CN219826138U - Floor post-pouring construction structure - Google Patents
Floor post-pouring construction structure Download PDFInfo
- Publication number
- CN219826138U CN219826138U CN202320979535.2U CN202320979535U CN219826138U CN 219826138 U CN219826138 U CN 219826138U CN 202320979535 U CN202320979535 U CN 202320979535U CN 219826138 U CN219826138 U CN 219826138U
- Authority
- CN
- China
- Prior art keywords
- beam structure
- pipe
- steel bars
- floor
- pipe fitting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 24
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 34
- 239000010959 steel Substances 0.000 claims abstract description 34
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims abstract description 13
- 239000003292 glue Substances 0.000 claims description 10
- 238000009434 installation Methods 0.000 abstract description 5
- 238000002513 implantation Methods 0.000 abstract description 3
- 238000009435 building construction Methods 0.000 abstract description 2
- 230000007547 defect Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000001788 irregular Effects 0.000 description 2
- 238000013459 approach Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000002990 reinforced plastic Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model is applicable to the technical field of building construction, and provides a floor post-pouring construction structure, which comprises the following components: a beam structure; the number of the pipe fittings is several, the pipe fittings are distributed at intervals along the length direction of the beam structure, the central line of the pipe fittings is perpendicular to the length direction of the beam structure and embedded in the beam structure, and at least one end of each pipe fitting extends to the surface of the beam structure; the steel bars penetrate into the pipe fitting after the beam structure is finished and before the floor slab is poured. Before the beam structure is poured, the utility model does not need to pre-embed reinforcing steel bars, thereby avoiding potential safety hazards caused by exposing the reinforcing steel bars outside, or increases construction operation for avoiding the beam template installation to bend the reinforcing steel bars before the beam structure is constructed, or does not damage the concrete layer of the beam structure to cause unreliable quality due to the implantation of the reinforcing steel bars before the floor slab is poured.
Description
Technical Field
The utility model belongs to the technical field of building construction, and particularly relates to a floor post-pouring construction structure.
Background
Part of the floor slabs need to be poured for the second time due to building functions or construction reasons, namely beams and the floor slabs are separately constructed, and the Liang Zaijiao floor slabs are poured first, so that floor slab reinforcing steel bars need to be reserved on the peripheral beams. There are generally two approaches: the first is reserved steel bars, which have the defects that the reserved steel bars can be bent when the beam is poured, and the steel bars are exposed outside in the early use process, so that potential safety hazards are caused. The second is the post-planting bar, which has the defects of complicated on-site drilling operation, damage to the poured concrete beam, unreliable quality, and time and labor consumption because the bearing capacity is determined by experiments.
Disclosure of Invention
The utility model provides a floor post-pouring construction structure, which aims to solve the problems of potential safety hazard caused by exposed reinforcing steel bars or unreliable quality caused by damage of post-planted reinforcing steel bars to a concrete beam when longitudinal post-pouring floor slabs are adopted in the prior art.
The utility model is realized in such a way that a floor post-pouring construction structure comprises:
a beam structure;
the number of the pipe fittings is several, the pipe fittings are distributed at intervals along the length direction of the beam structure, the central line of the pipe fittings is perpendicular to the length direction of the beam structure and embedded in the beam structure, and at least one end of each pipe fitting extends to the surface of the beam structure;
and the steel bars penetrate into the pipe fitting after the beam structure is finished and before the floor slab is poured.
Further, the spacing distance between two adjacent pipes is 200mm.
Further, the minimum diameter of the pipe fitting for the steel bar to penetrate is at least 2mm larger than the diameter of the steel bar.
Further, when only one end of the pipe extends to the surface of the beam structure, the inner wall of the pipe and the steel bars are prefilled by the planted bar glue.
Further, the inner wall surface of the pipe member has a height difference in a length direction thereof.
Further, the pipe fitting adopts a corrugated pipe.
Further, the diameter of the middle part of the pipe fitting is larger than the diameter of the two ends of the pipe fitting.
Further, the inner wall of the pipe fitting is provided with a plurality of protrusions and/or a plurality of concave parts along the length direction of the inner wall.
The utility model has the beneficial effects that the beam structure is provided with the installation space by adopting the pipe fitting pre-embedding mode, after the beam pouring is finished, the pipe fitting is internally provided with the channel through which the steel bars can penetrate, before the floor pouring is carried out, the steel bars are respectively penetrated with a plurality of pipe fittings so as to carry out pouring construction operation on the floor, before the beam structure is poured, the pre-embedding of the floor steel bars is not needed, the hidden safety hazards caused by the fact that the steel bars are exposed outside are avoided, or the construction operation is increased by installing the floor template for avoiding the steel bars to bend the steel bars before the beam structure is constructed, or the quality is unreliable caused by the fact that the concrete layer of the beam structure is not damaged by the implantation of the steel bars before the floor post-pouring.
Drawings
FIG. 1 is a schematic structural diagram of a floor slab post-pouring construction structure before pouring;
fig. 2 is a schematic structural diagram of a floor slab after pouring of the floor slab post-pouring construction structure provided by the utility model.
Reference numerals illustrate:
1. a beam structure; 2. a pipe fitting; 3. reinforcing steel bars; 10. and (3) floor slabs.
Detailed Description
The present utility model will be described in further detail with reference to the drawings and examples, in order to make the objects, technical solutions and advantages of the present utility model more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the utility model.
Referring to fig. 1-2, an embodiment of the present utility model provides a post-cast construction structure for a floor slab, which includes a beam structure 1, pipe members 2, and reinforcing steel bars 3. The number of the pipe fittings 2 is a plurality of pipe fittings 2 are distributed at intervals along the length direction of the beam structure 1 (the whole number of the pipe fittings 2 distributed on the beam structure 1 is not completely drawn in the figure), the central line of the pipe fittings 2 is perpendicular to the length direction of the beam structure 1 and buried in the beam structure 1, at least one end of each pipe fitting 2 extends to the surface of the beam structure 1, namely, the pipe fittings 2 can penetrate the beam structure 1 on one side or penetrate the beam structure 1 on two sides, specifically, when the beam structure 1 is positioned around the building structure, the pipe fittings 2 penetrate the beam structure 1 on one side, when the beam structure 1 is positioned in the middle of the building structure, the pipe fittings 2 penetrate the beam structure 1 on two sides, and the reinforcing steel bars 3 penetrate the pipe fittings 2 after the beam structure 1 is finished and before pouring of the floor slab 10.
The beam structure 1 is provided with the installation space for the steel bars 3 by adopting the mode of embedding the pipe fittings 2, after beam pouring is completed, channels through which the steel bars 3 can penetrate are formed in the pipe fittings 2, and before floor 10 pouring is carried out, the steel bars 3 are respectively penetrated with a plurality of pipe fittings 2 so that the floor 10 can be subjected to pouring construction operation.
According to the floor post-pouring construction structure provided by the embodiment of the utility model, before the beam structure 1 is poured, the steel bars 3 are not needed to be embedded, so that potential safety hazards caused by the fact that the steel bars 3 are exposed outside are avoided, or the steel bars 3 are bent by avoiding the installation of a beam template before the beam structure 1 is constructed, or before the floor 10 is poured, the concrete layer of the beam structure 1 is not damaged by the implantation of the steel bars 3, so that the quality is unreliable, the operation is simple, and the safety and the reliability are realized.
Further, the distance between two adjacent pipe fittings 2 is 200mm. So can reasonable lay pipe fitting 2 quantity, both avoided pipe fitting 2 quantity too much to lead to producing the extravagant cost of material and increased, still avoided pipe fitting 2 quantity too little to lead to floor 10 to pour the poor problem of back intensity.
Further, the minimum diameter of the pipe fitting 2 for the steel bar 3 to penetrate is at least 2mm larger than the diameter of the steel bar 3. So, can smoothly pass through when guaranteeing that reinforcing bar 3 wears to establish pipe fitting 2 to improve installation effectiveness. The minimum diameter of penetration refers to the minimum diameter that needs to be met when the inside of the pipe fitting 2 is not a regular smooth plane, so as to ensure that the steel bar 3 can penetrate the pipe fitting 2.
Further, when only one end of the pipe fitting 2 extends to the surface of the beam structure 1, the inner wall of the pipe fitting 2 and the steel bars 3 are prefilled by the bar planting glue. Therefore, when the pipe fitting 2 penetrates through the beam structure 1 on one side, the inside of the gap of the pipe fitting 2 is prefilled by the planted bar glue, so that reliable connection between the steel bar 3 and the pipe fitting 2 is ensured, and the steel bar 3 is prevented from falling off from the pipe fitting 2.
When needing to be described, when the pipe fitting 2 penetrates the beam structure 1 from two sides, the beam structure 1 is positioned in the middle of the building structure, when the steel bar 3 penetrates the pipe fitting 2, two ends of the steel bar 3 also need to penetrate the single-side penetrating pipe fitting 2 positioned on the beam structure 1 around the building structure, so that the gap in the pipe fitting 2 of the beam structure 1 from two sides does not need to be pre-buried and fixed by the bar planting glue, and the construction efficiency is improved.
Further, the inner wall surface of the pipe member 2 has a height difference in the length direction thereof. The height difference refers to that the inside of the pipe fitting 2 is not in a regular smooth plane structure, but the inner wall is arranged in an irregular structure, so that when the gap of the pipe fitting 2 is embedded by the bar planting glue, the filling area of the bar planting glue can be increased, and an irregular shape can be generated after the bar planting glue is solidified, thereby improving the connection stability of the steel bar 3 and the pipe fitting 2.
In particular, the tube 2 may be a bellows. Therefore, after the bar planting glue is filled, the connection stability of the steel bar 3 and the pipe fitting 2 can be improved.
Furthermore, the diameter of the middle part of the tube 2 can be larger than the diameters of the two ends of the tube 2. In addition, a plurality of protrusions and/or a plurality of depressions may be provided on the inner wall of the pipe 2 along the length direction thereof. Therefore, by adopting the scheme, the connection stability of the steel bar 3 and the pipe fitting 2 can be improved after the reinforced plastic glue is filled.
The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the utility model.
Claims (8)
1. A floor post-cast construction structure, comprising:
a beam structure;
the number of the pipe fittings is several, the pipe fittings are distributed at intervals along the length direction of the beam structure, the central line of the pipe fittings is perpendicular to the length direction of the beam structure and embedded in the beam structure, and at least one end of each pipe fitting extends to the surface of the beam structure;
and the steel bars penetrate into the pipe fitting after the beam structure is finished and before the floor slab is poured.
2. A floor post-cast construction structure as defined in claim 1, wherein the spacing distance between two adjacent tubes is 200mm.
3. A floor post-cast construction structure as defined in claim 1, wherein the minimum diameter of the pipe through which the reinforcing steel bar is inserted is at least 2mm greater than the diameter of the reinforcing steel bar.
4. A floor post-cast construction structure according to any one of claims 1 to 3, wherein when only one end of the pipe extends to the surface of the beam structure, the pipe inner wall and the reinforcing steel bar are pre-filled with a bar planting glue.
5. A floor post-cast construction structure according to claim 4, wherein the inner wall surface of the pipe member has a height difference along the length direction thereof.
6. A floor post-cast construction structure according to claim 5, wherein the pipe member is a corrugated pipe.
7. A floor post-cast construction structure as defined in claim 5, wherein the diameter of the middle portion of the pipe is greater than the diameter of the two ends of the pipe.
8. The floor post-pouring construction structure according to claim 5, wherein the inner wall of the pipe is provided with a plurality of protrusions and/or a plurality of depressions along the length direction thereof.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202320979535.2U CN219826138U (en) | 2023-04-20 | 2023-04-20 | Floor post-pouring construction structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202320979535.2U CN219826138U (en) | 2023-04-20 | 2023-04-20 | Floor post-pouring construction structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN219826138U true CN219826138U (en) | 2023-10-13 |
Family
ID=88247481
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202320979535.2U Active CN219826138U (en) | 2023-04-20 | 2023-04-20 | Floor post-pouring construction structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN219826138U (en) |
-
2023
- 2023-04-20 CN CN202320979535.2U patent/CN219826138U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101603336B (en) | Precast concrete short-pier shear wall with infilling wall panel and connecting method thereof | |
CN103790265B (en) | A kind of prefabricated assembled steel tube concrete core pillar is put more energy into the making assembly method of shear wall | |
CN108104567B (en) | Concrete tower drum longitudinal joint connecting structure and method, prefabricating method of sheet body and concrete tower drum | |
CN104847014A (en) | Vertical connection structure for precast concrete shear walls and construction method | |
CN101672007A (en) | Constructing method of precast pier footing for bridge | |
CN207228617U (en) | A kind of concrete-pouring template float Structure for basement barricade single side formwork | |
CN109812620B (en) | Method for encapsulating one-time pouring large-caliber steel pipe concrete | |
CN113293802A (en) | Construction method of inspection well | |
CN112144509A (en) | Construction method of underground continuous wall, joint and connection structure thereof | |
CN219826138U (en) | Floor post-pouring construction structure | |
CN113700046A (en) | Basement structure antiseep bushing apparatus | |
CN111255163A (en) | A restraint steel pipe overlap joint structure for prefabricating vertical member | |
CN217713886U (en) | Comprehensive utilization platform in ultra-long distance small-diameter tunnel | |
JP2007262848A (en) | Laying method for pipe culvert | |
CN216787229U (en) | Basement outer wall post-cast strip assembled shutoff steel sheet structure | |
CN216108526U (en) | Underground continuous wall structure for foundation pit support | |
CN113373977A (en) | Basement exterior wall and construction method thereof | |
CN210238895U (en) | Hollow superstructure of no roof beam | |
CN205444570U (en) | Wallboard connected node | |
CN212453344U (en) | A restraint steel pipe overlap joint structure for prefabricating vertical member | |
KR20140110526A (en) | A fixing coupler used a burial slab of an outer wall of an underground construction and a burial slab construction method using it | |
CN209430248U (en) | A kind of buried Central drain discharge structure of novel tunnel | |
CN209260748U (en) | A kind of stepped tower crane | |
JP4869363B2 (en) | Pipe laying method | |
CN221072722U (en) | Underground utility tunnel connection structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |