CN218714287U - Install convenient steel construction factory building aluminized zinc die mould battenboard - Google Patents

Install convenient steel construction factory building aluminized zinc die mould battenboard Download PDF

Info

Publication number
CN218714287U
CN218714287U CN202222939894.3U CN202222939894U CN218714287U CN 218714287 U CN218714287 U CN 218714287U CN 202222939894 U CN202222939894 U CN 202222939894U CN 218714287 U CN218714287 U CN 218714287U
Authority
CN
China
Prior art keywords
zinc
aluminum
thimble
factory building
battenboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222939894.3U
Other languages
Chinese (zh)
Inventor
李爱军
张永升
侯利君
张倍佳
郑云云
胡敏
安亚军
于振丽
武俊芳
梁捷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Second Construction Group Co Ltd
Original Assignee
Shanxi Second Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Second Construction Group Co Ltd filed Critical Shanxi Second Construction Group Co Ltd
Priority to CN202222939894.3U priority Critical patent/CN218714287U/en
Application granted granted Critical
Publication of CN218714287U publication Critical patent/CN218714287U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model provides a simple steel construction factory building aluminize zinc die mould battenboard of installation, relates to aluminize zinc die mould battenboard installation technical field, and it includes the aluminize zinc steel sheet, the middle part of aluminize zinc steel sheet is provided with the sandwich layer, it has coupling assembling one to peg graft in one side of aluminize zinc steel sheet, it has coupling assembling two to peg graft in the opposite side of aluminize zinc steel sheet. This install convenient steel construction factory building aluminized zinc die mould battenboard aligns respectively through the both ends that will contain two aluminized zinc steel sheets of sandwich layer, and wherein the public end of connection of one aluminized zinc steel sheet one end aligns with the female end of being connected of another aluminized zinc steel sheet one end, then pegs graft the inner wall that the slot was seted up in female end one end of being connected to the inserted block of connecting public end one end to reach the effect of quick installation concatenation.

Description

Install convenient steel construction factory building aluminized zinc die mould battenboard
Technical Field
The utility model relates to an installation technical field of zinc die mould battenboard of aluminizing specifically is a steel construction factory building zinc die mould battenboard convenient for installation.
Background
The steel structure factory building mainly refers to a house body formed by combining a bearing member and an aluminum-zinc compression sandwich board, wherein the structure type can be divided into a light steel structure factory building and a heavy steel structure factory building, the steel structure factory building has the advantages of light building weight, high strength, large span and short construction period, and is recycled without pollution, so the steel structure factory building is widely applied to various industries.
When the aluminum-zinc plated compression-type sandwich board at the present stage is installed, a support needs to be fixed firstly, screws are arranged, the installation is troublesome, the independent sandwich board cannot be assembled conveniently, the problems of protection of the aluminum-zinc plated compression-type sandwich board and inconvenience in disassembly under the condition of no need of use are solved, and the construction period of a factory building is prolonged due to complex installation procedures.
SUMMERY OF THE UTILITY MODEL
The utility model provides a steel construction factory building aluminized zinc die mould battenboard that the installation is convenient possesses the simple operation and is convenient for splice installation and quick advantage of dismantling to solve the loaded down with trivial details inconvenient problem of operation of traditional aluminized zinc die mould battenboard installation.
In order to achieve the above purpose, the utility model provides the following technical scheme: an aluminum-zinc plated profiled sandwich board of a steel structure factory building, which is convenient to install, comprises an aluminum-zinc plated steel plate, wherein the middle part of the aluminum-zinc plated steel plate is provided with a sandwich layer, one side of the aluminum-zinc plated steel plate is spliced with a first connecting component, and the other side of the aluminum-zinc plated steel plate is spliced with a second connecting component;
the first connecting component comprises a male connecting end, an inserting block, a positioning hole and a first clamping groove, the male connecting end is inserted into one end of the aluminum-zinc-plated steel plate, the inserting block is arranged at one end of the male connecting end, the inserting block is arranged on the top surface of the inserting block, and the first clamping groove is arranged on the surface of the other end of the male connecting end;
the second connecting component comprises a female connecting end, a slot, a fixing nail and a second clamping groove, the female connecting end is inserted into the other end of the aluminum-zinc-plated steel plate, the slot is formed in the surface of one end of the female connecting end, and the second clamping groove is formed in the surface of the other end of the female connecting end.
As a preferred technical scheme of the utility model, coupling assembling two still includes flexible hole, spacing groove, the inside wall surface at the slot is seted up to flexible hole symmetry, the inside wall in flexible hole is seted up to the spacing groove.
As a preferred technical scheme of the utility model, coupling assembling two still includes thimble, positioning spring, thimble movable mounting is at the inner wall in flexible hole, positioning spring's one end fixed mounting is at the inner wall in flexible hole.
As a preferred technical scheme of the utility model, the quantity of locating hole is a plurality of groups and is linear distribution and be circular in the shape of the top surface of inserted block and locating hole.
Compared with the prior art, the utility model provides a steel construction factory building aluminized zinc die mould battenboard that the installation is convenient possesses following beneficial effect:
1. this install convenient steel construction factory building aluminized zinc die mould battenboard aligns respectively through the both ends that will contain two aluminized zinc steel sheets of sandwich layer, and wherein the public end of connection of one aluminized zinc steel sheet one end aligns with the female end of being connected of another aluminized zinc steel sheet one end, then pegs graft the inner wall that the slot was seted up in female end one end of being connected to the inserted block of connecting public end one end to reach the effect of quick installation concatenation.
2. This install convenient steel construction factory building aluminize zinc die mould battenboard, through setting up the locating hole that the thimble mainly used was seted up with the inserted block top and cooperate the use to consolidate and connect the connection between public end and the connection female end, and then strengthen the connection steadiness of aluminizing zinc die mould battenboard.
Drawings
FIG. 1 is a schematic view of a three-dimensional structure of an aluminum-zinc plated profiled sandwich board for a steel structure factory building, which is convenient and fast to install;
FIG. 2 is a schematic structural view of the aluminum-zinc plated steel plate of the present invention;
FIG. 3 is a schematic view of the structure of the male connection end of the present invention;
FIG. 4 is a schematic view of the structure of the female connection end of the present invention;
FIG. 5 is a schematic view of the slot structure of the present invention;
fig. 6 is an enlarged schematic view of the part a in fig. 5 according to the present invention.
In the figure: 1. an aluminum-zinc plated steel plate; 2. a sandwich layer; 3. connecting a male end; 4. connecting the female end; 5. a slot; 6. inserting a block; 7. a first clamping groove; 8. a second clamping groove; 9. a thimble; 10. fixing nails; 11. a positioning spring; 12. a telescopic hole; 13. a limiting groove; 14. and (7) positioning the holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Please refer to fig. 1-6, the utility model discloses a steel construction factory building aluminium-zinc-plated die mould battenboard convenient to install, including aluminium-zinc-plated steel sheet 1, the middle part of aluminium-zinc-plated steel sheet 1 is provided with sandwich layer 2, and one side of aluminium-zinc-plated steel sheet 1 is pegged graft and is had coupling assembling one, and the opposite side of aluminium-zinc-plated steel sheet 1 is pegged graft and is had coupling assembling two.
Specifically, coupling assembling one is including connecting public end 3, inserted block 6, locating hole 14, draw-in groove 7, connects public end 3 and pegs graft in the one end of aluminizing zinc steel sheet 1, and inserted block 6 is opened and is set up in the one end of connecting public end 3, and inserted block 6 is seted up on the top surface of inserted block 6, and draw-in groove 7 is seted up on the other end surface of connecting public end 3.
In this embodiment, connect public end 3 mainly to be used for being connected with inserted block 6 through the setting, wherein connect the inserted block 6 that 3 one ends of public end were seted up and mainly play and carry out the effect of splicing to aluminized zinc steel sheet 1, the size of draw-in groove 7 and the size adaptation of aluminized zinc steel sheet 1.
Concretely, coupling assembling two is including connecting female end 4, slot 5, staple 10, draw-in groove two 8, connects female end 4 and pegs graft at the other end of aluminizing zinc steel sheet 1, and slot 5 sets up the one end surface at connecting female end 4, and draw-in groove two 8 sets up the other end surface at connecting female end 4.
In this embodiment, connect female end 4 mainly to be used for with be connected public end 3 through the setting and be connected, wherein will connect the inserted block 6 that 3 one ends of public end set up and peg graft with the slot 5 of being connected 4 one ends of female end and setting up to convenient completion battenboard's installation, wherein staple 10 mainly is used for connecting female end 4 and connecting public end 3 and the fixed of aluminizing zinc steel sheet 1, and then guarantees to connect public end 3 and the steadiness of connecting female end 4 and aluminizing zinc steel sheet 1 and being connected.
Specifically, the second connecting assembly further comprises a telescopic hole 12 and a limiting groove 13, the telescopic hole 12 is symmetrically formed in the surface of the inner side wall of the slot 5, and the limiting groove 13 is formed in the inner side wall of the telescopic hole 12.
In this embodiment, the telescopic hole 12 is mainly used to provide a space for the movement of the component in the second connecting assembly, and the limiting groove 13 is mainly used to limit the component in the second connecting assembly.
Specifically, the second connecting assembly further comprises a thimble 9 and a positioning spring 11, the thimble 9 is movably mounted on the inner wall of the telescopic hole 12, and one end of the positioning spring 11 is fixedly mounted on the inner wall of the telescopic hole 12.
In this embodiment, the thimble 9 is mainly used to cooperate with the positioning hole 14 formed in the top of the insert 6, so as to reinforce the connection between the male end 3 and the female end 4, and the positioning spring 11 is mainly used to position and reset the thimble 9, wherein the initial state of the positioning spring 11 is in the original length state, and the telescopic amount of the thimble 9 is maximized.
Specifically, the size of the thimble 9 matches with the size of the telescopic hole 12, wherein the thimble 9 is T-shaped, the side edges of the two sides of the thimble 9 are movably connected with the inner wall of the limiting groove 13, and one end of the thimble 9 is provided with an arc blunt port.
In this embodiment, the outside of thimble 9 is provided with the stopper and spacing groove 13 cooperate and use and then reach the spacing effect to thimble 9, and wherein the blunt mouth of arc that the thimble 9 outside set up is mainly convenient for peg graft of thimble 9 and locating hole 14.
Specifically, the number of the positioning holes 14 is several groups and is linearly distributed on the top surface of the insert block 6, and the shape of the positioning holes 14 is circular.
In this embodiment, a plurality of groups of positioning holes 14 are provided to be mainly used for being matched with a plurality of groups of ejector pins 9, so as to further enhance the connection stability of the aluminum-zinc-plated steel plate 1.
The utility model discloses a theory of operation and use flow: when in use, two ends of two aluminum-zinc-plated steel plates 1 containing a sandwich layer 2 are respectively aligned, wherein a connecting male end 3 at one end of one aluminum-zinc-plated steel plate 1 is aligned with a connecting female end 4 at one end of the other aluminum-zinc-plated steel plate 1, then an inserting block 6 connected with one end of the male end 3 is inserted into the inner wall provided with a slot 5 at one end of the connecting female end 4, wherein the edge of the outer side of the inserting block 6 extrudes the inner side section of a thimble 9 in the inserting process, because the inner side end of the thimble 9 is provided with an arc blunt port, the thimble 9 contracts along the inner wall of a telescopic hole 12 under the extrusion of the inserting block 6, and a positioning spring 11 is in a compression state and stores certain elastic potential energy under the extrusion of the thimble 9, when the limiting block arranged on the outer side of the thimble 9 moves to the maximum position along the inner wall of the limiting groove 13, the thimble 9 also contracts to the maximum position at the moment, one end of the insert 6 is completely attached to the inner wall of the slot 5 at the moment, the thimble 9 rapidly resets under the action of elastic potential energy stored by the positioning spring 11 at the moment, the inner side end of the thimble 9 is rapidly inserted into the inner wall of the positioning hole 14 at the moment, and meanwhile, a plurality of groups of thimbles 9 are inserted into the positioning hole 14, so that the male end 3 and the female end 4 are spliced, the convenient installation effect of the aluminum-zinc-plated steel plates 1 is achieved, when the aluminum-zinc-plated steel plates 1 need to be disassembled, the two aluminum-zinc-plated steel plates 1 are forcefully pulled out to separate one end of the insert 6 from the inner wall of the slot 5, and then the disassembly is completed.
It should be noted that, in this document, terms such as "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrases "comprising a," "8230," "8230," or "comprising" does not exclude the presence of additional like elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a install convenient steel construction factory building aluminize zinc die mould battenboard, includes aluminize zinc steel sheet (1), its characterized in that: the middle part of the aluminum-zinc plated steel plate (1) is provided with a sandwich layer (2), one side of the aluminum-zinc plated steel plate (1) is spliced with a first connecting component, and the other side of the aluminum-zinc plated steel plate (1) is spliced with a second connecting component;
the first connecting component comprises a male connecting end (3), an inserting block (6), a positioning hole (14) and a first clamping groove (7), the male connecting end (3) is inserted into one end of the aluminum-zinc-plated steel plate (1), the inserting block (6) is arranged at one end of the male connecting end (3), the inserting block (6) is arranged on the top surface of the inserting block (6), and the first clamping groove (7) is arranged on the surface of the other end of the male connecting end (3);
the second connecting component comprises a female connecting end (4), a slot (5), a fixing nail (10) and a second clamping groove (8), the female connecting end (4) is connected with the other end of the aluminum-zinc-plated steel plate (1) in an inserting mode, the slot (5) is arranged on one end surface of the female connecting end (4), and the second clamping groove (8) is arranged on the other end surface of the female connecting end (4).
2. The aluminum-zinc plated profiled sandwich board convenient to install for the steel structure factory building, according to claim 1, is characterized in that: the second connecting assembly further comprises a telescopic hole (12) and a limiting groove (13), the inner side wall surfaces of the slots (5) are symmetrically formed in the telescopic hole (12), and the inner side wall of the telescopic hole (12) is formed in the limiting groove (13).
3. The aluminum-zinc plated profiled sandwich board convenient and fast to install for the steel structure workshop according to claim 1, and is characterized in that: and the second connecting assembly further comprises a thimble (9) and a positioning spring (11), the thimble (9) is movably mounted on the inner wall of the telescopic hole (12), and one end of the positioning spring (11) is fixedly mounted on the inner wall of the telescopic hole (12).
4. The aluminum-zinc plated profiled sandwich board convenient to install for the steel structure factory building, according to claim 3, is characterized in that: the size of the thimble (9) is matched with that of the telescopic hole (12), wherein the thimble (9) is T-shaped, the side edges of two sides of the thimble (9) are movably connected with the inner wall of the limiting groove (13), and one end of the thimble (9) is provided with an arc blunt port.
5. The aluminum-zinc plated profiled sandwich board convenient to install for the steel structure factory building, according to claim 1, is characterized in that: the number of the positioning holes (14) is a plurality of groups, the positioning holes are linearly distributed on the top surface of the inserting block (6), and the positioning holes (14) are circular.
CN202222939894.3U 2022-11-04 2022-11-04 Install convenient steel construction factory building aluminized zinc die mould battenboard Active CN218714287U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222939894.3U CN218714287U (en) 2022-11-04 2022-11-04 Install convenient steel construction factory building aluminized zinc die mould battenboard

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222939894.3U CN218714287U (en) 2022-11-04 2022-11-04 Install convenient steel construction factory building aluminized zinc die mould battenboard

Publications (1)

Publication Number Publication Date
CN218714287U true CN218714287U (en) 2023-03-24

Family

ID=85605010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222939894.3U Active CN218714287U (en) 2022-11-04 2022-11-04 Install convenient steel construction factory building aluminized zinc die mould battenboard

Country Status (1)

Country Link
CN (1) CN218714287U (en)

Similar Documents

Publication Publication Date Title
CN218714287U (en) Install convenient steel construction factory building aluminized zinc die mould battenboard
CN215716359U (en) Aluminum veneer for curtain wall convenient to assemble
CN214062015U (en) Non-bearing assembled novel wall
CN216042335U (en) Panel concatenation fastener and panel mosaic structure
CN115198929B (en) Wall body mounting frame structure
CN216893277U (en) PVC (polyvinyl chloride) spliced plate with fixing structure
CN215368185U (en) Novel integrative general formula triangle keel structure
CN215443086U (en) Concatenation formula building templates with waterproof construction
CN110056108B (en) Convenient mounting structure of curtain
CN110528806B (en) Install formula environmental protection coating board additional
CN112431402A (en) Building template
CN217897108U (en) Flush joint structure of shingle nail
CN202265977U (en) Fixed connecting piece for male and female slots of wood plastic boards
CN214885410U (en) Scaffold connecting device for building construction
CN216042336U (en) Dalle connection structure
CN216042371U (en) Novel plate connecting structure
CN215670451U (en) Card formula concatenation subassembly of inserting
CN217998573U (en) Board connection structure of assembled furred ceiling
CN214220377U (en) Modular wood-plastic assembled wall decoration for interior decoration
CN217215786U (en) High-strength assembled cable bridge
CN213206212U (en) Concatenation extension abnormal shape nest of tubes
CN216042337U (en) Panel concatenation tenon fourth of twelve earthly branches structure and panel connection structure
CN215670156U (en) Assembling structure of grid decorative plate and flat plate
CN220889046U (en) Wall connecting frame of color steel house
CN220987081U (en) Spliced corrugated board cat nest

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant