CN220550541U - Crack control green engineering precast tubular pile - Google Patents

Crack control green engineering precast tubular pile Download PDF

Info

Publication number
CN220550541U
CN220550541U CN202321478862.6U CN202321478862U CN220550541U CN 220550541 U CN220550541 U CN 220550541U CN 202321478862 U CN202321478862 U CN 202321478862U CN 220550541 U CN220550541 U CN 220550541U
Authority
CN
China
Prior art keywords
tubular pile
precast tubular
protective coating
polymer protective
pipe piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321478862.6U
Other languages
Chinese (zh)
Inventor
吴刚
赵茂浪
王盛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Xinghua Infrastructure Engineering Co ltd
Original Assignee
Jiangsu Xinghua Infrastructure Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Xinghua Infrastructure Engineering Co ltd filed Critical Jiangsu Xinghua Infrastructure Engineering Co ltd
Priority to CN202321478862.6U priority Critical patent/CN220550541U/en
Application granted granted Critical
Publication of CN220550541U publication Critical patent/CN220550541U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses an anti-cracking green engineering precast tubular pile, which comprises a concrete precast tubular pile, reinforcement cages, end plates, an inner polymer protective coating and an outer polymer protective coating, wherein the reinforcement cages are embedded in the concrete precast tubular pile, the inner wall of the concrete precast tubular pile is coated with the inner polymer protective coating, and the outer wall of the concrete precast tubular pile is coated with the outer polymer protective coating. The method is characterized in that a set of prefabricated prestressed pipe piles are provided for green engineering, a prestressed reinforcement structure is arranged inside the prestressed pipe piles, the cracking of the pipe piles can be reduced, and the inner and outer surfaces of the pipe piles are coated with protective layers successively, so that the surfaces of the pipe piles can be effectively protected from being corroded by the external environment, the generation of cracks is reduced, and the problem that the existing prefabricated pipe piles are easily corroded by the external environment after the foundation is inserted into a construction site, so that the cracks on the surfaces of the prefabricated pipe piles are largely generated is solved.

Description

Crack control green engineering precast tubular pile
Technical Field
The utility model relates to the technical field of precast tubular piles, in particular to an anti-cracking green engineering precast tubular pile.
Background
The prefabricated pipe pile is a prefabricated and poured pipe pile structure and is used for supporting the foundation of structures such as buildings, bridges, wharfs and tunnels, the length and the diameter of the prefabricated pipe pile can be customized according to the needs, and the prefabricated pipe pile is usually between a few meters and tens of meters and is also an indispensible supporting structure for supporting the foundation of a green engineering building.
The existing precast tubular pile surface is usually in direct contact with a foundation by a concrete structure, however, when the tubular pile is inserted into the foundation, soil blocks of the foundation and a later moist environment can erode the concrete structure on the precast tubular pile surface, so that cracks are generated, and the service life of the precast tubular pile is influenced.
Based on the existing precast tubular pile, the following defects exist: after the existing precast tubular pile is inserted into a foundation of a construction site, the existing precast tubular pile is easily corroded by the external environment, so that a large number of cracks are generated on the surface of the precast tubular pile. Therefore, we propose an anti-cracking green engineering precast tubular pile.
Disclosure of Invention
The utility model mainly aims to provide an anti-cracking green engineering precast tubular pile which can effectively solve the problems in the background technology.
In order to achieve the above purpose, the technical scheme adopted by the utility model is as follows:
the utility model provides a green engineering precast tubular pile of crack control line, includes concrete precast tubular pile, steel reinforcement cage and end plate, still includes interior polymer protective coating and outer polymer protective coating, pre-buried steel reinforcement cage has in the concrete precast tubular pile, the coating of concrete precast tubular pile inner wall has interior polymer protective coating, the coating of concrete precast tubular pile outer wall has outer polymer protective coating.
Further, both ends of the reinforcement cage are respectively welded with end plates.
Further, the outer polymer protective coating is filled with glass fibers.
Further, the inner polymer protective coating and the outer polymer protective coating are both made of polyurethane materials.
Compared with the prior art, the utility model has the following beneficial effects: the assembly consisting of the concrete precast tubular pile, the reinforcement cage, the end plate, the inner polymer protective coating and the outer polymer protective coating is used for providing a set of precast prestressed tubular pile for green engineering, and the inside is provided with a prestressed reinforcement structure, so that the cracking of the tubular pile can be reduced, and the inside and the outside of the tubular pile are sequentially coated with the protective layer, so that the surface of the tubular pile can be effectively protected from being corroded by the external environment, the generation of cracks is reduced, and the problem that the surface of the precast tubular pile is easily corroded by the external environment after the foundation is inserted into a construction site in the prior art is solved, so that the cracks are largely generated on the surface of the precast tubular pile.
Drawings
Fig. 1 is a schematic diagram of the overall structure of an anti-cracking green engineering precast tubular pile.
Fig. 2 is a schematic view of a concrete precast tubular pile of the anti-crack green engineering precast tubular pile according to the present utility model.
Fig. 3 is a schematic cross-sectional structure of a concrete precast tubular pile of the anti-crack green engineering precast tubular pile.
In the figure: 1. prefabricating a pipe pile by using concrete; 2. a reinforcement cage; 3. a reinforcement cage; 4. an outer polymeric protective coating; 5. glass fibers; 6. end plates.
Detailed Description
The utility model is further described in connection with the following detailed description, in order to make the technical means, the creation characteristics, the achievement of the purpose and the effect of the utility model easy to understand.
As shown in fig. 1-3, the anti-cracking green engineering precast tubular pile comprises a concrete precast tubular pile 1, a reinforcement cage 2, an end plate 6, an inner polymer protective coating 3 and an outer polymer protective coating 4, wherein the reinforcement cage 2 is embedded in the concrete precast tubular pile 1, the inner wall of the concrete precast tubular pile 1 is coated with the inner polymer protective coating 3, and the outer wall of the concrete precast tubular pile 1 is coated with the outer polymer protective coating 4.
Wherein, the both ends of steel reinforcement cage 2 are welded respectively and are connected with end plate 6.
Wherein the outer polymer protective coating 4 is filled with glass fibers 5.
Wherein, the inner polymer protective coating 3 and the outer polymer protective coating 4 are made of polyurethane materials.
The utility model relates to an anti-cracking green engineering precast tubular pile, which is characterized in that when in operation, personnel select a precast concrete tubular pile 1 which is precast in a factory and provided with a reinforcement cage 2, compared with the traditional site construction, the precast concrete tubular pile 1 which is precast in the factory reduces pollution to the surrounding environment and the production process of destroying precast members, can effectively utilize resources, reduces waste, has an effect of saving energy, then the personnel spray inner polymer protective coating 3 on the inner wall of the precast concrete tubular pile 1, realizes the protection on the inner wall of the tubular pile, then coats outer polymer protective coating 4 on the outer wall of the precast concrete tubular pile 1, and fills and mixes the outer polymer protective coating 4 through glass fibers 5, thereby further increasing the strength of the outer wall of the precast concrete tubular pile 1, reducing the abrasion and damage of soil blocks in a foundation to the outer wall of the precast concrete tubular pile 1, protecting the surface of the precast tubular pile from the corrosion of the external environment, and ensuring the stability of the precast tubular pile.
The foregoing has shown and described the basic principles and main features of the present utility model and the advantages of the present utility model. It will be understood by those skilled in the art that the present utility model is not limited to the embodiments described above, and that the above embodiments and descriptions are merely illustrative of the principles of the present utility model, and various changes and modifications may be made without departing from the spirit and scope of the utility model, which is defined in the appended claims. The scope of the utility model is defined by the appended claims and equivalents thereof.

Claims (4)

1. The utility model provides a green engineering precast tubular pile of crack control line, includes concrete precast tubular pile (1), steel reinforcement cage (2) and end plate (6), its characterized in that still includes interior polymer protective coating (3) and outer polymer protective coating (4), pre-buried steel reinforcement cage (2) in concrete precast tubular pile (1), concrete precast tubular pile (1) inner wall coating has inner polymer protective coating (3), concrete precast tubular pile (1) outer wall coating has outer polymer protective coating (4).
2. The crack-resistant green engineered precast tubular pile of claim 1, wherein: two ends of the reinforcement cage (2) are respectively welded with end plates (6).
3. The crack-resistant green engineered precast tubular pile of claim 1, wherein: the outer polymer protective coating (4) is filled with glass fibers (5).
4. The crack-resistant green engineered precast tubular pile of claim 1, wherein: the inner polymer protective coating (3) and the outer polymer protective coating (4) are made of polyurethane materials.
CN202321478862.6U 2023-06-12 2023-06-12 Crack control green engineering precast tubular pile Active CN220550541U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321478862.6U CN220550541U (en) 2023-06-12 2023-06-12 Crack control green engineering precast tubular pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321478862.6U CN220550541U (en) 2023-06-12 2023-06-12 Crack control green engineering precast tubular pile

Publications (1)

Publication Number Publication Date
CN220550541U true CN220550541U (en) 2024-03-01

Family

ID=90006378

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321478862.6U Active CN220550541U (en) 2023-06-12 2023-06-12 Crack control green engineering precast tubular pile

Country Status (1)

Country Link
CN (1) CN220550541U (en)

Similar Documents

Publication Publication Date Title
CN109183607B (en) Prefabricated spliced UHPC pipe-concrete ultrahigh pier and construction method
CN110952996B (en) Method and material for reinforcing electric power tunnel by fiber grid reinforced polymer mortar
CN104947709A (en) Pre-assembled single-compartment municipal tunnel and construction method thereof
CN204690783U (en) A kind of prefabricated assembled single cabin municipal administration synthesis pipe gallery
CN106438213B (en) Tower drum for wind driven generator
CN113513015A (en) Semi-prefabricated concrete reinforcement cage underground continuous wall and construction method
CN113202173A (en) Construction method for temporarily replacing cross-foundation-pit concrete pipe with steel pipe in deep foundation pit construction
CN111173004A (en) Special-shaped precast pile zipper type supporting structure and construction method thereof
CN106592777A (en) Assembly type steel-concrete combined beam column joint structure and implementation method thereof
CN220550541U (en) Crack control green engineering precast tubular pile
CN211689844U (en) Corrugated steel reinforcing arch utilizing high-strength grouting material
CN111663566A (en) Underground cylindrical reinforced concrete combined outer wall structure and construction method
CN216973425U (en) Inclined prefabricated steel pile foundation pit supporting system capable of being supported and excavated firstly
CN214993221U (en) Corrugated steel plate-concrete composite structure suitable for culvert reinforcement and transformation
CN213014350U (en) Transmission line pole tower cast-in-place pile foundation for strong corrosion area
CN212612442U (en) Concrete anticorrosion device
CN210289224U (en) Steel wire cloth reinforced structure for building restoration
CN112343074A (en) Spliced prefabricated root key type digging foundation
CN219045174U (en) Waterproof structure of pile head of filling pile
CN111576432A (en) Prefabricated foundation pit additionally provided with elevator and construction method
CN110685483A (en) Large-scale coal storage bin top plate prefabricating and assembling method
CN111894030A (en) Cast-in-place pile anticorrosion foundation of power transmission line tower and construction method thereof
CN104213515A (en) Method for repairing embedded corrugated steel structure by using steel fiber sprayed concrete
CN215801653U (en) Prefabricated spliced elevator foundation pit device
CN219219284U (en) Sedimentation repair structure of rain sewage inspection well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant