CN220703068U - Structure of embedded screw rod attached to wall of tower crane - Google Patents
Structure of embedded screw rod attached to wall of tower crane Download PDFInfo
- Publication number
- CN220703068U CN220703068U CN202322397251.5U CN202322397251U CN220703068U CN 220703068 U CN220703068 U CN 220703068U CN 202322397251 U CN202322397251 U CN 202322397251U CN 220703068 U CN220703068 U CN 220703068U
- Authority
- CN
- China
- Prior art keywords
- wall
- embedded screw
- screw rod
- attached
- tower crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 43
- 239000010959 steel Substances 0.000 claims abstract description 43
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 15
- 238000005728 strengthening Methods 0.000 claims description 7
- 238000004519 manufacturing process Methods 0.000 abstract description 5
- 239000011435 rock Substances 0.000 abstract description 4
- 238000009435 building construction Methods 0.000 abstract description 2
- 210000005069 ears Anatomy 0.000 abstract description 2
- 238000009434 installation Methods 0.000 description 7
- 230000008901 benefit Effects 0.000 description 5
- 230000002787 reinforcement Effects 0.000 description 5
- 238000010586 diagram Methods 0.000 description 2
- 101100334009 Caenorhabditis elegans rib-2 gene Proteins 0.000 description 1
- 230000006978 adaptation Effects 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000009194 climbing Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model relates to the technical field of building construction and discloses a structure of a wall-attached embedded screw of a tower crane, which comprises a positioning steel plate, wherein a plurality of reinforcing ribs are fixedly arranged at the bottom of the positioning steel plate, a positioning hole is formed in the top of the positioning steel plate, an embedded screw assembly is arranged in the positioning hole, a first nut is connected with the outer side of the embedded screw assembly in a threaded manner, a second nut is connected with the outer side of the embedded screw assembly in a threaded manner, and two wall-attached ears are fixedly arranged at the top of the positioning steel plate. This structure of embedded screw of wall is attached to tower crane, the design of embedded screw subassembly not only can increase the area of contact and concrete structure post to the later stage only need take off the location steel sheet, can not leave the hole on the wall body, can not influence the aesthetic property, and this structure of embedded screw of wall is attached to tower crane, a plurality of reinforcing members's design not only can strengthen its stability, avoids causing the hoist to take place to rock, and manufacturing cost is lower simultaneously, the facilitate promotion.
Description
Technical Field
The utility model relates to the technical field of building construction, in particular to a structure of a wall-attached embedded screw of a tower crane.
Background
The maximum height of the initial installation height of the tower crane cannot exceed the free independent height, if the installation height needs to exceed the independent height, the tower crane needs to be firstly attached and then can continue climbing, and when the wall attaching device is installed, an important process is the wall attaching embedded part.
Chinese patent publication No.: CN211998566U, disclosing: the utility model provides a super high-rise tower crane attaches wall structure, this super high-rise tower crane attaches wall structure utilizes otic placode and screw rod, nut and structure to carry out fixed connection, and otic placode and steel sheet, screw rod and nut all can recycle many times, but this super high-rise tower crane attaches wall structure, and recoverable steel sheet, screw rod and nut are retrieved after, can leave the breach on the wall, influence the aesthetic property, do not set up a plurality of additional strengthening, influence tower crane's stability easily, cause to rock, the practicality is relatively poor.
Disclosure of Invention
(one) solving the technical problems
Aiming at the defects of the prior art, the utility model provides a structure of a wall-attached embedded screw of a tower crane, which aims to solve the problems in the background.
(II) technical scheme
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a structure of pre-buried screw rod of tower crane wall-attached, includes the location steel sheet, a plurality of strengthening ribs of location steel sheet bottom fixed mounting, the locating hole is seted up at the location steel sheet top, the inside pre-buried screw rod subassembly that is provided with of locating hole, pre-buried screw rod subassembly outside threaded connection has the nut one, pre-buried screw rod subassembly outside threaded connection has the nut two, a wall double-lug plate is attached in location steel sheet top fixed mounting, a plurality of fixed plates of wall double-lug plate outside fixed mounting, fixed hole one is seted up in the fixed plate outside, fixed hole two is seted up in the fixed plate outside, a plurality of reinforcement of fixed mounting in wall double-lug plate outside, wall double-lug plate outside fixed mounting connecting plate is attached.
Preferably, the reinforcing ribs are positioned at the bottom of the positioning steel plate, and a plurality of reinforcing ribs are distributed at equal intervals.
Through above-mentioned technical scheme, because of self location steel sheet, have moderate intensity, can bear certain load and pressure to relatively the price is comparatively economical and practical, can reduce manufacturing cost, convenient to popularize and use, and a plurality of strengthening ribs can improve its anti deformability.
Preferably, the embedded screw rod assembly is of a J-shaped structure, the positioning holes and the embedded screw rod assembly are arranged in the same two groups, and each group of positioning holes and the embedded screw rod assembly are arranged in the same three groups.
Through above-mentioned technical scheme, "J" font structure's pre-buried screw rod subassembly, the area of contact that can increase contact and concrete structure post to the design of the locating hole and the pre-buried screw rod subassembly of same two sets of can further advance holistic anti deformation ability, avoid causing the drop.
Preferably, the first nut and the second nut are matched with the embedded screw rod assembly, the first nut is located at the bottom of the positioning steel plate, and the second nut is located at the top of the positioning steel plate.
Through the technical scheme, the first nut can be firstly installed at the embedded screw assembly, then the embedded screw assembly is inserted at the positioning hole, the second nut can be installed again after concrete is poured, the second nut only needs to be rotated during disassembly and assembly, quick disassembly and assembly of the positioning steel plate can be achieved, and repeated use can be facilitated.
Preferably, the two wall-attached double-lug plates are provided with the same two, and the other side of the connecting plate and the other wall-attached double-lug plate are fixedly installed.
Through above-mentioned technical scheme, after installing pre-buried screw rod subassembly, through the opposite side of connecting plate with another wall double lug plate be fixed mounting, can improve the joint strength between two wall double lug plates that attach, avoid causing whole hoist to rock.
Preferably, the fixing plates are provided with the same two fixing holes, the first fixing holes and the second fixing holes are of a round structure, and the reinforcing pieces are provided with the same four fixing holes.
Through above-mentioned technical scheme, through two fixed plates, can realize improving the joint strength between location steel sheet and the wall-attached double-lug board, the quick installation to tower crane is realized to accessible fixed orifices one and fixed orifices two to the reinforcement is provided with same four, can further improve the joint strength between location steel sheet and the wall-attached double-lug board.
Compared with the prior art, the utility model provides a structure of the embedded screw rod attached to the wall of the tower crane, which has the following beneficial effects:
1. according to the structure of the embedded screw rod attached to the wall of the tower crane, the contact area between the contact and the concrete structural column can be increased due to the design of the embedded screw rod component with the J-shaped structure, and the positioning steel plate is only required to be taken down in the later stage, so that holes are not left in the wall body, and the attractiveness is not affected;
2. this structure of embedded screw rod of tower crane wall-attached, a plurality of reinforcement assemblies's design not only can strengthen its stability, avoids causing the hoist to take place to rock, and manufacturing cost is lower simultaneously, facilitate promotion.
Drawings
FIG. 1 is a schematic perspective view of the first embodiment of the present utility model;
FIG. 2 is a schematic diagram of a second perspective structure of the present utility model;
FIG. 3 is a schematic view of the installation structure of the positioning steel plate and the reinforcing ribs of the present utility model;
fig. 4 is a schematic diagram of the splitting structure of the embedded screw assembly and the wall-attached double-lug plate.
Wherein: 1. positioning a steel plate; 2. reinforcing ribs; 3. positioning holes; 4. embedding a screw assembly; 5. a first nut; 6. a second nut; 7. wall-attached double-lug plate; 8. a fixing plate; 9. a first fixing hole; 10. a second fixing hole; 11. a reinforcing member; 12. and (5) connecting a plate.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Embodiment one:
as shown in fig. 1-4, the structure of the embedded screw rod attached to the wall of the tower crane provided by the utility model comprises a positioning steel plate 1, wherein a plurality of reinforcing ribs 2 are fixedly arranged at the bottom of the positioning steel plate 1, a positioning hole 3 is formed in the top of the positioning steel plate 1, an embedded screw rod assembly 4 is arranged in the positioning hole 3, a first nut 5 is in threaded connection with the outer side of the embedded screw rod assembly 4, a second nut 6 is in threaded connection with the outer side of the embedded screw rod assembly 4, a wall attaching double-lug plate 7 is fixedly arranged at the top of the positioning steel plate 1, a plurality of fixing plates 8 are fixedly arranged at the outer side of the wall attaching double-lug plate 7, a first fixing hole 9 is formed at the outer side of the fixing plate 8, a plurality of reinforcing pieces 11 are fixedly arranged at the outer side of the wall attaching double-lug plate 7, and a connecting plate 12 is fixedly arranged at the outer side of the wall attaching double-lug plate 7.
Specifically, the strengthening rib 2 is located the bottom of location steel sheet 1, and a plurality of strengthening ribs 2 are the equidistance and distribute, and the advantage is, because of own location steel sheet 1, has moderate intensity, can bear certain load and pressure to the price is comparatively economical and practical relatively, can reduce manufacturing cost, facilitate promotion uses, and a plurality of strengthening ribs 2 can improve its anti deformability.
Specifically, embedded screw rod subassembly 4 is "J" font structure, and locating hole 3 and embedded screw rod subassembly 4 are provided with same two sets of, and every locating hole 3 of group is provided with same three with embedded screw rod subassembly 4, and the advantage is, embedded screw rod subassembly 4 of "J" font structure can increase the area of contact and concrete structure post to the design of locating hole 3 and embedded screw rod subassembly 4 of same two sets of can further advance holistic anti deformability, avoids causing the drop.
Specifically, first nut 5 and second nut 6 and pre-buried screw rod subassembly 4 looks adaptation, first nut 5 is located the bottom of location steel sheet 1, and second nut 6 is located the top of location steel sheet 1, and the advantage is, can install first nut 5 in pre-buried screw rod subassembly 4 department earlier, inserts pre-buried screw rod subassembly 4 in locating hole 3 departments afterwards, after pouring concrete, can install second nut 6 again, only need rotate second nut 6 in the dismouting, can realize the quick assembly disassembly to location steel sheet 1, can be convenient for repeatedly usable.
Embodiment two:
as shown in fig. 1-4, as an improvement of the previous embodiment, specifically, two wall-attached double-lug plates 7 are provided with the same two, and the other side of the connecting plate 12 and the other wall-attached double-lug plate 7 are fixedly installed, which has the advantage that after the embedded screw assembly 4 is installed, the connecting strength between the two wall-attached double-lug plates 7 can be improved through the fixed installation of the other side of the connecting plate 12 and the other wall-attached double-lug plate 7.
Specifically, fixed plate 8 is provided with same two, and fixed orifices one 9 and fixed orifices two 10 are "circle" structure, and reinforcement 11 is provided with same four, and the advantage is, through two fixed plates 8, can realize improving the joint strength between positioning steel plate 1 and the wall-attached double lug plate 7, and quick installation to tower crane is realized to fixed orifices one 9 and fixed orifices two 10 to reinforcement 11 is provided with same four, can further improve the joint strength between positioning steel plate 1 and the wall-attached double lug plate 7.
Working principle: when the novel concrete pouring device is used, the first nut 5 can be firstly installed at the position of the embedded screw rod assembly 4, then the embedded screw rod assembly 4 is inserted into the position of the positioning hole 3, the second nut 6 can be installed again after concrete is poured, the second nut 6 only needs to be rotated during disassembly and assembly, quick disassembly and assembly of the positioning steel plate 1 can be realized, the novel concrete pouring device can be used repeatedly conveniently, the contact area between the contact and a concrete structural column can be increased through the embedded screw rod assembly 4 with a J-shaped structure, the contact area of the positioning holes 3 and the embedded screw rod assembly 4 in the same two groups can be further improved, the integral deformation resistance can be improved in advance, the falling off is avoided, the positioning steel plate 1 is provided with moderate strength, certain load and pressure can be borne, the novel concrete pouring device is relatively economical and practical, the production cost can be reduced, the novel concrete pouring device is convenient to popularize and the plurality of reinforcing ribs 2 can improve the deformation resistance of the novel concrete pouring device, the connection strength between the positioning steel plate 1 and the wall attaching plate 7 can be improved through the two fixing plates 8, the quick installation of the crane can be realized through the first fixing holes 9 and the second fixing holes 10, and the tower type reinforcing piece 11 is provided with the same four fixing holes, and the connection strength between the two ears of the positioning steel plate 1 and the wall attaching plate 7 can be further improved.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The utility model provides a structure of pre-buried screw rod of tower crane wall-attached, includes location steel sheet (1), its characterized in that: the utility model discloses a wall double-lug plate (7) is attached to location steel sheet (1) outside fixed mounting a plurality of strengthening ribs (2), locating hole (3) are seted up at location steel sheet (1) top, locating hole (3) inside is provided with pre-buried screw rod subassembly (4), pre-buried screw rod subassembly (4) outside threaded connection has nut one (5), pre-buried screw rod subassembly (4) outside threaded connection has nut two (6), location steel sheet (1) top fixed mounting attaches wall double-lug plate (7), attach wall double-lug plate (7) outside fixed mounting a plurality of fixed plates (8), fixed hole one (9) are seted up in the fixed plate (8) outside, fixed hole two (10) are seted up in the fixed plate (8) outside, attach wall double-lug plate (7) outside fixed mounting connecting plate (12).
2. The structure of the embedded screw attached to the wall of the tower crane according to claim 1, wherein: the reinforcing ribs (2) are positioned at the bottom of the positioning steel plate (1), and a plurality of reinforcing ribs (2) are distributed at equal intervals.
3. The structure of the embedded screw attached to the wall of the tower crane according to claim 1, wherein: the embedded screw rod assembly (4) is of a J-shaped structure, the positioning holes (3) and the embedded screw rod assembly (4) are arranged in the same two groups, and each group of the positioning holes (3) and the embedded screw rod assembly (4) are arranged in the same three groups.
4. The structure of the embedded screw attached to the wall of the tower crane according to claim 1, wherein: the first nut (5) and the second nut (6) are matched with the embedded screw rod assembly (4), the first nut (5) is located at the bottom of the positioning steel plate (1), and the second nut (6) is located at the top of the positioning steel plate (1).
5. The structure of the embedded screw attached to the wall of the tower crane according to claim 1, wherein: the two wall-attached double-lug plates (7) are arranged in the same manner, and the other side of the connecting plate (12) and the other wall-attached double-lug plate (7) are fixedly installed.
6. The structure of the embedded screw attached to the wall of the tower crane according to claim 1, wherein: the fixing plates (8) are provided with the same two fixing holes, the first fixing holes (9) and the second fixing holes (10) are of a round structure, and the reinforcing pieces (11) are provided with the same four fixing holes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322397251.5U CN220703068U (en) | 2023-09-05 | 2023-09-05 | Structure of embedded screw rod attached to wall of tower crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322397251.5U CN220703068U (en) | 2023-09-05 | 2023-09-05 | Structure of embedded screw rod attached to wall of tower crane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220703068U true CN220703068U (en) | 2024-04-02 |
Family
ID=90452054
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322397251.5U Active CN220703068U (en) | 2023-09-05 | 2023-09-05 | Structure of embedded screw rod attached to wall of tower crane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220703068U (en) |
-
2023
- 2023-09-05 CN CN202322397251.5U patent/CN220703068U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212224695U (en) | Bracing device is used in installation of prefabricated post for assembly type structure | |
CN111197349A (en) | Steel structure assembly type building convenient to install and assembly method | |
CN220703068U (en) | Structure of embedded screw rod attached to wall of tower crane | |
CN201574551U (en) | External wall heat-preservation wall plate no-frame anchoring structure part | |
CN109296075B (en) | High deformability assembled frame structure beam-column connection node | |
CN214462400U (en) | A bracket structure for fixing double-deck protection frame | |
CN201265214Y (en) | Steel plate anchorage block used for external pre-stress reinforcement structure | |
CN212317547U (en) | Novel shear force wall reinforcing and supporting system | |
CN203008233U (en) | K-structure unit assembly | |
CN202509625U (en) | Fastening type mobile steel structure house | |
CN219118885U (en) | Steel structure large-scale venue installation structure capable of being rapidly assembled | |
CN219653947U (en) | Girder steel and concrete PC roof beam connection structure | |
CN209854908U (en) | Novel connecting node | |
CN203144901U (en) | Square pipe bridge face plate | |
CN212897185U (en) | Reinforcing structure for building construction | |
CN211646731U (en) | Integrated assembled steel construction building | |
CN219451061U (en) | H-shaped steel girder lower support reinforced concrete beam structure | |
CN217949332U (en) | High strength light steel structure for building | |
CN221298242U (en) | Novel embedded part and tool thereof | |
CN210122758U (en) | Integrated assembly type steel structure building | |
CN213062631U (en) | Easily-disassembled cross beam for steel structure construction | |
CN221031822U (en) | Pre-buried base for outdoor products | |
CN215564720U (en) | Novel independent plate bottom support body | |
CN214784772U (en) | Horizontal inner support dismantling structure | |
CN219412452U (en) | Simple climbing device for tower flange |