pipeline 13 and check valve 12; Then, the water in the cold water chamber 5 adds in the warm water chamber 7 by pipeline 1 and check valve 14, so constantly circulation.Because the water that adds in the hot hydroecium is heated warm water, thereby lack heat time heating time again, so, can realize the hot water without interruption of boiler.
For fully absorbing the heat energy in the flue 3, improve heat exchanger effectiveness, on the top of flue 3 water pipe 4 that communicates with cold water chamber 5 is set, water pipe 4 is horizontally through flue; The middle part of flue is provided with the water pipe 16 that communicates with warm water chamber 7, and water pipe 16 is horizontally through flue; The water pipe 10 that communicates with hot hydroecium is set between main chamber 9 and the subsidiary combustion chamber 11.For prevent that the water in cold water chamber 5 and the warm water chamber 7 from absorbing heat, and is provided with heat-insulation layer 17 respectively between cold water chamber 5 and hot hydroecium 8, warm water chamber 7 and hot hydroecium 8 in hot hydroecium 8.
Claims (3)
1. high-efficiency and continuous water supply boiler, comprise the chamber that is filled with water, the water inlet pipe that is connected with the chamber of being filled with water and outlet pipe, the hot hydroecium that it is characterized in that being filled with water the indoor warm water chamber that sets gradually cold water chamber from top to bottom, is connected with cold water chamber by pipeline and check valve, is connected by pipeline and check valve with warm water chamber, hot hydroecium is communicated with outlet pipe, and cold water chamber is communicated with water inlet pipe.
2. high-efficiency and continuous water supply boiler according to claim 1, the epimere, stage casing, hypomere that it is characterized in that flue be the water pipe that is connected with cold water chamber, warm water chamber, hot hydroecium of setting respectively.
3. high-efficiency and continuous water supply boiler according to claim 1 is characterized in that being provided with respectively between cold water chamber and hot hydroecium, warm water chamber and the hot hydroecium heat-insulation layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 02267408 CN2549391Y (en) | 2002-05-31 | 2002-05-31 | High-performance continuous water supplying boiler |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 02267408 CN2549391Y (en) | 2002-05-31 | 2002-05-31 | High-performance continuous water supplying boiler |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2549391Y true CN2549391Y (en) | 2003-05-07 |
Family
ID=33733003
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 02267408 Expired - Fee Related CN2549391Y (en) | 2002-05-31 | 2002-05-31 | High-performance continuous water supplying boiler |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2549391Y (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107477856A (en) * | 2017-08-10 | 2017-12-15 | 邵阳信多利科技发展有限公司 | A kind of gasification of biomass hot-water boiler |
-
2002
- 2002-05-31 CN CN 02267408 patent/CN2549391Y/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107477856A (en) * | 2017-08-10 | 2017-12-15 | 邵阳信多利科技发展有限公司 | A kind of gasification of biomass hot-water boiler |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100595495C (en) | Open back water reciprocating flue type normal pressure boiler | |
CN2549391Y (en) | High-performance continuous water supplying boiler | |
CN202915405U (en) | Energy-saving environment-friendly heating furnace | |
CN201003798Y (en) | Kitchen range water heater | |
CN2556564Y (en) | Solar heating gas compensating device | |
CN2241825Y (en) | Pre-heating energy-saving range ignitor | |
CN206846800U (en) | A kind of multipurpose coal stove | |
CN2639789Y (en) | Volumetric multistage heating anthracite energy saving water heating boiler | |
CN2278871Y (en) | Multifunctional energy-saving stove | |
CN2435632Y (en) | Multi-functional oil-burning pressureless hot water boiler | |
CN200952735Y (en) | Efficient energy-saving back-firing warming stove | |
CN2517983Y (en) | Efficiency honeycomb Briquette water heating boiler | |
CN201025400Y (en) | Fuel coal boiling water furnace | |
CN2593112Y (en) | Pressureless double-mantle hot-water stove | |
CN2245191Y (en) | High efficiency water heater | |
CN2548033Y (en) | Domestic efficient energy-saving heating stove | |
CN2141519Y (en) | Forced circulation and combustion device for coal warming stove | |
CN2293773Y (en) | Water heater | |
CN2656883Y (en) | Coal-fired water supply boiler | |
CN2387456Y (en) | Boiler | |
CN2599469Y (en) | Oil-fired gas-fired atmospheric water-heating boiler | |
CN205014604U (en) | Multiloop plant specimen | |
CN201003850Y (en) | Ternary heating energy-saving boiler | |
CN2418383Y (en) | Flashing energy-aving heating stove | |
CN201251277Y (en) | Multifunctional environmental protection and energy saving burner |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20030507 Termination date: 20100531 |