CN2286281Y - Vertical double-chamber combustion coal staggered water-tube boiler - Google Patents

Vertical double-chamber combustion coal staggered water-tube boiler Download PDF

Info

Publication number
CN2286281Y
CN2286281Y CN 97215167 CN97215167U CN2286281Y CN 2286281 Y CN2286281 Y CN 2286281Y CN 97215167 CN97215167 CN 97215167 CN 97215167 U CN97215167 U CN 97215167U CN 2286281 Y CN2286281 Y CN 2286281Y
Authority
CN
China
Prior art keywords
combustion chamber
furnace
arch
chamber
radiation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 97215167
Other languages
Chinese (zh)
Inventor
田同德
秦昭起
李青山
肖振明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WENJIAO BOILER FACTORY CHANGCHUN CITY
Original Assignee
WENJIAO BOILER FACTORY CHANGCHUN CITY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WENJIAO BOILER FACTORY CHANGCHUN CITY filed Critical WENJIAO BOILER FACTORY CHANGCHUN CITY
Priority to CN 97215167 priority Critical patent/CN2286281Y/en
Application granted granted Critical
Publication of CN2286281Y publication Critical patent/CN2286281Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Solid-Fuel Combustion (AREA)

Abstract

The utility model discloses a vertical double-chamber combustion coal staggered water-pipe furnace, which is provided with an internal furnace. A radiation arch is arranged along the midposition of the height of a furnace chamber. The lower part of the radiation arch forms an arch shape and the middle part of the radiation arch is provided with a central hole. The furnace chamber is divided into an upper combustion chamber and a lower combustion chamber. The lower combustion chamber is composed of a fire grate, the lower part of a furnace liner and the radiation arch. Four heating secondary air pipes are arranged in the middle of the lower combustion chamber. Spiral flame is formed by the secondary air and the flue gas, and the fuel is uniformly mixed, strongly disturbed, and completely combusted. The upper combustion chamber is transversally provided with more than two rows of interlaced water pipes and is also provided with a smoke baffle plate and a dust removal plate. Thereby, the fullness of the flue gas is favorable, and smoke falls on the radiation arch and is combusted again. The utility model has the advantages of compact structure, high thermal efficiency, and wide developing foreground.

Description

Vertical twin chamber combustion coal staggered water-tube boiler
The utility model relates to a kind of civilian industry boiler, particularly relates to a kind of vertical twin chamber combustion coal staggered water-tube boiler.
Domestic what now moved is the vertical water tube boiler of fuel with the coal, still uses bulk coal, is not equipped with secondary wind, does not also install chimney arch, by flue and tube bank heat exchange, flue gas flow is short, and it is big to leak coal, cause the exhaust gas temperature height, heat loss is big, and dust exhausting concentration is up to 400mg/Nm 3, oke exhaust blackness is up to Lin Geman 2-3 level, and serious environment pollution surpasses the environmental protection restriction, and water mobile inequality of being heated in parallel pipe, and the part in-tube fouling is serious, and the inconvenience cleaning causes water pipe to break, and influences service life.
At above-mentioned situation, the purpose of this utility model is to provide a kind of so vertical twin chamber combustion coal staggered water-tube boiler, fire the chamber down and accept the spiral flame that the effect of rotation secondary hot-air produces down, make to mix, combustion intensification has strengthened the heat transfer to flue, radiation and convection heat transfer' heat-transfer by convection are continued to accept in last combustion chamber, fully absorb flue gas heat, reduced exhaust gas temperature and dust exhausting concentration, improved the thermal efficiency of boiler.
For achieving the above object, the utility model has been taked following technical measures: most external is a furnace outside-lining, interior is furnace internal-lining, the bottom is a fixed grate, the radiation arch is housed along the middle part of furnace height burner hearth is divided into two combustion chambers up and down, encircle by radiation, furnace internal-lining bottom and fire grate constitute combustion chamber down, four secondary air channels are housed in it, the outlet of secondary wind is loaded on the oblique perforate ejection in secondary air channel top secondary wind, make down the combustion chamber form spiral flame, flue heating surface is carried out high temperature heat transfer, there is staggered water pipe more than two rows last combustion chamber along the height lateral arrangement, between the water pipe of close furnace internal-lining and the furnace internal-lining half moon smoke barrier is housed respectively along highly staggered water pipe second row and topmost row second from the bottom, stops the short circuit of rising flue gas, strengthen disturbance, enhancing is to the radiation of last combustion chamber heating surface and the heat transfer of convection current, flue dust drops on and accepts heat radiation on the radiation arch and rekindle under staggered water pipe and smoke barrier effect, and flue gas discharges out of the furnace afterwards.
Major advantage of the present utility model
1, burning briquette, its volume size is even, not only reduces the leakage coal but also reach even ventilation;
2, adopt arch radiation arch, help reflect heat, the secondary wind of ejection has been heated and has formed spiral flame, and combustion chamber combustion intensification is mixed, and the temperature height burns fully, strengthened heat transfer;
3, fire the chamber on and be furnished with the above staggered water pipe of two rows, be furnished with smoke barrier, to the washing away and disturbance of staggered water pipe, strengthen the convection current of top heating surface and the heat transfer of radiation when strengthening flue gas and upwards flowing, the flue dust that keeps off rekindles;
4, integral arrangement compact and reasonable, heat is fully transmitted, and exhaust gas temperature is low, thermal efficiency height
The utility model is described in further detail below in conjunction with drawings and Examples.
Figure is the vertical twin chamber of a utility model combustion coal staggered water-tube boiler cutaway view.
As shown in the figure: the shell of boiler is a furnace outside-lining 13, interior is furnace internal-lining 12, radiation arch 6 is housed along the middle part of furnace height, burner hearth is divided into combustion chamber 3 and last combustion chamber 9 down, fire the fixed grate 2 of chamber 3 down by the bottom, furnace internal-lining 12 bottoms and bottom are arch, the centre has 6 compositions of radiation arch of centre bore 7, in inner bag (12), four secondary air channels 4 are housed apart from center line is uniform around equidistant, secondary wind outlet 5 is equipped with on the top of airduct 4, make the secondary wind of ejection and the flame-shaped curl of rising, the strong degree of filling that burns is good, dedusting plate 8 is equipped with in the position, middle and lower part of last combustion chamber 9, and leave logical cigarette gap 14 between the radiation arch 6, along the above staggered water pipe 11 of two rows highly laterally is housed, with several second rows in its underpart, between the top row's second from the bottom water pipe 11 and the inwall of furnace internal-lining 12 half moon smoke barrier 10 is housed respectively, prevent that flue gas is in the place's short circuit of furnace internal-lining wall, thereby strengthen flue gas washing away and disturbance to water pipe, increase is to the radiation of heating surface and the heat exchange of convection current, the dirt slag that dedusting plate 8 both can force the flue gas of rising to carry returns down the combustion chamber and rekindles, the flame that can force rising again upwards flows around mesopore 14 outflows of dedusting plate and radiation arch are full of again.Air channel 1 also is equipped with in the bottom.
The utility model is compared with old-fashioned vertical water tube boiler, and important breakthrough is arranged on the structure, adopts the arch spoke Penetrate arch, the Secondary Air outlet can form spiral flame and Combustion of Mould Coal etc. with flue gas, and lower combustion chamber heat is concentrated, The temperature height, mix disturbance and strongly conduct heat. Flue gas enters the combustion chamber, has adopted dedusting plate and has kept out the wind Plate makes the heat of flue gas fully pass to heating surface with radiation and convection type, and exhaust gas temperature is low, the thermal efficiency Height, the total compact and reasonable.

Claims (1)

  1. A kind of vertical twin chamber combustion coal staggered water-tube boiler, mainly by flue, water pipe, the fire grate parts are formed, it is characterized in that: the shell of boiler is furnace outside-lining (13), interior is furnace internal-lining (12), it is arch that the bottom is housed along the middle part of furnace height, the radiation arch (6) that the centre has centre bore (7) is divided into combustion chamber (3) and last combustion chamber (9) down with burner hearth, under to fire chamber (3) be fixed grate (2) by the bottom, the bottom of furnace internal-lining (12) and radiation arch (6) are formed, in inner bag (12) apart from center line equidistant around uniform four secondary air channels (4) that are equipped with, airduct (4) top has secondary wind outlet (5), dedusting anti-(8) is equipped with in the middle and lower part of last combustion chamber (9), and leave logical cigarette gap (14) between the radiation arch (6), along the above staggered water pipe (11) of two rows highly laterally is housed, between the inwall of several second rows and top row's second from the bottom water pipe (11) and furnace internal-lining (12) under the height half moon smoke barrier (10) is housed respectively, boiler bottom is equipped with air channel (1).
CN 97215167 1997-04-29 1997-04-29 Vertical double-chamber combustion coal staggered water-tube boiler Expired - Fee Related CN2286281Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 97215167 CN2286281Y (en) 1997-04-29 1997-04-29 Vertical double-chamber combustion coal staggered water-tube boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 97215167 CN2286281Y (en) 1997-04-29 1997-04-29 Vertical double-chamber combustion coal staggered water-tube boiler

Publications (1)

Publication Number Publication Date
CN2286281Y true CN2286281Y (en) 1998-07-15

Family

ID=33932418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 97215167 Expired - Fee Related CN2286281Y (en) 1997-04-29 1997-04-29 Vertical double-chamber combustion coal staggered water-tube boiler

Country Status (1)

Country Link
CN (1) CN2286281Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102168886A (en) * 2010-12-30 2011-08-31 河南农业大学 Combustion furnace for flue-cured bulk curing barn
CN105387454A (en) * 2015-12-13 2016-03-09 李培明 Multifunctional combined combustion boiler
CN106051717A (en) * 2016-06-27 2016-10-26 珠海格力智能装备有限公司 Steam boiler device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102168886A (en) * 2010-12-30 2011-08-31 河南农业大学 Combustion furnace for flue-cured bulk curing barn
CN105387454A (en) * 2015-12-13 2016-03-09 李培明 Multifunctional combined combustion boiler
CN106051717A (en) * 2016-06-27 2016-10-26 珠海格力智能装备有限公司 Steam boiler device

Similar Documents

Publication Publication Date Title
CN2286281Y (en) Vertical double-chamber combustion coal staggered water-tube boiler
CN201277704Y (en) Full water jacket coal burning boiler with flashback staged grate
CN2784752Y (en) Environment-friendly vertical coal-gasified and coal-fired boiler
CN2131017Y (en) Boiler
CN201434501Y (en) Hanging furnace baffle type coal burning semi-gasification environment-protective and energy-saving boiler
CN201206893Y (en) Smoke abatement antiscaling energy saving hot water boiler
CN200940928Y (en) Forward/reverse purifying burning boiler having coal gasifying 3 chambers
CN2384169Y (en) Vertical shell energy-saving coal-fired water heating boiler
CN1670431A (en) Three return stroke half fire coal, fuel oil and gas-fired smokeless boiler
CN2296951Y (en) Atmospheric vertical double-fire box vortex boiler
CN218237428U (en) Split gas chamber combustion furnace
CN2596200Y (en) Smokeless gasifying rotary boiler
CN2906448Y (en) Ternary-burning normal-pressure coal-burning hot water boiler
CN218210079U (en) Composite device of water heater of gasification furnace
CN201811422U (en) Horizontal multipass anti-burning boiler
CN212132407U (en) Biomass boiler structure
CN2286283Y (en) Vertical three-drum two-return combustion coal water-tube boiler
CN2204396Y (en) Vertical pressureless boiler
CN2338077Y (en) Implement for eliminating smoke and removing dust
CN2380856Y (en) Vertical square atmospheric water heater
CN2274316Y (en) Normal-pressure boiler
CN2419482Y (en) Double boiler with four reverse vertical pipes
CN2266100Y (en) Vertical energy-saving atmospheric heating boiler
CN2602309Y (en) Gasification smokeless coal boiler
CN2296975Y (en) Vertical atmospheric steam-water boiler

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee