CN217541473U
CN217541473U CN202221447562.7U CN202221447562U CN217541473U CN 217541473 U CN217541473 U CN 217541473U CN 202221447562 U CN202221447562 U CN 202221447562U CN 217541473 U CN217541473 U CN 217541473U
Authority
CN
China
Prior art keywords
main part
heating furnace
furnace main
main body
aluminum alloy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221447562.7U
Other languages
Chinese (zh)
Inventor
郭立峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Otto Fuchs Technology Shenyang Co ltd
Original Assignee
Otto Fuchs Technology Shenyang Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Otto Fuchs Technology Shenyang Co ltd filed Critical Otto Fuchs Technology Shenyang Co ltd
Priority to CN202221447562.7U priority Critical patent/CN217541473U/en
Application granted granted Critical
Publication of CN217541473U publication Critical patent/CN217541473U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Tunnel Furnaces (AREA)

Abstract

The utility model discloses an aluminum alloy bar heating furnace, including the preheater main part, the heating furnace main part is installed to one side of preheater main part, and heating furnace main part inside and outside structure is the same with the inside and outside structure of preheater main part, the equal movable mounting in front of preheater main part and heating furnace main part has the sealing door, the guide rail is installed to the inner diapire of preheater main part, the inboard movable mounting of preheater main part has the bottom plate, first limiting plate is installed to the inside wall of bottom plate, the pulley is installed to the bottom of bottom plate, and the pulley gomphosis is in the inboard of guide rail. The utility model discloses a pulley gomphosis is in the inboard of guide rail to guarantee the bottom plate in the inboard stability of preheater main part, slide in the inboard of guide rail through the pulley, thereby be convenient for the staff and take out the bottom plate from the inside of preheater main part, thereby make things convenient for the aluminum alloy bar after the staff will process to take out, improve the work efficiency of staff to aluminum alloy bar subsequent processing.

Description

Aluminum alloy bar heating furnace
Technical Field
The utility model relates to an aluminum alloy bar processing technology field specifically is an aluminum alloy bar heating furnace.
Background
The heating furnace is a device for heating materials or workpieces to a rolling forging temperature in the metallurgical industry, and can be divided into a continuous heating furnace and a chamber type heating furnace, the heating furnace is applied to various industries such as petroleum, chemical engineering, metallurgy, machinery, heat treatment, surface treatment, building materials, electronics, materials, light industry, daily chemicals, pharmacy and the like, the heating furnace is required to be used for processing aluminum alloy bars, but the existing heating furnace still has certain defects when in use.
The heating furnace in the prior art has the following defects:
when the existing heating furnace is used, most workers who are not convenient to use take out the aluminum alloy bars inside the heating furnace, and the workers who are not convenient to use carry out subsequent treatment on the aluminum alloy bars, so that the working efficiency of the workers is reduced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an aluminum alloy bar heating furnace to solve the problem that proposes among the above-mentioned background art.
In order to achieve the purpose, the utility model provides the following technical scheme, an aluminum alloy bar heating furnace, which comprises a preheating furnace main body, wherein a heating furnace main body is arranged on one side of the preheating furnace main body, and the internal and external structures of the heating furnace main body are the same as those of the preheating furnace main body;
the utility model discloses a preheating furnace, including preheating furnace main part, heating furnace main part, guide rail, the inboard movable mounting of preheating furnace main part has a bottom plate, first limiting plate is installed to the inside wall of bottom plate, the pulley is installed to the bottom of bottom plate, and the pulley gomphosis is in the inboard of guide rail, the equal movable mounting in front of preheating furnace main part and heating furnace main part has a sealing door, the guide rail is installed to the interior diapire of preheating furnace main part, the inboard movable mounting of preheating furnace main part has the bottom plate, first limiting plate is installed to the inside wall of bottom plate, the pulley gomphosis is in the bottom of bottom plate.
Preferably, a controller is installed on the outer wall of one side of the preheating furnace main body, the outer wall of the controller is connected with an access door through a hinge, a heat insulation layer is arranged inside the preheating furnace main body, a heating pipe is installed on the inner wall of the preheating furnace main body, isolation glass is installed inside the preheating furnace main body, and the isolation glass is located on the outer side of the heating pipe.
Preferably, a plurality of groups of buffer springs are installed at the bottom of the preheating furnace main body, and the bottoms of the plurality of groups of buffer springs are connected with anti-skid plates.
Preferably, the top of the heating furnace main body and the top of the preheating furnace main body are both provided with exhaust pipes, and the bottom ends of the exhaust pipes respectively penetrate through the interior of the heating furnace main body and the interior of the preheating furnace main body.
Preferably, the top of the preheating furnace main body and the top of the heating furnace main body are both provided with a hoister, the output end of the hoister is provided with a connecting plate, and the bottom of the connecting plate is connected with the top of the sealing door.
Preferably, the supporting net is installed to the inside wall of bottom plate, and the supporting net is located the below of first limiting plate.
Preferably, the telescopic link is installed at the top of bottom plate, the outer wall of telescopic link runs through and installs the gim peg, the second limiting plate is installed at the top of telescopic link, the spacing groove has all been seted up at the top of second limiting plate and first limiting plate.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses a pulley gomphosis is in the inboard of guide rail to guarantee the stability of bottom plate in the inboard of preheater main part, slide in the inboard of guide rail through the pulley, thereby be convenient for the staff takes out the bottom plate from the inside of preheater main part, thereby make things convenient for the aluminum alloy bar after the staff will process to take out, improve the work efficiency of staff to aluminum alloy bar follow-up processing.
2. The utility model discloses when using, run through the inboard at second limiting plate and first limiting plate with the aluminum alloy bar through the spacing groove, can part the aluminum alloy bar in an orderly manner through the spacing groove to improve the work efficiency of aluminum alloy bar heating, can adjust the distance between second limiting plate and the first limiting plate through the telescopic link, thereby make second limiting plate and first limiting plate can carry on spacingly to the aluminum alloy bar of different specifications.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic structural view of the preheating furnace body of the present invention;
FIG. 3 is a schematic sectional view of the preheating furnace and the heating furnace of the present invention;
fig. 4 is a schematic view of the structure of the rack of the present invention.
In the figure: 1. a preheating furnace main body; 101. a controller; 102. an access door; 103. a thermal insulation layer; 104. heating a tube; 105. a buffer spring; 106. a cleat; 107. an insulating glass; 108. a guide rail; 2. a sealing door; 201. a hoist; 202. a connecting plate; 3. a base plate; 301. a pulley; 302. a first limit plate; 303. a limiting groove; 304. a support net; 4. a telescopic rod; 401. a fixing bolt; 402. and a second limiting plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1, 2 and 3, a heating furnace for aluminum alloy bar stock:
the preheating furnace comprises a preheating furnace body 1, a guide rail 108 is installed on the inner bottom wall of the preheating furnace body 1, a bottom plate 3 is movably installed on the inner side of the preheating furnace body 1, a first limiting plate 302 is installed on the inner side wall of the bottom plate 3, a pulley 301 is installed at the bottom of the bottom plate 3, the pulley 301 is embedded in the inner side of the guide rail 108, a supporting net 304 is installed on the inner side wall of the bottom plate 3, the supporting net 304 is located below the first limiting plate 302, a telescopic rod 4 is installed at the top of the bottom plate 3, a fixing bolt 401 penetrates through the outer wall of the telescopic rod 4, a second limiting plate 402 is installed at the top of the telescopic rod 4, and limiting grooves 303 are formed in the tops of the second limiting plate 402 and the first limiting plate 302;
can provide the mounted position for first limiting plate 302 and telescopic link 4 through bottom plate 3, the aluminum alloy bar passes through the inboard that spacing groove 303 runs through at second limiting plate 402 and first limiting plate 302, can support the aluminum alloy bar through supporting mesh 304, guarantee the stability of aluminum alloy bar, can part the aluminum alloy bar in an orderly manner through spacing groove 303, thereby improve the work efficiency that the aluminum alloy bar heated, can adjust the distance between second limiting plate 402 and the first limiting plate 302 through telescopic link 4, thereby make second limiting plate 402 and first limiting plate 302 can carry out spacingly to the aluminum alloy bar of different specifications, support the inside flexible regulation pole of telescopic link 4 through rotating gim peg 401, thereby fix telescopic link 4, through the inboard of pulley 301 gomphosis at guide rail 108, thereby guarantee the stability of bottom plate 3 in the inboard of preheater main part 1, slide in the inboard of guide rail 108 through pulley 301, thereby be convenient for the staff to take out bottom plate 3 from the inside of preheater main part 1.
Referring to fig. 1, 2 and 4, a heating furnace for aluminum alloy bar stock:
the preheating furnace comprises a preheating furnace main body 1, a heating furnace main body 109 is installed on one side of the preheating furnace main body 1, the internal and external structures of the heating furnace main body 109 are the same as those of the preheating furnace main body 1, exhaust pipes 1010 are installed on the tops of the heating furnace main body 109 and the preheating furnace main body 1, the bottom ends of the exhaust pipes 1010 penetrate through the insides of the heating furnace main body 109 and the preheating furnace main body 1 respectively, a controller 101 is installed on the outer wall of one side of the preheating furnace main body 1, the outer wall of the controller 101 is connected with an access door 102 through hinges, a heat insulation layer 103 is arranged inside the preheating furnace main body 1, a heating pipe 104 is installed on the inner wall of the preheating furnace main body 1, an isolation glass 107 is installed inside the preheating furnace main body 1 and located outside the heating pipe 104, a plurality of buffer springs 105 are installed at the bottom of the preheating furnace main body 1, the bottoms of the plurality of the buffer springs 105 are connected with an anti-slip plate 106, a sealing door 2 is movably installed on the front surfaces of the preheating furnace main body 1 and the heating furnace main body 109, an elevator 201 is installed at the tops of the preheating furnace main body 1 and the heating furnace main body 109, an output end of the elevator 201, and a connecting plate 202 is connected with the top of the sealing door 2;
can heat in advance the aluminum alloy bar through preheater body 1, can heat the processing to the aluminum alloy bar through heating furnace owner 109, the operation of preheater body 1 can be controlled through controller 101, can overhaul the inside of controller 101 through opening access door 102, can reduce the loss of the inside heat of preheater body 1 through insulating layer 103, make preheater body 1 can heat the aluminum alloy bar better, can protect heating pipe 104 through isolation glass 107, prevent that heating pipe 104 from receiving external influence and damaging, can make preheater body 1 and heating furnace owner 109 have the buffering effect through buffer spring 105, guarantee the stability of preheater body 1 and heating furnace owner 109 when using through antiskid ribbed tile 106, it opens and shuts to drive sealing door 2 through lifting machine 201 operation accessible connecting plate 202, thereby make things convenient for the staff to open and shut sealing door 2.
The working principle is that the sealing door 2 can be driven to lift and open and close by the aid of the connection plate 202 when the elevator 201 runs, installation positions can be provided for the first limiting plate 302 and the telescopic rod 4 through the bottom plate 3, aluminum alloy bars penetrate through the inner sides of the second limiting plate 402 and the first limiting plate 302 through the limiting groove 303, the aluminum alloy bars can be supported by the supporting net 304, the stability of the aluminum alloy bars is guaranteed, the distance between the second limiting plate 402 and the first limiting plate 302 can be adjusted by the telescopic rod 4, the second limiting plate 402 and the first limiting plate 302 can limit the aluminum alloy bars with different specifications, the telescopic adjusting rods inside the telescopic rod 4 are abutted by rotating the fixing bolt 401, the telescopic rod 4 is fixed, the pulley 301 is embedded in the inner side of the guide rail 108, the stability of the bottom plate 3 in the inner side of the preheating furnace main body 1 is guaranteed, the pulley 301 slides in the inner side of the guide rail 108, and the bottom plate 3 can be taken out from the preheating furnace main body 1 by workers.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. The utility model provides an aluminum alloy bar heating furnace, includes preheater main part (1), its characterized in that: a heating furnace main body (109) is installed on one side of the preheating furnace main body (1), and the internal and external structures of the heating furnace main body (109) are the same as those of the preheating furnace main body (1);
the utility model discloses a preheating furnace, including preheating furnace main part (1) and heating furnace main part (109), the equal movable mounting in front of preheating furnace main part (1) and heating furnace main part (109) has sealing door (2), guide rail (108) are installed to the inner bottom wall of preheating furnace main part (1), the inboard movable mounting of preheating furnace main part (1) has bottom plate (3), first limiting plate (302) are installed to the inside wall of bottom plate (3), pulley (301) are installed to the bottom of bottom plate (3), and pulley (301) gomphosis is in the inboard of guide rail (108).
2. The aluminum alloy bar heating furnace of claim 1, wherein: controller (101) are installed to one side outer wall of preheater main part (1), there are access door (102) controller (101) outer wall through hinged joint, the inside of preheater main part (1) is provided with insulating layer (103), heating pipe (104) are installed to the inner wall of preheater main part (1), the internally mounted of preheater main part (1) has isolation glass (107), and isolation glass (107) are located the outside of heating pipe (104).
3. The aluminum alloy bar heating furnace of claim 1, wherein: the bottom of the preheating furnace main body (1) is provided with a plurality of groups of buffer springs (105), and the bottoms of the plurality of groups of buffer springs (105) are connected with anti-skid plates (106).
4. The aluminum alloy bar heating furnace of claim 1, wherein: exhaust pipes (1010) are installed at the tops of the heating furnace main body (109) and the preheating furnace main body (1), and the bottom ends of the exhaust pipes (1010) penetrate through the interiors of the heating furnace main body (109) and the preheating furnace main body (1) respectively.
5. The aluminum alloy bar heating furnace of claim 1, wherein: lifting machines (201) are installed at the tops of the preheating furnace main body (1) and the heating furnace main body (109), connecting plates (202) are installed at the output ends of the lifting machines (201), and the bottoms of the connecting plates (202) are connected with the tops of the sealing doors (2).
6. The aluminum alloy bar heating furnace of claim 1, wherein: the supporting net (304) is installed to the inside wall of bottom plate (3), and supporting net (304) are located the below of first limiting plate (302).
7. The aluminum alloy bar heating furnace of claim 1, wherein: the telescopic link (4) is installed at the top of bottom plate (3), the outer wall of telescopic link (4) runs through and installs gim peg (401), second limiting plate (402) is installed at the top of telescopic link (4), spacing groove (303) have all been seted up with the top of first limiting plate (302) to second limiting plate (402).
CN202221447562.7U 2022-06-10 2022-06-10 Aluminum alloy bar heating furnace Active CN217541473U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221447562.7U CN217541473U (en) 2022-06-10 2022-06-10 Aluminum alloy bar heating furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221447562.7U CN217541473U (en) 2022-06-10 2022-06-10 Aluminum alloy bar heating furnace

Publications (1)

Publication Number Publication Date
CN217541473U true CN217541473U (en) 2022-10-04

Family

ID=83442711

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221447562.7U Active CN217541473U (en) 2022-06-10 2022-06-10 Aluminum alloy bar heating furnace

Country Status (1)

Country Link
CN (1) CN217541473U (en)

Similar Documents

Publication Publication Date Title
JP7117033B2 (en) Electric lifting type aerial work platform
CN211689169U (en) Energy-saving steel rolling heating furnace
CN111575644A (en) Zinc impregnation system
CN217541473U (en) Aluminum alloy bar heating furnace
JP3397724B2 (en) Brick intake device to coke oven
CN215668163U (en) Anti-corrosion metal surface treatment device
CN213728578U (en) Cooling bed heat preservation device
CN210119112U (en) Tunnel furnace door with good sealing performance
CN116659242A (en) Industrial furnace door structure
CN221527108U (en) Compact drying tank
KR20030053400A (en) Device for changing hearth roll of annealing furnace
CN113483564A (en) Industrial energy-saving kiln for firing ceramic products
CN213475870U (en) Automatic coke pot capping device
CN212133308U (en) Surrounding type industrial furnace kiln door opening and closing mechanism
CN107883771A (en) Conveying device of roller hearth furnace
CN207452184U (en) A kind of aluminium sheet annealing furnace
CN208964404U (en) A kind of hanging device of glass curtain wall
CN107282655B (en) Easy maintenance goes up and down to keep off steel device
CN216039734U (en) Whole heat treatment device of cold roll
CN220951888U (en) Heat treatment system for preventing deformation of high-precision large-sized metal part
CN206359154U (en) A kind of steel construction secondary member hoisting device
CN218879993U (en) High-efficient environmental protection double-chamber vacuum quenching furnace
CN211420252U (en) Suspension type heat treatment furnace for casting processing
CN214060583U (en) Bogie type double-door heat treatment furnace
CN220393550U (en) Glass cooling device capable of reducing stress

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant