Double channel smoke heating air preheater Download PDFInfo
- Publication number
- CN2305615Y CN2305615Y CN 97221719 CN97221719U CN2305615Y CN 2305615 Y CN2305615 Y CN 2305615Y CN 97221719 CN97221719 CN 97221719 CN 97221719 U CN97221719 U CN 97221719U CN 2305615 Y CN2305615 Y CN 2305615Y
- Authority
- CN
- China
- Prior art keywords
- utility
- model
- air preheater
- heating air
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Air Supply (AREA)
Abstract
The utility model relates to a double channel smoke heating air preheater for alkali recovery furnaces in paper manufacture industry. The utility model is composed of a smoke passage pipe and an air passage pipe. A partition plate is arranged between the two passage pipes, and heat pipes are installed in the two passages by penetrating through the partition plate. The utility model has the advantages of simple structure, small size, light weight, favorable heat transfer property, no dust deposition, and long service life.
Description
The utility model relates to the two pass flue gas heating air preheater that alkali recovery furnace is used on a kind of paper industry.
At present, the flue gas heating air preheater that alkali recovery furnace uses is to be arranged in together by several air funnel spacing parallel arrangings, constitute heating unit (is the product of Wuhan Boiler Works of CN2050537U as patent publication No.), several heating units are together in series, form air preheater.This mechanism is because air is by entering down several air funnels from several air funnels, after air is through several like this heating units, the resistance that is subjected to is very big, not only can not satisfy the requirement of alkali recovery furnace to blast, and make the blower fan power consumption very high, and this volume is big, complex structure, weld seam is many, the problem of leaking out is difficult for solving, and has strengthened the rear portion cold end corrosion, and heat transfer coefficient is low, air funnel is horizontally disposed with, sode ash can produce accumulation on air funnel, increase flue resistance, has influenced the service life and the result of use of equipment greatly, the equipment consumptive material is many, and is uneconomical.
The purpose of this utility model is exactly needs that use at above-mentioned situation with in conjunction with alkali recovery furnace and the two pass flue gas heating air preheater of using on a kind of novel alkali recovery furnace is provided.
The purpose of this utility model is achieved like this, and adds dividing plate between two, constitutes bitubular binary channels, passes dividing plate and adorn a plurality of super heat-conductive pipes in the bitubular.
The utility model is simple in structure, and is easy to install, and cost is low, easily produce, and the heat transfer efficiency height, dust stratification not, the life-span is long, and economic and social benefit is remarkable.
Below in conjunction with accompanying drawing structure of the present utility model is elaborated.
Fig. 1 is a structural profile front view of the present utility model.
Fig. 2 is a vertical view of the present utility model.
Fig. 3 is a left side of the present utility model (right side) view.
Provided by Fig. 1, the utility model is to be made of exhaust gases passes pipe 2, air duct 1, dividing plate 3, heat pipe 4, and 1 of exhaust gases passes pipe 2 and air duct are equipped with dividing plate 3, constitutes flue gas and air binary channels, and passing dividing plate 3 angle mount in two passages has heat pipe 4.For the needs of installing, the mouth of air duct 1 can be in the side (being non-straight tubular) sometimes.Heat pipe 4 adopts commercially available super heat-conductive pipe.
In use, the utility model is contained on the alkali recovery furnace high-temperature flue, when high-temperature flue gas enters from left end in the exhaust gases passes pipe 2, when superheater tube 4 districts, heat transferred heat pipe 4 bottoms, discharge preheater from right-hand member, and air enters from the air duct 1 of right-hand member, when flowing through heat pipe 4 districts, obtains heat from the upper end of heat pipe 4, discharge from left end, thereby finish exchange heat.Be noted that the utility model especially when installing and using, heat pipe will keep vertical with horizontal direction, to eliminate the accumulation of sode ash on heat pipe.
From the above, when the high-temperature flue gas that comes out from alkali recovery furnace flows through exhaust gases passes the built-in super heat-conductive pipe of heat transferred, the other end of super heat-conductive pipe is in air duct, when air flows through air duct, obtain the heat that heat pipe passes over, thereby improved temperature, reach the preheating purpose, and because two passages are straight-through separately, the air current flow resistance is little, the heat transfer efficiency height, the preheater volume is little, in light weight, cost is low, economy and durability, and the easy problem of leaking out that solves, since simple in structure, be easy to make and give birth to, have bright popularizing application prospect.
Claims (3)
1, a kind of two pass flue gas heating air preheater, be to constitute by exhaust gases passes pipe and air duct, it is characterized in that between exhaust gases passes pipe (2) and air duct (1) dividing plate (3) being housed, constitute flue gas and air binary channels, pass dividing plate (3) heat pipe (4) is housed in two passages.
2, two pass flue gas heating air preheater according to claim 1 is characterized in that said heat pipe (4) is a super heat-conductive pipe.
3, two pass flue gas heating air preheater according to claim 1 is characterized in that said heat pipe is to pass dividing plate (3) angle mount in two passages.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 97221719 CN2305615Y (en) | 1997-07-12 | 1997-07-12 | Double channel smoke heating air preheater |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 97221719 CN2305615Y (en) | 1997-07-12 | 1997-07-12 | Double channel smoke heating air preheater |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2305615Y true CN2305615Y (en) | 1999-01-27 |
Family
ID=33937025
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 97221719 Expired - Fee Related CN2305615Y (en) | 1997-07-12 | 1997-07-12 | Double channel smoke heating air preheater |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2305615Y (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104121690A (en) * | 2014-07-22 | 2014-10-29 | 芜湖长启炉业有限公司 | Flue cleaning heat blower |
-
1997
- 1997-07-12 CN CN 97221719 patent/CN2305615Y/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104121690A (en) * | 2014-07-22 | 2014-10-29 | 芜湖长启炉业有限公司 | Flue cleaning heat blower |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN2784851Y (en) | Smoke tube type jet heat exchanger | |
CN100516750C (en) | Heat exchange compressor | |
CN2305615Y (en) | Double channel smoke heating air preheater | |
CN112484062A (en) | Energy-saving and emission-reducing system for tail flue gas of gas boiler | |
CN110173712A (en) | Air-water heat exchanger with perpendicular fins | |
CN1800762A (en) | Hot-air furnace combined by combustion chamber and dustproof multi-stage heat exchanger with burning-resistant device | |
CN201819239U (en) | Composited tube air preheater | |
CN1115842A (en) | High efficiency gas furnace | |
WO2022088687A1 (en) | Air and coal gas parallel connection integrated flue gas temperature reducing and energy saving device for coal gas boiler | |
CN201173574Y (en) | Integral horizontal type machine burning hot-air stove | |
CN2156402Y (en) | Boiler smoke waste heat recovery device | |
CN212746938U (en) | Large-scale living beings hot-blast furnace heat exchanger | |
CN2462247Y (en) | Granular fuel heating stove | |
CN2284928Y (en) | Pulse tube hot-air furnace | |
CN2212169Y (en) | Multiple wind-temp coal burning hot-wind stove | |
CN2893518Y (en) | Energy-saving gas combustion water heater | |
CN2202130Y (en) | Long-life horizontal hot-blast stove | |
CN101956995B (en) | Composite tube air preheater | |
CN210801590U (en) | Energy-saving and environment-friendly boiler using electricity and biomass | |
CN220582478U (en) | Energy-saving double-drum longitudinal boiler | |
CN206771327U (en) | Biomass boiler | |
CN2217776Y (en) | U-shape-tube type prehater | |
CN2281503Y (en) | Gas boiler | |
CN87217184U (en) | Preheater heating air with condensing-water and steam | |
CN208349578U (en) | A kind of condensed type combustion gas module furnace |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |