CN217631392U - Clamp for adjusting foundation bolt in power transmission line foundation construction - Google Patents

Clamp for adjusting foundation bolt in power transmission line foundation construction Download PDF

Info

Publication number
CN217631392U
CN217631392U CN202221338428.3U CN202221338428U CN217631392U CN 217631392 U CN217631392 U CN 217631392U CN 202221338428 U CN202221338428 U CN 202221338428U CN 217631392 U CN217631392 U CN 217631392U
Authority
CN
China
Prior art keywords
plate
transmission line
rod
fixed
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221338428.3U
Other languages
Chinese (zh)
Inventor
徐斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202221338428.3U priority Critical patent/CN217631392U/en
Application granted granted Critical
Publication of CN217631392U publication Critical patent/CN217631392U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model provides a fixture for adjusting foundation bolts in power transmission line foundation construction, which comprises a fixing component, wherein the fixing component comprises a first fixing plate, a square rod, a second fixing plate, a fixing rod, a moving plate, a connecting rod, an arc-shaped plate, a foundation bolt body, a first screw rod and a first knob; the first fixing plate is provided with two square rods, one side of the first fixing plate is fixedly provided with the two square rods, and the end portions of the square rods are fixedly provided with the second fixing plate. The utility model discloses first knob drives the movable plate through first screw rod and removes, and the movable plate passes through the connecting rod and drives the arc and remove, and the arc is fixed the rag bolt body, rotates the second knob again, and the second knob drives the second fixed plate through the second screw rod and removes, adjusts through observing the scale plate, and the second fixed plate drives the rag bolt body through the square pole and removes, then pours the concrete in pouring the template, and the regulation of being convenient for can not increase staff's work load.

Description

Clamp for adjusting foundation bolt in power transmission line foundation construction
Technical Field
The utility model relates to a transmission line engineering construction technical field, in particular to anchor clamps that are used for transmission line foundation construction rag bolt to adjust.
Background
The existing power transmission line foundation concrete pouring construction is usually carried out by clamping with temporarily processed wood boards and adjusting the sizes of all parts by matching with a steel tape. The operation usually takes a long time, the foundation bolt adjusting time of the excavation type foundation of the common 220kV power transmission line engineering is about 30% of the whole pouring time, and the construction efficiency is greatly reduced;
in the pouring process, the foundation screws are relatively displaced due to the fact that the wood members are not stable enough along with the concrete continuously impacting the foundation bolts. Thereby making construction technical personnel carry out the secondary adjustment to rag bolt as the circumstances. Under this kind of condition, rag bolt's body receives the foundation concrete all directions pressure very big, and the adjustment is very difficult and the degree of rectifying is limited, increases staff's work load, reduces the efficiency of construction, for this reason, provides a anchor clamps that is used for transmission line foundation construction rag bolt to adjust.
SUMMERY OF THE UTILITY MODEL
In view of this, the utility model discloses it is hoped to provide an anchor clamps for transmission line foundation construction rag bolt adjustment to solve or alleviate the technical problem that exists among the prior art, provide a profitable selection at least.
The embodiment of the utility model provides a technical scheme is so realized: a clamp for adjusting foundation bolts in power transmission line foundation construction comprises a fixing assembly, wherein the fixing assembly comprises a first fixing plate, a square rod, a second fixing plate, a fixing rod, a moving plate, a connecting rod, an arc-shaped plate, a foundation bolt body, a first screw and a first knob;
first fixed plate is equipped with two, one side fixed mounting of first fixed plate has two square poles, the tip fixed mounting of square pole has the second fixed plate, rotate between first fixed plate and the second fixed plate that corresponds and install first screw rod, threaded connection has two movable plates on the first screw rod, one side of first fixed plate and the equal fixed mounting in one side of the second fixed plate that corresponds have two dead levers, sliding connection has the carriage release lever on the dead lever, one side fixed connection of the tip of carriage release lever and the movable plate that corresponds, the opposite side fixed mounting of movable plate has the connecting rod, the tip fixed mounting of connecting rod has the arc, two swing joint has the rag bolt body between the arc, the tip of first screw rod extends to outside and the fixed mounting of the first fixed plate that corresponds has first knob.
Further preferably, the both sides of second fixed plate all are equipped with the diaphragm, the equal fixed mounting in both sides of diaphragm has the rectangular plate, and the rectangular plate supports the gag lever post.
Further preferably, a second screw rod is rotatably mounted between the two rectangular plates, the end of the second screw rod extends out of the corresponding rectangular plate and is fixedly provided with a second knob, and the distance between the two second fixing plates can be adjusted by rotating the second knob.
Further preferably, the second fixing plate is in threaded connection with the corresponding second screw, and the distance between the anchor bolt bodies can be adjusted through the second fixing plate.
Further preferably, two fixed mounting has the gag lever post between the rectangular plate, gag lever post and the second fixed plate sliding connection who corresponds, the gag lever post is spacing to the second fixed plate, appears the skew when preventing to remove.
Further preferably, the top fixed mounting of diaphragm has the scale plate, two first screw holes have been seted up on the diaphragm, can observe the distance through the scale plate.
Further preferably, a second threaded hole and a square hole are formed in the second fixing plate, the second threaded hole is in threaded connection with a corresponding second screw, the inner wall of the square hole is in sliding connection with the outer side of the corresponding limiting rod, and the second screw plays a role in locking after moving.
Preferably, the moving plate is provided with third threaded holes, the thread turning directions of the two third threaded holes are opposite, and the third threaded holes are in threaded connection with the first screw rod, so that the two moving plates can move towards the direction close to each other.
The embodiment of the utility model provides a owing to adopt above technical scheme, it has following advantage:
the utility model discloses first knob drives the movable plate through first screw rod and removes, the movable plate passes through the connecting rod and drives the arc and remove, the arc is fixed the rag bolt body, rotate the second knob again, the second knob drives the second fixed plate through the second screw rod and removes, adjust through observing the scale plate, the second fixed plate drives the rag bolt body through the square pole and removes, then pour the concrete in pouring the template, pour the back, take off first fixed plate again, thereby make the rag bolt body fixed more stable, and the regulation of being convenient for, can not increase staff's work load.
The foregoing summary is provided for the purpose of description only and is not intended to be limiting in any way. In addition to the illustrative aspects, embodiments, and features described above, further aspects, embodiments, and features of the present invention will be readily apparent by reference to the drawings and following detailed description.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings needed to be used in the embodiments or technical descriptions will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present application, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a three-dimensional structure of the present invention;
FIG. 2 is a top perspective view of the present invention;
FIG. 3 is a right side perspective view of the present invention;
fig. 4 is an enlarged structural view of the area a in fig. 1 according to the present invention;
fig. 5 is an enlarged structural view of the area B in fig. 2 according to the present invention.
Reference numerals: 1. a fixing component; 2. a first fixing plate; 3. a square bar; 4. a second fixing plate; 5. fixing the rod; 6. a travel bar; 7. moving the plate; 8. a connecting rod; 9. an arc-shaped plate; 10. a foundation bolt body; 11. a first screw; 12. a first knob; 13. a transverse plate; 14. a rectangular plate; 15. a second screw; 16. a second knob; 17. a limiting rod; 18. a scale plate; 19. a first threaded hole.
Detailed Description
In the following, only certain exemplary embodiments are briefly described. As those skilled in the art will recognize, the described embodiments may be modified in various different ways, all without departing from the spirit or scope of the present invention. Accordingly, the drawings and description are to be regarded as illustrative in nature, and not as restrictive.
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
As shown in fig. 1-5, an embodiment of the present invention provides a fixture for adjusting foundation bolts in power transmission line foundation construction, including a fixing component 1, where the fixing component 1 includes a first fixing plate 2, a square bar 3, a second fixing plate 4, a fixing rod 5, a moving rod 6, a moving plate 7, a connecting rod 8, an arc plate 9, a foundation bolt body 10, a first screw 11, and a first knob 12;
first fixed plate 2 is equipped with two, one side fixed mounting of first fixed plate 2 has two square poles 3, the tip fixed mounting of square pole 3 has second fixed plate 4, rotate between first fixed plate 2 and the second fixed plate 4 that corresponds and install first screw rod 11, threaded connection has two movable plates 7 on the first screw rod 11, one side of first fixed plate 2 and the equal fixed mounting in one side of the second fixed plate 4 that corresponds have two dead levers 5, sliding connection has carriage release lever 6 on the dead lever 5, the tip of carriage release lever 6 and one side fixed connection of the movable plate 7 that corresponds, the opposite side fixed mounting of movable plate 7 has connecting rod 8, the tip fixed mounting of connecting rod 8 has arc 9, movable contact has rag bolt body 10 between two arc 9, the tip of first screw rod 11 extends to corresponding first fixed plate 2 outside and fixed mounting have first knob 12.
In one embodiment, the second fixing plate 4 is provided with a horizontal plate 13 on both sides, a rectangular plate 14 is fixedly mounted on both sides of the horizontal plate 13, and the horizontal plate 13 supports the rectangular plate 14.
In one embodiment, a second screw 15 is rotatably installed between the two rectangular plates 14, an end of the second screw 15 extends out of the corresponding rectangular plate 14 and is fixedly installed with a second knob 16, and the second knob 16 can drive the corresponding second screw 15 to rotate.
In one embodiment, the second fixing plates 4 are threadedly coupled to corresponding second screw rods 15, and the distance between the two second fixing plates 4 is adjustable by the second screw rods 15.
In one embodiment, a limiting rod 17 is fixedly installed between the two rectangular plates 14, the limiting rod 17 is slidably connected with the corresponding second fixing plate 4, and the limiting rod 17 limits the second fixing plate 4.
In one embodiment, a scale plate 18 is fixedly mounted on the top of the transverse plate 13, and two first threaded holes 19 are formed in the transverse plate 13, so that the transverse plate 13 can be fixed through the first threaded holes 19.
In one embodiment, the second fixing plate 4 is provided with a second threaded hole and a square hole, the second threaded hole is in threaded connection with the corresponding second screw 15, the inner wall of the square hole is in sliding connection with the outer side of the corresponding limiting rod 17, and the second screw 15 is in threaded connection with the second threaded hole, so that the second fixing plate 4 can be fixed after moving.
In one embodiment, the moving plate 7 is provided with third threaded holes, the thread directions of the two third threaded holes are opposite, and the third threaded holes are in threaded connection with the first threaded rods 11, so that the two moving plates 7 can move in the direction of approaching each other.
The utility model discloses at the during operation: during the use, the rag bolt body 10 is the separation state with arc 9, on moving first fixed plate 2 to the external pouring template that has supported well, fix diaphragm 13 through first screw hole 19 through external bolt, thereby increase stability, place rag bolt body 10 between two corresponding arc 9 immediately, rotate first knob 12, first knob 12 drives corresponding first screw 11 and rotates, first screw 11 drives two movable plates 7 and moves, under the effect that third screw hole screw thread revolves to opposite, make two relative movable plates 7 move to the direction that is close to each other, movable plate 7 drives movable rod 6 and slides on corresponding dead lever 5, simultaneously 7 drives connecting rod 8 and moves, connecting rod 8 drives corresponding arc movable plate 9 and moves, two relative arc 9 fix rag bolt body 10, rotate second knob 16 again, second knob 16 drives corresponding second screw 15 and rotates, second screw 15 drives second fixed plate 4 and moves, make two second fixed plates 4 move to the direction that is close to each other, second fixed plate 4 is on the rag bolt body 10, thereby it can get the stable fixing plate 10 of adjusting through the corresponding adjusting bolt body 18 to pass through the adjusting bolt body 18, thereby the rag bolt body is convenient for the adjusting the lower side of pouring template that the rag bolt body moves, thereby the lower side of pouring template that the lower side of pouring of the lower side of the slab 2.
The above description is only for the specific embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily think of various changes or substitutions within the technical scope of the present invention, which should be covered by the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (8)

1. The utility model provides an anchor clamps for transmission line foundation construction rag bolt adjustment, includes fixed subassembly (1), its characterized in that: the fixing assembly (1) comprises a first fixing plate (2), a square rod (3), a second fixing plate (4), a fixing rod (5), a moving rod (6), a moving plate (7), a connecting rod (8), an arc-shaped plate (9), a foundation bolt body (10), a first screw rod (11) and a first knob (12);
first fixed plate (2) are equipped with two, one side fixed mounting of first fixed plate (2) has two square poles (3), the tip fixed mounting of square pole (3) has second fixed plate (4), rotate between first fixed plate (2) and the second fixed plate (4) that corresponds and install first screw rod (11), threaded connection has two movable plates (7) on first screw rod (11), the equal fixed mounting in one side of first fixed plate (2) and the second fixed plate (4) that corresponds has two dead levers (5), sliding connection has carriage release lever (6) on dead lever (5), the tip of carriage release lever (6) and one side fixed connection of the second fixed plate (7) that corresponds, the opposite side fixed mounting of movable plate (7) has connecting rod (8), the tip fixed mounting of connecting rod (8) has arc (9), two movable contact has the lower margin body (10) between arc (9), the tip of first screw rod (11) extends to the first fixed mounting outside first fixed plate (2) that corresponds and has first knob (12).
2. The clamp for adjusting foundation bolts in power transmission line foundation construction according to claim 1, wherein: the both sides of second fixed plate (4) all are equipped with diaphragm (13), the equal fixed mounting in both sides of diaphragm (13) has rectangular plate (14).
3. The clamp for adjusting foundation bolts in power transmission line foundation construction according to claim 2, wherein: two second screw rods (15) are rotatably installed between the rectangular plates (14), and the end parts of the second screw rods (15) extend to the outside of the corresponding rectangular plates (14) and are fixedly provided with second knobs (16).
4. The clamp for adjusting the foundation bolts in power transmission line foundation construction according to claim 1, wherein: the second fixing plate (4) is in threaded connection with the corresponding second screw (15).
5. The clamp for adjusting the foundation bolts in power transmission line foundation construction according to claim 2, wherein: two fixed mounting has gag lever post (17) between rectangular plate (14), gag lever post (17) and corresponding second fixed plate (4) sliding connection.
6. The clamp for adjusting the foundation bolts for the foundation construction of the power transmission line according to claim 2, wherein: the top of the transverse plate (13) is fixedly provided with a scale plate (18), and two first threaded holes (19) are formed in the transverse plate (13).
7. The clamp for adjusting foundation bolts in power transmission line foundation construction according to claim 1, wherein: and a second threaded hole and a square hole are formed in the second fixing plate (4), the second threaded hole is in threaded connection with the corresponding second screw (15), and the inner wall of the square hole is in sliding connection with the outer side of the corresponding limiting rod (17).
8. The clamp for adjusting foundation bolts in power transmission line foundation construction according to claim 1, wherein: and third threaded holes are formed in the moving plate (7), the thread turning directions of the two third threaded holes are opposite, and the third threaded holes are in threaded connection with the first screw rods (11).
CN202221338428.3U 2022-05-31 2022-05-31 Clamp for adjusting foundation bolt in power transmission line foundation construction Active CN217631392U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221338428.3U CN217631392U (en) 2022-05-31 2022-05-31 Clamp for adjusting foundation bolt in power transmission line foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221338428.3U CN217631392U (en) 2022-05-31 2022-05-31 Clamp for adjusting foundation bolt in power transmission line foundation construction

Publications (1)

Publication Number Publication Date
CN217631392U true CN217631392U (en) 2022-10-21

Family

ID=83620872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221338428.3U Active CN217631392U (en) 2022-05-31 2022-05-31 Clamp for adjusting foundation bolt in power transmission line foundation construction

Country Status (1)

Country Link
CN (1) CN217631392U (en)

Similar Documents

Publication Publication Date Title
CN203905491U (en) Adjustable device for supporting shear wall casting die and upright post casting die
CN217631392U (en) Clamp for adjusting foundation bolt in power transmission line foundation construction
CN210313247U (en) Tower crane attaches wall connecting device
CN108049630A (en) A kind of civil engineering work formwork connection device
CN215747863U (en) Assembled engineering steel drilling clamping device
CN214615043U (en) Prefabricated component reserved steel bar positioning and correcting device
CN210236938U (en) Control box convenient for adjusting and arranging angle and used for torque limiter
CN201980865U (en) Detachable temporary stop buffer used for suspending monorail crane
CN218148489U (en) Circular equipment foundation template device
CN215859061U (en) But angle regulation's supporting template for construction
CN206016259U (en) A kind of adjustable beam die plate reinforcing jacking device
CN206530052U (en) A kind of combination type supporting device
CN218406522U (en) Fixing device for building template
CN220320495U (en) River-crossing bracket for rain sewage pipeline
CN219489435U (en) Tower crane jacking Liang Suoxiao
CN220167574U (en) House transformation reinforced floor slab formwork support device
CN214530546U (en) Headstock gear installing support
CN220909114U (en) Balcony anti-bank template structure
CN210422101U (en) Communication tower for electronic information engineering
CN216734700U (en) Multi-beam bathymeter mounting rack convenient to mount and high in adaptability
CN220093824U (en) Clamping device for machining PC steel bars
CN221219661U (en) Concrete pouring template fixing system for transformer substation frame beam
CN215670111U (en) Connecting device with reinforcing structure for building structure design
CN219839351U (en) Steel member anti-hoisting lifting device
CN113756449B (en) Large-span steel beam column structure and member thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant