CN219826138U - Floor post-pouring construction structure - Google Patents

Floor post-pouring construction structure Download PDF

Info

Publication number
CN219826138U
CN219826138U CN202320979535.2U CN202320979535U CN219826138U CN 219826138 U CN219826138 U CN 219826138U CN 202320979535 U CN202320979535 U CN 202320979535U CN 219826138 U CN219826138 U CN 219826138U
Authority
CN
China
Prior art keywords
beam structure
pipe
steel bars
floor
pipe fitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320979535.2U
Other languages
Chinese (zh)
Inventor
苗晓飞
董玉柱
曹廷
雷军
刘斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Shenzhen Co ltd Of China Construction Fifth Engineering Bureau
Original Assignee
Third Construction Shenzhen Co ltd Of China Construction Fifth Engineering Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Shenzhen Co ltd Of China Construction Fifth Engineering Bureau filed Critical Third Construction Shenzhen Co ltd Of China Construction Fifth Engineering Bureau
Priority to CN202320979535.2U priority Critical patent/CN219826138U/en
Application granted granted Critical
Publication of CN219826138U publication Critical patent/CN219826138U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model is applicable to the technical field of building construction, and provides a floor post-pouring construction structure, which comprises the following components: a beam structure; the number of the pipe fittings is several, the pipe fittings are distributed at intervals along the length direction of the beam structure, the central line of the pipe fittings is perpendicular to the length direction of the beam structure and embedded in the beam structure, and at least one end of each pipe fitting extends to the surface of the beam structure; the steel bars penetrate into the pipe fitting after the beam structure is finished and before the floor slab is poured. Before the beam structure is poured, the utility model does not need to pre-embed reinforcing steel bars, thereby avoiding potential safety hazards caused by exposing the reinforcing steel bars outside, or increases construction operation for avoiding the beam template installation to bend the reinforcing steel bars before the beam structure is constructed, or does not damage the concrete layer of the beam structure to cause unreliable quality due to the implantation of the reinforcing steel bars before the floor slab is poured.

Description

Floor post-pouring construction structure
Technical Field
The utility model belongs to the technical field of building construction, and particularly relates to a floor post-pouring construction structure.
Background
Part of the floor slabs need to be poured for the second time due to building functions or construction reasons, namely beams and the floor slabs are separately constructed, and the Liang Zaijiao floor slabs are poured first, so that floor slab reinforcing steel bars need to be reserved on the peripheral beams. There are generally two approaches: the first is reserved steel bars, which have the defects that the reserved steel bars can be bent when the beam is poured, and the steel bars are exposed outside in the early use process, so that potential safety hazards are caused. The second is the post-planting bar, which has the defects of complicated on-site drilling operation, damage to the poured concrete beam, unreliable quality, and time and labor consumption because the bearing capacity is determined by experiments.
Disclosure of Invention
The utility model provides a floor post-pouring construction structure, which aims to solve the problems of potential safety hazard caused by exposed reinforcing steel bars or unreliable quality caused by damage of post-planted reinforcing steel bars to a concrete beam when longitudinal post-pouring floor slabs are adopted in the prior art.
The utility model is realized in such a way that a floor post-pouring construction structure comprises:
a beam structure;
the number of the pipe fittings is several, the pipe fittings are distributed at intervals along the length direction of the beam structure, the central line of the pipe fittings is perpendicular to the length direction of the beam structure and embedded in the beam structure, and at least one end of each pipe fitting extends to the surface of the beam structure;
and the steel bars penetrate into the pipe fitting after the beam structure is finished and before the floor slab is poured.
Further, the spacing distance between two adjacent pipes is 200mm.
Further, the minimum diameter of the pipe fitting for the steel bar to penetrate is at least 2mm larger than the diameter of the steel bar.
Further, when only one end of the pipe extends to the surface of the beam structure, the inner wall of the pipe and the steel bars are prefilled by the planted bar glue.
Further, the inner wall surface of the pipe member has a height difference in a length direction thereof.
Further, the pipe fitting adopts a corrugated pipe.
Further, the diameter of the middle part of the pipe fitting is larger than the diameter of the two ends of the pipe fitting.
Further, the inner wall of the pipe fitting is provided with a plurality of protrusions and/or a plurality of concave parts along the length direction of the inner wall.
The utility model has the beneficial effects that the beam structure is provided with the installation space by adopting the pipe fitting pre-embedding mode, after the beam pouring is finished, the pipe fitting is internally provided with the channel through which the steel bars can penetrate, before the floor pouring is carried out, the steel bars are respectively penetrated with a plurality of pipe fittings so as to carry out pouring construction operation on the floor, before the beam structure is poured, the pre-embedding of the floor steel bars is not needed, the hidden safety hazards caused by the fact that the steel bars are exposed outside are avoided, or the construction operation is increased by installing the floor template for avoiding the steel bars to bend the steel bars before the beam structure is constructed, or the quality is unreliable caused by the fact that the concrete layer of the beam structure is not damaged by the implantation of the steel bars before the floor post-pouring.
Drawings
FIG. 1 is a schematic structural diagram of a floor slab post-pouring construction structure before pouring;
fig. 2 is a schematic structural diagram of a floor slab after pouring of the floor slab post-pouring construction structure provided by the utility model.
Reference numerals illustrate:
1. a beam structure; 2. a pipe fitting; 3. reinforcing steel bars; 10. and (3) floor slabs.
Detailed Description
The present utility model will be described in further detail with reference to the drawings and examples, in order to make the objects, technical solutions and advantages of the present utility model more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the utility model.
Referring to fig. 1-2, an embodiment of the present utility model provides a post-cast construction structure for a floor slab, which includes a beam structure 1, pipe members 2, and reinforcing steel bars 3. The number of the pipe fittings 2 is a plurality of pipe fittings 2 are distributed at intervals along the length direction of the beam structure 1 (the whole number of the pipe fittings 2 distributed on the beam structure 1 is not completely drawn in the figure), the central line of the pipe fittings 2 is perpendicular to the length direction of the beam structure 1 and buried in the beam structure 1, at least one end of each pipe fitting 2 extends to the surface of the beam structure 1, namely, the pipe fittings 2 can penetrate the beam structure 1 on one side or penetrate the beam structure 1 on two sides, specifically, when the beam structure 1 is positioned around the building structure, the pipe fittings 2 penetrate the beam structure 1 on one side, when the beam structure 1 is positioned in the middle of the building structure, the pipe fittings 2 penetrate the beam structure 1 on two sides, and the reinforcing steel bars 3 penetrate the pipe fittings 2 after the beam structure 1 is finished and before pouring of the floor slab 10.
The beam structure 1 is provided with the installation space for the steel bars 3 by adopting the mode of embedding the pipe fittings 2, after beam pouring is completed, channels through which the steel bars 3 can penetrate are formed in the pipe fittings 2, and before floor 10 pouring is carried out, the steel bars 3 are respectively penetrated with a plurality of pipe fittings 2 so that the floor 10 can be subjected to pouring construction operation.
According to the floor post-pouring construction structure provided by the embodiment of the utility model, before the beam structure 1 is poured, the steel bars 3 are not needed to be embedded, so that potential safety hazards caused by the fact that the steel bars 3 are exposed outside are avoided, or the steel bars 3 are bent by avoiding the installation of a beam template before the beam structure 1 is constructed, or before the floor 10 is poured, the concrete layer of the beam structure 1 is not damaged by the implantation of the steel bars 3, so that the quality is unreliable, the operation is simple, and the safety and the reliability are realized.
Further, the distance between two adjacent pipe fittings 2 is 200mm. So can reasonable lay pipe fitting 2 quantity, both avoided pipe fitting 2 quantity too much to lead to producing the extravagant cost of material and increased, still avoided pipe fitting 2 quantity too little to lead to floor 10 to pour the poor problem of back intensity.
Further, the minimum diameter of the pipe fitting 2 for the steel bar 3 to penetrate is at least 2mm larger than the diameter of the steel bar 3. So, can smoothly pass through when guaranteeing that reinforcing bar 3 wears to establish pipe fitting 2 to improve installation effectiveness. The minimum diameter of penetration refers to the minimum diameter that needs to be met when the inside of the pipe fitting 2 is not a regular smooth plane, so as to ensure that the steel bar 3 can penetrate the pipe fitting 2.
Further, when only one end of the pipe fitting 2 extends to the surface of the beam structure 1, the inner wall of the pipe fitting 2 and the steel bars 3 are prefilled by the bar planting glue. Therefore, when the pipe fitting 2 penetrates through the beam structure 1 on one side, the inside of the gap of the pipe fitting 2 is prefilled by the planted bar glue, so that reliable connection between the steel bar 3 and the pipe fitting 2 is ensured, and the steel bar 3 is prevented from falling off from the pipe fitting 2.
When needing to be described, when the pipe fitting 2 penetrates the beam structure 1 from two sides, the beam structure 1 is positioned in the middle of the building structure, when the steel bar 3 penetrates the pipe fitting 2, two ends of the steel bar 3 also need to penetrate the single-side penetrating pipe fitting 2 positioned on the beam structure 1 around the building structure, so that the gap in the pipe fitting 2 of the beam structure 1 from two sides does not need to be pre-buried and fixed by the bar planting glue, and the construction efficiency is improved.
Further, the inner wall surface of the pipe member 2 has a height difference in the length direction thereof. The height difference refers to that the inside of the pipe fitting 2 is not in a regular smooth plane structure, but the inner wall is arranged in an irregular structure, so that when the gap of the pipe fitting 2 is embedded by the bar planting glue, the filling area of the bar planting glue can be increased, and an irregular shape can be generated after the bar planting glue is solidified, thereby improving the connection stability of the steel bar 3 and the pipe fitting 2.
In particular, the tube 2 may be a bellows. Therefore, after the bar planting glue is filled, the connection stability of the steel bar 3 and the pipe fitting 2 can be improved.
Furthermore, the diameter of the middle part of the tube 2 can be larger than the diameters of the two ends of the tube 2. In addition, a plurality of protrusions and/or a plurality of depressions may be provided on the inner wall of the pipe 2 along the length direction thereof. Therefore, by adopting the scheme, the connection stability of the steel bar 3 and the pipe fitting 2 can be improved after the reinforced plastic glue is filled.
The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the utility model.

Claims (8)

1. A floor post-cast construction structure, comprising:
a beam structure;
the number of the pipe fittings is several, the pipe fittings are distributed at intervals along the length direction of the beam structure, the central line of the pipe fittings is perpendicular to the length direction of the beam structure and embedded in the beam structure, and at least one end of each pipe fitting extends to the surface of the beam structure;
and the steel bars penetrate into the pipe fitting after the beam structure is finished and before the floor slab is poured.
2. A floor post-cast construction structure as defined in claim 1, wherein the spacing distance between two adjacent tubes is 200mm.
3. A floor post-cast construction structure as defined in claim 1, wherein the minimum diameter of the pipe through which the reinforcing steel bar is inserted is at least 2mm greater than the diameter of the reinforcing steel bar.
4. A floor post-cast construction structure according to any one of claims 1 to 3, wherein when only one end of the pipe extends to the surface of the beam structure, the pipe inner wall and the reinforcing steel bar are pre-filled with a bar planting glue.
5. A floor post-cast construction structure according to claim 4, wherein the inner wall surface of the pipe member has a height difference along the length direction thereof.
6. A floor post-cast construction structure according to claim 5, wherein the pipe member is a corrugated pipe.
7. A floor post-cast construction structure as defined in claim 5, wherein the diameter of the middle portion of the pipe is greater than the diameter of the two ends of the pipe.
8. The floor post-pouring construction structure according to claim 5, wherein the inner wall of the pipe is provided with a plurality of protrusions and/or a plurality of depressions along the length direction thereof.
CN202320979535.2U 2023-04-20 2023-04-20 Floor post-pouring construction structure Active CN219826138U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320979535.2U CN219826138U (en) 2023-04-20 2023-04-20 Floor post-pouring construction structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320979535.2U CN219826138U (en) 2023-04-20 2023-04-20 Floor post-pouring construction structure

Publications (1)

Publication Number Publication Date
CN219826138U true CN219826138U (en) 2023-10-13

Family

ID=88247481

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320979535.2U Active CN219826138U (en) 2023-04-20 2023-04-20 Floor post-pouring construction structure

Country Status (1)

Country Link
CN (1) CN219826138U (en)

Similar Documents

Publication Publication Date Title
CN101603336B (en) Precast concrete short-pier shear wall with infilling wall panel and connecting method thereof
CN103790265B (en) A kind of prefabricated assembled steel tube concrete core pillar is put more energy into the making assembly method of shear wall
CN108104567B (en) Concrete tower drum longitudinal joint connecting structure and method, prefabricating method of sheet body and concrete tower drum
CN104847014A (en) Vertical connection structure for precast concrete shear walls and construction method
CN101672007A (en) Constructing method of precast pier footing for bridge
CN207228617U (en) A kind of concrete-pouring template float Structure for basement barricade single side formwork
CN109812620B (en) Method for encapsulating one-time pouring large-caliber steel pipe concrete
CN113293802A (en) Construction method of inspection well
CN112144509A (en) Construction method of underground continuous wall, joint and connection structure thereof
CN219826138U (en) Floor post-pouring construction structure
CN113700046A (en) Basement structure antiseep bushing apparatus
CN111255163A (en) A restraint steel pipe overlap joint structure for prefabricating vertical member
CN217713886U (en) Comprehensive utilization platform in ultra-long distance small-diameter tunnel
JP2007262848A (en) Laying method for pipe culvert
CN216787229U (en) Basement outer wall post-cast strip assembled shutoff steel sheet structure
CN216108526U (en) Underground continuous wall structure for foundation pit support
CN113373977A (en) Basement exterior wall and construction method thereof
CN210238895U (en) Hollow superstructure of no roof beam
CN205444570U (en) Wallboard connected node
CN212453344U (en) A restraint steel pipe overlap joint structure for prefabricating vertical member
KR20140110526A (en) A fixing coupler used a burial slab of an outer wall of an underground construction and a burial slab construction method using it
CN209430248U (en) A kind of buried Central drain discharge structure of novel tunnel
CN209260748U (en) A kind of stepped tower crane
JP4869363B2 (en) Pipe laying method
CN221072722U (en) Underground utility tunnel connection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant