CN220014517U - Auxiliary positioning device for installation of building steel girder - Google Patents

Auxiliary positioning device for installation of building steel girder Download PDF

Info

Publication number
CN220014517U
CN220014517U CN202321322549.3U CN202321322549U CN220014517U CN 220014517 U CN220014517 U CN 220014517U CN 202321322549 U CN202321322549 U CN 202321322549U CN 220014517 U CN220014517 U CN 220014517U
Authority
CN
China
Prior art keywords
building
adjusting
mounting bracket
girder steel
steel beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321322549.3U
Other languages
Chinese (zh)
Inventor
付祥辉
付志辉
晏小梅
付婷成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Nanbo Construction Engineering Co ltd
Original Assignee
Hunan Nanbo Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Nanbo Construction Engineering Co ltd filed Critical Hunan Nanbo Construction Engineering Co ltd
Priority to CN202321322549.3U priority Critical patent/CN220014517U/en
Application granted granted Critical
Publication of CN220014517U publication Critical patent/CN220014517U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to the technical field of building steel beam installation tools, and discloses an auxiliary positioning device for building steel beam installation, which comprises a first building steel beam body and a second building steel beam body, wherein a first installation frame and a second installation frame are arranged at the tops of the first building steel beam body and the second building steel beam body, an adjusting mechanism for adjusting the distance between the first installation frame and the second installation frame is arranged between two groups of limiting rods on the surface of one side of the first installation frame opposite to the surface of the second installation frame, and two groups of lifting mechanisms for aligning the first building steel beam body with the second building steel beam body are symmetrically arranged on the first installation frame and the second installation frame. This building girder steel installation is with auxiliary positioning device has solved in prior art, still needs the workman to strike the girder steel calibration by hand when controlling the alignment to two girder steel, can cause the impaired problem of girder steel when wasting time and energy.

Description

Auxiliary positioning device for installation of building steel girder
Technical Field
The utility model relates to the technical field of building steel girder installation tools, in particular to an auxiliary positioning device for building steel girder installation.
Background
The steel beam is a long steel with an I-shaped section, is divided into three types of common I-steel, light I-steel and H-steel, and is widely used for various building structures, bridges, vehicles, supports, machinery and the like.
In the prior art, when the butt joint of the steel beams is needed between the welding steel beams fixedly installed on the upright posts, the hoisting steel beams are required to be hoisted to the air by using a crane, and after the welding steel beams are manually aligned with the hoisting steel beams, the welding fixation is performed again, and when the two steel beams are horizontally aligned, the steel beam calibration is still needed to be manually knocked by a worker, so that the steel beams are damaged while time and labor are wasted.
Disclosure of Invention
(one) solving the technical problems
Aiming at the defects of the prior art, the utility model provides an auxiliary positioning device for mounting a building steel beam, which has the advantages of applicability to steel beams of different specifications and convenient operation, and solves the problems that in the prior art, when the steel beams are needed to be butted between welding steel beams fixedly mounted on an upright post, a crane is needed to be used for hanging a hoisting steel beam into the air, and after the welding steel beam is manually aligned with the hoisting steel beam, the welding fixation is performed, and when the two steel beams are horizontally aligned, a worker still needs to manually knock the steel beam for calibration, which is time-consuming and labor-consuming and causes damage to the steel beam.
(II) technical scheme
The technical scheme for solving the technical problems is as follows: the utility model provides an auxiliary positioning device is used in installation of building girder steel, includes first building girder steel body and the second building girder steel body that need dock, the top of first building girder steel body and second building girder steel body is provided with first mounting bracket and second mounting bracket, one side surface that first mounting bracket and second mounting bracket are relative is connected with the gag lever post, one side surface that first mounting bracket and second mounting bracket are relative just is located and is provided with the adjustment mechanism who is used for adjusting interval between first mounting bracket and the second mounting bracket between two sets of gag lever posts, equal symmetry installs two sets of lifting mechanism that are used for first building girder steel body and second building girder steel body alignment on first mounting bracket and the second mounting bracket.
Preferably, the adjusting mechanism comprises two groups of fixing plates symmetrically arranged on the first mounting frame and the second mounting frame, two groups of fixing plates are connected with adjusting screws on the surfaces of one sides opposite to the fixing plates, nuts are arranged on the surfaces of each group of adjusting screws in a threaded mode, adjusting frames are fixedly arranged on the outer surfaces of the nuts, and two groups of handles are symmetrically arranged on the surfaces of the adjusting frames.
Preferably, one end of the adjusting screw is installed on the surface of the fixing plate, and the other end of the adjusting screw penetrates through the nut and extends to the inside of the adjusting frame.
Preferably, the lifting mechanism comprises a plurality of groups of fastening screws which are arranged in the first installation frame and the second installation frame in a threaded manner, each group of fastening screws are fixedly provided with an adjusting knob at the top end, positioning rods are movably connected in the first installation frame and the second installation frame, and the bottom ends of the fastening screws are connected with locking plates.
Preferably, the bottom of the fastening screw rod is connected with the locking plate through a swivel mount, and the bottom of the positioning rod is arranged on the surface of the locking plate.
The beneficial effects of the utility model are as follows:
1) This building girder steel installation is with auxiliary positioning device, in the use, place the device in the concatenation department of first building girder steel body and second building girder steel body, rotate the handle afterwards and make it drive the alignment jig and rotate, at this moment two sets of adjusting screw remove towards relative or opposite direction to drive first mounting bracket and second mounting bracket and remove towards both sides through the fixed plate, make the device can use the building girder steel of different size specifications, application scope is wider.
2) After the distance between the first mounting frame and the second mounting frame is adjusted, the adjusting knob is rotated to drive the fastening screw to rotate, so that the fastening screw drives the locking plate to clamp on the surface of the steel beam, the overall stability of the device can be guaranteed, whether the joint of the first building steel beam body and the second building steel beam body is horizontal or not is observed, if the end of the first building steel beam body is higher than the second building steel beam body, the adjusting knob on the second building steel beam body is only required to be rotated to drive the end of the second building steel beam body to rise and align with the first building steel beam body through the locking plate, otherwise, the adjusting knob on the first building steel beam body is rotated, so that the steel beam can be conveniently aligned, and meanwhile, the trouble of knocking the steel beam is also omitted.
Drawings
FIG. 1 is a schematic view of the mounting structure of the present utility model;
FIG. 2 is a top view of the present utility model;
FIG. 3 is a side view of the present utility model;
fig. 4 is a bottom view of the present utility model.
In the figure: 1. a first building steel girder body; 2. a second building steel girder body; 3. a first mounting frame; 4. a second mounting frame; 5. a limit rod; 6. an adjusting mechanism; 601. a fixing plate; 602. adjusting a screw; 603. a nut; 604. an adjusting frame; 605. a handle; 7. a lifting mechanism; 701. fastening a screw; 702. an adjustment knob; 703. a positioning rod; 704. and a locking plate.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
1-4, an auxiliary positioning device for mounting a building steel beam comprises a first building steel beam body 1 and a second building steel beam body 2 which need to be in butt joint, wherein a first mounting frame 3 and a second mounting frame 4 are arranged at the top of the first building steel beam body 1 and the second building steel beam body 2, a limiting rod 5 is connected to one side surface of the first mounting frame 3 opposite to the second mounting frame 4, and an adjusting mechanism 6 for adjusting the distance between the first mounting frame 3 and the second mounting frame 4 is arranged between the two groups of limiting rods 5 on one side surface of the first mounting frame 3 opposite to the second mounting frame 4;
the adjusting mechanism 6 comprises two groups of fixing plates 601 symmetrically arranged on the first mounting frame 3 and the second mounting frame 4, adjusting screws 602 are connected to the surfaces of one opposite sides of the two groups of fixing plates 601, nuts 603 are arranged on the surfaces of the adjusting screws 602 in a threaded mode, adjusting frames 604 are fixedly arranged on the outer surfaces of the two groups of nuts 603, and two groups of handles 605 are symmetrically arranged on the surfaces of the adjusting frames 604.
Specifically, one end of the adjusting screw 602 is mounted on the surface of the fixing plate 601, the other end penetrates the nut 603 and extends to the inside of the adjusting frame 604, and the structure is simple in structure and easy to operate while guaranteeing the stability of the first mounting frame 3 and the second mounting frame 4 in adjustment.
In the second embodiment, as shown in fig. 1 to 4, on the basis of the first embodiment, two groups of lifting mechanisms 7 for aligning the first building steel beam body 1 with the second building steel beam body 2 are symmetrically installed on the first installation frame 3 and the second installation frame 4, each lifting mechanism 7 comprises a plurality of groups of fastening screws 701 which are installed in the first installation frame 3 and the second installation frame 4 in a threaded manner, the top end of each group of fastening screws 701 is fixedly provided with an adjusting knob 702, positioning rods 703 are movably connected in the first installation frame 3 and the second installation frame 4, and the bottom end of each group of fastening screws 701 is connected with a locking plate 704.
Specifically, the bottom of fastening screw 701 is connected with locking plate 704 through the swivel mount, and the surface at locking plate 704 is installed to the bottom of locating lever 703, and this structure cooperation locating lever 703 through setting up can effectively prevent that locking plate 704 and fastening screw 701 from taking place to co-rotate.
Working principle: when the device is used, the device is placed at the splicing position of the first building steel girder body 1 and the second building steel girder body 2, then the handle 605 is rotated to enable the device to drive the adjusting frame 604 to rotate, at this time, two groups of adjusting screws 602 move towards opposite or opposite directions, and the first mounting frame 3 and the second mounting frame 4 are driven to move towards two sides through the fixing plate 601, so that the device can use building steel girders of different sizes, the application range is wider, after the spacing adjustment of the first mounting frame 3 and the second mounting frame 4 is completed, the adjusting knob 702 is rotated to drive the fastening screw 701 to rotate, the locking plate 704 is driven to clamp the surface of the steel girders, the overall stability of the device can be ensured, then whether the joint of the first building steel girder body 1 and the second building steel girder body 2 is horizontal or not is observed, if the end of the first building steel girder body 1 is higher than the second building steel girder body 2, at this time, the adjusting knob 702 positioned on the second building steel girder body 2 is driven to rise through the locking plate 704 and is aligned with the first building steel girder body 1, otherwise, the adjusting knob 702 on the first building steel girder body 1 is rotated, the whole device can be conveniently knocked.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, the element defined by the phrase "comprising one … …" does not exclude the presence of other identical elements in a process, method, article or apparatus that comprises the element, while the terms "left", "right", "top" and "bottom" as used herein refer to the elements as placed in fig. 1. The terms "front" and "rear" as used herein refer to the operator facing the dispensing device, being closer to the operator than the operator, and farther from the operator than the operator.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides an auxiliary positioning device is used in installation of building girder steel, includes first building girder steel body (1) and second building girder steel body (2) that need dock, its characterized in that: the utility model discloses a building girder steel body, including first building girder steel body (1), second building girder steel body (2), first mounting bracket (3) and second mounting bracket (4) are provided with at the top of first building girder steel body (1), one side surface that first mounting bracket (3) are relative with second mounting bracket (4) is connected with gag lever post (5), one side surface that first mounting bracket (3) are relative with second mounting bracket (4) just is located between two sets of gag lever posts (5) and is provided with adjustment mechanism (6) that are used for adjusting interval between first mounting bracket (3) and second mounting bracket (4), equal symmetry installs on first mounting bracket (3) and second mounting bracket (4) two sets of lifting mechanism (7) that are used for first building girder steel body (1) and second building girder steel body (2) to aim at.
2. The auxiliary positioning device for mounting a building steel beam according to claim 1, wherein: the adjusting mechanism (6) comprises two groups of fixing plates (601) symmetrically arranged on the first mounting frame (3) and the second mounting frame (4), two groups of adjusting screws (602) are connected to the surfaces of one opposite sides of the fixing plates (601), nuts (603) are arranged on the surfaces of the adjusting screws (602) in a threaded mode, adjusting frames (604) are fixedly arranged on the outer surfaces of the nuts (603), and two groups of handles (605) are symmetrically arranged on the surfaces of the adjusting frames (604).
3. The auxiliary positioning device for mounting a building steel beam according to claim 2, wherein: one end of the adjusting screw (602) is arranged on the surface of the fixed plate (601), and the other end of the adjusting screw penetrates through the nut (603) and extends to the inside of the adjusting frame (604).
4. The auxiliary positioning device for mounting a building steel beam according to claim 1, wherein: the lifting mechanism (7) comprises a plurality of groups of fastening screws (701) which are arranged in a first installation frame (3) and a second installation frame (4) in a threaded mode, each group of fastening screws (701) are fixedly provided with adjusting knobs (702) at the top ends, positioning rods (703) are movably connected in the first installation frame (3) and the second installation frame (4), and each group of fastening screws (701) are connected with locking plates (704) at the bottom ends.
5. The auxiliary positioning device for mounting a building steel beam according to claim 4, wherein: the bottom end of the fastening screw (701) is connected with the locking plate (704) through a swivel mount, and the bottom end of the positioning rod (703) is arranged on the surface of the locking plate (704).
CN202321322549.3U 2023-05-29 2023-05-29 Auxiliary positioning device for installation of building steel girder Active CN220014517U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321322549.3U CN220014517U (en) 2023-05-29 2023-05-29 Auxiliary positioning device for installation of building steel girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321322549.3U CN220014517U (en) 2023-05-29 2023-05-29 Auxiliary positioning device for installation of building steel girder

Publications (1)

Publication Number Publication Date
CN220014517U true CN220014517U (en) 2023-11-14

Family

ID=88679350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321322549.3U Active CN220014517U (en) 2023-05-29 2023-05-29 Auxiliary positioning device for installation of building steel girder

Country Status (1)

Country Link
CN (1) CN220014517U (en)

Similar Documents

Publication Publication Date Title
CN208347302U (en) The high-supported formwork structure integrally formed for concrete frame floor and beam
CN210031518U (en) Cable-stayed bridge cable guide pipe installation positioning device
CN220014517U (en) Auxiliary positioning device for installation of building steel girder
CN210031519U (en) Adjustable bridge construction strutting arrangement
CN112091535B (en) Processing method of curved curtain wall plate
CN111379222A (en) Multi-section type prefabricated box girder transportation and hydraulic installation equipment
CN215858982U (en) Follow-on corner support of encorbelmenting
CN211219393U (en) Clamp for welding reinforcing steel bar column
CN109304591B (en) Comb plate assembly tooling structure of escalator
CN220747727U (en) Butt joint positioning device for steel beam installation
CN112962945A (en) Corner bracket structure and construction method
CN220592060U (en) Bridge bracket arm mounting die
CN112031419A (en) Box girder mounting bracket and mounting and using method thereof
CN215756015U (en) Positioning fixture for segment beam hoisting hole
CN212652950U (en) Welding fixture
CN221247517U (en) Diaphragm plate assembly fixture
CN216283536U (en) Measuring device for building structure engineering
CN216713886U (en) Large-scale stand docks supplementary calibration tool
CN211499849U (en) Prefabricated plate construction locating rack
CN214195616U (en) Guardrail base reinforcing bar location rack
CN220202470U (en) Positioning device for erecting steel box girder
CN220029162U (en) Beam welding auxiliary fixture
CN213615024U (en) Welding positioning device for steel structure light steel supporting beam
CN218405084U (en) High-speed railway bridge protection wall installation device
CN221236319U (en) Externally hung wallboard unsupported self-adjusting high-precision equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant