CN217810482U - Device for capping hollow bridge pier - Google Patents

Device for capping hollow bridge pier Download PDF

Info

Publication number
CN217810482U
CN217810482U CN202222107571.8U CN202222107571U CN217810482U CN 217810482 U CN217810482 U CN 217810482U CN 202222107571 U CN202222107571 U CN 202222107571U CN 217810482 U CN217810482 U CN 217810482U
Authority
CN
China
Prior art keywords
capping
hollow
prefabricated plate
pouring
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222107571.8U
Other languages
Chinese (zh)
Inventor
雷鹏波
王飞
焦翔
侯宇天
张天忠
曹福
叶世良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Railway Construction Co Ltd
Original Assignee
CCCC Second Railway Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Railway Construction Co Ltd filed Critical CCCC Second Railway Construction Co Ltd
Priority to CN202222107571.8U priority Critical patent/CN217810482U/en
Application granted granted Critical
Publication of CN217810482U publication Critical patent/CN217810482U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a device for hollow mound of bridge capping relates to hollow mound technical field of bridge, including hollow mound body and prefabricated plate, the inner wall of hollow mound body is provided with the mount table, the beneficial effects of the utility model are that: through pouring the mount table in advance in its department of being about to the capping when pouring hollow mound body and be used for putting up the scaffold, be convenient for the installation sets up the template, square steel crossbeam and square timber erect the roof beam, it shortens greatly with putting up the scaffold distance from the bottom to put up the scaffold at the top of mount table, thereby reduce and put construction cycle, reduce dismouting work load, reduce manpower construction cost, the capping of more being convenient for is used, place platform and prefabricated plate through setting up in advance, can directly place the prefabricated plate when carrying out the capping through prefabricated plate in advance and place the bench side, increase concrete placement intensity, and reduced the construction cycle that lays the reinforcing bar on the template and be used for increasing concrete strength, reduce construction period again, construction intensity has been guaranteed simultaneously.

Description

Device for capping hollow bridge pier
Technical Field
The utility model relates to a hollow mound technical field of bridge specifically is a device that is used for hollow mound of bridge to seal a roof.
Background
The hollow pier is a hollow pier, and refers to a pier which is made of concrete or reinforced concrete into a hollow thin-wall structure and the like, the hollow pier structure is widely applied to bridge design, and the manufactured pier has the advantages of small sectional area, large section modulus, material saving, light dead weight, and good structural rigidity and strength. However, in the construction process of the hollow pier structure, when the beam part of the hollow pier cavity top cover is constructed, a direct manhole cannot be arranged on the pier top, an auxiliary structure is required, when the hollow pier is capped, a scaffold with the same height as the pier per se needs to be built in the hollow pier, and then a template can be laid for pouring concrete for capping, but the construction mode has the following defects; the scaffold is long in construction period from the bottom of the hollow pier, inconvenient to construct, large in later-period dismantling workload, time-consuming and labor-consuming, and high in construction cost, so that the device for capping the hollow pier of the bridge is provided.
SUMMERY OF THE UTILITY MODEL
The utility model provides a be not enough to prior art, the utility model provides a device for hollow mound of bridge binds has solved the problem that proposes in the above-mentioned background art.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a device for hollow mound of bridge binds, includes hollow mound body and prefabricated plate, the inner wall of hollow mound body is provided with the mount table, the scaffold frame is installed at the top of mount table, the top fixed mounting of scaffold frame has the template, the square steel crossbeam is installed to the top of the inside form of hollow mound body, the square wood is installed at the top of square steel crossbeam and is erected the roof beam.
Preferably, the inside of hollow mound body and the top that is located the square steel crossbeam are provided with places the platform, the prefabricated plate with place the platform cooperation, a plurality of pouring hole has been seted up to the inside of prefabricated plate, two connecting rods are installed at the top of prefabricated plate, the top fixed mounting of connecting rod has rings, the top of prefabricated plate is provided with the strengthening rib.
Preferably, a pouring bin is arranged above the template and on the inner side of the placing table, and bin sealing concrete is poured inside the pouring bin.
Preferably, the pouring hole is matched with the cabin sealing concrete.
Preferably, the top of the precast slab is also poured with cabin sealing concrete.
Preferably, top beams are poured on the top of the hollow pier body and the top of the cabin sealing concrete.
The utility model provides a device for hollow mound of bridge seals, possesses following beneficial effect:
1. this a device for hollow mound of bridge binds, through when pouring the hollow mound body it is about to bind the mount table in advance and be used for building the scaffold frame in the department of pouring, be convenient for the installation set up template, square steel crossbeam and square timber and erect the roof beam, build the scaffold frame at the top of mount table and build the scaffold frame distance from the bottom and shorten greatly to the construction cycle is built in the reduction, reduces dismouting work load, reduces manpower construction cost, the use of more being convenient for binds.
2. This a device for hollow mound of bridge capping places platform and prefabricated plate through setting up in advance, can directly place the prefabricated plate and place the bench side through prefabricated plate in advance when carrying out the capping, increases concrete placement intensity, and has reduced the construction cycle that lays the reinforcing bar and be used for increasing the concrete intensity on the template, reduces construction period again, has guaranteed construction strength simultaneously.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the pouring of the present invention;
fig. 3 is a schematic diagram of the prefabricated panels of the present invention.
In the figure: 1. a hollow pier body; 2. a mounting table; 3. a scaffold; 4. a template; 5. a square steel beam; 6. a square wood vertical beam; 7. a placing table; 8. prefabricating a slab; 9. a pouring hole; 10. a connecting rod; 11. a hoisting ring; 12. reinforcing ribs; 13. a storehouse is poured; 14. sealing the concrete; 15. a top beam.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 3, the present invention provides a technical solution: a device for capping a hollow bridge pier comprises a hollow pier body 1 and precast slabs 8, wherein a pouring bin 13 is arranged above a template 4 and on the inner side of a placing table 7, the interior of the template 4 and the precast slabs 8 is hollow after the template 4 and the precast slabs 8 are installed when the bin 13 are poured, bin sealing concrete 14 is poured above the inner template 4 of the hollow pier body 1 so as to form capping, the bin sealing concrete 14 is poured inside the pouring bin 13, the bin sealing concrete 14 is also poured on the top of the precast slabs 8, top beams 15 are poured on the tops of the hollow pier body 1 and the bin sealing concrete 14,
the inner wall of hollow pier body 1 is provided with mount table 2, mount table 2 is the device of pouring hollow pier body 1 simultaneously, it is short apart from hollow pier body 1 top distance, it is short to build 3 periods of scaffold, the takedown time is also short, scaffold 3 is installed at the top of mount table 2, scaffold 3's top fixed mounting has template 4, template 4 is the board that current hollow pier construction concreting used, need demolish it after having pour concrete setting, square steel crossbeam 5 is installed to the top of hollow pier body 1's inside template 4, square steel crossbeam 5's top is installed square timber and is erected roof beam 6, square steel crossbeam 5 and square timber erect roof beam 6's primary function is the intensity that is used for reinforcing concrete 14 of closing a storehouse, through pouring mount table 2 in advance at it will be about to close a department when pouring hollow pier body 1, be used for building scaffold 3, be convenient for the installation and set up template 4, square steel crossbeam 5 and square timber erect roof beam 6, scaffold 3 and follow bottom 3 distance greatly shorten at the top of mount table 2, thereby reduce and build the construction period, reduce the construction work volume, the dismouting of being convenient for building, the construction cost of construction is more used.
The inside of hollow pier body 1 and the top that is located square steel crossbeam 5 are provided with places platform 7, prefabricated plate 8 and the cooperation of placing platform 7, a plurality of pouring hole 9 has been seted up to the inside of prefabricated plate 8, the main effect of pouring hole 9 is convenient for pour a sealed storehouse concrete 14 to pouring 13 inside, also can pour a sealed storehouse concrete 14 to pouring 13 in advance certainly, after pouring and accomplishing hoist prefabricated plate 8 to cooperating with placing platform 7 again, prefabricated plate 8's main effect is through prefabricated reinforcing rib 12 increase sealed storehouse concrete 14's intensity with setting up in advance, reduce construction cycle, pouring hole 9 and the cooperation of sealed storehouse concrete 14, two connecting rods 10 are installed at prefabricated plate 8's top, connecting rod 10's top fixed mounting has rings 11, rings 11's main effect is used for the later stage to hoist through the loop wheel machine and go into hollow pier body 1 inside and place platform 7 cooperation, prefabricated plate 8's top is provided with reinforcing rib 12, place platform 7 and prefabricated plate 8 through setting up in advance, can directly place prefabricated plate 8 when carrying out the capping through the prefabricated plate 8 in advance and place platform 7 top, reduce and increase the construction period of construction again, the construction intensity of construction is used for the construction, the construction intensity of concrete reduction once more, construction time has been used for the construction period.
To sum up, when the device for capping the hollow bridge pier is used, firstly, a scaffold 3 is built above an installation platform 2, then a template 4, a square steel crossbeam 5 and a square wood vertical beam 6 are laid, after the scaffold is completed, a crane is used for matching with a hanging ring 11 to hoist a precast slab 8 to the position above a placing platform 7 in a hollow pier body 1, and then, cabin sealing concrete 14 can be poured for capping, and the cabin sealing concrete 14 enters a pouring cabin 13 through a pouring hole 9 during pouring; in another mode, the closed bin concrete 14 can be poured into the pouring bin 13 in advance, then the prefabricated slab 8 is hoisted, the method is flexible and changeable, finally, the top of the prefabricated slab 8 is fully poured through the closed bin concrete 14, capping can be completed, after the capping is completed, the top beam 15 is poured above the hollow pier body 1 and the closed bin concrete 14, finally, the scaffold 3 and the template 4 can be detached after the concrete is solidified, and the device is short in construction period and low in personnel cost during installation and detachment.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a device for hollow mound of bridge capping, includes hollow mound body (1) and prefabricated plate (8), its characterized in that: the inner wall of hollow mound body (1) is provided with mount table (2), scaffold (3) are installed at the top of mount table (2), the top fixed mounting of scaffold (3) has template (4), square steel crossbeam (5) are installed to the top of inside forms (4) of hollow mound body (1), square wood is installed at the top of square steel crossbeam (5) and is erected roof beam (6).
2. The device for capping the hollow pier of the bridge according to claim 1, wherein: the inside of hollow mound body (1) and the top that is located square steel crossbeam (5) are provided with places platform (7), prefabricated plate (8) with place platform (7) cooperation, a plurality of pouring hole (9) have been seted up to the inside of prefabricated plate (8), two connecting rods (10) are installed at the top of prefabricated plate (8), the top fixed mounting of connecting rod (10) has rings (11), the top of prefabricated plate (8) is provided with strengthening rib (12).
3. The device for capping the hollow pier of the bridge according to claim 1, wherein: a pouring bin (13) is arranged above the template (4) and on the inner side of the placing platform (7), and bin sealing concrete (14) is poured inside the pouring bin (13).
4. The device for capping the hollow pier of the bridge according to claim 2, wherein: the pouring hole (9) is matched with the cabin sealing concrete (14).
5. The device for capping the hollow pier of the bridge according to claim 1, wherein: and the top of the precast slab (8) is also poured with cabin sealing concrete (14).
6. The device for capping the hollow pier of the bridge according to claim 1, wherein: and top beams (15) are poured on the tops of the hollow pier body (1) and the cabin sealing concrete (14).
CN202222107571.8U 2022-08-11 2022-08-11 Device for capping hollow bridge pier Active CN217810482U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222107571.8U CN217810482U (en) 2022-08-11 2022-08-11 Device for capping hollow bridge pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222107571.8U CN217810482U (en) 2022-08-11 2022-08-11 Device for capping hollow bridge pier

Publications (1)

Publication Number Publication Date
CN217810482U true CN217810482U (en) 2022-11-15

Family

ID=83974432

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222107571.8U Active CN217810482U (en) 2022-08-11 2022-08-11 Device for capping hollow bridge pier

Country Status (1)

Country Link
CN (1) CN217810482U (en)

Similar Documents

Publication Publication Date Title
CN109944161B (en) Steel box concrete bent pier on steel pipe arch bridge arch and construction method
CN103104091A (en) Sliding mold whole lifting platform and construction method
CN114575589B (en) Construction method for electric hoist lifting formwork of steel reinforced concrete structural column
CN111364422A (en) Site construction method of prefabricated corridor
CN217810482U (en) Device for capping hollow bridge pier
CN209053124U (en) A kind of assembled piping lane that plateization is prefabricated
CN216689076U (en) A prefabricated apron that is used for hollow mound top to pour construction
CN217680907U (en) Interior pulling type exempts from to tear open composite forms and concrete section of thick bamboo wall
CN207110035U (en) Assembled steel tendon concrete frame structure based on steel plate connection joint
CN115110765A (en) Construction method and device for shear wall at deformation joint
CN211549715U (en) Full-circle double-lining inverted arch construction template system for long-distance tunnel
CN210658451U (en) Open cut method composite assembly formula underground structure
CN114033234A (en) Novel main tower crown structure and sectional installation method thereof
CN208152409U (en) A kind of parapet of roofing
CN201695705U (en) Steel frame reinforced column
CN101324086A (en) Construction method of large-span box-shaped variable cross-section reinforced concrete arch
CN217399903U (en) Prefabricated hollow sandwich steel pipe concrete structure based on pressed steel plates and reinforcing ribs
CN214785820U (en) Multifunctional wellhead lifting operation platform
CN212763984U (en) Movable concrete prefabricating device
CN218091615U (en) Stiff steel structure column
CN214656397U (en) Totally-enclosed separated operating platform for ultrahigh hollow thin-wall pier
CN211285689U (en) Semi-assembled retaining wall
CN214993081U (en) Recyclable steel concrete structure gap bridge
CN210684967U (en) Assembly integral structure board wall node connection structure
CN2061580U (en) Shuttering device for lifting removal form of box-type building member

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant