CN219604071U - Temporary passage-protecting surface structure of central dividing strip of expressway - Google Patents

Temporary passage-protecting surface structure of central dividing strip of expressway Download PDF

Info

Publication number
CN219604071U
CN219604071U CN202223043909.4U CN202223043909U CN219604071U CN 219604071 U CN219604071 U CN 219604071U CN 202223043909 U CN202223043909 U CN 202223043909U CN 219604071 U CN219604071 U CN 219604071U
Authority
CN
China
Prior art keywords
steel plates
pavement
dividing strip
temporary
central dividing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223043909.4U
Other languages
Chinese (zh)
Inventor
张文
罗旭东
陈竞飞
雷明
赵赛先
杜燕群
廖鹏庆
殷宇翔
杨晨
杨婵君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong communication Planning and Design Institute Group Co Ltd
Original Assignee
Guangdong communication Planning and Design Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong communication Planning and Design Institute Group Co Ltd filed Critical Guangdong communication Planning and Design Institute Group Co Ltd
Priority to CN202223043909.4U priority Critical patent/CN219604071U/en
Application granted granted Critical
Publication of CN219604071U publication Critical patent/CN219604071U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a temporary passage-protecting surface structure of a central dividing strip of an expressway, which comprises a pavement structure layer of the central dividing strip, wherein a filling pit is formed in the upper part of a pipeline protection layer of the central dividing strip of the pavement structure layer, a graded broken stone base layer is filled in the filling pit, a pavement panel is paved on the upper part of the graded broken stone base layer, the pavement panel is formed by splicing a plurality of pattern steel plates, a plurality of longitudinal channel steel and a plurality of transverse channel steel which are distributed in a crossing way are welded on the lower surface of the pattern steel plates, and the adjacent pattern steel plates are spliced through connecting steel plates. The temporary road surface protection structure has the advantages of convenience in field pavement and dismantling, less equipment required by field construction, short construction time and repeated use for many times.

Description

Temporary passage-protecting surface structure of central dividing strip of expressway
Technical Field
The utility model belongs to the technical field of road engineering design, and particularly relates to a temporary road surface protection structure of a central dividing strip of an expressway.
Background
The central separation belt of the expressway plays a role in separating opposite traffic during normal use, and has a key role in improving the safety of expressway driving and playing the functions of highway projects. In the reconstruction and expansion construction period of the expressway, temporary road surfaces are required to be arranged for realizing traffic conversion on the left side and the right side and ensuring traffic to pass without interruption.
The conventional temporary pavement structure adopts a asphalt concrete or cement concrete structure, and has the defects of long site construction period, more required mechanical equipment, larger working surface and unrepeatable use after the temporary pavement is broken.
Disclosure of Invention
The utility model aims to provide a temporary passage-protecting surface structure of a central dividing strip of an expressway, which can be quickly installed and removed and can be repeatedly used for a plurality of times.
The aim of the utility model can be achieved by the following technical scheme.
The utility model provides a highway central authorities separate band temporary protection way face structure, includes the road surface structural layer of central authorities separate band, the filler hole has been seted up on the central authorities separate band pipeline protective layer upper portion of road surface structural layer, fill and build the gradation rubble basic unit in the filler hole, road surface panel is laid on the upper portion of gradation rubble basic unit, road surface panel is formed by the concatenation of polylith decorative pattern steel sheet, the lower surface welding of decorative pattern steel sheet has a plurality of vertical channel-section steel and a plurality of horizontal channel-section steel of cross distribution, splices through connecting steel sheet between the adjacent decorative pattern steel sheet.
The temporary road surface protection structure is constructed on the central dividing strip of the expressway, after the anti-collision fence and the curb of the central dividing strip are removed, the current road surface structure layer, the pipeline of the central dividing strip and the drainage system of the central dividing strip are kept from being damaged, a filling pit is formed after partial filling soil is excavated at the upper part of the pipeline protection layer of the central dividing strip, and a graded broken stone base layer is filled in the filling pit to serve as a bearing foundation of a road surface panel during the passing. The lower surfaces of the pattern steel plates for splicing the pavement panels are welded with longitudinal channel steel and transverse channel steel for structural reinforcement. The upper surface of the pattern steel plate is used as a traffic lane to play a role in preventing the vehicle from skidding, and the pattern steel plate is preferably as thick as possible to reduce deformation of the vehicle.
The utility model also has the following preferred designs:
according to the utility model, the end part of the pattern steel plate is provided with the panel bolt hole, the connecting steel plate is provided with the connecting piece bolt hole, and the pattern steel plate is connected with the connecting steel plate through bolts.
The thickness of the graded broken stone base layer is more than or equal to 35cm, and the compactness is more than or equal to 95%.
The length of the patterned steel plate is 1-2 times of the width, so that the patterned steel plate is convenient to lift, transport, pave and dismantle.
The elevation of the pavement panel is the same as that of the pavement at two sides, so that the upper surface of the pavement panel is level with the pavement at two sides, the pavement at two sides is connected, the pavement panel is integrated, a temporary passage-protecting surface of the central separation belt is formed, traffic at two sides is converted during passage-protecting, and traffic is ensured not to interrupt passage.
The utility model has the following beneficial effects:
1. the central dividing strip of the expressway is of a fixed width according to design specifications, and the characteristic is fully utilized by the utility model. The pavement panel of the temporary passageway-protecting surface structure paved on the conventional site is set to be the pattern steel plate which can be prefabricated in a factory, so that the mass production is facilitated. The temporary road surface protection structure has the advantages of convenience in field pavement and dismantling, less equipment required by field construction, short construction time and repeated use for many times.
2. The road surface structure is formed by paving the graded broken stone base layer on the central dividing belt of the expressway and assembling the processed road surface panels, so that traffic on two sides of the central dividing belt can be converted during the expansion construction of the expressway, and traffic is ensured not to be interrupted.
3. The pavement panel of the main body part of the pavement structure adopts the patterned steel plate to strengthen the anti-skid performance of the pavement, and the lower surface of the patterned steel plate is reinforced by adopting the channel steel with longitudinal grooves welded in a staggered way so as to improve the anti-deformation capability.
Drawings
FIG. 1 is a schematic illustration of a temporary passageway surface structure of a high speed highway central separator of the present utility model, with the curb and anti-collision rail to be removed shown in phantom;
FIG. 2 is an elevation view of a patterned steel sheet of the pavement slab of the present utility model;
FIG. 3 is a bottom view of the pavement slab of the present utility model;
fig. 4 is a schematic view of a joined steel sheet according to the present utility model.
Reference numerals illustrate: the road surface slab comprises a 1-road surface panel, a 2-graded broken stone base layer, a 3-road surface structural layer, a 4-central partition belt pipeline, a 5-central partition belt drainage system, a 6-curb, a 7-anti-collision fence, a 11-pattern steel plate, a 12-longitudinal channel steel, a 13-transverse channel steel, a 14-panel bolt hole, a 15-connecting steel plate and a 16-connecting piece bolt hole.
Detailed Description
The following surfaces are presented in conjunction with the drawings and examples to better understand and practice the technical solution of the present utility model by those of ordinary skill in the art.
Referring to fig. 1 to 4, a temporary road surface protection structure for a central division belt of an expressway comprises a pavement structure layer 3 of the central division belt, a filling pit is formed in the upper portion of a protection layer of a pipeline 4 of the central division belt of the pavement structure layer 3, a graded broken stone base layer 2 is filled in the filling pit, a pavement panel 1 is paved on the upper portion of the graded broken stone base layer 2, the pavement panel 1 is formed by splicing a plurality of pattern steel plates 11, a plurality of longitudinal channel steel 12 and a plurality of transverse channel steel 13 which are distributed in a crossing manner are welded on the lower surface of the pattern steel plates 11, and the adjacent pattern steel plates 11 are spliced through connecting steel plates 15.
As a preferred embodiment:
the end of the pattern steel plate 11 is provided with a panel bolt hole 14, the connecting steel plate 15 is provided with a connecting piece bolt hole 16, and the pattern steel plate 11 is connected with the connecting steel plate 15 through bolts.
The thickness of the graded broken stone base layer 2 is more than or equal to 35cm, and the compactness is more than or equal to 95%.
The length of the patterned steel plate 11 is 1-2 times of the width, so that the patterned steel plate is convenient to lift, transport, pave and dismantle.
The temporary road surface structure of the present utility model is constructed on a central division strip of an expressway, as shown in fig. 1, after an anti-collision fence 7 and a curb 6 indicated by broken lines of the central division strip are removed, the current road surface structure layer 3, the central division strip pipeline 4 and the central division strip drainage system 5 of the central division strip are kept undamaged, a filling pit is formed after partial soil is removed from the top surface, namely the upper part of a protective layer of the central division strip pipeline 4, and a graded macadam base layer 2 is filled in the filling pit to serve as a bearing foundation of the road surface panel 1 during the maintenance period.
The above embodiments are only preferred embodiments of the present utility model, but not limiting, and any modifications and improvements based on the concept of the present utility model should fall within the scope of the present utility model, and the specific scope of the present utility model is defined by the claims.

Claims (5)

1. The utility model provides a highway central authorities separate area temporary security way face structure, includes the road surface structural layer of central authorities separate area, its characterized in that: the road surface panel is formed by splicing a plurality of pattern steel plates, a plurality of longitudinal channel steel and a plurality of transverse channel steel which are distributed in a crossing way are welded on the lower surface of the pattern steel plates, and the adjacent pattern steel plates are spliced through connecting steel plates.
2. The highway central dividing strip temporary passageway-keeping surface structure according to claim 1, wherein: panel bolt holes are formed in the end portions of the pattern steel plates, connecting piece bolt holes are formed in the connecting steel plates, and the pattern steel plates are connected with the connecting steel plates through bolts.
3. The highway central dividing strip temporary passageway-keeping surface structure according to claim 2, wherein: the thickness of the graded broken stone base layer is more than or equal to 35cm, and the compactness is more than or equal to 95%.
4. A highway central separator temporary access protection surface structure according to claim 3, wherein: the length of the patterned steel plate is 1-2 times of the width.
5. The highway central separator temporary access protection surface structure according to claim 4, wherein: the elevation of the pavement panel is the same as that of the pavement on two sides.
CN202223043909.4U 2022-11-16 2022-11-16 Temporary passage-protecting surface structure of central dividing strip of expressway Active CN219604071U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223043909.4U CN219604071U (en) 2022-11-16 2022-11-16 Temporary passage-protecting surface structure of central dividing strip of expressway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223043909.4U CN219604071U (en) 2022-11-16 2022-11-16 Temporary passage-protecting surface structure of central dividing strip of expressway

Publications (1)

Publication Number Publication Date
CN219604071U true CN219604071U (en) 2023-08-29

Family

ID=87742967

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223043909.4U Active CN219604071U (en) 2022-11-16 2022-11-16 Temporary passage-protecting surface structure of central dividing strip of expressway

Country Status (1)

Country Link
CN (1) CN219604071U (en)

Similar Documents

Publication Publication Date Title
CN109853375B (en) Bridge expansion joint reserved notch of assembled structure and construction method thereof
CN111254779B (en) Embedding method for improving cracking of pavement around luminous floor tiles
CN208762812U (en) Steel bearing plate connecting structure of assembled pavement
CN111254778B (en) Embedding structure and method for preventing cracking of luminous mark of concrete pavement
CA2594808A1 (en) System and method for reinforcing aggregate particles, and structures resulting therefrom
CN112695582A (en) Assembly type construction and repair structure of highway pavement and rapid construction method thereof
CN106168031B (en) Multifunctional steel sheet pile cofferdam
CN220746626U (en) Mountain area box culvert backfill integrated configuration
CN219604071U (en) Temporary passage-protecting surface structure of central dividing strip of expressway
CN208235303U (en) A kind of precast prestressed modularization viaduct
JP2017008619A (en) Repair method of driving lane with swollen road bed of mountain tunnel of expressway, and suspension pier used therewith
CN113389159A (en) Frame type concrete guardrail for central separation belt
CN111926649A (en) Reinforced integrally-built crossing plate for railway special line and line rail fixing device
CN111778800B (en) Highway subgrade reinforcing structure and method
CN107858886B (en) Viaduct foundation peripheral ground road and construction method thereof
CN113389218A (en) Retaining wall structure for entrance and exit of road bridge and construction method thereof
CN212505689U (en) Reinforced integrally-built crossing plate for railway special line and line rail fixing device
CN218322165U (en) Steel construction combination beam type temporary pavement
CN219793507U (en) Assembled construction passageway
CN110804916A (en) Construction method for newly-built road to pass through existing road under traffic state
CN110644308A (en) Construction method for paving road on debris flow soft foundation
CN221276301U (en) Prefabricated concrete beam slab and steel structure pier combination keep-through bridge
CN211446551U (en) Road overpass bridge structure
CN219010844U (en) Prefabricated assembled concrete pavement slab with step end penetrating bolt connection
CN214033983U (en) Assembled transverse intercepting ditch

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant