CN220848826U CN202322639632.XU CN202322639632U CN220848826U CN 220848826 U CN220848826 U CN 220848826U CN 202322639632 U CN202322639632 U CN 202322639632U CN 220848826 U CN220848826 U CN 220848826U
Authority
CN
China
Prior art keywords
construction platform
fixedly connected
building installation
installation construction
platform according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322639632.XU
Other languages
Chinese (zh)
Inventor
王秀真
张延奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Yuanrun Construction Development Co ltd
Original Assignee
Shandong Yuanrun Construction Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Yuanrun Construction Development Co ltd filed Critical Shandong Yuanrun Construction Development Co ltd
Priority to CN202322639632.XU priority Critical patent/CN220848826U/en
Application granted granted Critical
Publication of CN220848826U publication Critical patent/CN220848826U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a building installation construction platform, which relates to the technical field of building construction and comprises a lifting frame and a protective fence fixedly arranged at the top of the lifting frame, wherein two support plates are fixedly arranged in the protective fence, a winding roller is rotatably arranged between the two support plates, a motor is fixedly arranged on the side wall of one support plate, the output end of the motor penetrates through the corresponding support plate and is fixedly connected with one end of the winding roller, a traction rope is fixedly connected in the winding roller, the other end of the traction rope is fixedly connected with a hook, and a guide mechanism is arranged at the top of the protective fence. According to the utility model, through the winding roller, winding or releasing of the traction rope can be realized in the rotating process of the winding roller, so that after a constructor enters the protective fence, the material can be lifted after being hung by the hook arranged at the tail end of the traction rope, and the potential safety hazard in the climbing process of the constructor is effectively reduced.

Description

Building installation construction platform
Technical Field
The utility model relates to the technical field of building construction, in particular to a building installation construction platform.
Background
When the wall decoration operation is carried out on a building site or indoors, the construction cannot be directly carried out due to the fact that the wall surface of a building is high, and a construction platform or a scaffold is usually needed to be erected for assistance.
In the process of realizing the application, the applicant finds that the existing construction platform is generally free of a material transportation structure, so that the problem is that constructors need to manually carry materials to climb the construction platform, the whole process is laborious, and certain potential safety hazards exist.
Disclosure of utility model
The present utility model has been made in view of the above-mentioned problems with existing construction platforms.
Therefore, the utility model aims to provide a building installation construction platform, which solves the problems that constructors need to manually carry materials to climb the construction platform, the whole process is laborious and certain potential safety hazards exist.
In order to achieve the above object, the present utility model provides the following technical solutions:
The utility model provides a building installation construction platform, includes crane and fixed rail guard that sets up in the crane top, the inside of rail guard is fixed to be provided with two backup pads, two rotate between the backup pad and be provided with the wind-up roll, one of them the fixed motor that is provided with of lateral wall of backup pad, the output of motor runs through the backup pad that corresponds and with the one end fixed connection of wind-up roll, the inside fixedly connected with haulage rope of wind-up roll, the other end fixedly connected with couple of haulage rope, the top of rail guard is provided with guiding mechanism, guiding mechanism and haulage rope assorted utilize the wind-up roll that sets up, can realize the rolling or release to the haulage rope at wind-up roll pivoted in-process, and then can promote after constructor gets into the inside back of rail guard through setting up in the terminal couple of haulage rope to the material and articulate the back, effectively reduced the potential safety hazard of constructor climbing in-process.
Preferably, guiding mechanism includes mounting panel and a plurality of U-shaped board, the mounting panel sets up in the top and the bottom fixedly connected with U-shaped pole of rail guard, the through-hole has been seted up to one side of rail guard, the inside of through-hole is worn to locate by the U-shaped pole activity, every the U-shaped board is all fixed to be set up in the upper surface of mounting panel, every the inside of U-shaped board is all fixed the cover and is equipped with the bracing piece, every the pole wall of bracing piece has all rotated the leading wheel, every the leading wheel all with haulage rope assorted utilizes the guiding mechanism who sets up, can guide the haulage rope, has avoided haulage rope and rail guard to take place the friction.
Preferably, the fixed two fixed plates that are provided with of one side inner wall of rail guard, two joint movement wears to be equipped with the inserted bar between the fixed plate, two jacks have been seted up to the inside of mounting panel, two the inserted bar all with jack assorted utilizes the inserted bar that sets up, can realize spacing to the mounting panel after inserted bar and the jack that corresponds peg graft, avoids the position of mounting panel to take place to remove.
Preferably, the baffle has been cup jointed to the fixed pole wall of inserted bar, fixedly be provided with between baffle and the fixed plate that corresponds with the inserted bar activity cup joint the spring, utilize baffle and the spring that sets up, can extrude the baffle through the elasticity of spring, make baffle drive inserted bar and the jack that corresponds keep stablely pegging graft.
Preferably, the surface fixedly connected with cloth pocket of couple utilizes the cloth pocket that sets up, can carry out the splendid attire to the material that is inconvenient for the articulated transportation.
Preferably, the pull ring is fixedly arranged at the lower end of the inserted link, and the arranged pull ring is utilized to facilitate driving the inserted link to move so as to pull out the pull link from the corresponding jack.
In the technical scheme, the utility model has the technical effects and advantages that:
According to the utility model, through the winding roller, winding or releasing of the traction rope can be realized in the rotating process of the winding roller, so that after a constructor enters the protective guard, the material can be lifted after being hung by the hook arranged at the tail end of the traction rope, and the potential safety hazard in the climbing process of the constructor is effectively reduced.
Drawings
In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the drawings required for the embodiments will be briefly described below, and it is apparent that the drawings in the following description are only some embodiments described in the present utility model, and other drawings may be obtained according to these drawings for a person having ordinary skill in the art.
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic cross-sectional view of the present utility model;
Fig. 3 is an enlarged schematic view of the portion a of fig. 2 according to the present utility model.
Reference numerals illustrate:
1. A lifting frame; 2. a guard rail; 3. a support plate; 4. a wind-up roll; 5. a motor; 6. a traction rope; 7. a hook; 8. a mounting plate; 9. a U-shaped plate; 10. a U-shaped rod; 11. a support rod; 12. a guide wheel; 13. a fixing plate; 14. a rod; 15. a baffle; 16. a spring; 17. a cloth bag; 18. and (5) a pull ring.
Detailed Description
In order to make the technical scheme of the present utility model better understood by those skilled in the art, the present utility model will be further described in detail with reference to the accompanying drawings.
The embodiment of the utility model discloses a building installation construction platform.
The utility model provides a building installation construction platform as shown in figures 1-3, which comprises a lifting frame 1 and a protective fence 2 fixedly arranged at the top of the lifting frame 1, wherein two support plates 3 are fixedly arranged in the protective fence 2, a winding roller 4 is rotatably arranged between the two support plates 3, a motor 5 is fixedly arranged on the side wall of one support plate 3, the output end of the motor 5 penetrates through the corresponding support plate 3 and is fixedly connected with one end of the winding roller 4, a traction rope 6 is fixedly connected in the winding roller 4, the other end of the traction rope 6 is fixedly connected with a hook 7, a guide mechanism is arranged at the top of the protective fence 2 and matched with the traction rope 6, winding or releasing of the traction rope 6 can be realized in the rotating process of the winding roller 4 by utilizing the winding roller 4, and further, after a constructor enters the interior of the protective fence 2, materials are hung and then lifted through the hook 7 arranged at the tail end of the traction rope 6, so that potential safety hazards in the climbing process of constructors are effectively reduced.
As shown in fig. 1-2, guiding mechanism includes mounting panel 8 and a plurality of U-shaped plates 9, mounting panel 8 sets up in the top of rail guard 2 and bottom fixedly connected with U-shaped pole 10, the through-hole has been seted up to one side of rail guard 2, the inside of through-hole is worn to locate by the activity of U-shaped pole 10, every U-shaped plate 9 is all fixed to be set up in the upper surface of mounting panel 8, the inside of every U-shaped plate 9 all is fixed the cover and is equipped with bracing piece 11, the pole wall of every bracing piece 11 has all rotated and has cup jointed leading wheel 12, every leading wheel 12 all with haulage rope 6 assorted, utilize the guiding mechanism who sets up, can guide haulage rope 6, the friction takes place for haulage rope 6 and rail guard 2 has been avoided.
As shown in fig. 3, two fixing plates 13 are fixedly arranged on one side inner wall of the guard rail 2, inserting rods 14 are arranged between the two fixing plates 13 in a co-moving mode, two inserting holes are formed in the mounting plate 8, the two inserting rods 14 are matched with the inserting holes, the limiting of the mounting plate 8 can be achieved after the inserting rods 14 are inserted into the corresponding inserting holes, and the position of the mounting plate 8 is prevented from moving.
As shown in fig. 3, the baffle 15 is fixedly sleeved on the rod wall of the inserted rod 14, a spring 16 movably sleeved with the inserted rod 14 is fixedly arranged between the baffle 15 and the corresponding fixed plate 13, and the baffle 15 can be pressed by the elasticity of the spring 16 by utilizing the arranged baffle 15 and the spring 16, so that the baffle 15 drives the inserted rod 14 to be stably inserted into the corresponding jack.
As shown in fig. 1-2, the surface of the hook 7 is fixedly connected with a cloth bag 17, and materials inconvenient to hang and transport can be contained by using the cloth bag 17.
As shown in fig. 3, the pull ring 18 is fixedly provided at the lower end of the insert rod 14, and the insert rod 14 can be conveniently driven to move by using the provided pull ring 18, so that the pull rod can be conveniently pulled out from the inside of the corresponding jack.
While certain exemplary embodiments of the present utility model have been described above by way of illustration only, it will be apparent to those of ordinary skill in the art that modifications may be made to the described embodiments in various different ways without departing from the spirit and scope of the utility model. Accordingly, the drawings and description are to be regarded as illustrative in nature and not as restrictive of the scope of the utility model, which is defined by the appended claims.

Claims (6)

1. The utility model provides a building installation construction platform, includes crane (1) and fixed rail guard (2) that set up in crane (1) top, its characterized in that, the inside of rail guard (2) is fixed to be provided with two backup pads (3), two rotate between backup pad (3) and be provided with wind-up roll (4), one of them the fixed motor (5) that are provided with of lateral wall of backup pad (3), the output of motor (5) runs through corresponding backup pad (3) and with the one end fixed connection of wind-up roll (4), the inside fixedly connected with haulage rope (6) of wind-up roll (4), the other end fixedly connected with couple (7) of haulage rope (6), the top of rail guard (2) is provided with guiding mechanism, guiding mechanism and haulage rope (6) assorted.
2. The building installation construction platform according to claim 1, wherein the guiding mechanism comprises a mounting plate (8) and a plurality of U-shaped plates (9), the mounting plate (8) is arranged above the protective guard (2) and is fixedly connected with a U-shaped rod (10) at the bottom, a through hole is formed in one side of the protective guard (2), the U-shaped rod (10) movably penetrates through the inside of the through hole, each U-shaped plate (9) is fixedly arranged on the upper surface of the mounting plate (8), a supporting rod (11) is fixedly sleeved in each U-shaped plate (9), a guiding wheel (12) is rotatably sleeved on the rod wall of each supporting rod (11), and each guiding wheel (12) is matched with the traction rope (6).
3. The building installation construction platform according to claim 2, wherein two fixing plates (13) are fixedly arranged on the inner wall of one side of the protective guard (2), inserting rods (14) are arranged between the two fixing plates (13) in a co-movable mode, two inserting holes are formed in the installation plate (8), and the two inserting rods (14) are matched with the inserting holes.
4. A building installation construction platform according to claim 3, wherein the wall of the inserted link (14) is fixedly sleeved with a baffle (15), and a spring (16) movably sleeved with the inserted link (14) is fixedly arranged between the baffle (15) and the corresponding fixed plate (13).
5. The building installation construction platform according to claim 1, wherein the surface of the hook (7) is fixedly connected with a cloth bag (17).
6. A building installation construction platform according to claim 3, wherein the lower end of the spigot (14) is fixedly provided with a pull ring (18).
CN202322639632.XU 2023-09-27 2023-09-27 Building installation construction platform Active CN220848826U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322639632.XU CN220848826U (en) 2023-09-27 2023-09-27 Building installation construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322639632.XU CN220848826U (en) 2023-09-27 2023-09-27 Building installation construction platform

Publications (1)

Publication Number Publication Date
CN220848826U true CN220848826U (en) 2024-04-26

Family

ID=90739975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322639632.XU Active CN220848826U (en) 2023-09-27 2023-09-27 Building installation construction platform

Country Status (1)

Country Link
CN (1) CN220848826U (en)

Similar Documents

Publication Publication Date Title
CN109339687B (en) Folding lifting device suitable for mine aerial work
CN105502223A (en) High-altitude working platform for line construction
CN215859952U (en) Stable and efficient aerial ladder
CN112411979B (en) Frame of climbing that board is automatic to receive and release turns over
CN213011574U (en) Rapid unhooking device and hoisting mechanism
CN115402909A (en) Super high-rise inclined double-layer special-shaped curtain wall construction device
CN220848826U (en) Building installation construction platform
CN210480708U (en) Automatic rope arranging device for coal mine winch
CN217201855U (en) Pipeline elevating gear of building electromechanical installation usefulness
CN217038861U (en) Hanger type lifting cigarette hanging frame system
CN214360009U (en) Material lifting device for building decoration
CN211310175U (en) Guardrail board uninstallation auxiliary device
CN113323346A (en) Operation platform for decoration outer vertical surface
CN109231036B (en) Building promotes panel with fixed steady equipment of hanging
CN218091947U (en) Suspension type hanging basket
CN216810846U (en) Low-cost scaffold for building engineering construction
CN221140934U (en) Safety protection device for hoisting color steel tile
CN2313962Y (en) Pile press
CN112942775B (en) Installation operation platform for housing construction
CN211871181U (en) Safety lifting device for building
CN219193348U (en) Conveying machine for pavement plates in bins
CN220539251U (en) Brick delivery device for house construction
CN215439393U (en) Hoisting device for building materials
CN113277436B (en) Lifting device for constructional engineering
CN218174413U (en) Wall pre-buried ironware installation construction structures