CN219604833U - Hanging basket for assembled building construction - Google Patents

Hanging basket for assembled building construction Download PDF

Info

Publication number
CN219604833U
CN219604833U CN202320791058.7U CN202320791058U CN219604833U CN 219604833 U CN219604833 U CN 219604833U CN 202320791058 U CN202320791058 U CN 202320791058U CN 219604833 U CN219604833 U CN 219604833U
Authority
CN
China
Prior art keywords
hanging basket
hanging
basket
plate
supporting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320791058.7U
Other languages
Chinese (zh)
Inventor
付春雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shiyan Chubang Engineering Construction Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202320791058.7U priority Critical patent/CN219604833U/en
Application granted granted Critical
Publication of CN219604833U publication Critical patent/CN219604833U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)

Abstract

The utility model discloses an assembled hanging basket for building construction, which comprises a hanging basket A, a hanging basket B, a hanging ring and hanging rings, and further comprises the following components: the eight positioning grooves are respectively formed in four corners at the top end of the hanging basket A and four corners at the bottom end of the hanging basket B; the lower support plates are sleeved at the bottom ends of the left side and the right side of the hanging basket A through concave cavities formed by the lower support plates; the upper support plates are sleeved at the bottom ends of the left side and the right side of the hanging basket B through concave cavities formed by the upper support plates and the lower support plates; the inserting plate is arranged at the bottom end of the upper supporting plate and is inserted into an inner cavity at the outer side of the top of the matched lower supporting plate; the two groups of through holes are respectively formed at the front end and the rear end of the outer side of the plugboard. This hanging flower basket for assembled building construction can realize double-deck hanging flower basket, and the workman of being convenient for can be simultaneously to the construction of two-layer building, improves work efficiency to distance between the adjustable double-deck hanging flower basket.

Description

Hanging basket for assembled building construction
Technical Field
The utility model relates to the technical field of assembly type building construction tools, in particular to a hanging basket for assembly type building construction.
Background
The assembled building is a novel building mode, the building is completed by prefabricating components in factories and then assembling in site, the building mode can save a great deal of time and cost, and can improve the quality and reliability of the building, in the assembled building, a tower crane is one of indispensable equipment, the prefabricated components can be helped to be detached from a truck and installed on the correct position of the building, an assembled building construction basket is a tool for high-altitude construction, a safe and reliable high-altitude operation environment can be provided, and the assembled building construction basket is one of indispensable important equipment in modern building construction;
however, the existing assembly type construction hanging basket is only one layer, so that workers can only construct one layer of a building, the working efficiency is low, the existing requirements cannot be met, and therefore, the double-layer and adjustable hanging basket for assembly type construction is provided for solving the problems.
Disclosure of Invention
The utility model aims to solve the technical problems that in the prior art, an assembled type construction hanging basket is only one layer, so that workers can only construct one layer by one layer, and the working efficiency is low.
In order to achieve the above purpose, the utility model adopts the following technical scheme: the utility model provides an assembled hanging flower basket for construction, includes hanging flower basket A, hanging flower basket B, link and rings, still includes: the eight positioning grooves are respectively formed in four corners at the top end of the hanging basket A and four corners at the bottom end of the hanging basket B; the lower support plates are sleeved at the bottom ends of the left side and the right side of the hanging basket A through concave cavities formed by the lower support plates; the upper support plates are sleeved at the bottom ends of the left side and the right side of the hanging basket B through concave cavities formed by the upper support plates and the lower support plates; the plugboard is arranged at the bottom end of the upper supporting board, is inserted into an inner cavity at the outer side of the top of the matched lower supporting board, and supports and fixes the hanging basket B above the hanging basket A under the cooperation of the lower supporting board, the upper supporting board and the plugboard; the two groups of through holes are respectively formed at the front end and the rear end of the outer side of the plugboard; the two bolts A are respectively inserted into the tops of the front end and the rear end of the outer side of the lower supporting plate, and the inner ends of the bolts A penetrate through holes in corresponding positions and extend out of the lower supporting plate; the nut is screwed at the inner end of the outer wall of the bolt A and is tightly attached to the inner side of the lower supporting plate, and under the action of the through hole, the bolt A and the nut, the inserting plate is locked and fixed in the lower supporting plate, so that the lower supporting plate and the upper supporting plate are fixedly connected, the height of the inserting plate and the upper supporting plate can be adjusted, and the distance between the hanging basket A and the hanging basket B can be adjusted; the eight locking mechanisms are respectively arranged at the front and rear ends of the inner sides of the top ends of the two lower supporting plates and the front and rear ends of the inner sides of the bottom ends of the two upper supporting plates, and can lock and fix the lower supporting plates and the upper supporting plates on the corresponding hanging basket A and hanging basket B under the cooperation of the locking mechanisms and the positioning grooves.
Compared with the prior art, the utility model has the beneficial effects that:
according to the utility model, the hanging basket B can be supported and fixed above the hanging basket A through the matching of the lower supporting plate, the upper supporting plate and the plugboard, the plugboard can be locked and fixed in the lower supporting plate through the matching of the through holes, the bolts A and the nuts, the lower supporting plate and the upper supporting plate are connected and fixed, and the lower supporting plate and the upper supporting plate can be locked and fixed on the corresponding hanging basket A and hanging basket B through the matching of the locking mechanism and the positioning groove, so that a double-layer hanging basket is realized, a worker can conveniently construct a two-layer building at the same time, and the working efficiency is improved;
according to the utility model, through the matching of the through holes, the bolts A and the nuts, the plugboards with different heights can be locked and adjusted, so that the distance between the hanging basket A and the hanging basket B can be adjusted according to the requirements.
Drawings
FIG. 1 is a schematic view of a front cross-sectional structure of the present utility model;
FIG. 2 is an enlarged schematic view of the structure shown at A in FIG. 1;
fig. 3 is a schematic left-hand cross-sectional view of the hollow block of fig. 2.
In the figure: 1. a hanging basket A; 2. a hanging basket B; 3. hanging rings; 4. a hanging ring; 5. a positioning groove; 6. a lower support plate; 7. an upper support plate; 8. inserting plate; 9. a through hole; 10. a bolt A; 11. a nut; 12. a hollow block; 13. a partition plate; 14. a positioning rod; 15. a spring; 16. a through port; 17. triangular blocks; 18. and a bolt B.
Detailed Description
The present utility model will be described in further detail with reference to the accompanying drawings.
The present embodiment is only for explanation of the present utility model and is not to be construed as limiting the present utility model, and modifications to the present embodiment may be made by those skilled in the art as required for the inventive contribution to the art after having read the present description, but are intended to be protected by the patent law within the scope of the present claims.
The utility model discloses a hanging basket for assembly type building construction, which solves the technical problems in the prior art, and has the following overall thought:
examples
See fig. 1, 2, 3; the hanging basket for the assembled building construction comprises a hanging basket A1, a hanging basket B2, hanging rings 3, hanging rings 4, positioning grooves 5, a lower supporting plate 6, an upper supporting plate 7, an inserting plate 8, through holes 9, bolts A10, nuts 11 and a locking mechanism, wherein the hanging basket A1 and the hanging basket B2 are made of light-weight high-strength aluminum alloy or steel, are light in weight, good in rigidity, corrosion-resistant and long in service life, meanwhile, ladders can be arranged on the front sides of the hanging basket A1 and the hanging basket B2, workers can conveniently enter the hanging basket B2 above, the working safety and convenience are improved, a plurality of hanging rings 3 are arranged on the tops of the front sides of the hanging baskets A1 and the hanging baskets B2, two hanging rings 4 are arranged on the left side and the right side of the top of the hanging basket B2, the hanging rings 3 are used for hanging safety ropes for workers, and eight positioning grooves 5 are respectively formed in four corners of the top of the hanging basket A1 and four corners of the bottom of the hanging basket B2 and are used for locking the lower supporting plate 6 and the upper supporting plate 7 in cooperation with the locking mechanism; two F-shaped lower support plates 6 are sleeved at the bottom ends of the left side and the right side of the hanging basket A1 through concave cavities formed by the lower support plates; the two F-shaped upper support plates 7 are sleeved at the bottom ends of the left side and the right side of the hanging basket B2 through concave cavities formed by the upper support plates; the plugboard 8 is arranged at the bottom end of the upper supporting board 7, the plugboard 8 is inserted into an inner cavity at the outer side of the top of the matched lower supporting board 6, the length and the thickness of the plugboard 8 are matched with the shape of the concave cavity of the lower supporting board 6 and the upper supporting board 7, so that the plugboard 8 is tightly and seamlessly matched with the lower supporting board 6 and the upper supporting board 7, and the hanging basket B2 is supported and fixed above the hanging basket A1 under the matching of the lower supporting board 6, the upper supporting board 7 and the plugboard 8; two groups of through holes 9 are respectively formed at the front end and the rear end of the outer side of the plugboard 8, and the number and the positions of the through holes 9 can be adjusted according to actual needs so as to realize locking and adjustment of the plugboards 8 with different heights; two bolts A10 are respectively inserted into the top parts of the front end and the rear end of the outer side of the lower support plate 6, and the inner ends of the bolts A10 penetrate through holes 9 at corresponding positions and extend out of the lower support plate 6; the nut 11 is screwed on the inner end of the outer wall of the bolt A10 and is tightly attached to the inner side of the lower supporting plate 6, the inserting plate 8 is locked and fixed in the lower supporting plate 6 under the action of the through hole 9, the bolt A10 and the nut 11, so that the lower supporting plate 6 and the upper supporting plate 7 are fixedly connected, the height adjustment of the inserting plate 8 and the upper supporting plate 7 can be realized, and the distance between the hanging basket A1 and the hanging basket B2 can be further adjusted; eight locking mechanisms are respectively arranged at the front and rear ends of the inner sides of the top ends of the two lower support plates 6 and the front and rear ends of the inner sides of the bottom ends of the two upper support plates 7, and can lock and fix the lower support plates 6 and the upper support plates 7 on the corresponding hanging basket A1 and hanging basket B2 under the cooperation of the locking mechanisms and the positioning grooves 5.
In specific implementation, two groups of ten through holes 9 are respectively formed in the front end and the rear end of the outer side of the plugboard 8, the number of each group of through holes 9 is five, and the through holes are arranged from top to bottom, so that bolts A10 are inserted into the tops of the front end and the rear end of the outer side of the lower support board 6, penetrate through the through holes 9 in corresponding positions and extend out of the lower support board 6, and the plugboard 8 is locked and fixed in the lower support board 6 through nuts 11.
During concrete implementation, the lower support plate 6 and the upper support plate 7 are of an F-shaped structure, the lower support plate 6 and the upper support plate are arranged up and down in opposite directions, the height of the lower support plate 6 is larger than that of the upper support plate 7, stable support is realized through the sleeving connection of the concave cavity and the connection of the plugboard 8, and the structure has the advantages of being simple in structure, easy to install and detach, high in adaptability and the like, and can be widely applied to the field of building construction.
In particular embodiments, the locking mechanism comprises: the eight hollow blocks 12 are respectively arranged at front and rear ends of the inner sides of the top ends of the two lower support plates 6 and front and rear ends of the inner sides of the bottom ends of the two upper support plates 7; the partition plate 13 is arranged at the upper middle part of the inner cavity of the hollow block 12 and divides the inner cavity into two parts; the T-shaped positioning rod 14 is inserted on the partition plate 13, the bottom of the positioning rod 14 penetrates through the lower support plate 6 to extend into the matched positioning groove 5, the top of the positioning rod 14 is positioned above the partition plate 13, and the lower support plate 6, the hanging basket A1 and the upper support plate 7 and the hanging basket B2 can be locked under the cooperation of the positioning rod 14 and the positioning groove 5; one end of each of the two springs 15 is clamped at the top end of the corresponding positioning rod 14, the other end of each of the two springs 15 is clamped at the top end of the inner cavity of the corresponding hollow block 12, the springs 15 are in a stretching state, and after the positioning rod 14 is out of limit, the springs 15 can drive the positioning rod 14 to move upwards to reset under the action of elasticity of the springs 15; the through hole 16 is formed in the middle of the front side of the positioning rod 14; the triangular block 17 is arranged in the middle of the bottom end of the inner cavity of the through hole 16; the bolt B18 is in threaded connection with the bottom end of the front side of the hollow block 12, the rear end of the bolt B18 is inserted into the through hole 16 and is attached to the top end of the triangular block 17, and the positioning rod 14 can be limited and fixed under the cooperation of the bolt B18 and the hollow block 12, so that the lower support plate 6 and the hanging basket A1 and the upper support plate 7 and the hanging basket B2 are firmly locked.
In order to facilitate the bolt B18 to push the positioning rod 14 to move downwards by extruding the inclined surface of the triangular block 17 and prevent the top end of the triangular block 17 from being mistakenly clamped into the thread of the bolt B18, the top of the triangular block 17 and the rear end of the bolt B18 are both arc-shaped.
To ensure that the detent lever 14 can be completely disengaged from the detent 5, the detent lever 14 is inserted into the detent 5 a length less than the distance between the top of the detent lever 14 and the top of the cavity of the hollow block 12.
During the use, unscrew nut 11 from bolt A10, can extract bolt A10 from through-hole 9, picture peg 8 loses fixedly, can upwards or the low-rise height of regulation, and then can realize the distance between hanging flower basket B2 and the hanging flower basket A1, after adjusting, reinsert bolt A10 and run through corresponding through-hole 9 again, the rethread nut 11 locks fixedly, can fix again between hanging flower basket B2 and the hanging flower basket A1, the workman can utilize the ladder to enter into in hanging flower basket B2 from the front side of hanging flower basket B2 and hanging flower basket A1, under the cooperation of hanging flower basket B2 and hanging flower basket A1, can realize the use of double-deck hanging flower basket, the workman can be convenient for simultaneously to the construction of two-layer building, work efficiency is improved, rotate bolt B18, under the spiro union cooperation of bolt B18 and hollow block 12, can make bolt B18 forward movement when rotating, bolt B18 separates with the triangle block 17 gradually, make locating lever 14 lose spacing, under the elastic force effect of spring 15, can drive locating lever 14 upwards to remove, locating lever 14 and constant head 5, lower backup pad 6 and hanging flower basket A lose fixedly and can be dismantled with the whole, and can be carried out in order to disassemble.
The embodiments described above are for the convenience of those skilled in the art to understand and use the present utility model, and it is apparent to those skilled in the art that various modifications can be made to the embodiments and the general principles described herein can be applied to other embodiments without inventive effort, and thus, the present utility model is not limited to the above embodiments, and those skilled in the art should, based on the disclosure of the present utility model, make improvements and modifications without departing from the scope of the utility model.

Claims (6)

1. The utility model provides an assembled hanging flower basket for construction, includes hanging flower basket A (1), hanging flower basket B (2), link (3) and rings (4), its characterized in that still includes:
the positioning grooves (5) are respectively formed in four corners at the top end of the hanging basket A (1) and four corners at the bottom end of the hanging basket B (2);
the lower support plates (6) are sleeved at the bottom ends of the left side and the right side of the hanging basket A (1) through concave cavities formed by the lower support plates (6) in an F shape;
the upper support plates (7) are sleeved at the bottom ends of the left side and the right side of the hanging basket B (2) through concave cavities formed by the upper support plates (7) in an F shape;
the inserting plate (8) is arranged at the bottom end of the upper supporting plate (7), the inserting plate (8) is inserted into an inner cavity at the outer side of the top of the matched lower supporting plate (6), and the hanging basket B (2) is supported and fixed above the hanging basket A (1) under the cooperation of the lower supporting plate (6), the upper supporting plate (7) and the inserting plate (8);
the two groups of through holes (9) are respectively arranged at the front end and the rear end of the outer side of the plugboard (8);
the bolts A (10), two bolts A (10) are respectively inserted into the tops of the front end and the rear end of the outer side of the lower supporting plate (6), and the inner ends of the bolts A (10) penetrate through holes (9) at corresponding positions and extend out of the lower supporting plate (6);
the nut (11) is tightly screwed at the inner end of the outer wall of the bolt A (10) and is tightly attached to the inner side of the lower supporting plate (6), the inserting plate (8) is locked and fixed in the lower supporting plate (6) under the action of the through hole (9), the bolt A (10) and the nut (11), the lower supporting plate (6) and the upper supporting plate (7) are connected and fixed, and meanwhile, the height adjustment of the inserting plate (8) and the upper supporting plate (7) can be realized, so that the distance between the hanging basket A (1) and the hanging basket B (2) can be adjusted;
the eight locking mechanisms are respectively arranged at the front and rear ends of the inner sides of the top ends of the two lower supporting plates (6) and the front and rear ends of the inner sides of the bottom ends of the two upper supporting plates (7), and can lock and fix the lower supporting plates (6) and the upper supporting plates (7) on the corresponding hanging basket A (1) and hanging basket B (2) under the matching of the locking mechanisms and the positioning grooves (5).
2. A hanging basket for assembled building construction according to claim 1, wherein: two groups of ten through holes (9) are respectively formed in the front end and the rear end of the outer side of the plugboard (8), the number of each group of through holes (9) is five, the through holes are arranged from top to bottom in a clearance mode, so that bolts A (10) are inserted into the tops of the front end and the rear end of the outer side of the lower supporting board (6), penetrate through the through holes (9) in corresponding positions and extend out of the lower supporting board (6), and the plugboard (8) is locked and fixed in the lower supporting board (6) through nuts (11).
3. A hanging basket for assembled building construction according to claim 1, wherein: the lower support plate (6) and the upper support plate (7) are of an F-shaped structure, the lower support plate and the upper support plate are arranged in an up-down opposite mode, and the height of the lower support plate (6) is larger than that of the upper support plate (7).
4. A hanging basket for assembled building construction according to claim 1, wherein: the locking mechanism includes:
the eight hollow blocks (12) are respectively arranged at the front and rear ends of the inner sides of the top ends of the two lower support plates (6) and the front and rear ends of the inner sides of the bottom ends of the two upper support plates (7);
the division plate (13) is arranged at the middle upper part of the inner cavity of the hollow block (12) to divide the inner cavity into two parts;
the positioning rod (14) is inserted into the partition plate (13), the bottom of the positioning rod (14) penetrates through the lower support plate (6) and extends into the matched positioning groove (5), the top of the positioning rod (14) is positioned above the partition plate (13), and the lower support plate (6) and the hanging basket A (1) and the upper support plate (7) and the hanging basket B (2) can be locked under the cooperation of the positioning rod (14) and the positioning groove (5);
one end of each spring (15) is clamped at the top end of the corresponding locating rod (14), and the other end of each spring is clamped at the top end of the inner cavity of the corresponding hollow block (12);
the through hole (16) is formed in the middle of the front side of the positioning rod (14);
the triangular block (17) is arranged in the middle of the bottom end of the inner cavity of the through hole (16);
bolt B (18), bolt B (18) spiro union is in the front side bottom of hollow piece (12), and laminating in triangle piece (17) top in spliced eye (16) of the rear end of bolt B (18) under the cooperation of bolt B (18) and hollow piece (12), can with locating lever (14) spacing fixed, and then guarantee to carry out firm locking between lower backup pad (6) and hanging flower basket A (1) and last backup pad (7) and hanging flower basket B (2).
5. The basket for modular construction according to claim 4, wherein: the tops of the triangular blocks (17) and the rear ends of the bolts B (18) are arc-shaped.
6. The basket for modular construction according to claim 4, wherein: the length of the positioning rod (14) inserted into the positioning groove (5) is smaller than the distance between the top of the positioning rod (14) and the top of the inner cavity of the hollow block (12).
CN202320791058.7U 2023-04-11 2023-04-11 Hanging basket for assembled building construction Active CN219604833U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320791058.7U CN219604833U (en) 2023-04-11 2023-04-11 Hanging basket for assembled building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320791058.7U CN219604833U (en) 2023-04-11 2023-04-11 Hanging basket for assembled building construction

Publications (1)

Publication Number Publication Date
CN219604833U true CN219604833U (en) 2023-08-29

Family

ID=87756325

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320791058.7U Active CN219604833U (en) 2023-04-11 2023-04-11 Hanging basket for assembled building construction

Country Status (1)

Country Link
CN (1) CN219604833U (en)

Similar Documents

Publication Publication Date Title
CN219604833U (en) Hanging basket for assembled building construction
CN212201206U (en) Assembled movable building construction platform
CN217299473U (en) Connecting structure of steel structure column
CN213772901U (en) Mounting structure of metal bracket
CN214995860U (en) Wall-attached support base plate
CN213927434U (en) Auxiliary attachment device for attached lifting scaffold of overhead structure of super high-rise building
CN211466261U (en) Vertical stop gear that screws up
CN110804946A (en) Maintenance method for large-displacement modulus type telescopic device
CN217600321U (en) Modular fan overhauling and maintaining platform
CN221422653U (en) Scaffold node and scaffold
CN221346235U (en) High-strength climbing bracket assembly
CN214784804U (en) Plant roof net rack mounting structure
CN216109440U (en) Convenient quick detach formula aluminum alloy flower type handrail
CN218538901U (en) Elevator car convenient to install and dismantle fast
CN217680739U (en) Building structure design beam column reinforced structure
CN213296838U (en) Constructional engineering steel construction roof girder steel connects fixed knot to be constructed
CN220117700U (en) Building construction builds current frame of jumping fast
CN217353683U (en) Reinforced structure for building structure roof beam
CN219491685U (en) High strength scaffold connecting piece for building
CN114524064B (en) Scaffold device for ship and working method
CN218028199U (en) Splicing structure of steel structure
CN220868772U (en) Building climbing frame net piece connecting device
CN219931697U (en) Aluminum alloy section bar structure for protective guard
CN212053700U (en) Keel plate connecting device for attached lifting scaffold
CN212095208U (en) Assembling equipment for steel structure beam support connecting piece

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20231011

Address after: No. 4, Group 4, Shizigou Village, Liuliping Town, Danjiangkou City, Shiyan City, Hubei Province, 442000

Patentee after: Huang Sen

Address before: No. 29, Songyuan Community, Jinzhou District, Dalian City, Liaoning Province, 116699, 1-8-5

Patentee before: Fu Chunyu

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231025

Address after: No. 402, Building 3, North Side of Caishen Middle Road, Liuliping Town, Danjiangkou City, Shiyan City, Hubei Province, 442000

Patentee after: Shiyan Chubang Engineering Construction Co.,Ltd.

Address before: No. 4, Group 4, Shizigou Village, Liuliping Town, Danjiangkou City, Shiyan City, Hubei Province, 442000

Patentee before: Huang Sen

TR01 Transfer of patent right