CN218352027U - Cable installation auxiliary frame for electric power engineering construction - Google Patents

Cable installation auxiliary frame for electric power engineering construction Download PDF

Info

Publication number
CN218352027U
CN218352027U CN202222486690.9U CN202222486690U CN218352027U CN 218352027 U CN218352027 U CN 218352027U CN 202222486690 U CN202222486690 U CN 202222486690U CN 218352027 U CN218352027 U CN 218352027U
Authority
CN
China
Prior art keywords
base
cable
auxiliary frame
electric power
power engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222486690.9U
Other languages
Chinese (zh)
Inventor
赵宪中
吴巨辉
张海燕
曹振华
刘法听
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Jintian Power Engineering Design Co ltd
Original Assignee
Henan Jintian Power Engineering Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Jintian Power Engineering Design Co ltd filed Critical Henan Jintian Power Engineering Design Co ltd
Priority to CN202222486690.9U priority Critical patent/CN218352027U/en
Application granted granted Critical
Publication of CN218352027U publication Critical patent/CN218352027U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model relates to a cable erection auxiliary technical field discloses a cable erection auxiliary frame for electric power engineering construction, the on-line screen storage device comprises a base, fixed mounting has the fixed column on the base, fixed mounting has a plurality of climbing handles on the fixed column, be equipped with the moving part that drives the cable activity on the fixed column, the moving part includes conveyer belt and rubber card strip, the vertical setting of conveyer belt is on the fixed column, rubber card strip fixed mounting is on the conveyer belt, the bottom fixed mounting of base has the universal wheel, be provided with the ground piece of grabbing that prevents the base to remove on the base. The cable laying device aims to solve the problems that the existing cable is complex to install, large in operation difficulty coefficient, huge in workload, low in work risk coefficient and low in construction efficiency due to various defects of the traditional method, and the laying progress of the cable is influenced, and the physical strength of constructors is greatly tested.

Description

Cable installation auxiliary frame for electric power engineering construction
Technical Field
The utility model belongs to the technical field of the cable installation is supplementary, concretely relates to cable installation auxiliary frame for electric power engineering construction.
Background
The wire and cable is used for transmitting electric (magnetic) energy, information and wire products for realizing electromagnetic energy conversion. A wire cable in a broad sense, also referred to as a cable for short, refers to an insulated cable, which can be defined as: an aggregate consisting of; one or more insulated wire cores, and their respective possible coatings, total protective layers and outer jackets, the cable may also have additional conductors without insulation.
For some areas with special conditions, an overhead cable needs to be laid outdoors to achieve the purpose of transmitting electric energy, two construction personnel are usually adopted for laying the cable, the two construction personnel climb onto two telegraph poles respectively, the cable is pulled to an iron cable position by hands, and then the iron cable and the cable are fixed by another working personnel.
SUMMERY OF THE UTILITY MODEL
The utility model aims at: the cable laying device solves the problems that the existing cable is complex to install, large in operation difficulty coefficient, huge in workload, low in work risk coefficient and low in construction efficiency due to various defects of a traditional method, and the laying progress of the cable is influenced, and the physical strength of constructors is greatly tested.
In order to realize the technical purpose, the utility model discloses a technical scheme as follows:
the utility model provides a cable installation auxiliary frame for electric power engineering construction, includes the base, fixed mounting has the fixed column on the base, fixed mounting has a plurality of climbing handles on the fixed column, be equipped with the moving part that drives the cable activity on the fixed column.
Further inject, the moving part includes conveyer belt and rubber card strip, the vertical setting of conveyer belt is on the fixed column, rubber card strip fixed mounting is on the conveyer belt.
Further, the bottom of the base is fixedly provided with universal wheels, and the base is provided with a ground grabbing piece for preventing the base from moving.
Further inject, grab ground piece and include the fixing base, rotate on the fixing base and install the rotor plate, fixed mounting has a plurality of pawl on the rotor plate.
Further inject, the through-hole has been seted up on the fixing base, the rotating plate has seted up the bar groove with the fixing base rotation installation department, movable mounting has the U-shaped movable rod on the base, the tip activity of U-shaped movable rod is pegged graft in the through-hole, and when the pawl stretched into the ground, the U-shaped movable rod stretched into the bar inslot.
Further limited, a reinforcing rib is fixedly arranged between the base and the fixed column.
Adopt above-mentioned technical scheme's utility model, have following advantage:
1. the utility model discloses, set up the moving part that drives the cable activity on the fixed column, when the workman scrambleed to the fixed column upper end, the accessible moving part upwards drove the cable, made things convenient for the workman to take, improved the efficiency of laying of cable.
2. The utility model discloses, set up the universal wheel in the bottom of base, conveniently remove the auxiliary frame, after pushing away to the mounting point, change the rotor plate to pressing close to with ground, make the pawl on the rotor plate stretch into ground, increased the frictional force on base and ground, prevent that the auxiliary frame from producing in the use and sliding.
3. The utility model discloses, after the pawl on the rotor plate stretched into ground, the U-shaped movable rod passed the through-hole and stretched into the bar inslot, prevented that the rotor plate from rotating, made the rotor plate produce the supporting role to the auxiliary frame, avoided the auxiliary frame to produce and emptyd.
Drawings
The present invention can be further illustrated by the non-limiting examples given in the accompanying drawings;
fig. 1 is a schematic structural view of the cable installation auxiliary frame for power engineering construction of the present invention;
fig. 2 is a schematic structural view of the U-shaped movable rod of the auxiliary cable installation frame for power engineering in a state of being separated from the fixed seat;
FIG. 3 is an enlarged schematic view of the structure at A in FIG. 2;
FIG. 4 is an enlarged schematic view of the structure at B in FIG. 2;
fig. 5 is the utility model relates to a structure schematic diagram of transfer plate in cable installation auxiliary frame for electric power engineering construction.
The main element symbols are as follows:
1. a base; 2. fixing the column; 3. climbing a handle;
4. a conveyor belt; 41. rubber clamping strips;
5. a fixed seat; 51. a rotating plate; 52. chamfering; 53. a through hole; 54. a U-shaped movable rod;
6. and (7) reinforcing ribs.
Detailed Description
The present invention will be described in detail with reference to the drawings and specific embodiments, and it should be noted that in the drawings or the description, similar or identical parts are provided with the same reference numerals, and the implementation manner not shown or described in the drawings is known to those of ordinary skill in the art. In addition, directional terms, such as "upper", "lower", "top", "bottom", "left", "right", "front", "rear", and the like, used in the embodiments are only directions referring to the drawings, and are not intended to limit the scope of the present invention.
As shown in fig. 1-5, the utility model discloses a cable installation auxiliary frame for electric power engineering construction, including base 1, fixed mounting has fixed column 2 on the base 1, and fixed mounting has a plurality of climbing handles 3 on the fixed column 2, is equipped with the moving part that drives the cable activity on the fixed column 2.
The moving part includes conveyer belt 4 and rubber card strip 41, and 4 vertical settings of conveyer belt are on fixed column 2, and 41 fixed mounting of rubber card strip are on conveyer belt 4.
The bottom of base 1 is fixed with the universal wheel, is provided with on the base 1 to prevent the ground piece of grabbing that base 1 removed.
The ground grabbing piece comprises a fixed seat 5, a rotating plate 51 is rotatably mounted on the fixed seat 5, and a plurality of inverted teeth 52 are fixedly mounted on the rotating plate 51.
The fixing seat 5 is provided with a through hole 53, the rotary mounting position of the rotary plate 51 and the fixing seat 5 is provided with a strip-shaped groove, the base 1 is movably provided with a U-shaped movable rod 54, the end part of the U-shaped movable rod 54 is movably inserted in the through hole 53, and when the inverted tooth 52 extends into the ground, the U-shaped movable rod 54 extends into the strip-shaped groove.
A reinforcing rib 6 is fixedly arranged between the base 1 and the fixed column 2.
The utility model discloses a use method as follows:
when the auxiliary frame is used, the auxiliary frame is pushed to the mounting point, the rotating plate 51 is rotated until the auxiliary frame is rotated to be close to the ground, and the inverted teeth 52 extend into the ground, so that the friction force between the base 1 and the ground is increased, and the auxiliary frame is prevented from sliding in the using process;
after the inverted teeth 52 on the rotating plate 51 extend into the ground, the U-shaped movable rod 54 penetrates through the through hole 53 and extends into the strip-shaped groove, so that the rotating plate 51 is prevented from rotating, the rotating plate 51 can support the auxiliary frame, and the auxiliary frame is prevented from toppling;
go into between rubber card strip 41 and the conveyer belt 4 with cable end card, when constructor climbs to fixed column 2 upper end through climbing handle 3, conveyer belt 4 work upwards drives the cable, makes things convenient for the constructor to take, has improved the efficiency of laying of cable.
It is right above the utility model provides a pair of cable installation auxiliary frame for electric power engineering construction has carried out detailed introduction. The description of the specific embodiments is only intended to facilitate an understanding of the method of the invention and its core concept. It should be noted that, for those skilled in the art, without departing from the principle of the present invention, the present invention can be further modified and modified, and such modifications and modifications also fall within the protection scope of the appended claims.

Claims (6)

1. The utility model provides a cable installation auxiliary frame for electric power engineering construction, includes base (1), its characterized in that: the cable climbing device is characterized in that a fixing column (2) is fixedly mounted on the base (1), a plurality of climbing handles (3) are fixedly mounted on the fixing column (2), and a moving part for driving a cable to move is arranged on the fixing column (2).
2. The cable installation auxiliary frame for electric power engineering construction as claimed in claim 1, wherein: the moving part comprises a conveying belt (4) and rubber clamping strips (41), the conveying belt (4) is vertically arranged on the fixed column (2), and the rubber clamping strips (41) are fixedly arranged on the conveying belt (4).
3. The cable installation auxiliary frame for electric power engineering construction as claimed in claim 1, wherein: the bottom fixed mounting of base (1) has the universal wheel, be provided with the piece of grabbing that prevents base (1) removal on base (1).
4. The cable installation auxiliary frame for electric power engineering construction as claimed in claim 3, wherein: grab ground piece and include fixing base (5), rotate on fixing base (5) and install rotating plate (51), fixed mounting has a plurality of pawl (52) on rotating plate (51).
5. The cable installation auxiliary frame for electric power engineering construction as claimed in claim 4, wherein: the improved structure is characterized in that the fixing seat (5) is provided with a through hole (53), the rotating plate (51) and the fixing seat (5) are rotatably installed to form a strip-shaped groove, the base (1) is movably provided with a U-shaped movable rod (54), the end part of the U-shaped movable rod (54) is movably inserted into the through hole (53), and when the inverted tooth (52) extends into the ground, the U-shaped movable rod (54) extends into the strip-shaped groove.
6. The cable installation auxiliary frame for electric power engineering construction as claimed in claim 1, wherein: and a reinforcing rib (6) is fixedly arranged between the base (1) and the fixing column (2).
CN202222486690.9U 2022-09-20 2022-09-20 Cable installation auxiliary frame for electric power engineering construction Active CN218352027U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222486690.9U CN218352027U (en) 2022-09-20 2022-09-20 Cable installation auxiliary frame for electric power engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222486690.9U CN218352027U (en) 2022-09-20 2022-09-20 Cable installation auxiliary frame for electric power engineering construction

Publications (1)

Publication Number Publication Date
CN218352027U true CN218352027U (en) 2023-01-20

Family

ID=84918551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222486690.9U Active CN218352027U (en) 2022-09-20 2022-09-20 Cable installation auxiliary frame for electric power engineering construction

Country Status (1)

Country Link
CN (1) CN218352027U (en)

Similar Documents

Publication Publication Date Title
CN107013080B (en) A kind of power grid electric pole erection construction method
CN205377168U (en) Erect leap device of power transmission line
CN113315044A (en) Cable termination for electric power construction
CN209855803U (en) Comprehensive trolley for tunnel construction
CN218352027U (en) Cable installation auxiliary frame for electric power engineering construction
CN208553034U (en) A kind of Multifunctional sports volleyball post
CN202094530U (en) Moving pulley for reeling and unreeling overhead cables in bypass operation
CN210084604U (en) Electric power construction project management device
CN211377405U (en) Laying tool for high-voltage cable
CN206148640U (en) Wire earth clamp with two hanging wire modes
CN111725725B (en) Multifunctional wire arranging tool vehicle for assembling distribution box and using method thereof
CN210885083U (en) Cable trench cover carrying device
CN207920040U (en) A kind of intelligent construction Special hanging basket
CN207889768U (en) A kind of handling device
CN212695441U (en) Cable breakpoint wiring device for power engineering
CN212751478U (en) Low-voltage power distribution cabinet
CN216959123U (en) Bridge installation auxiliary device for safety type cable construction
CN221396544U (en) Construction cable erection device for power engineering
CN209786650U (en) Drawing tool for cable laying
CN214133354U (en) Semi-hard coaxial cable outer conductor drawing device
CN211830023U (en) Reinforced assembled support for subway traffic
CN214411728U (en) Device is installed and removed to transformer substation's earth connection
CN217947614U (en) Transportation lifting device for power transformation and distribution equipment
CN216808034U (en) Three-dimensional operation auxiliary device of electric power construction