CN217379618U - Novel wallboard installation dry-hanging system - Google Patents

Novel wallboard installation dry-hanging system Download PDF

Info

Publication number
CN217379618U
CN217379618U CN202220642816.4U CN202220642816U CN217379618U CN 217379618 U CN217379618 U CN 217379618U CN 202220642816 U CN202220642816 U CN 202220642816U CN 217379618 U CN217379618 U CN 217379618U
Authority
CN
China
Prior art keywords
line
spare
subassembly
dry
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220642816.4U
Other languages
Chinese (zh)
Inventor
佘学彬
张猛
袁梓翔
吕赫
秦锦峰
王博怀
郭锐
吴永杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nature Home China Co ltd
Original Assignee
Nature Home China Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nature Home China Co ltd filed Critical Nature Home China Co ltd
Priority to CN202220642816.4U priority Critical patent/CN217379618U/en
Application granted granted Critical
Publication of CN217379618U publication Critical patent/CN217379618U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model discloses a novel wallboard installation hang system futilely, including hanging the system futilely, hang the system futilely and include separated time piece one, separated time piece two, separated time piece three and separated time piece four, external corner line spare, reentrant corner line spare, roof line spare, skirting line subassembly by the separated time subassembly include with the skirting line spare one of being connected, sliding connection is in skirting line spare two, keel spare, dry pendant, binding off line subassembly and staggered floor lamp line spare of one end and constitute, the dry pendant is hung and is leaned on keel spare, and the back mounted of dry pendant has the installation wallboard. The utility model discloses in, through setting up a whole set of system of hanging futilely to utilize separated time subassembly, external corner line spare, internal corner line spare, terminal line spare, skirting line subassembly, dry pendant, binding off line subassembly to carry out the fixed at no dead angle to each angle of installation wallboard, make installation wallboard by stable the hanging lean on the wall when simple to operate, and because the existence of fossil fragments spare, make to have the space between wall and the installation wallboard, effectually carry out dampproofing etc..

Description

Novel wallboard installation dry-hanging system
Technical Field
The utility model relates to a technical field is hung futilely to the wallboard, specifically is a novel wallboard installation hang system futilely.
Background
The wallboard installation that has now on the market, the majority is all by means such as gluing, nailing to be fixed on carpenter's board basic unit, though the flexible operation, is applicable to multiple wall veneer mixed installation, but the shortcoming is obvious, difficult location, and installation operation is nonstandard, fragile wall, and the unable dismantlement of product carries out the reutilization, in addition, when using hardware system to install the wallboard, the wallboard of a thickness size just must be equipped with the five metals that corresponds the size. When wallboards with different thicknesses exist in a product system, various hardware cannot be used universally, and SKUs of a factory are increased, so that a novel wallboard mounting dry hanging system is provided.
SUMMERY OF THE UTILITY MODEL
The utility model discloses aim at solving one of the technical problem that exists among the prior art or the correlation technique.
Therefore, the utility model discloses the technical scheme who adopts does:
the utility model provides a novel wallboard installation hang system futilely, includes and hangs the system futilely, hang the system futilely and constitute by separated time subassembly, external corner line spare, internal corner line spare, roof line spare, skirting line subassembly, keel spare, dry pendant, binding off line subassembly and staggered floor lamp line spare, the dry pendant is hung and is leaned on keel spare, and the back mounted of dry pendant has the installation wallboard.
The present invention may be further configured in a preferred embodiment as: the wire distributing assembly comprises a first wire distributing piece, a second wire distributing piece, a third wire distributing piece and a fourth wire distributing piece.
By adopting the technical scheme, different wire distributing assemblies can be selected according to requirements, so that the structure can provide multiple choices.
The present invention may be further configured in a preferred embodiment as: the skirting line assembly comprises a first skirting line piece connected with the mounting wall board and a second skirting line piece connected to one end of the first skirting line piece in a sliding mode.
Through adopting above-mentioned technical scheme, can select whether to slide the position of skirting line spare two according to the width of below skirting line to the multiple width of adaptation.
The present invention may be further configured in a preferred embodiment as: the closing-up line assembly comprises a closing-up line I and a closing-up line II, and the closing-up line I and the closing-up line II are respectively installed at different positions of the installation wallboard.
Through adopting above-mentioned technical scheme for the position that the binding off line subassembly can be with is fixed more firm, the pleasing to the eye degree after the effectual promotion equipment.
By adopting the technical scheme, the utility model discloses the beneficial effect who gains does:
1. the utility model discloses in, through setting up a whole set of system of hanging futilely to utilize separated time subassembly, external corner line spare, internal corner line spare, terminal line spare, skirting line subassembly, dry pendant, binding off line subassembly to carry out the fixed at no dead angle to each angle of installation wallboard, make installation wallboard by stable the hanging lean on the wall when simple to operate, and because the existence of fossil fragments spare, make to have the space between wall and the installation wallboard, effectually carry out dampproofing etc..
2. The utility model discloses in, through the mode of pre-installation fossil fragments spare, can carry out accurate location, the effectual position of having guaranteed the installation wallboard can not the error, dismantles more convenient and fast simultaneously, sets up different specifications in addition and makes the installation wallboard that can be suitable for different thickness, the effectual practicality that has promoted the device.
Drawings
Fig. 1 is a schematic view of a branching assembly according to an embodiment of the present invention;
fig. 2 is a schematic view of an external corner line member according to an embodiment of the present invention;
fig. 3 is a schematic view of an internal corner line member according to an embodiment of the present invention;
fig. 4 is a schematic view of a top line member according to an embodiment of the present invention;
fig. 5 is a schematic view of a skirting line assembly according to an embodiment of the present invention;
FIG. 6 is a schematic view of a skirting line assembly according to an embodiment of the present invention;
figure 7 is a schematic view of a keel according to an embodiment of the invention;
fig. 8 is a schematic view of the keel installation according to an embodiment of the invention;
fig. 9 is a schematic view of a dry-hang element according to an embodiment of the present invention;
fig. 10 is a schematic view of a dry-hang element according to an embodiment of the present invention;
fig. 11 is a schematic view of a closing-up line assembly according to an embodiment of the present invention;
fig. 12 is a schematic view of a partial installation according to an embodiment of the present invention.
Reference numerals:
110. a wire branching assembly; 111. a first branching piece; 112. a second branching piece; 113. a third branching piece; 114. a wire distributing part IV; 120. an external corner line piece; 130. a reentrant corner line member; 140. a wire-jacking member; 150. a skirting line assembly; 151. a skirting line piece I; 152. a skirting line piece II; 160. a keel member; 170. a dry hanging part; 180. a closing line assembly; 181. a closing line I; 182. a closing line II; 190. a staggered layer lamp wire member;
200. and (6) installing the wallboard.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in further detail with reference to the accompanying drawings in combination with the following embodiments. It should be noted that the embodiments and features of the embodiments of the present invention may be combined with each other without conflict.
It is to be understood that such description is merely exemplary and is not intended to limit the scope of the present invention.
Some embodiments of the present invention provide a novel wall panel mounting dry hanging system.
The first embodiment is as follows:
with reference to fig. 1-12, the utility model provides a pair of novel wallboard installation system of hanging futilely, including the system of hanging futilely, the system of hanging futilely comprises separated time subassembly 110, external corner line piece 120, internal corner line piece 130, top line piece 140, skirting line subassembly 150, fossil fragments piece 160, the dry-hanging piece 170, binding off line subassembly 180 and staggered floor lamp line piece 190 constitute, the dry-hanging piece 170 is hung and is leaned on fossil fragments piece 160, and the back mounted of dry-hanging piece 170 has installation wallboard 200, cooperation through between each structure, can be with the position of installing wallboard 200 firmly fix on the wall, and because the existence of fossil fragments piece 160, make to have certain space between installation wallboard 200 and the wall, thereby installation wallboard 200 can not corroded by moisture, effectually carry out a dampproofing mould proof.
Example two:
with reference to fig. 1, on the basis of the first embodiment, the distributing component 110 includes a first distributing component 111, a second distributing component 112, a third distributing component 113, and a fourth distributing component 114, and different requirements are met by setting different types of distributing components 110, for example, a gap between the installed wall boards 200 needs to be enlarged, and a maximum gap can be achieved by selecting the fourth distributing component 114, otherwise, the first distributing component 111 is selected, which effectively improves the flexibility of structural use.
Specifically, skirting line subassembly 150 includes skirting line spare one 151 of being connected with installation wallboard 200, sliding connection is at skirting line spare two 152 of a skirting line spare 151 one end, through the position of sliding adjustment skirting line spare two 152, can be suitable for different width and get the skirting line to guarantee the firm of connecting between the structure, the too wide or too narrow condition of skirting line subassembly 150 can not appear, has improved the practicality of device.
Example three:
referring to fig. 12, in the above embodiment, the closing-up line assembly 180 includes the first closing-up line 181 and the second closing-up line 182, the first closing-up line 181 and the second closing-up line 182 are respectively installed at different positions of the installation wall board 200, and are installed at different positions of the installation wall board 200 through the first closing-up line 181 and the second closing-up line 182, so as to implement comprehensive fixation of the position of the installation wall board 200, and implement installation of the lamp line by matching with the staggered-layer lamp line piece 190, thereby effectively improving reliability of the device.
The utility model discloses a theory of operation and use flow: firstly, the keel member 160 is fixed on the wall surface, then the dry hanging member 170 is installed at the corresponding position of the back surface of the installation wall board 200, the line distributing assembly 110 is installed between the two installation wall boards 200, the external corner line member 120 and the internal corner line member 130 are respectively installed at the external corner and the internal corner of the junction of the installation wall boards 200, the top line member 140 and the skirting line member 150 are respectively installed at the top and the bottom of the installation wall boards 200, the installation wall boards 200 are assembled, and finally the binding off line assembly 180 is used for final fixation.
In the present application, the term "plurality" means two or more unless expressly defined otherwise. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items. The terms "mounted," "connected," "fixed," and the like are to be construed broadly, and for example, "connected" may be a fixed connection, a removable connection, or an integral connection; "coupled" may be direct or indirect through an intermediary. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
It will be understood that when an element is referred to as being "mounted to," "secured to" or "disposed on" another element, it can be directly on the other element or intervening elements may also be present. When an element is referred to as being "connected" to another element, it can be directly connected to the other element or intervening elements may also be present. The terms "vertical," "horizontal," "upper," "lower," "left," "right," and the like as used herein are for illustrative purposes only and do not denote a unique embodiment.
In the description of the present specification, the description of the terms "one embodiment," "some embodiments," "specific embodiments," etc., means that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the claims and their equivalents.

Claims (4)

1. The utility model provides a novel wallboard installation hangs system futilely, its characterized in that, includes and hangs the system futilely, hang the system futilely and constitute by separated time subassembly (110), external corner line spare (120), reentrant corner line spare (130), top line spare (140), skirting line subassembly (150), fossil fragments spare (160), dry-hanging piece (170), binding off line subassembly (180) and staggered floor lamp line spare (190), hang and lean on fossil fragments spare (160) dry-hanging piece (170), and the back mounted of dry-hanging piece (170) has installation wallboard (200).
2. A novel wall panel mounting dry hang system as claimed in claim 1, wherein the wire distributing assembly (110) comprises a first wire distributing part (111), a second wire distributing part (112), a third wire distributing part (113) and a fourth wire distributing part (114).
3. A novel wall panel mounting dry hang system as claimed in claim 1, wherein the skirting line assembly (150) comprises a first skirting line piece (151) connected with the mounting wall panel (200), and a second skirting line piece (152) slidably connected with one end of the first skirting line piece (151).
4. A novel wall panel mounting dry hang system as claimed in claim 1, wherein the binding off line assembly (180) comprises a first binding off line (181) and a second binding off line (182), the first binding off line (181) and the second binding off line (182) are respectively mounted at different positions of the mounting wall panel (200).
CN202220642816.4U 2022-03-23 2022-03-23 Novel wallboard installation dry-hanging system Active CN217379618U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220642816.4U CN217379618U (en) 2022-03-23 2022-03-23 Novel wallboard installation dry-hanging system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220642816.4U CN217379618U (en) 2022-03-23 2022-03-23 Novel wallboard installation dry-hanging system

Publications (1)

Publication Number Publication Date
CN217379618U true CN217379618U (en) 2022-09-06

Family

ID=83102902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220642816.4U Active CN217379618U (en) 2022-03-23 2022-03-23 Novel wallboard installation dry-hanging system

Country Status (1)

Country Link
CN (1) CN217379618U (en)

Similar Documents

Publication Publication Date Title
CN107268866B (en) Combined type grade-falling suspended ceiling and installation method
EP0890331B1 (en) System for connecting juxtapposed sectional boards
US3528636A (en) Support bracket for electrical fixtures
US7861986B2 (en) Bracket and method for supporting a cubicle wall on a movable wall having horizontal mounting channels
CN107268865B (en) Modular drop-level ceiling device and installation method
US7219477B2 (en) Siding trim
CA2980094A1 (en) Flush or lap siding system
US10928031B2 (en) Indirect light cove
CN217379618U (en) Novel wallboard installation dry-hanging system
IE47934B1 (en) A device for joining panels
CN210342403U (en) Assembled aluminum plate ceiling structure
US20200063447A1 (en) Perimeter pocket system
US20070271869A1 (en) Corner framing member
CN110670910A (en) Assembled kitchen
CN214090810U (en) Matching structure of top line mounting assembly and wall panel
CN214462186U (en) Suspended ceiling modeling structure
CN215764790U (en) Lamp slot structure
CN211286483U (en) Fixed buckle of multiple spot, decoration material and fixed subassembly of decoration material
CN108577397B (en) Wall hanging system and installation method
CN217998722U (en) Sectional type decorative board mounting structure
CN211143866U (en) Assembled kitchen
CN214941948U (en) Dry wall
CN215484286U (en) Double-sided wood-plastic wallboard and double-sided wood-plastic wallboard mounting structure
CN211572358U (en) Wallboard fastener
CN219158142U (en) Hidden furred ceiling connecting piece

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant