CN218758435U - Concealed installation structure for pipeline packing prefabricated plate - Google Patents

Concealed installation structure for pipeline packing prefabricated plate Download PDF

Info

Publication number
CN218758435U
CN218758435U CN202222765407.6U CN202222765407U CN218758435U CN 218758435 U CN218758435 U CN 218758435U CN 202222765407 U CN202222765407 U CN 202222765407U CN 218758435 U CN218758435 U CN 218758435U
Authority
CN
China
Prior art keywords
cement board
thin cement
wall body
slim
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222765407.6U
Other languages
Chinese (zh)
Inventor
李伟
张洁
李新
田辉
刘奂麟
贾莹
张亚妮
孟令轩
许佳群
席硕
许泽昭
赵振印
孙涛
王淼
潘云鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Bureau Group Decoration Engineering Co Ltd
Original Assignee
China Construction First Group Corp Ltd
China Construction First Bureau Group Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, China Construction First Bureau Group Decoration Engineering Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN202222765407.6U priority Critical patent/CN218758435U/en
Application granted granted Critical
Publication of CN218758435U publication Critical patent/CN218758435U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Panels For Use In Building Construction (AREA)

Abstract

The utility model discloses a prefabricated plate mounting structure is sealed to hidden pipeline, including structure wall body and the pipeline of setting in structure wall body department, still including the slim cement board that surrounds the pipeline, the both ends of slim cement board dock with the structure wall body respectively, be equipped with L type mounting between the slim cement board outside and the structure wall body, L type mounting one end and structure wall connection, the other end and slim cement board are connected, the inside shaping of tip that slim cement board is close to the structure wall body has the tip to consolidate the rib, the slim cement board is equipped with bight in its corner department and consolidates the rib. This application is through slim cement board and L shape mounting as encapsulating the structure, and the construction is simple, and maneuverability is strong, has reduced construction cost, and processing cycle is short, and the installation is swift, sound construction.

Description

Concealed installation structure for pipeline packing prefabricated plate
Technical Field
The utility model relates to a technical field that the pipeline was sealed is sealed especially relates to a prefabricated plate mounting structure is sealed to hidden pipeline.
Background
In decoration engineering, it is common practice for kitchens, toilets, halls needing decoration and public area wall surfaces to encounter functional pipelines
The surface decoration treatment is carried out after the encapsulation and the method of the area, and the pipeline of the type is encapsulated by brick masonry and light steel dragon at present
The artificial bone plate is mainly used for packaging as a base layer, and a small part of the artificial bone plate is constructed by using galvanized square steel as a framework in a dry hanging manner. Has high cost and labor
Multiple procedures, scattered working surfaces, rotting of artificial boards, fire hazards and the like. In particular to the problems of high cost, scattered engineering quantity and the like
The problem of annoying the project.
SUMMERY OF THE UTILITY MODEL
The utility model provides a prefabricated plate mounting structure is sealed to hidden pipeline, the construction is simple, and maneuverability is strong, has reduced construction cost, and processing cycle is short, and the installation is swift, sound construction.
The technical problem to be solved is that: at present, the pipeline encapsulation of the type mainly takes brick masonry and light steel keel artificial boards as base layers for encapsulation, and a small part of the pipeline is constructed by using galvanized square steel as a framework in a dry hanging way. The problems of high cost, multiple working procedures, scattered working surfaces, fire hazard of rotting of artificial boards and the like exist. In particular to the problem that the project is always difficult due to the problems of high cost, scattered engineering quantity and the like.
In order to solve the technical problem, the utility model adopts the following technical scheme:
the utility model discloses prefabricated plate mounting structure is sealed to hidden pipeline, including structure wall body and the pipeline of setting in structure wall body department, still including the slim cement board that surrounds the pipeline, the both ends of slim cement board dock with the structure wall body respectively, be equipped with L type mounting between the slim cement board outside and the structure wall body, L type mounting one end and structure wall body coupling, the other end is connected with the slim cement board, the inside shaping of tip that the slim cement board is close to the structure wall body has the tip to consolidate the rib, the slim cement board is equipped with bight in its angle point department and consolidates the rib.
The utility model discloses prefabricated plate mounting structure is sealed to hidden pipeline, it is further, slim cement board is reinforced concrete structure.
The utility model discloses prefabricated plate mounting structure is sealed to hidden pipeline, it is further, slim cement board is L shape.
The utility model discloses prefabricated plate mounting structure is sealed to hidden pipeline, it is further, slim cement board is the U-shaped.
The utility model discloses prefabricated plate mounting structure is sealed to hidden pipeline, it is further, the access hole has been seted up on the slim cement board.
The utility model discloses prefabricated plate mounting structure is sealed to hidden pipeline, it is further, it has the structure to glue to seal to fill between slim cement board and the structure wall body.
The utility model discloses prefabricated plate mounting structure is sealed to hidden pipeline, it is further, slim cement board is external to be equipped with the wire net, the wire net is equipped with the plastering layer outward.
The utility model discloses prefabricated plate mounting structure is sealed to hidden pipeline, it is further, the outer ceramic tile that pastes of layer of plastering.
Compared with the prior art, the utility model, following beneficial effect has:
1. the thin cement plate and the L-shaped fixing piece are used as the packaging structure, so that the construction is simple, the operability is strong, the construction cost is reduced, the processing period is short, the installation is rapid, and the structure is firm;
2. the application uses cement and steel bars, is convenient to obtain materials, has low technical difficulty, can carry out streamlined construction and has wide application;
3. the construction quality is effectively improved, and common quality problems such as encapsulation, cracking, rotting and the like caused by masonry and artificial boards are avoided;
4. the use of artificial boards is reduced, the use of masonry bricks is reduced, resources are saved, and the pollution of construction waste to the environment is reduced;
5. the end reinforcing ribs are arranged, so that the fixing position of the expansion screw is reinforced on one hand, the thin cement board is prevented from being damaged when the expansion screw is arranged, and on the other hand, the thickness of the end of the thin cement board is increased, and the thin cement board is prevented from being collided and damaged in the transferring process; the corner reinforcing ribs are arranged, so that the thickness of the corners of the thin cement board is increased, and the structural strength of the corners of the thin cement board is enhanced.
The present invention will be further explained with reference to the accompanying drawings.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of another embodiment of the thin cement panel of the present invention;
FIG. 3 is a schematic view of the thin cement board of the present invention with an access hole;
fig. 4 is a schematic diagram of the steel wire mesh arranged on the thin cement board of the utility model.
Reference numerals are as follows:
1. a structural wall; 2. a pipeline; 3. a thin cement board; 4. an L-shaped fixing member; 5. an expansion screw; 6. an end reinforcing rib; 7. corner reinforcing ribs; 8. an access hole; 9. structural adhesive; 10. steel wire mesh; 11. plastering layer; 12. and (6) ceramic tiles.
Detailed Description
As shown in fig. 1-4, the installation structure of the concealed pipe-encapsulated precast slab of the present invention comprises a structural wall 1 and a pipe 2 disposed at the structural wall 1, a thin cement board 3 is surrounded outside the pipe 2, both ends of the thin cement board 3 are butted with the structural wall 1 respectively, a plurality of L-shaped fixing members 4,L are disposed between the outer side of the thin cement board 3 and the structural wall 1, one end of each of the L-shaped fixing members 4,L is fixed with the structural wall 1 through an expansion screw 5, the other end of each of the L-shaped fixing members is fixed with the thin cement board 3 through the expansion screw 5, an end reinforcing rib 6 is formed inward at the end of the thin cement board 3 close to the structural wall 1, the thin cement board 3 is provided with a corner reinforcing rib 7 at its corner point, the end reinforcing rib 6 is disposed, on one hand, the fixing position of the expansion screw 5 is reinforced, damage to the thin cement board 3 when the expansion screw 5 is avoided, on the other hand, the thickness of the end of the thin cement board 3 is increased, and the damage caused by collision during the transportation process is avoided; by providing the corner reinforcing ribs 7, the thickness of the corners of the thin cement panel 3 is increased, and the structural strength of the corners of the thin cement panel 3 is enhanced.
The thin cement plate 3 is of a reinforced concrete structure, and the shape of the thin cement plate can be an L-shaped structure or a U-shaped structure according to the arrangement position of the pipeline 2 on the structural wall 1, so as to adapt to the installation of the pipelines 2 at different positions.
The thin cement plate 3 is provided with an access hole 8, which is convenient for the pipeline 2 to be overhauled. And structural adhesive 9 is filled between the thin cement board 3 and the structural wall 1 for sealing.
Further, a steel wire mesh 10 is hung outside the thin cement board 3, a plastering layer 11 is arranged outside the steel wire mesh 10, and a ceramic tile 12 is adhered outside the plastering layer 11, so that the decorative performance of the packaging structure is ensured.
The application has the following advantages:
4. this application is through thin cement slab 3 and L shape mounting as encapsulating the structure, and the construction is simple, and maneuverability is strong, has reduced construction cost, and processing cycle is short, and the installation is swift, sound construction.
5. This application uses cement and reinforcing bar, and convenient for materials, the technical degree of difficulty is low, but streamlined construction, uses extensively.
6. The construction quality is effectively improved, and common quality problems such as encapsulation, cracking, rotting and the like caused by masonry and artificial boards are avoided.
4. The use of artificial boards is reduced, the use of masonry bricks is reduced, resources are saved, and the pollution of construction waste to the environment is reduced.
The above-mentioned embodiments are merely illustrative of the preferred embodiments of the present invention, and are not intended to limit the scope of the present invention, and various modifications and improvements made by those skilled in the art without departing from the spirit of the present invention should fall within the protection scope defined by the claims of the present invention.

Claims (8)

1. Hidden pipeline encapsulation prefabricated plate mounting structure, including structural wall (1) and setting pipeline (2) in structural wall (1) department, its characterized in that: still including thin cement board (3) that surrounds pipeline (2), the both ends of thin cement board (3) dock with structure wall body (1) respectively, be equipped with L type mounting (4) between thin cement board (3) outside and structure wall body (1), L type mounting (4) one end is connected with structure wall body (1), and the other end is connected with thin cement board (3), the inside shaping of tip that thin cement board (3) are close to structure wall body (1) has tip reinforcing rib (6), thin cement board (3) are equipped with bight reinforcing rib (7) in its angular point department.
2. The concealed duct enclosure precast panel installation structure of claim 1, wherein: the thin cement plate (3) is of a reinforced concrete structure.
3. The concealed duct enclosure precast panel installation structure of claim 1, wherein: the thin cement plate (3) is L-shaped.
4. The concealed duct enclosure precast panel installation structure of claim 1, wherein: the thin cement plate (3) is U-shaped.
5. The concealed duct enclosure precast panel installation structure of claim 1, wherein: the thin cement plate (3) is provided with an access hole (8).
6. The concealed duct enclosure precast panel installation structure of claim 1, wherein: and a structural adhesive (9) is filled between the thin cement board (3) and the structural wall body (1) for sealing.
7. The concealed duct enclosure precast panel installation structure of claim 1, wherein: the thin cement board (3) is externally hung with a steel wire mesh (10), and a plastering layer (11) is arranged outside the steel wire mesh (10).
8. The concealed duct enclosure precast panel installation structure of claim 7, wherein: ceramic tiles (12) are adhered outside the plastering layer (11).
CN202222765407.6U 2022-10-20 2022-10-20 Concealed installation structure for pipeline packing prefabricated plate Active CN218758435U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222765407.6U CN218758435U (en) 2022-10-20 2022-10-20 Concealed installation structure for pipeline packing prefabricated plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222765407.6U CN218758435U (en) 2022-10-20 2022-10-20 Concealed installation structure for pipeline packing prefabricated plate

Publications (1)

Publication Number Publication Date
CN218758435U true CN218758435U (en) 2023-03-28

Family

ID=85700498

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222765407.6U Active CN218758435U (en) 2022-10-20 2022-10-20 Concealed installation structure for pipeline packing prefabricated plate

Country Status (1)

Country Link
CN (1) CN218758435U (en)

Similar Documents

Publication Publication Date Title
CN103374986B (en) A kind of multifunction combined light weight concrete construction curtain wall and preparation method thereof
CN104032888A (en) Integrally prefabricated multifunctional composite external wall panel and industrial building external wall
CN202595943U (en) Toilet steel frame lightweight partition wall
CN105696744A (en) Integral autoclaved aerated concrete wallboard and production process thereof
CN202099901U (en) Troweling structure for treatment on junction part of concrete wall column and filler wall
CN216713468U (en) Building template and wall body adopting same
CN205116541U (en) Foaming light aggregate concrete partition plate
CN218758435U (en) Concealed installation structure for pipeline packing prefabricated plate
WO2024055622A1 (en) Prefabricated component formed by reverse laying and production process therefor
CN218714288U (en) Decoration-free building structure
CN201155162Y (en) Granite, terrazzo emulated heat insulation composite board
CN2143643Y (en) Fire-proof sound insulation and heat insulation light sheet
CN114525883A (en) Precast simple partition wall board and manufacturing method thereof
CN102535847A (en) Method for constructing gypsum self-insulation outer wall block masonry
CN113718994A (en) Connecting structure and method for keel wall and masonry wall
CN2931620Y (en) Assembly wall
CN203947671U (en) Integral prefabricated multi-functional compound external wall panel and industrialized building exterior wall
CN2878570Y (en) Partition plate with four-wall planed matchboards free of plastering
CN2683743Y (en) Glass fiber reinforced cement wrapped foaming concrete construction wall plate
CN208748909U (en) On-site assembly cladding
CN208280385U (en) A kind of connecting structure of multifunctional light partition plate
CN218881315U (en) Multifunctional inverted-beating prefabricated member capable of being connected with back and assembly structure thereof
CN216920808U (en) Keel wall and masonry wall connecting structure
CN206554331U (en) A kind of sound insulation cracking resistance decorates prefabricated indoor partition panel
CN211899098U (en) Thin wall based on steel frame, plate and stone

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant