CN219672091U - Scaffold upright rod switching device - Google Patents

Scaffold upright rod switching device Download PDF

Info

Publication number
CN219672091U
CN219672091U CN202321127001.3U CN202321127001U CN219672091U CN 219672091 U CN219672091 U CN 219672091U CN 202321127001 U CN202321127001 U CN 202321127001U CN 219672091 U CN219672091 U CN 219672091U
Authority
CN
China
Prior art keywords
wall
shaped steel
switching device
holes
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321127001.3U
Other languages
Chinese (zh)
Inventor
郭春荣
赵金兴
张兴俊
侍相福
薛俊豪
周谋韬
赵尚君
汪于翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Technology Construction Co Ltd
Original Assignee
China Construction Eighth Engineering Division Technology Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Technology Construction Co Ltd filed Critical China Construction Eighth Engineering Division Technology Construction Co Ltd
Application granted granted Critical
Publication of CN219672091U publication Critical patent/CN219672091U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/10Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
    • Y02A40/25Greenhouse technology, e.g. cooling systems therefor

Landscapes

  • Ladders (AREA)

Abstract

The utility model relates to the technical field of scaffolds, in particular to a scaffold upright rod switching device which comprises glass steps and a switching mechanism, wherein the switching mechanism comprises U-shaped steel and an upright rod, first through holes distributed equidistantly are formed in the outer wall of one end of the U-shaped steel, a fixed plate is slidably connected to the outer wall of one end of the U-shaped steel, second through holes distributed equidistantly are formed in the outer wall of the bottom of the fixed plate, the second through holes are matched with the first through holes, and the upright rod is arranged on the outer wall of one end of the corresponding fixed plate.

Description

Scaffold upright rod switching device
Technical Field
The utility model relates to the technical field of scaffolds, in particular to a scaffold upright rod switching device.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is carried out smoothly, is used for external walls, interior decoration or places with higher storey heights and cannot be constructed directly, and has wide application prospect. The scaffold is erected on a flat ground generally, but when the scaffold is required to be erected in interior decoration, part of the building needs to be dismantled due to complex building structure or shielding of other decorative components, and the scaffold is restored after being used, so that the working procedure and the engineering cost are increased, and unnecessary waste is caused. For example, when the height of the two floors is too high, a scaffold needs to be erected, and the glass stairs leading to the two floors are positioned below the two floors of suspended ceilings, the glass stairs need to be dismantled to meet the requirement of scaffold erection.
Disclosure of Invention
The utility model aims to provide a scaffold upright rod switching device which is used for solving the problems in the background technology.
The technical scheme of the utility model is as follows: the utility model provides a scaffold frame upright pole switching device, includes glass step and switching mechanism, switching mechanism includes U-shaped steel and pole setting.
Preferably, the outer wall of one end of the U-shaped steel is provided with first through holes which are distributed equidistantly.
Preferably, the outer wall of one end of the U-shaped steel is slidably connected with a fixing plate, second through holes distributed at equal distances are formed in the outer wall of the bottom of the fixing plate, the second through holes are matched with the first through holes, and the upright rods are arranged on the outer wall of one end of the corresponding fixing plate.
Preferably, the first through hole and the corresponding second through hole are internally and slidably connected with the same fixing screw, and the circumferential outer wall of the fixing screw is rotationally connected with a fixing nut through threads.
Preferably, two fixing holes are formed in two sides of the outer wall of the top of the U-shaped steel, and the inner walls of the fixing holes opposite to the U-shaped steel are connected with the same fastening screw in a sliding mode.
Preferably, the circumferential outer wall of the fastening screw is rotationally connected with a fastening nut through threads.
The utility model provides a scaffold vertical rod switching device through improvement, which has the following improvement and advantages compared with the prior art:
the scaffold upright rod switching device can be installed on the glass pedal in a non-contact manner, so that the upright rod avoids the glass pedal and can safely erect the scaffold, the glass pedal is not required to be dismantled, the working procedures are reduced, the construction period is shortened, and the resources are saved.
Drawings
The utility model is further explained below with reference to the drawings and examples:
FIG. 1 is a schematic diagram of the front view of the present utility model;
FIG. 2 is a schematic view of the U-shaped steel structure of the present utility model;
FIG. 3 is a schematic view of the structure of the pole and mounting plate of the present utility model;
fig. 4 is a schematic perspective view of the present utility model.
Reference numerals illustrate:
1. u-shaped steel; 2. fastening a screw; 3. a fastening nut; 4. a vertical rod; 5. a fixing plate; 6. glass steps; 7. a first through hole.
Detailed Description
The following detailed description of the present utility model clearly and fully describes the technical solutions of the embodiments of the present utility model, and it is apparent that the described embodiments are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
The utility model provides a scaffold upright rod switching device through improvement, which comprises the following technical scheme:
as shown in fig. 1-4, the scaffold upright rod switching device comprises a glass step 6 and a switching mechanism, wherein the switching mechanism comprises a U-shaped steel 1 and an upright rod 4,U, the U-shaped steel 1 can slide on the outer wall of the glass step 6, and the upright rod 4 is a cylindrical steel pipe column with the diameter of 50mm and the wall thickness of 5 mm.
Further, the outer wall of one end of the U-shaped steel 1 is provided with first through holes 7 which are distributed equidistantly, and the U-shaped steel 1 is a U-shaped steel pipe column with the length of 300mm, the width of 400mm, the height of 75mm and the wall thickness of 10 mm.
Further, the outer wall of one end of the U-shaped steel 1 is slidably connected with a fixing plate 5, second through holes distributed at equal intervals are formed in the outer wall of the bottom of the fixing plate 5, the second through holes are matched with the first through holes 7, the vertical rods 4 are arranged on the outer wall of one end of the corresponding fixing plate 5, and the fixing plate 5 is a rectangular steel plate with the length of 200mm and the width of 200mm and the thickness of 10 mm.
Further, the first through hole 7 and the corresponding second through hole are connected with the same fixing screw in a sliding manner, the circumference outer wall of the fixing screw is connected with a fixing nut through screw threads in a rotating manner, and the fixing plate 5 can be installed on the U-shaped steel 1 through the fixing screw and the fixing nut.
Further, two fixing holes are formed in two sides of the outer wall of the top of the U-shaped steel 1, the inner walls of the corresponding fixing holes of the two U-shaped steel 1 are connected with the same fastening screw 2 in a sliding mode, and the two following U-shaped steel 1 can be conveniently fixed.
Further, the fastening screw 2 is connected with the fastening nut 3 through screw thread rotation on the circumference outer wall, can fix adjacent U-shaped steel 1 through fastening screw 2 and fastening nut 3 to fix pole setting 4 and fixed plate 5 on glass is stepped 6.
Working principle: the installation position of the switching mechanism of the vertical rod 4 is measured according to the position of the glass step 6, then the two U-shaped steel materials 1 are sleeved outside the glass step 6 to form a sleeve structure, the two U-shaped steel materials 1 are fixed outside the glass step 6 by using the fastening screw rod 2 and the fastening nut 3, and the fixing plate 5 provided with the vertical rod 4 is fixed on the outer wall of the U-shaped steel material 1 by the fixing screw rod and the fixing nut, so that a scaffold can be installed on the vertical column 4 without disassembling the glass step 6, the working procedures are reduced, the construction period is shortened, and resources are saved.

Claims (6)

1. The scaffold upright rod switching device comprises a glass step (6) and a switching mechanism, and is characterized in that the switching mechanism comprises U-shaped steel (1) and an upright rod (4).
2. The scaffold pole switching device of claim 1, wherein: the outer wall of one end of the U-shaped steel (1) is provided with first through holes (7) which are distributed equidistantly.
3. The scaffold pole switching device of claim 2, wherein: the U-shaped steel (1) one end outer wall sliding connection has fixed plate (5), and fixed plate (5) bottom outer wall has seted up the second through-hole that the equidistance distributes, and second through-hole and first through-hole (7) assorted, pole setting (4) are installed at corresponding fixed plate (5) one end outer wall.
4. A scaffold pole switching device according to claim 3, wherein: the first through holes (7) and the corresponding second through holes are internally connected with the same fixing screw in a sliding manner, and the circumferential outer wall of the fixing screw is connected with a fixing nut through screw threads in a rotating manner.
5. The scaffold pole switching device of claim 1, wherein: two fixing holes are formed in two sides of the outer wall of the top of the U-shaped steel (1), and the inner walls of the fixing holes opposite to the U-shaped steel (1) are connected with the same fastening screw (2) in a sliding mode.
6. The scaffold pole switching device of claim 5, wherein: the circumferential outer wall of the fastening screw rod (2) is rotationally connected with a fastening nut (3) through threads.
CN202321127001.3U 2022-09-29 2023-05-11 Scaffold upright rod switching device Active CN219672091U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202222593182 2022-09-29
CN2022225931820 2022-09-29

Publications (1)

Publication Number Publication Date
CN219672091U true CN219672091U (en) 2023-09-12

Family

ID=87893097

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321127001.3U Active CN219672091U (en) 2022-09-29 2023-05-11 Scaffold upright rod switching device

Country Status (1)

Country Link
CN (1) CN219672091U (en)

Similar Documents

Publication Publication Date Title
CN209924120U (en) Assembled light steel frame structure building system
CN106801510B (en) Early dismantling system for plastic template
CN110805257B (en) Flower basket overhanging type section steel bearing beam structure and construction method
CN108756241B (en) Device is established to shear force wall outside floor template of encorbelmenting
CN103352564B (en) Horizontal structure shuttering system and construction method
CN104963408A (en) Building structure and construction method thereof
CN211396814U (en) Steel frame factory building with stable connection of supporting beams and supporting columns
CN219672091U (en) Scaffold upright rod switching device
CN219732331U (en) Steel beam connecting device for assembled building
CN213509726U (en) Construction template adjustable support for construction
CN214117434U (en) Building structure convenient to installation
CN211775944U (en) Support arrangement for quicken installation of taking one's place of PC wall body
CN210369894U (en) Adjustable falling plate template support system of assembled
CN211548795U (en) Adapting template connection conversion structure for aluminum template construction
CN211499704U (en) External protection frame for construction of centering assembly type shear wall structure
CN204475514U (en) A kind of building structure
CN215716238U (en) Fire hose fixing frame for prefabricated steel structure residential building
CN220226367U (en) Detachable and adjustable post-cast strip independent support steel column
CN219034132U (en) Multilayer full-assembled building construction limb protection system
CN112727152B (en) Connection structure between construction stair and floor in deep basal pit
CN221296010U (en) Simple lifting installation tool for pipeline
CN216973717U (en) Beam column connection structure is built in room
CN210857975U (en) Fastener for scaffold tripod
CN219240952U (en) Steel structure framework of assembled building wall
CN216641052U (en) Keel structure with adjustable

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant