CN220099981U - Concrete prefabricated well with hoop locking structure - Google Patents

Concrete prefabricated well with hoop locking structure Download PDF

Info

Publication number
CN220099981U
CN220099981U CN202321596744.5U CN202321596744U CN220099981U CN 220099981 U CN220099981 U CN 220099981U CN 202321596744 U CN202321596744 U CN 202321596744U CN 220099981 U CN220099981 U CN 220099981U
Authority
CN
China
Prior art keywords
well
hoop
locking structure
arc
shaped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321596744.5U
Other languages
Chinese (zh)
Inventor
张发庆
朱大伟
张州
田卫平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG YONGDA ELECTRIC POWER INDUSTRY CO LTD
Original Assignee
ZHEJIANG YONGDA ELECTRIC POWER INDUSTRY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG YONGDA ELECTRIC POWER INDUSTRY CO LTD filed Critical ZHEJIANG YONGDA ELECTRIC POWER INDUSTRY CO LTD
Priority to CN202321596744.5U priority Critical patent/CN220099981U/en
Application granted granted Critical
Publication of CN220099981U publication Critical patent/CN220099981U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Branch Pipes, Bends, And The Like (AREA)

Abstract

The utility model relates to the technical field of prefabricated wells, in particular to a concrete prefabricated well with a hoop locking structure. Comprising the following steps: the well seat is provided with a plurality of interfaces in a protruding mode in the circumferential direction, positioning steps are arranged in the interfaces, and sealing elements are arranged in the positioning steps; the branch pipe is arranged in the interface and is sleeved with the sealing piece; and the anchor ear is in sealing connection with the corresponding interface through a fastener. The utility model provides the concrete prefabricated well with the anchor ear locking structure, which has good sealing effect, no offset of the branch pipe and good stability.

Description

Concrete prefabricated well with hoop locking structure
Technical Field
The utility model relates to the technical field of prefabricated wells, in particular to a concrete prefabricated well with a hoop locking structure.
Background
The concrete inspection well is generally arranged below the municipal road, is convenient to maintain and install for power supply, water drainage, pollution discharge, communication, cable television, gas pipes, street lamp circuits and the like of the urban underground infrastructure, is convenient to regularly inspect and maintain the pipelines at regular intervals, ensures the safety and smoothness of the pipelines, thoroughly changes the traditional bricked inspection well structure of the precast concrete inspection well, has the characteristics of high strength, rapid assembly construction and tight joints, and can solve the defects of the clay brick inspection well, thereby greatly improving the field operation speed of the inspection well and shortening the construction period.
Chinese patent CN218713290U discloses a concrete prefabricated inspection well for underground buried pipelines, comprising a prefabricated concrete base plate, a prefabricated concrete cylindrical well body and a prefabricated concrete inverted funnel-shaped top well ring, wherein a connecting well body lower annular tongue-and-groove is arranged on the top end surface of the prefabricated concrete base plate, a connecting base plate annular tongue-and-groove is arranged on the lower bottom surface of the prefabricated concrete cylindrical well body, a connecting well ring annular tongue-and-groove is arranged on the upper top surface of the prefabricated concrete cylindrical well body, a left connecting pipeline circular through hole and a right connecting pipeline circular through hole are respectively arranged on the prefabricated concrete cylindrical well body, and a connecting well body annular tongue-and-groove is arranged on the lower bottom surface of the prefabricated concrete inverted funnel-shaped top well ring; the prefabricated concrete cylindrical well body is connected with the prefabricated concrete base plate through the butt joint of the annular rabbet of the connecting base plate and the annular rabbet of the lower part of the connecting well body; the prefabricated concrete inverted funnel-shaped top well ring is connected with the prefabricated concrete cylindrical well body; the prefabricated concrete base plate, the prefabricated concrete cylindrical well body and the prefabricated concrete inverted funnel-shaped top well ring are in butt joint to form a closed well body.
However, after the technical scheme is used for a long time, the phenomenon that soil subsides and sinks and collapses is very easy to occur on the roadbed around the well cover plate of the prefabricated well, the branch pipes incline, the sealing effect is poor, and therefore sewage leakage is caused to pollute the soil.
Disclosure of Invention
The utility model aims at overcoming the defects of the prior art, and provides a concrete prefabricated well with a hoop locking structure, which realizes the function of tightly mounting and sealing between a branch pipe and a branch pipe hole on a well seat by matching a hoop with a sealing element, thereby solving the problem of soil pollution caused by sewage leakage due to sinking of the branch pipe caused by soil settlement.
In order to achieve the above purpose, the present utility model provides the following technical solutions:
a concrete prefabricated well having a hoop locking structure, comprising:
the well seat is provided with a plurality of interfaces in a protruding mode in the circumferential direction, positioning steps are arranged in the interfaces, and sealing elements are arranged in the positioning steps;
the branch pipe is arranged in the interface and is sleeved with the sealing piece; and
the anchor ear is in sealing connection with the corresponding interface through a fastener.
Preferably, the positioning step extends inwards from the outer side edge of the interface, and the width dimension of the positioning step is D.
Preferably, the size of the sealing member is adapted to the size of the positioning step.
Preferably, a plurality of mounting holes are uniformly distributed on the circumferential edge of the interface.
Preferably, nuts or expansion screws are embedded in the mounting holes.
Preferably, the anchor ear comprises two arc-shaped single elements which are symmetrically arranged, and two ends of the arc-shaped single elements are fixedly connected through locking pieces.
Preferably, the arc-shaped single element comprises an arc-shaped hoop body, two ends of the arc-shaped hoop body are respectively provided with a first connecting part parallel to the axis of the arc-shaped hoop body, and the outer side wall of the arc-shaped hoop body is provided with at least one second connecting part fixedly connected with the corresponding interface edge.
Preferably, a space L is left between the second connecting portion and the inner edge of the arc-shaped hoop body, and the space L is smaller than the width dimension D of the positioning step.
Preferably, the outer diameter of the anchor ear is matched with the inner diameter of the interface.
The utility model has the beneficial effects that:
according to the utility model, the locating step is arranged in the connector and matched with the hoop sleeved outside the branch pipe, and the sealing element is arranged in the locating step, so that the sealing element is extruded by the hoop, the locating step also forms an extrusion effect on the sealing element, a better sealing effect can be achieved, the branch pipe is fixed by combining the second connecting part arranged on the hoop, and the tight sealing reliability is ensured while firm fixation is realized.
In conclusion, the utility model has the advantages of good sealing effect, no offset of the branch pipe, good stability and the like.
Drawings
FIG. 1 is a cross-sectional view of the present utility model;
FIG. 2 is an enlarged view at A of FIG. 1;
FIG. 3 is a front view of the present utility model;
FIG. 4 is a front view and a top view of an arc-shaped unit cell according to the present utility model.
Reference numerals: 1-a well seat; 11-interface; 12-positioning the step; 13-mounting holes; 2-branch pipes; 21-a seal; 3-hoops; 31-a fastener; 32-arc-shaped unit pieces; 321-an arc-shaped hoop body; 322-first connection portion; 323-a second connection; 33-locking member.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
In the description of the present utility model, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings are merely for convenience in describing the present utility model and simplifying the description, and do not indicate or imply that the apparatus or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present utility model. Furthermore, the terms "first," "second," and the like, are used for descriptive purposes only and are not to be construed as indicating or implying a relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defining "a first" or "a second" may explicitly or implicitly include one or more such feature. In the description of the present utility model, the meaning of "a plurality" is two or more, unless explicitly defined otherwise.
Examples
As shown in fig. 1 to 4, this embodiment provides a concrete prefabricated well with a hoop locking structure, including: the well seat 1 is provided with a plurality of interfaces 11 in a protruding mode in the circumferential direction, a positioning step 12 is arranged in the interfaces 11, and a sealing element 21 is arranged in the positioning step 12; a branch pipe 2 installed in the interface 11, wherein the branch pipe 2 is sleeved with the sealing element 21; and the anchor ear 3 is in sealing connection with the corresponding interface 11 through a fastener 31.
In this embodiment, the positioning step 12 extends inward from the outer edge of the interface 11, and has a width dimension D, so that the positioning step 12 has a limiting effect on the sealing element 21, thereby enhancing the sealing effect of the sealing element 21.
At the same time, the dimensions of the sealing element 21 are adapted to the dimensions of the positioning step 12, i.e. the width dimension of the sealing element 21 is preferably smaller than the width dimension of the positioning step 12, so that the remaining space can accommodate the edge portion of the anchor ear 3, so that it can press the sealing element 21.
Moreover, a plurality of mounting holes 13 are uniformly distributed on the circumferential edge of the connector 11, nuts or expansion screws are pre-buried in the mounting holes 13, so that the fastening of the fastening piece 31 is facilitated, the reliability of connection and fixation is improved, and the problem of soil pollution caused by sewage leakage due to sinking of the branch pipe 2 caused by soil settlement is solved.
In this embodiment, the anchor ear 3 includes two symmetrically disposed arc-shaped unit elements 32, two ends of the two arc-shaped unit elements 32 are fixedly connected through a locking member 33, the arc-shaped unit elements 32 include an arc-shaped hoop body 321, two ends of the arc-shaped hoop body 321 are respectively provided with a first connecting portion 322 parallel to the axis thereof, the outer side wall of the arc-shaped hoop body is provided with at least one second connecting portion 323 fixedly connected with the corresponding edge of the interface 11, when a plurality of second connecting portions 323 are present, preferably, a plurality of second connecting portions 323 are uniformly distributed on the outer side wall of the arc-shaped hoop body 321, a space L is reserved between the second connecting portions 323 and the inner side edge of the arc-shaped hoop body 321, the space L is smaller than the width dimension D of the positioning step 12, enough installation space is reserved for the sealing member 21, so that the sealing member 21 can be squeezed conveniently, and when the anchor ear 3 is locked by the fastener 31, the anchor ear 3 has a squeezing effect on the sealing member 21, and the sealing member 21 is further improved.
In addition, in this embodiment, the outer diameter of the anchor ear 3 is adapted to the inner diameter of the interface 11, so as to avoid the problem that the sealing effect of the sealing element 21 is poor due to the fact that the anchor ear 3 cannot press the sealing element 21 well due to the mismatching of the sizes of the anchor ear 3 and the interface 11.
The installation process of the embodiment is as follows: firstly, the sealing element 21 and the anchor ear 3 are respectively sleeved on the branch pipe 2 in sequence and are received in the insertion interface 11 together, so that the sealing element 21 is just clamped inside the positioning step 12, then the anchor ear 3 is fixedly connected with the well seat 1 by screwing the fastener 31 into the mounting hole 13, and at the moment, the edge part of the anchor ear 3 can continuously squeeze the sealing element 21 until the fastener 31 is completely fixed.
The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the utility model.

Claims (9)

1. A concrete prefabricated well having a hoop locking structure, comprising:
the well seat is provided with a plurality of interfaces in a protruding mode in the circumferential direction, positioning steps are arranged in the interfaces, and sealing elements are arranged in the positioning steps;
the branch pipe is arranged in the interface and is sleeved with the sealing piece; and
the anchor ear is in sealing connection with the corresponding interface through a fastener.
2. A precast concrete well with a hoop locking structure according to claim 1, wherein the positioning step extends inwards from the outer edge of the joint and has a width dimension D.
3. A precast concrete well having a hoop locking structure according to claim 1, wherein the size of the sealing member is adapted to the size of the positioning step.
4. The precast concrete well with the hoop locking structure of claim 1, wherein a plurality of mounting holes are uniformly distributed on the circumferential edge of the connector.
5. The precast concrete well with the hoop locking structure of claim 4, wherein nuts or expansion bolts are pre-embedded in the mounting holes.
6. The concrete prefabricated well with the anchor ear locking structure according to claim 1, wherein the anchor ear comprises two symmetrically arranged arc-shaped single elements, and two ends of the arc-shaped single elements are fixedly connected through locking pieces.
7. The concrete prefabricated well with the hoop locking structure according to claim 6, wherein the arc-shaped single element comprises an arc-shaped hoop body, two ends of the arc-shaped hoop body are respectively provided with a first connecting part parallel to the axis of the arc-shaped hoop body, and the outer side wall of the arc-shaped hoop body is provided with at least one second connecting part fixedly connected with the corresponding interface edge.
8. The precast concrete well with the hoop locking structure of claim 7, wherein a distance L is left between the second connecting portion and the inner edge of the arc-shaped hoop body, and the distance L is smaller than the width dimension D of the positioning step.
9. A precast concrete well having a hoop locking structure according to any one of claims 1 to 8 wherein the outer diameter of the hoop is adapted to the inner diameter of the interface.
CN202321596744.5U 2023-06-21 2023-06-21 Concrete prefabricated well with hoop locking structure Active CN220099981U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321596744.5U CN220099981U (en) 2023-06-21 2023-06-21 Concrete prefabricated well with hoop locking structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321596744.5U CN220099981U (en) 2023-06-21 2023-06-21 Concrete prefabricated well with hoop locking structure

Publications (1)

Publication Number Publication Date
CN220099981U true CN220099981U (en) 2023-11-28

Family

ID=88842225

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321596744.5U Active CN220099981U (en) 2023-06-21 2023-06-21 Concrete prefabricated well with hoop locking structure

Country Status (1)

Country Link
CN (1) CN220099981U (en)

Similar Documents

Publication Publication Date Title
CN102518199B (en) Hermetic connecting method for bell mouth of plastic inspection well
CN213979225U (en) Inspection well structure for drainage system
CN220099981U (en) Concrete prefabricated well with hoop locking structure
CN211312769U (en) Connecting member of plastic pipe and concrete prefabricated inspection well
CN205617425U (en) Prefabricated structure of assembling of utility tunnel
CN213776704U (en) Anticorrosive steel pipe fixed knot of socket joint formula constructs
CN212715248U (en) Assembled inspection shaft
CN214090253U (en) Urban municipal drainage pipeline inspection shaft structure
CN214116915U (en) Novel assembled inspection shaft connection structure
CN211649446U (en) Double-wall corrugated pipe buckle sealing connection device
KR200402713Y1 (en) connection structure of pipe for a manhole
CN220225632U (en) Convex socket inspection well and branch pipe connection structure
CN113154151A (en) Pipeline connecting structure for municipal water supply and drainage
CN102561397B (en) Manhole for improving joint sealing performance
CN220704591U (en) Waterproof well
CN212772713U (en) Inspection well chamber
CN220888882U (en) Inspection shaft transitional coupling structure
CN220080102U (en) Concrete pipe inspection well
CN201129585Y (en) Bidirectional socket pipe parts
CN219453073U (en) Bolt connection type concrete rectangular jacking pipe
CN215060216U (en) Reinforced concrete rigid socket pipe
CN217679260U (en) Rectangular waterproof pipe joint
CN211976145U (en) Drainage pipe for municipal works
CN218468451U (en) Municipal administration water supply and drainage pipeline connection structure
CN217927568U (en) Pre-buried positioning sleeve of electrical equipment installation engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant