Prior art keywords
piece
protection
construction platform
platform based
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202323257970.3U
Other languages
Chinese (zh)
Inventor
李宏银
李帅
罗逊
邵阳
蒋剑峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mcc South China Construction Engineering Co ltd
Original Assignee
Mcc South China Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mcc South China Construction Engineering Co ltd filed Critical Mcc South China Construction Engineering Co ltd
Priority to CN202323257970.3U priority Critical patent/CN221321695U/en
Application granted granted Critical
Publication of CN221321695U publication Critical patent/CN221321695U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The application relates to the field of building construction, in particular to a protection operation integrated construction platform based on temporary support, which comprises a connecting piece, a connecting plate, a supporting piece and a protection piece. The application has the effect of solving the problems that the construction is difficult to be convenient and the construction safety is difficult to be compatible when the well mouth and the periphery of the well mouth are constructed in the related technology to a certain extent.

Description

Protection operation integrated construction platform based on temporary support
Technical Field
The application relates to the field of building construction, in particular to a protection operation integrated construction platform based on temporary support.
Background
Temporary supports are structures used during construction or maintenance of a building in order to support the structure of the building or to maintain its stability. This may include supporting structural elements such as walls, floors, beams and columns for safe construction work during construction. Temporary support is a temporary element in the building process, and does not have the characteristics of lifting function, working platform and the like. While an integrated construction platform generally refers to a device used in construction, finishing, or maintenance work that provides a work platform, support structure, and other functions so that workers may work at high altitudes or in difficult-to-reach areas in order to provide the safety and convenience conditions required by the workers to perform the high-altitude work.
In the related art, for an elevator hoistway in a building, which is a vertical passage in an elevator system, through different floors of a building to enable an elevator to travel up and down, the elevator hoistway is usually a vertical deep well, and its structure must be strong enough to support the weight of the elevator and related equipment, and thus it is a very important part of the building construction for the construction of the elevator hoistway. When the elevator shaft is constructed in the actual site, the elevator shaft is difficult to construct, the construction risk is high, the common protection construction of the traditional elevator shaft is to set up a scaffold in the elevator shaft, and a protection iron fence door is arranged at the door opening of the elevator shaft. The mode is high in risk of protecting a construction scheme, high-altitude falling objects are dangerous, and construction of erecting and dismantling the scaffold is difficult.
Aiming at the prior art, in the construction process of the elevator shaft, a scaffold inconvenient to construct is usually required to be erected when the construction safety is ensured, and a protective iron fence door is arranged at the elevator shaft door, so that the construction is also inconvenient. Therefore, a construction platform is needed that is convenient for constructors to construct at the wellhead and can ensure the safety of constructors.
Disclosure of utility model
The application provides a protection operation integrated construction platform based on temporary support, which aims to solve the problem that the construction and the construction safety are difficult to be compatible when a wellhead and the periphery of the wellhead are constructed in the related art.
The application provides a protection operation integrated construction platform based on temporary support, which adopts the following technical scheme:
A protection operation integrated construction platform based on temporary support comprises
One end of each connecting piece is fixedly connected to the well mouth of the elevator well, a plurality of connecting pieces are arranged, and the connecting pieces are uniformly distributed on the peripheral wall of the well mouth of the elevator well;
The connecting plates are simultaneously erected on a plurality of connecting pieces, the connecting pieces erected by the connecting plates are all positioned on the same peripheral side wall of the wellhead, a plurality of connecting plates are arranged, and the adjacent connecting plates are mutually vertical;
The support piece is erected on the connecting plate; and
The protection piece is located below the support piece and is used for carrying out safety protection on workers.
By adopting the technical scheme, the protection operation integrated construction platform based on temporary support is arranged to be a combination of the connecting piece, the connecting plate, the supporting piece and the protecting piece, so that when an elevator wellhead is to be constructed, the connecting piece is embedded in the corner of the wall, the connecting plate is installed, the supporting piece is paved and the protecting piece is installed, the anti-seepage requirement of the shear wall can be met, and meanwhile, the construction operation and the protection requirement are met. Compared with the traditional scaffold erecting mode, the scaffold erecting mode solves the problems that the traditional steel pipe fastener type operation platform of the elevator shaft is erected with materials, time and labor are wasted, each layer of fastener type scaffold is not required to be erected, the operation platform is provided for process penetration, the investment of edge protection hardware is reduced, the safe construction and the construction progress are improved, and the construction cost is saved. The application solves the problems that the construction is difficult to be convenient and the construction safety is difficult to be compatible when the well mouth and the periphery of the well mouth are constructed in the related technology to a certain extent.
Optionally, the connecting piece is an equilateral angle steel.
Through adopting above-mentioned technical scheme, set up the connecting piece into equilateral angle steel, the constructor of being convenient for more carries out pre-buried or is the installation to the connecting piece.
Optionally, the dimension of the equilateral angle steel is 90mm×90mm×6mm, and the length of the equilateral angle steel is 200mm.
Through adopting above-mentioned technical scheme, the size setting of equilateral angle steel can be applicable to the elevator well head of most sizes, and the suitability is wider.
Optionally, the connection plate is a wood scaffold board, and the size of the connection plate is 90mm×40mm.
Through adopting above-mentioned technical scheme, the size setting of connecting plate and connecting piece adaptation setting have promoted the stability of protection operation integration construction platform effectively.
Optionally, the support member is a form for a construction site.
Through adopting above-mentioned technical scheme, set up support piece into the template that job site is commonly used for when the integrated construction platform of protection operation needs to be made, can draw materials on the spot, it is more convenient, also reduced construction cost to a certain extent.
Optionally, a reinforcement is further disposed between the connecting plate and the supporting member, the reinforcement includes a first reinforcing plate and a second reinforcing plate, the first reinforcing plate is perpendicular to the second reinforcing plate, the first reinforcing plate is provided with a plurality of reinforcing plates, and the second reinforcing plate is provided with a plurality of reinforcing plates.
By adopting the technical scheme, the stability of the protection operation integrated construction platform is further enhanced by the arrangement of the reinforcing piece, and the safety of the protection operation integrated construction platform is effectively improved.
Optionally, a plurality of the first reinforcing plates are arranged at 180mm intervals, and a plurality of the second reinforcing plates are arranged at 180mm intervals.
Through adopting above-mentioned technical scheme, the setting of polylith first reinforcing plate and polylith second reinforcing plate accords with the atress characteristic of support piece more, can further promote the security of protection operation integration construction platform.
Optionally, the protection piece is a safety net, and the safety net is hung on the connecting piece positioned at the corner of the wellhead of the elevator shaft.
Through adopting above-mentioned technical scheme, set up the protector into safe pocket net, safe pocket net can provide important guarantee when the unexpected circumstances take place in the construction to guarantee on-the-spot constructor's life safety to the maximize.
In summary, the present application includes at least one of the following beneficial technical effects:
1. The protection operation integrated construction platform based on temporary support is arranged to be a combination of the connecting piece, the connecting plate, the supporting piece and the protecting piece, so that when an elevator shaft mouth is to be constructed, the connecting piece is embedded in the corner of the wall, the connecting plate is installed, the supporting piece is laid, and the protecting piece is installed, thereby meeting the anti-permeability requirement of the shear wall and meeting the construction operation and protection requirements. Compared with the traditional scaffold erecting mode, the scaffold erecting method solves the problems of material consumption, time consumption and labor consumption in erecting the traditional steel pipe fastener type operation platform of the elevator shaft, does not need to erect a fastener type scaffold at each layer, provides an operation platform for process penetration, reduces the investment of edge protection hardware, improves the safe construction and construction progress, saves the construction cost, improves the construction efficiency and has extremely high popularization value;
2. The protection operation integrated construction platform can be effectively used as temporary support based on some common materials in a construction site by arranging the connecting pieces into equilateral angle steel, arranging the connecting plates into wood scaffold boards and arranging the supporting pieces into templates for the construction site, so that the protection operation integrated construction platform is convenient to install and detach, and the construction efficiency is effectively improved;
3. The guard is provided as a safety net to maximize the life safety of the field constructors.
Drawings
Fig. 1 is a top view of a protection operation integrated construction platform based on temporary support according to an embodiment of the present application.
Fig. 2 is a section A-A of fig. 1.
Fig. 3 is an enlarged view of area a in fig. 2.
Reference numerals illustrate:
1. A connecting piece; 11. equilateral angle steel; 2. a connecting plate; 21. wood scaffold boards; 3. a support; 31. a template; 4. a guard; 41. a safety net; 5. a reinforcing member; 51. a first reinforcing plate; 52. and a second reinforcing plate.
Detailed Description
The application is described in further detail below with reference to fig. 1-3.
The embodiment of the application discloses a protection operation integrated construction platform based on temporary support.
It should be noted that, in the description of the present invention, it should be understood that the terms "center", "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the apparatus or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present invention.
It should be further noted that, the protection operation integrated construction platform based on temporary support provided in the embodiment of the present application only provides a safe construction platform, which cannot replace safety devices, such as safety belts, helmets, etc., required in construction.
Referring to fig. 1 and 2, a protection operation integrated construction platform based on temporary support includes a connecting piece 1, a connecting plate 2, a supporting piece 3 and a protecting piece 4, when an elevator wellhead and the periphery are to be constructed, the connecting piece 1 is pre-buried at the corner of a wall body, after the connecting piece 1 is pre-buried, the connecting plate 2 can be lapped on the connecting piece 1 after the construction of the structural wall body of a building is finished, then the supporting piece 3 and the protecting piece 4 are installed, and the protection operation integrated construction platform is also installed, so that on-site constructors can safely construct the elevator wellhead and the periphery, and meanwhile, the whole construction platform is convenient to install and detach, meanwhile, the construction cost is saved, and the problems that the construction and the construction safety are difficult to be convenient when the wellhead and the wellhead periphery are constructed in the related technology are solved to a certain extent.
In the embodiment of the application, one end of the connecting piece 1 is fixedly connected to the well mouth of the elevator shaft, a plurality of connecting pieces 1 are arranged, and the plurality of connecting pieces 1 are uniformly distributed on the peripheral wall of the well mouth of the elevator shaft. Specifically, the connecting piece 1 in the embodiment of the application is pre-buried at the wellhead of the elevator shaft, so that the connecting piece 1 and a structural member of a building form a whole, and the stress effect is more reasonable. In other embodiments, the connector 1 may be post-installed, but it should be noted that if the connector 1 is post-installed, it is necessary to leave a portion of the reinforcing steel bar in the structural member and the connector 1 of the present application to be welded, which is also an embodiment in which the present application can be implemented.
Further, the connecting piece 1 in the application is an equilateral angle steel 11. The dimensions of the equilateral angle steel 11 are 90mm×90mm×6mm, and the length of the equilateral angle steel 11 is 200mm.
The connecting piece 1 is arranged to be the equilateral angle steel 11, when site constructors pre-buried the equilateral angle steel 11, the embedding direction of the equilateral angle steel 11 is ensured to be right, the possibility of the connecting piece 1 embedding error caused by the size is effectively reduced, and the connecting piece 1 is more conveniently pre-buried or installed by constructors. At the same time, for the dimensions of the equilateral angle pieces 11 provided in the embodiments of the application, they are adapted to the dimensions of most building elevator doors.
It should be noted that, regarding the specific dimensions of the connector 1 according to the present application, the dimensions of 90mm×90mm×6mm are set, which are designed by combining a great deal of engineering experience and by performing strict mechanical calculation, and therefore, the present application is not limited thereto.
In the embodiment of the application, the connecting plates 2 are simultaneously erected on the plurality of connecting pieces 1, the plurality of connecting pieces 1 erected by the connecting plates 2 are all positioned on the same peripheral side wall of the wellhead, a plurality of connecting plates 2 are arranged, and the adjacent connecting plates 2 are mutually vertical. Specifically, one connecting plate 2 is connected to a plurality of connecting pieces 1, that is, the connecting pieces 1 bear the force transmitted by one connecting plate 2 together, so that the structure is more reasonable.
Further, the connection plate 2 is a wood scaffold plate 21, and the dimension of the connection plate 2 is 90mm×40mm. It can be seen that the connecting plate 2 in the application is matched with the connecting piece 1, and meanwhile, the connecting plate 2 is arranged as a wood scaffold board 21 which is visible everywhere on the construction site, so that a great deal of cost is effectively saved for the integrated construction platform.
In the embodiment of the application, the supporting piece 3 is erected on the connecting plate 2. The support 3 is a form 31 for a construction site.
The support piece 3 is arranged to be the template 31 commonly used in a construction site, so that when the protection operation integrated construction platform needs to be manufactured, local materials can be obtained, the construction is more convenient, and the construction cost is reduced to a certain extent. In addition, the construction site templates 31 are usually integrally formed wood templates 31, and the friction force between the wood templates 31 and the wood scaffold boards 21 is larger, so that the connecting plates 2 and the supporting pieces 3 can be lapped more stably, and the safety of the integrated construction platform is further ensured.
Referring to fig. 2 and 3, in order to make the support 3 more stable, a reinforcement 5 is further provided between the support 3 and the connection plate 2, the reinforcement 5 including a first reinforcement plate 51 and a second reinforcement plate 52, the first reinforcement plate 51 and the second reinforcement plate 52 being perpendicular to each other, the first reinforcement plate 51 being provided with a plurality of pieces, the second reinforcement plate 52 being provided with a plurality of pieces.
The stability of the protection operation integrated construction platform is further enhanced by the arrangement of the reinforcing piece 5, and the safety of the protection operation integrated construction platform is effectively improved.
The plurality of first reinforcing plates 51 are arranged at 180mm intervals from each other, and the plurality of second reinforcing plates 52 are arranged at 180mm intervals from each other.
The 180mm interval setting of polylith first reinforcing plate 51 and polylith second reinforcing plate 52 accords with the atress characteristic of support piece 3 more, can further promote the security of protection operation integration construction platform.
Referring to fig. 3, in the embodiment of the present application, a guard 4 is located under the support 3, and the guard 4 is used for safety protection of workers.
Specifically, the protection member 4 is a safety net 41, and the safety net 41 is hung on the connection member 1 at the corner of the shaft mouth of the elevator shaft.
The protection piece 4 is arranged to be the safety pocket net 41, one of the safety pocket nets 41 can pocket falling constructors under the accident condition, the two safety pocket nets 41 have better buffering effect, the secondary injury to the constructors caused by falling can be reduced as far as possible, and the safety pocket net 41 can provide important guarantee when the accident condition occurs in construction so as to maximally guarantee the life safety of the on-site constructors.
The embodiment of the application provides a protection operation integrated construction platform based on temporary support, which is implemented by the following principle: the protection operation integrated construction platform based on temporary support is arranged to be a combination of the connecting piece 1, the connecting plate 2, the supporting piece 3 and the protecting piece 4, so that when an elevator shaft mouth is to be constructed, the connecting piece 1 is embedded in the corner of the wall, the connecting plate 2 is installed, the supporting piece 3 is paved and the protecting piece 4 is installed, the anti-seepage requirement of the shear wall can be met, and meanwhile, the construction operation and protection requirements are met. Compared with the traditional scaffold erecting mode, the scaffold erecting mode solves the problems that the traditional steel pipe fastener type operation platform of the elevator shaft is erected with materials, time and labor are wasted, each layer of fastener type scaffold is not required to be erected, the operation platform is provided for process penetration, the investment of edge protection hardware is reduced, the safe construction and the construction progress are improved, and the construction cost is saved. The application solves the problems that the construction is difficult to be convenient and the construction safety is difficult to be compatible when the well mouth and the periphery of the well mouth are constructed in the related technology to a certain extent.
The above embodiments are not intended to limit the scope of the present application, so: all equivalent changes in structure, shape and principle of the application should be covered in the scope of protection of the application.

Claims (8)

1. Protection operation integration construction platform based on interim support for elevator shaft department, its characterized in that includes:
The elevator shaft comprises a plurality of connecting pieces (1), wherein one end of each connecting piece (1) is fixedly connected to the well mouth of the elevator shaft, the plurality of connecting pieces (1) are arranged, and the plurality of connecting pieces (1) are uniformly distributed on the peripheral wall of the well mouth of the elevator shaft;
the connecting plates (2) are simultaneously erected on a plurality of connecting pieces (1), the connecting pieces (1) erected by the connecting plates (2) are all positioned on the same peripheral side wall of the wellhead, a plurality of connecting plates (2) are arranged, and the adjacent connecting plates (2) are mutually vertical;
The support piece (3), the said support piece (3) is set up on the said junction plate (2); and
The protection piece (4), the protection piece (4) is located the below of support piece (3), protection piece (4) are used for carrying out safety protection to the workman.
2. The protection operation integrated construction platform based on temporary support according to claim 1, wherein the connecting piece (1) is an equilateral angle steel (11).
3. The protection operation integrated construction platform based on temporary support according to claim 2, wherein the dimension of the equilateral angle steel (11) is 90mm×90mm×6mm, and the length of the equilateral angle steel (11) is 200mm.
4. The protection operation integrated construction platform based on temporary support according to claim 1, wherein the connecting plate (2) is a wood scaffold plate (21), and the dimension of the connecting plate (2) is 90mm×40mm.
5. The protection operation integrated construction platform based on temporary support according to claim 1, wherein the support (3) is a form (31) for construction site.
6. The protection operation integrated construction platform based on temporary support according to claim 1, wherein a reinforcement (5) is further arranged between the connecting plate (2) and the supporting piece (3), the reinforcement (5) comprises a first reinforcement plate (51) and a second reinforcement plate (52), the first reinforcement plate (51) and the second reinforcement plate (52) are perpendicular to each other, the first reinforcement plate (51) is provided with a plurality of blocks, and the second reinforcement plate (52) is provided with a plurality of blocks.
7. A protection work integrated construction platform based on temporary support according to claim 6, wherein a plurality of the first reinforcing plates (51) are arranged at 180mm intervals from each other, and a plurality of the second reinforcing plates (52) are arranged at 180mm intervals from each other.
8. The protection operation integrated construction platform based on temporary support according to claim 1, characterized in that the protection piece (4) is a safety net (41), the safety net (41) is hung on the connecting piece (1) at the wellhead corner of the elevator shaft.
CN202323257970.3U 2023-11-30 2023-11-30 Protection operation integrated construction platform based on temporary support Active CN221321695U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202323257970.3U CN221321695U (en) 2023-11-30 2023-11-30 Protection operation integrated construction platform based on temporary support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202323257970.3U CN221321695U (en) 2023-11-30 2023-11-30 Protection operation integrated construction platform based on temporary support

Publications (1)

Publication Number Publication Date
CN221321695U true CN221321695U (en) 2024-07-12

Family

ID=91799764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202323257970.3U Active CN221321695U (en) 2023-11-30 2023-11-30 Protection operation integrated construction platform based on temporary support

Country Status (1)

Country Link
CN (1) CN221321695U (en)

Similar Documents

Publication Publication Date Title
CN110512719B (en) Construction method of large-span interval corridor high-altitude formwork steel platform for high-rise residence
CN106400691B (en) Anti-collision wall mould bases integrated construction technique
CN102337782B (en) Lift system for constructing truss platform on top of tall and large space
CN105908960A (en) Construction rack for construction of high and large space
CN112177309A (en) Assembled protection platform used in building elevator shaft
CN210659200U (en) High-rise building elevator shaft operation platform
CN205476545U (en) Multipurpose combined strength construction ground protection shed structure support frame
CN221321695U (en) Protection operation integrated construction platform based on temporary support
CN105822076A (en) Construction edge safety protection warning fence
CN202401775U (en) Safety protection platform for elevator shaft
CN211524150U (en) Steel beam edge protection device
CN205314242U (en) Job site ground many function combination formula protection canopy
CN217174378U (en) Bridge anticollision barrier construction formwork with protective structure
CN208363666U (en) It is a kind of for build face side construction safety protection frame
CN110005182A (en) A kind of expanded type construction of lift well operation protective platform
CN206616876U (en) One kind is encorbelmented protective platform system
CN215670929U (en) Shear force wall elevator shaft assembled operation platform
CN205444955U (en) Protective device for elevator hoistway
CN212773587U (en) Novel detachable horizontal entrance to a cave protection instrument
CN113047594A (en) Movable climbing frame for elevator shaft and erection method thereof
CN208749068U (en) A kind of moveable exterior wall auxiliary finishing cage ladder of reversely hung Yong
CN209082509U (en) It is a kind of to fall to support the load bearing support structure of bracing members for underground structure deep basal pit
CN219840419U (en) Horizontal protection device for elevator shaft
CN102605964B (en) Separately mounted grille on elevator shaft opening and construction method of separately mounted grille
CN214091101U (en) Can promote elevator entrance to a cave protector

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant