CN217713907U - Supporting device for petroleum and natural gas pipeline construction and installation - Google Patents

Supporting device for petroleum and natural gas pipeline construction and installation Download PDF

Info

Publication number
CN217713907U
CN217713907U CN202220760456.8U CN202220760456U CN217713907U CN 217713907 U CN217713907 U CN 217713907U CN 202220760456 U CN202220760456 U CN 202220760456U CN 217713907 U CN217713907 U CN 217713907U
Authority
CN
China
Prior art keywords
gas pipeline
installation
support frame
oil
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220760456.8U
Other languages
Chinese (zh)
Inventor
王晓琦
曾煜
秦毅
刘玉珊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Gas Group Engineering Co ltd
Original Assignee
Shaanxi Gas Group Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Gas Group Engineering Co ltd filed Critical Shaanxi Gas Group Engineering Co ltd
Priority to CN202220760456.8U priority Critical patent/CN217713907U/en
Application granted granted Critical
Publication of CN217713907U publication Critical patent/CN217713907U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a strutting arrangement is used in oil and gas pipeline construction installation belongs to oil and gas pipeline construction technical field, set up the support frame in bottom plate top face both sides including bottom plate and slip, the central point of support frame puts the department and has seted up the through-hole, and the top screw thread of support frame is pegged graft and is had the screw rod, the roof of through-hole is provided with and rotates the pinch-off blades of being connected with the screw rod, and the diapire symmetry of through-hole has seted up the mounting groove, the top of mounting groove slides and pegs graft and has the lifter plate, and the diapire bilateral symmetry of mounting groove installs the electric putter fixed with the lifter plate, be fixed with the backup pad that is the arc structure between two lifter plates, the spout has all been seted up to the top face both sides of bottom plate, this strutting arrangement is used in oil and gas pipeline construction installation, the convenience of natural gas pipeline installation and butt joint has been promoted, be convenient for carry out the fixed stay to the natural gas pipeline of unidimension, strutting arrangement's suitability has been promoted.

Description

Supporting device for petroleum and natural gas pipeline construction and installation
Technical Field
The utility model belongs to the technical field of the oil and gas pipeline construction, concretely relates to strutting arrangement is used in oil and gas pipeline construction installation.
Background
The natural gas pipeline refers to a pipeline for conveying natural gas (including associated gas produced in oil fields) from a mining place or a processing plant to an urban gas distribution center or an industrial enterprise user, and is also called a gas conveying pipeline.
The support frame often need be used at the in-process of installation to current natural gas line because natural gas line's size diverse, and natural gas line need the height-adjusting to dock at the in-process of installation, and current strutting arrangement can't carry out fixed stay to the natural gas line of unidimensional not to the suitability that has leaded to strutting arrangement is poor.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a strutting arrangement is used in oil and gas pipeline construction installation to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a strutting arrangement is used in oil and gas pipeline construction installation, including bottom plate and the support frame of slip setting in bottom plate top face both sides, the central point of above-mentioned support frame puts the department and has seted up the through-hole, and the top screw thread of support frame is pegged graft and is had the screw rod, the roof of above-mentioned through-hole is provided with and rotates the clamp plate of being connected with the screw rod, and the diapire symmetry of through-hole has seted up the mounting groove, the top of above-mentioned mounting groove slides and pegs graft and has the lifter plate, and the diapire bilateral symmetry of mounting groove installs the electric putter fixed with the lifter plate, be fixed with the backup pad that is the arc structure between two above-mentioned lifter plates.
Furthermore, the sliding grooves are formed in two sides of the top end face of the bottom plate, and the bottom end of the bottom plate is fixed with the anti-slip mat in a rectangular array.
Furthermore, both ends of the support frame are respectively provided with a positioning part in a protruding manner, the bottom end of the positioning part is provided with a sliding block in a T-shaped structure in a protruding manner, and the sliding blocks are matched and inserted into the sliding grooves.
Furthermore, a connecting part is convexly arranged at the top end of the clamping plate, a knob is fixed at the top end of the screw rod, and the bottom end of the screw rod is rotatably inserted in the connecting part.
Furthermore, the bottom end of the side wall of one of the support frames is rotatably inserted with a driving rod through a bearing, and the driving rod is inserted in the other support frame in a threaded manner.
Furthermore, a driving plate is fixed on the side wall of the driving rod, and handles are fixed on the outer wall of the driving plate in an annular array.
This strutting arrangement is used in oil and gas pipeline construction installation's technological effect and advantage: the support frames are arranged on two sides of the top end face of the bottom plate in a sliding mode, the through holes are formed in the support frames, the clamping plates are embedded in the top ends of the through holes, the threaded and inserted screw rods on the top ends of the support frames are driven to rotate through the knobs, so that the clamping plates move downwards to clamp and fix the natural gas pipelines in the through holes, meanwhile, in the process of butt joint of the natural gas pipelines in the two support frames, the electric push rods in the mounting grooves on the two sides of the bottom wall of the through holes are started to move synchronously, the electric push rods drive the lifting plates and the support plates to move upwards, the support plates drive the natural gas pipelines to move synchronously in the moving process, the two natural gas pipelines are butt joint with each other, fixed support of the natural gas pipelines with different sizes is facilitated, and the applicability of the support device is improved; the top face both sides through at the bottom plate have all been seted up the spout, and support frame both sides location portion bottom all is provided with the slider of identical grafting in the spout, makes the support frame steadily remove on the top of bottom plate through the slider, is provided with the actuating lever simultaneously between two support frames, makes two support frames move in opposite directions through rotatory actuating lever to make the natural gas line contact in the support frame, promoted the convenience of natural gas line installation and butt joint.
Drawings
FIG. 1 is a schematic structural diagram of an embodiment of the present invention;
fig. 2 is a schematic diagram of a structure of a clamping plate according to an embodiment of the present invention;
fig. 3 is a schematic structural view of a support plate according to an embodiment of the present invention;
fig. 4 is a schematic view of a structure driving rod according to an embodiment of the present invention.
In the figure: 1. a base plate; 2. a non-slip mat; 3. a positioning part; 4. a chute; 5. a drive rod; 6. a knob; 7. a support frame; 8. a through hole; 9. a support plate; 10. a connecting portion; 11. a clamping plate; 12. a screw; 13. a lifting plate; 14. a slider; 15. mounting grooves; 16. an electric push rod; 17. a bearing; 18. a drive plate; 19. a handle.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Please refer to fig. 1-4, which illustrate a supporting device for petroleum and natural gas pipeline construction and installation, comprising a bottom plate 1 and supporting frames 7 slidably disposed on two sides of the top end surface of the bottom plate 1.
Referring to fig. 1 and 2, support frame 7 is provided with through all sliding in the top face both sides of bottom plate 1, through-hole 8 has been seted up in support frame 7, the top of through-hole 8 is embedded to have clamp plate 11, it is rotatory to drive screw rod 12 of support frame 7 top screw thread grafting through knob 6, thereby make clamp plate 11 move down press from both sides the gas pipeline in through-hole 8 and press from both sides tightly fixed, simultaneously in the in-process of gas pipeline butt joint in two support frames 7, start electric putter 16 synchronous motion in through-hole 8 diapire both sides mounting groove 15, make electric putter 16 drive lifter plate 13 and backup pad 9 rebound, make backup pad 9 drive gas pipeline synchronous motion at the in-process that removes, thereby make two gas pipeline butt joints each other, be convenient for carry out the fixed stay to the gas pipeline of different sizes, strutting arrangement's suitability has been promoted, through-hole 8 has been seted up in the central point department of support frame 7, and support frame 7's top screw thread grafting has screw rod 12, the roof of through-hole 8 is provided with clamp plate 11 that rotates the connection with screw rod 12, and the diapire symmetry has seted up 15, and the bottom plate 13 of the fixed slide groove 13 is the bottom plate 13 of arc-shaped array structure is seted up and 2 both sides of fixed slide groove 13 between two support plate 1 and the fixed slide groove 13, the bottom plate 13 has all seted up the fixed slide structure of the bottom plate 13.
Referring to fig. 3 and 4, sliding grooves 4 are formed in both sides of a top end face of a bottom plate 1, sliders 14 which are matched and inserted in the sliding grooves 4 are arranged at bottom ends of positioning portions 3 on both sides of a support frame 7, the support frame 7 is enabled to stably move on the top end of the bottom plate 1 through the sliders 14, meanwhile, a driving rod 5 is arranged between the two support frames 7, the two support frames 7 are enabled to move oppositely through rotation of the driving rod 5, so that natural gas pipelines in the support frames 7 are in contact, convenience in installation and butt joint of the natural gas pipelines is improved, the positioning portions 3 are convexly arranged at both ends of the support frames 7, the sliders 14 which are in a T-shaped structure are convexly arranged at the bottom ends of the positioning portions 3, the sliders 14 are matched and inserted in the sliding grooves 4, a connecting portion 10 is convexly arranged at the top end of a clamping plate 11, a knob 6 is fixed at the top end of a screw rod 12, the bottom end of the screw rod 12 is rotatably inserted in the connecting portion 10, a driving rod 5 is rotatably inserted in a bottom end of a side wall of one support frame 7 through a bearing 17, the driving rod 5 is rotatably inserted in a threaded manner, the driving rod 5, side wall of the other support frame 7, 18 is fixed on a side wall, and a handle 19 is fixed on an outer wall of the driving rod 5 in an annular array.
This strutting arrangement is used in oil and gas pipeline construction installation, place gas pipeline behind the 9 tops of backup pad in support frame 7 during the use, it is rotatory to hold knob 6 and drive screw rod 12, it is fixed to make pinch-off blades 11 move down press from both sides gas pipeline, it is rotatory to hold handle 19 and drive plate 18 and actuating lever 5, make two support frames 7 drive gas pipeline and move in opposite directions, start the 16 synchronous motion of electric putter in 8 diapire both sides mounting grooves 15 of through-hole, make electric putter 16 drive lifter plate 13 and backup pad 9 rebound, make backup pad 9 drive gas pipeline synchronous motion at the in-process that removes, thereby make two gas pipeline dock each other.
The above description is only the specific implementation manner of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art should be covered within the protection scope of the present invention in the technical scope disclosed by the present invention, according to the technical solution of the present invention and the concept of the present invention, equivalent replacement or change is added.

Claims (6)

1. The utility model provides a strutting arrangement is used in oil and gas pipeline construction installation, includes bottom plate (1) and slides and set up support frame (7) in bottom plate (1) top terminal surface both sides, its characterized in that: the center position department of support frame (7) has seted up through-hole (8), and the top screw thread of support frame (7) is pegged graft and has been had screw rod (12), the roof of through-hole (8) is provided with and rotates pinch-off blades (11) of being connected with screw rod (12), and the diapire symmetry of through-hole (8) has seted up mounting groove (15), the top of mounting groove (15) slides to be pegged graft and has lifter plate (13), and the diapire bilateral symmetry of mounting groove (15) installs electric putter (16) fixed with lifter plate (13), two be fixed with backup pad (9) that are the arc structure between lifter plate (13).
2. The supporting device for the construction and installation of the oil and gas pipeline according to claim 1, wherein: the anti-skidding mat is characterized in that sliding grooves (4) are formed in two sides of the top end face of the bottom plate (1), and anti-skidding mats (2) are fixed to the bottom end of the bottom plate (1) in a rectangular array mode.
3. The supporting device for the construction and installation of the oil and gas pipeline as claimed in claim 2, wherein: the supporting frame is characterized in that positioning portions (3) are arranged at two ends of the supporting frame (7) in a protruding mode, sliders (14) in T-shaped structures are arranged at the bottom ends of the positioning portions (3) in a protruding mode, and the sliders (14) are matched and inserted into the sliding grooves (4).
4. The supporting device for the construction and installation of the oil and gas pipeline according to claim 1, wherein: the top end of the clamping plate (11) is convexly provided with a connecting part (10), the top end of the screw rod (12) is fixedly provided with a knob (6), and the bottom end of the screw rod (12) is rotatably inserted into the connecting part (10).
5. The supporting device for the construction and installation of the oil and gas pipeline according to claim 1, wherein: one of them the lateral wall bottom of support frame (7) is passed through bearing (17) and is rotated the grafting and have actuating lever (5), actuating lever (5) screw thread is pegged graft in another support frame (7).
6. The supporting device for the construction and installation of the oil and gas pipeline according to claim 5, wherein: a driving plate (18) is fixed on the side wall of the driving rod (5), and handles (19) are fixed on the outer wall of the driving plate (18) in an annular array.
CN202220760456.8U 2022-04-01 2022-04-01 Supporting device for petroleum and natural gas pipeline construction and installation Active CN217713907U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220760456.8U CN217713907U (en) 2022-04-01 2022-04-01 Supporting device for petroleum and natural gas pipeline construction and installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220760456.8U CN217713907U (en) 2022-04-01 2022-04-01 Supporting device for petroleum and natural gas pipeline construction and installation

Publications (1)

Publication Number Publication Date
CN217713907U true CN217713907U (en) 2022-11-01

Family

ID=83790334

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220760456.8U Active CN217713907U (en) 2022-04-01 2022-04-01 Supporting device for petroleum and natural gas pipeline construction and installation

Country Status (1)

Country Link
CN (1) CN217713907U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117646829A (en) * 2024-01-29 2024-03-05 山西国强天然气输配有限公司 Natural gas pipeline installation auxiliary device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117646829A (en) * 2024-01-29 2024-03-05 山西国强天然气输配有限公司 Natural gas pipeline installation auxiliary device
CN117646829B (en) * 2024-01-29 2024-04-19 山西国强天然气输配有限公司 Natural gas pipeline installation auxiliary device

Similar Documents

Publication Publication Date Title
CN217713907U (en) Supporting device for petroleum and natural gas pipeline construction and installation
CN210703296U (en) Elastic pressing device for welding thin metal plate
CN209737072U (en) Stable machining clamp with pin storage groove
CN210209866U (en) Architectural decoration equipment of polishing
CN213532614U (en) Material positioning clamping moving manipulator device
CN211439258U (en) Pipe grinding device is used in utensil processing
CN210662113U (en) Diesel generating set installation device convenient to adjust
CN211490500U (en) Aluminum product machining clamp
CN210452267U (en) Hardware processing burnishing device
CN211249625U (en) Positioning device for steel processing
CN201931292U (en) Automatic tightening and loosening clamping jaw mechanism
CN207447970U (en) A kind of isometry block
CN215142929U (en) Surface cleaning device for magnet processing
CN218800676U (en) Clamp
CN215201622U (en) A quick mounting fixture for square frame work piece processing
CN217890063U (en) Welding device for machining automobile parts
CN212497500U (en) Electrical engineering station installation device
CN220641637U (en) Carbon processing loading attachment
CN218696230U (en) Frock is fixed to fishplate bar base board
CN213531658U (en) Automobile part clamp convenient to operate
CN218802900U (en) Quick pressfitting frock clamp
CN218639258U (en) Equipment for removing burrs on surface of hardware
CN213731635U (en) Fixing device is used in electromechanical maintenance of high stability
CN215711651U (en) Multi-applicability gland structure
CN219134248U (en) Reinforcing bar handling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant