CN2377279Y - Combined cable crane - Google Patents

Combined cable crane Download PDF

Info

Publication number
CN2377279Y
CN2377279Y CN 99230802 CN99230802U CN2377279Y CN 2377279 Y CN2377279 Y CN 2377279Y CN 99230802 CN99230802 CN 99230802 CN 99230802 U CN99230802 U CN 99230802U CN 2377279 Y CN2377279 Y CN 2377279Y
Authority
CN
China
Prior art keywords
anchor
cable
tower
utility
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 99230802
Other languages
Chinese (zh)
Inventor
李文琪
徐基伟
胡建军
杨如刚
万中茎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Luqiao Construction Co ltd
Original Assignee
Sichuan Road and Bridge (Group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Road and Bridge (Group) Co Ltd filed Critical Sichuan Road and Bridge (Group) Co Ltd
Priority to CN 99230802 priority Critical patent/CN2377279Y/en
Application granted granted Critical
Publication of CN2377279Y publication Critical patent/CN2377279Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a combined type cable loop wheel machine suitable for installation of large-span arched bridge multisection section arch rib (strength nature skeleton) installation or cable-stay bridge girder erection joint usefulness comprises hoist and mount part and anchor buckle part, and the cable tower hinge of cable loop wheel machine is on anchor tower (mound), and the knot cable and the anchor rope of anchor buckle part are alternately anchored on the anchor case at anchor tower (mound) top, utilize jack adjustment pulling force, make the horizontal resultant force of knot cable and anchor rope approach to zero. The utility model has the characteristics of construction convenient operation, the security is high, and the engineering progress is fast, and is with low costs, and the transparency is strong under specific topography condition.

Description

The combined type cable crane
The utility model relates to a kind of construction implement, the particularly a kind of multi-segmental arch rib (stiff skeleton) of long-span arch bridge, cable stayed bridge or combined type cable crane that the girder cantilever is installed of being applicable to.
The multi-segmental arch rib (stiff skeleton) of existing long-span arch bridge or the segmentation cantilever of cable-stayed bridge main-beam are installed, when constructing with cable crane, and lifting and button anchor system, adopt two independently mechanism's work, complex structure, cost height, especially when orographic condition did not allow, it was big to implement difficulty.
Goal of the invention of the present utility model is intended to overcome above-mentioned shortcoming, for specific orographic condition provides a kind of combined type cable crane that is applicable to that long-span arch bridge multi-segmental arch rib (stiff skeleton) or cable-stayed bridge main-beam cantilever are installed.
Goal of the invention of the present utility model is achieved in that the utility model is made up of handling mechanism and anchor deduction structure, handling mechanism includes Sarasota, is erected at the main rope on the Sarasota, regulate the anchorage that the main rope elevation plays the pulling force balanced action, coaster and the coaster of frame on main rope plays hoist cable and suspender, and drags drag cable and lifting tractor that coaster moves on main rope; Anchor deduction structure includes anchor tower (pier), and the anchor cable, knotted rope, jack, the oil pump that are erected at the anchor tower top have reached the anchorage of pulling force balanced action; Of the present utility model being characterised in that: Sarasota is located on the anchor tower by hinge knot mechanism rack, makes handling and anchor button two mechanisms form one, and the knotted rope on anchor tower pushes up and anchor cable intersect with steel strand or high-strength steel tow on the anchor case that is anchored at the anchor tower top.
The utility model is owing to transmit axial compression to anchor tower (pier) by hinge knot mechanism, and Sarasota does not bear moment of flexure.Knotted rope, anchor cable intersection are anchored on the anchor case on anchor tower (pier) top, utilize jack and oil pump to adjust the pulling force of knotted rope anchor cable, make the horizontal resultant of knotted rope and anchor cable level off to zero, the anchor case horizontal movement on anchor tower (pier) top is corresponding to level off to zero, by progressively putting the elevation that arch rib (stiff skeleton) or girder sections have been pieced together in a knotted rope and anchor cable adjustment.
The utility model is at the sections quantity of multi-segmental cantilever arch rib (stiff skeleton) or girder and the quantity and the Suo Li of lifting weight configuration knotted rope and anchor cable.
The utility model can be installed the multi-segmental arch rib (stiff skeleton) of arch bridge or the multi-segmental girder of cable stayed bridge by cantilever under the state of not establishing any horizontal guy.Especially under specific orographic condition, constructing operation is simple, and good stability is safe, and programming is fast, and the duration is short, and cost is low.
Provide accompanying drawing of the present utility model below:
Fig. 1 is a work schematic diagram of the present utility model.
Below in conjunction with drawings and Examples, the utility model is further described.
The utility model is made up of handling mechanism 1 and anchor deduction structure 2, and handling mechanism 1 comprises anchorage 3, Sarasota 4, main rope 5, suspender 6, coaster 7, drag cable 8, plays hoist cable 9, lifting tractor; Anchor deduction structure 2 comprises anchorage 3, knotted rope 10, anchor cable 11, anchor tower (pier) 12, jack 13, oil pump 14.The major function of handling mechanism 1 is the lifting member, vertical lift and vertically moving; The function of anchor deduction structure is to form dynamic equilibrium anchor button system with assembling members sections, closes up until arch rib (stiff skeleton) or girder.Of the present utility model being characterised in that: Sarasota 4 is erected on the anchor tower 12 by hinge knot mechanism 15, make 2 liang of mechanisms of handling and anchor button form one, the knotted rope 10 on anchor tower 12 tops intersects with anchor cable 11 usefulness steel strand or high-strength steel tow and is anchored on the anchor case at anchor tower 12 tops.Transmit axial compression to anchor tower (pier) 12 by hinge knot mechanism 15, Sarasota 4 does not bear moment of flexure; Knotted rope 10, anchor cable 11 adopt steel strand or high-strength steel tow, intersect and be anchored on the anchor case on anchor tower (pier) 12 tops, utilize jack 13 to adjust the pulling force of knotted rope 10, anchor cable 11, make the horizontal resultant of knotted rope 10 and anchor cable 11 level off to zero, the anchor case horizontal movement at anchor tower 12 (pier) top is corresponding to level off to zero, adjusts the elevation of piecing together arch rib (stiff skeleton) or girder sections by progressively putting a knotted rope 10 and anchor cable 11.(1#-18#) installs piecemeal from arch springing to vault as Fig. 1, the two sides symmetry is carried out, per 3 sections is one group, lift every group the interim fixing cable anchoring of the first two section skeleton, after lifting the 3rd section skeleton one group of fixedly knotted rope and anchor cable are installed, and remove interim knotted rope, utilize 13 stretch-draw of button anchorage cable stretching jack fixedly knotted rope 10 and anchor cable 11, adjust each section of skeleton elevation, up to installation final stage (18#), span centre close up and stressed after, symmetrical equilibrium ground, two sides loosens knotted rope 10 and anchor cable 11 by designing requirement, removes fully until knotted rope 10 and anchor cable 11, use of the present utility model, finished 2191 tons of skeleton liftings of 36 sections work in 50 days smoothly, every section weighs 61 tons, does not establish any horizontal guy.
The utility model constructing operation is convenient, is easy to control, and is safe, good stability, and programming is fast, and cost is low, and applicability is strong.

Claims (1)

1, a kind of combined type cable crane, form by handling mechanism (1) and anchor deduction structure (2), handling mechanism (1) comprises anchorage (3), Sarasota (4), main rope (5), suspender (6), coaster (7), drag cable (8), play hoist cable (9) and lifting tractor, anchor deduction structure (2) comprises anchorage (3), knotted rope (10), anchor cable (11), anchor tower (pier) (12), jack (13), oil pump (14), it is characterized in that: Sarasota (4) is erected on the anchor tower (12) by hinge knot mechanism (15), make handling mechanism (1) and anchor deduction structure (2) form one, the knotted rope (10) on anchor tower (12) top and anchor cable (11) intersect with steel strand or high-strength steel tow on the anchor case that is anchored at the anchor tower top.
CN 99230802 1999-01-22 1999-01-22 Combined cable crane Expired - Fee Related CN2377279Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 99230802 CN2377279Y (en) 1999-01-22 1999-01-22 Combined cable crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 99230802 CN2377279Y (en) 1999-01-22 1999-01-22 Combined cable crane

Publications (1)

Publication Number Publication Date
CN2377279Y true CN2377279Y (en) 2000-05-10

Family

ID=34019789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 99230802 Expired - Fee Related CN2377279Y (en) 1999-01-22 1999-01-22 Combined cable crane

Country Status (1)

Country Link
CN (1) CN2377279Y (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1330829C (en) * 2004-03-24 2007-08-08 大连理工大学 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge
CN100567644C (en) * 2007-05-09 2009-12-09 华东交通大学 A kind of joist type cable arch bridge structure and job practices
CN102756987A (en) * 2012-07-06 2012-10-31 葛洲坝集团第一工程有限公司 Cable machine main rope river-passing balance safety device
CN106012841A (en) * 2016-05-16 2016-10-12 中交路桥华南工程有限公司 Cable crane and installation method thereof
CN108118622A (en) * 2018-02-06 2018-06-05 中交二公局第二工程有限公司 A kind of steel-concrete composite beam cable-stayed bridge main cable and girder construction cable crane system
CN108455462A (en) * 2018-02-10 2018-08-28 湖北思泽新能源科技有限公司 A kind of cable crane
CN108557658A (en) * 2018-05-09 2018-09-21 湖北思泽新能源科技有限公司 A kind of cable crane
CN110886187A (en) * 2019-10-18 2020-03-17 安徽省路港工程有限责任公司 Cable crane system installation system and construction method thereof
CN113062231A (en) * 2021-04-06 2021-07-02 招商局重庆交通科研设计院有限公司 Cantilever pouring arch ring construction device and construction method
CN113445408A (en) * 2021-06-22 2021-09-28 中交一公局集团有限公司 Pier column for constructing arch bridge by cable-stayed hanging and buckling method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1330829C (en) * 2004-03-24 2007-08-08 大连理工大学 Integrated hoisting method and special slings for steel pipe concrete flexible cable arch bridge
CN100567644C (en) * 2007-05-09 2009-12-09 华东交通大学 A kind of joist type cable arch bridge structure and job practices
CN102756987A (en) * 2012-07-06 2012-10-31 葛洲坝集团第一工程有限公司 Cable machine main rope river-passing balance safety device
CN106012841A (en) * 2016-05-16 2016-10-12 中交路桥华南工程有限公司 Cable crane and installation method thereof
CN108118622A (en) * 2018-02-06 2018-06-05 中交二公局第二工程有限公司 A kind of steel-concrete composite beam cable-stayed bridge main cable and girder construction cable crane system
CN108455462A (en) * 2018-02-10 2018-08-28 湖北思泽新能源科技有限公司 A kind of cable crane
CN108557658A (en) * 2018-05-09 2018-09-21 湖北思泽新能源科技有限公司 A kind of cable crane
CN110886187A (en) * 2019-10-18 2020-03-17 安徽省路港工程有限责任公司 Cable crane system installation system and construction method thereof
CN113062231A (en) * 2021-04-06 2021-07-02 招商局重庆交通科研设计院有限公司 Cantilever pouring arch ring construction device and construction method
CN113062231B (en) * 2021-04-06 2022-02-18 招商局重庆交通科研设计院有限公司 Cantilever pouring arch ring construction device and construction method
CN113445408A (en) * 2021-06-22 2021-09-28 中交一公局集团有限公司 Pier column for constructing arch bridge by cable-stayed hanging and buckling method

Similar Documents

Publication Publication Date Title
CN100543235C (en) The method and system of erecting steel trusses by stay cable auxiliary complete cantilever
CN100543234C (en) A kind of closure method of large-span continuous steel truss arch
CN105565176B (en) A kind of asymmetric cable crane of single column
CN2377279Y (en) Combined cable crane
CN206553961U (en) The short light-duty expanded letter combined type Hanging Basket of tower cable-stayed bridge
CN107761542B (en) A kind of arch oblique pull combined system bridge and its construction method
CN105274941B (en) General construction method for partially ground-anchored cable-stayed suspension bridge
CN201106155Y (en) Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN109680835A (en) A kind of self-bearing type precast concrete wall panel, concrete walls, structural system and engineering method
CN105484503B (en) Inclined shuttle-shaped space truss hoisting method
CN203080400U (en) Extra-large span suspension bridge with uniparted hyperboloid space cable net main cables
CN108118622A (en) A kind of steel-concrete composite beam cable-stayed bridge main cable and girder construction cable crane system
CN109750600A (en) A kind of construction method of asymmetry cable crane
CN106698208A (en) Hoisting equipment and hoisting method for external transportation of super high-rise building
CN109629693A (en) The orthogonal suspended-cable structure of large span self-anchored type and construction method
CN101481903B (en) Method for constructing hilly region rope-suspension bridge main beam by span cable supported crane assembling
CN114781026A (en) Construction control method for single leaning tower cable-stayed bridge
CN206562264U (en) A kind of hanging device for transport outside high-rise building
CN108423565A (en) The erection of U-shaped twin beams gantry crane with hook and Demolition Construction method
CN210658022U (en) A one-way perpendicular commentaries on classics device for oblique steel tower of single limb
CN205934735U (en) A operation platform for stretch -draw of cantilever bent cap
RU2200699C2 (en) Method and device for mounting tension guys of tower crane load-lifting boom
CN207032062U (en) Tower with suspended cable available for Large-span Steel Box Beam construction
CN101649683A (en) Method for hoisting power transmission iron tower by assembly holding pole technology
CN212559207U (en) Bridge floor crane

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SICHUAN ROAD & BRIDGE CONSTRUCTION CO., LTD.

Free format text: FORMER NAME OR ADDRESS: SICHUAN HIGHWAY BRIDGE CONSTRUCTION GROUP CO., LTD.

CP01 Change in the name or title of a patent holder

Patentee after: Sichuan Luqiao Construction Co.,Ltd.

Patentee before: Sichuan Road and Bridge (Group) Co., Ltd.

C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee