CN218285867U CN202222313070.5U CN202222313070U CN218285867U CN 218285867 U CN218285867 U CN 218285867U CN 202222313070 U CN202222313070 U CN 202222313070U CN 218285867 U CN218285867 U CN 218285867U
Authority
CN
China
Prior art keywords
cable testing
testing bridge
install
mounting
drilling device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222313070.5U
Other languages
Chinese (zh)
Inventor
彭文骥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Haopeng Electromechanical Equipment Co ltd
Original Assignee
Hunan Haopeng Electromechanical Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Haopeng Electromechanical Equipment Co ltd filed Critical Hunan Haopeng Electromechanical Equipment Co ltd
Priority to CN202222313070.5U priority Critical patent/CN218285867U/en
Application granted granted Critical
Publication of CN218285867U publication Critical patent/CN218285867U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a drilling equipment is used in processing of big interval cable testing bridge belongs to cable testing bridge processing equipment field, including the equipment base, two stamping die are installed to the top symmetry of equipment base, install an erection joint board on two stamping die, install a fixed knot on the erection joint board and construct, fixed knot constructs and contains mounting substrate, the slipmat, the spliced pole, limit baffle and supporting spring, the slipmat has four and the symmetry to install the lower extreme at mounting substrate, the spliced pole has two and the symmetry to install the upper end at mounting substrate, through setting up fixed knot structure and fixed suction cup, make it mutually support, can be before stamping die contacts with big span cable testing bridge, fix big span cable testing bridge, thereby reduce the probability that produces the skew at the big span cable testing bridge of the in-process that punches, finally promote the precision that big span cable testing bridge punched, make the equipment of changing of big span cable testing bridge later stage.

Description

Drilling equipment is used in processing of big interval cable testing bridge
Technical Field
The utility model relates to a cable testing bridge processing equipment field, in particular to drilling equipment is used in processing of big interval cable testing bridge.
Background
The large-spacing cable bridge is assembled by pultrusion glass fiber reinforced plastic profiles and is suitable for power cables, control cables, lighting cables, accessories and the like. Compared with an iron bridge frame, the bridge frame has the advantages of long service life, convenience in installation, low cost, convenience in cutting, no need of maintenance and the like. Each bridge has 6 connecting holes at each end when the height of the bridge is 50 and 100, and each bridge has 12 connecting holes at each end when the height of the bridge is 150 and 200. The large-space cable bridge frame needs to be punched by punching equipment during machining, so that the subsequent assembly of the large-space cable bridge frame is facilitated.
Big interval cable bridge is in punching man-hour, because its length is longer, thereby make it receive the collision at the in-process that punches and produce the skew more easily, the perforating device of big interval cable bridge that has now simultaneously does not have corresponding fixed knot structure again when using, thereby make big interval cable bridge to punch man-hour, stamping die and the one-tenth of big interval cable bridge contact in the twinkling of an eye, big interval cable bridge produces the displacement easily, and then the position that punches produces the skew easily, finally influence the connection equipment in later stage.
SUMMERY OF THE UTILITY MODEL
To the problem that exists among the prior art, the utility model aims to provide a drilling equipment is used in processing of big span cable testing bridge can make it mutually support through setting up fixed knot structure and fixed suction cup, can be before stamping die and the contact of big span cable testing bridge, fix big span cable testing bridge to reduce the probability that produces the skew at the in-process big span cable testing bridge that punches, finally promote the precision that big span cable testing bridge punched, make the equipment of changing in big span cable testing bridge later stage.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a drilling equipment is used in processing of big interval cable testing bridge, includes the equipment base, two stamping die are installed to the top symmetry of equipment base, two install an erection joint board on the stamping die, install a fixed knot on the erection joint board and construct, fixed knot constructs contains mounting substrate, slipmat, spliced pole, limit baffle and supporting spring, the lower extreme at mounting substrate is installed to four and symmetry in the slipmat, the spliced pole has two and the symmetry to install the upper end at mounting substrate, limit baffle has two and installs respectively in the upper end of two spliced poles, supporting spring has two and overlaps respectively to establish on two spliced poles, install fixed suction cup in fixed knot structure's below on the equipment base.
Preferably, two support frames are symmetrically installed at the upper end of the equipment base, the equipment base and the support frames are fixedly installed together through bolts, and an installation groove is formed in the upper end of the equipment base between the two support frames.
Preferably, two a hydraulic cylinder structure is all installed to stamping die's upper end, hydraulic cylinder structural mounting is in the upper end of support frame, stamping die sets up the inboard at the support frame.
Preferably, the mounting and connecting plate is fixedly mounted on the two stamping dies through screws, two mounting through holes are symmetrically formed in the mounting and connecting plate, and the two mounting through holes penetrate through the upper end and the lower end of the mounting and connecting plate.
Preferably, the mounting base plate and the non-slip mat on the fixing structure are fixedly mounted together through viscose, the connecting column and the mounting base plate are of an integrally formed structure, the mounting base plate is located below the mounting connecting plate, the limiting baffle is located above the mounting connecting plate, the connecting column penetrates through the mounting through hole upwards and then is fixedly mounted together with the limiting baffle through screws, and the supporting spring is located between the mounting connecting plate and the mounting base plate.
Preferably, the fixed sucker is fixedly installed in an installation groove formed in the upper end of the equipment base through a screw.
Compared with the prior art, the utility model discloses following beneficial effect has:
through setting up fixed knot structure and fixed suction cup, make it mutually support, can be before stamping die and the contact of big span cable testing bridge, fix big span cable testing bridge to reduce the probability that produces the skew at the big span cable testing bridge of in-process that punches, finally promote the precision that big span cable testing bridge punched, make the equipment of changeing in big span cable testing bridge later stage.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic structural view of the fixing structure of the present invention;
fig. 3 is a schematic structural diagram of the mounting connection plate of the present invention.
In the figure: 1. an equipment base; 2. stamping a die; 3. mounting a connecting plate; 4. a fixed structure; 5. fixing the sucker; 6. a support frame; 7. a hydraulic cylinder structure; 8. mounting through holes; 9. a mounting substrate; 10. a non-slip mat; 11. connecting columns; 12. a limit baffle; 13. supporting the spring.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
Please refer to fig. 1 and fig. 3, a drilling device for processing a large-space cable bridge comprises an equipment base 1, two support frames 6 are symmetrically installed at the upper end of the equipment base 1, the equipment base 1 and the support frames 6 are fixedly installed together through bolts, an installation groove is formed between the two support frames 6 at the upper end of the equipment base 1, two stamping dies 2 are symmetrically installed above the equipment base 1, a hydraulic cylinder structure 7 is installed at the upper ends of the two stamping dies 2, the hydraulic cylinder structure 7 is installed at the upper end of the support frame 6, the stamping dies 2 are arranged at the inner sides of the support frames 6, an installation connecting plate 3 is installed on the two stamping dies 2, the installation connecting plate 3 is fixedly installed on the two stamping dies 2 through screws, two installation through holes 8 are symmetrically formed in the installation connecting plate 3, the two installation through holes 8 penetrate through the upper end and the lower end of the installation connecting plate 3, when the drilling device is used, the hydraulic cylinder structure 7 can push the stamping dies 2 to move downwards, and finally the stamping dies 2 can open holes of the large-space cable bridge below the installation connecting plate.
Please refer to fig. 1, as shown in fig. 2, a fixing structure 4 is installed on the installation connecting plate 3, the fixing structure 4 includes two installation substrates 9, non-slip mats 10, connection columns 11, limit baffles 12 and support springs 13, the non-slip mats 10 have four and are symmetrically installed at the lower ends of the installation substrates 9, the connection columns 11 have two and are symmetrically installed at the upper ends of the installation substrates 9, the limit baffles 12 have two and are respectively installed at the upper ends of the two connection columns 11, the support springs 13 have two and are respectively sleeved on the two connection columns 11, the installation substrates 9 and the non-slip mats 10 on the fixing structure 4 are fixedly installed together through adhesives, the connection columns 11 and the installation substrates 9 are of an integrated structure, the installation substrates 9 are located below the installation connecting plate 3, the limit baffles 12 are located above the installation connecting plate 3, the connection columns 11 are fixedly installed together with the limit baffles 12 after upwards passing through the installation through holes 8, the support springs 13 are located between the installation connecting plate 3 and the installation substrates 9, fixing suckers 5 are installed below the fixing structures on the fixing structure 4 on the equipment base 1, the cable rack can be matched with the cable in the later stage of punching process of punching a cable bridge, thereby the cable punching process is easier.
It should be noted that, the utility model relates to a drilling equipment is used in processing of big interval cable testing bridge, when using, the big interval cable testing bridge that waits to punch can be sent to two stamping die 2's below, big interval cable testing bridge also can be in between fixed suction cup 5 and the fixed knot structure 4 simultaneously, after the position of big interval cable testing bridge is suitable, fixed suction cup 5 can start to adsorb big interval cable testing bridge fixedly, pneumatic cylinder structure 7 can promote stamping die 2 and move down after that, fixed knot constructs 4 at this moment and can be along with stamping die 2 together moves down, before stamping die 2 contacts big interval cable testing bridge, slipmat 10 on the fixed knot constructs 4 can take the lead to contact big interval cable testing bridge earlier, thereby its fixed knot constructs 4 and can further compress tightly big interval cable testing bridge fixedly, along with the continuation of stamping die 2 move down, the supporting spring 13 on the fixed knot constructs 4 also can be compressed slowly, finally until big interval cable testing bridge accomplishes to punch, pneumatic cylinder structure 7 can make punching die 2 and fixed knot construct 4 and make progress and drive until final fixed knot construct 4 and break away from the contact, the contact with big interval cable testing bridge breaks away from the work simultaneously, thereby the cable testing bridge also can be loosened greatly to the cable testing bridge, thereby it further.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a drilling equipment is used in processing of large-interval cable testing bridge, includes equipment base (1), two stamping die (2), its characterized in that are installed to the top symmetry of equipment base (1): two install an erection joint board (3) on stamping die (2), install a fixed knot on erection joint board (3) and construct (4), fixed knot constructs (4) and contains mounting substrate (9), slipmat (10), spliced pole (11), limit baffle (12) and supporting spring (13), slipmat (10) have four and the symmetry to install the lower extreme in mounting substrate (9), spliced pole (11) have two and the symmetry to install the upper end in mounting substrate (9), limit baffle (12) have two and install the upper end at two spliced poles (11) respectively, supporting spring (13) have two and establish respectively on two spliced poles (11), install fixed suction cup (5) in the below of fixed knot constructs (4) on equipment base (1).
2. The drilling device for machining the large-spacing cable bridge frame as claimed in claim 1, wherein the drilling device comprises: two support frames (6) are symmetrically installed at the upper end of the equipment base (1), the equipment base (1) and the support frames (6) are fixedly installed together through bolts, and an installation groove is formed in the upper end of the equipment base (1) between the two support frames (6).
3. The drilling device for machining the large-spacing cable bridge frame as claimed in claim 2, wherein the drilling device comprises: two a hydraulic cylinder structure (7) is all installed to the upper end of stamping die (2), the upper end at support frame (6) is installed in hydraulic cylinder structure (7), stamping die (2) set up the inboard at support frame (6).
4. The drilling device for machining the large-spacing cable bridge frame as claimed in claim 3, wherein the drilling device comprises: the mounting connecting plate (3) is fixedly mounted on the two stamping dies (2) through screws, two mounting through holes (8) are symmetrically formed in the mounting connecting plate (3), and the mounting through holes (8) penetrate through the upper end and the lower end of the mounting connecting plate (3).
5. The drilling device for machining the large-spacing cable bridge frame as claimed in claim 4, wherein the drilling device comprises: mounting substrate (9) and slipmat (10) on fixed knot constructs (4) are in the same place through viscose fixed mounting, spliced pole (11) and mounting substrate (9) are the integrated into one piece structure, mounting substrate (9) are located the below of erection joint board (3), limit baffle (12) are located the top of erection joint board (3), spliced pole (11) upwards pass behind installation through-hole (8) and pass through screw fixed mounting with limit baffle (12) together, supporting spring (13) are located between erection joint board (3) and mounting substrate (9).
6. The drilling device for machining the large-spacing cable bridge frame as claimed in claim 5, wherein the drilling device comprises: the fixed sucker (5) is fixedly installed in an installation groove formed in the upper end of the equipment base (1) through a screw.
CN202222313070.5U 2022-09-01 2022-09-01 Drilling equipment is used in processing of big interval cable testing bridge Active CN218285867U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222313070.5U CN218285867U (en) 2022-09-01 2022-09-01 Drilling equipment is used in processing of big interval cable testing bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222313070.5U CN218285867U (en) 2022-09-01 2022-09-01 Drilling equipment is used in processing of big interval cable testing bridge

Publications (1)

Publication Number Publication Date
CN218285867U true CN218285867U (en) 2023-01-13

Family

ID=84812634

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222313070.5U Active CN218285867U (en) 2022-09-01 2022-09-01 Drilling equipment is used in processing of big interval cable testing bridge

Country Status (1)

Country Link
CN (1) CN218285867U (en)

Similar Documents

Publication Publication Date Title
CN218285867U (en) Drilling equipment is used in processing of big interval cable testing bridge
CN213294364U (en) Elevartor shaft frame construction based on BIM model processing that becomes more meticulous
CN210125667U (en) Large-tonnage quick stamping device
CN112296908A (en) Dedicated mechanical clamping device of hauler production
CN111974877B (en) Forming processing method for mounting metal anchoring part on integrated decorative curtain wall
CN216055286U (en) High-strength quick-pressing elastic sheet
CN218873797U (en) Section bar punching and pressing tool
CN220127375U (en) Punch press is used in production of copper covered steel earth bar
CN216732165U (en) Punching device of projector heat dissipation shell
CN217578670U (en) Photovoltaic glass punching calendering roller
CN218286001U (en) Air vent density adjusting device for aerated brick production and processing
CN220993419U (en) Nut pressing mechanism
CN221388487U (en) Arc forming die
CN216803278U (en) Novel press-fit pole tool
CN215148632U (en) High-elastic centering installation equipment of unit
CN215319378U (en) Connecting and limiting device for die table and platform
CN212076097U (en) Hauler installing support
CN220970562U (en) Battery steel casing panel beating punching press frock
CN214601379U (en) High-precision punching die for automobile parts
CN220659288U (en) Perforating device is used in aluminium piece processing
CN210816953U (en) Follow-on scaffold frame puncher
CN220928386U (en) Light steel keel paper gypsum board
CN221434619U (en) Novel steel plate punching mechanism
CN220901617U (en) Motorcycle accessory punching device
CN212019135U (en) Plum blossom structure nut stamping die

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant