CN217326211U - External wall insulation board installation construction mechanism for building construction - Google Patents

External wall insulation board installation construction mechanism for building construction Download PDF

Info

Publication number
CN217326211U
CN217326211U CN202123272533.XU CN202123272533U CN217326211U CN 217326211 U CN217326211 U CN 217326211U CN 202123272533 U CN202123272533 U CN 202123272533U CN 217326211 U CN217326211 U CN 217326211U
Authority
CN
China
Prior art keywords
insulation board
board
heated board
springs
mounting groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123272533.XU
Other languages
Chinese (zh)
Inventor
杨玉华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiang Xianhua
Original Assignee
Yuzhaozhi Shenyang Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuzhaozhi Shenyang Technology Co ltd filed Critical Yuzhaozhi Shenyang Technology Co ltd
Priority to CN202123272533.XU priority Critical patent/CN217326211U/en
Application granted granted Critical
Publication of CN217326211U publication Critical patent/CN217326211U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/90Passive houses; Double facade technology

Landscapes

  • Building Environments (AREA)
  • Finishing Walls (AREA)

Abstract

The utility model discloses an external wall insulation board construction mechanism for construction, including first heated board, second heated board and third heated board, first heated board and second heated board level set up, first heated board and the vertical setting of third heated board, a plurality of latch mechanisms have been seted up to the equidistant lateral wall that first heated board is relative with the second heated board, be equipped with a plurality of coupling mechanisms between first heated board and the second heated board, it is a plurality of coupling mechanism extends to in rather than relative latch mechanism respectively, be connected through strengthening mechanism between first heated board and the third heated board. The utility model has the advantages of reasonable design, can carry out erection joint to adjacent heated board in horizontal direction and the vertical direction respectively, the stability of guarantee heated board avoids it to take place the obscission, and then can ensure its life, and can ensure its aesthetic property.

Description

External wall insulation board installation construction mechanism for building construction
Technical Field
The utility model relates to an external wall insulation board construction technical field especially relates to an external wall insulation board construction mechanism for construction.
Background
The outer wall insulation board, also called a floor line building outer wall decoration integrated board, is produced in a factory and is used for on-site bonding construction on high-rise outer walls, indoor markets and industrial equipment, and has the characteristics of low manufacturing cost, good effect, corrosion resistance, no pollution and the like.
At present, when the construction of external wall insulation board installation, need splice the installation to the external wall insulation board and handle, connect fixedly the heated board through a plurality of bolts usually, not only complex operation, inefficiency influences the job schedule to the bolt exposes still influences its aesthetic property in the outside, for this we have designed an external wall insulation board construction mechanism for the construction and have solved above problem.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving among the prior art and generally connecting fixedly through a plurality of bolts to the heated board, not only complex operation, the inefficiency influences the job schedule, and the bolt exposes still to influence its aesthetic property problem in the outside, and the outer wall insulation board construction mechanism for construction installation that proposes, it can carry out erection joint to adjacent heated board in the horizontal direction and the vertical direction respectively, guarantee heated board's stability, avoid it to take place the obscission, and then can ensure its life, and can ensure its aesthetic property.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
an outer wall insulation board installation construction mechanism for building construction comprises a first insulation board, a second insulation board and a third insulation board, wherein the first insulation board and the second insulation board are horizontally arranged, the first insulation board and the third insulation board are vertically arranged, a plurality of clamping mechanisms are arranged on the side wall of the first insulation board opposite to the second insulation board at equal intervals, each clamping mechanism comprises a first clamping groove formed in the side wall of the first insulation board, the upper end and the lower end of each first clamping groove are respectively provided with a first fixing groove, the side wall of the second insulation board is provided with a second clamping groove, the upper end and the lower end of each second clamping groove are respectively provided with a second fixing groove, a plurality of connecting mechanisms are arranged between the first insulation board and the second insulation board and respectively extend into the clamping mechanisms opposite to the connecting mechanisms, each connecting mechanism comprises an installation board arranged between the first insulation board and the second insulation board, the both ends of mounting panel extend to first joint groove and second joint inslot respectively, first connection spout, two have all been seted up at one section upper and lower both ends that the mounting panel is located first joint inslot equal sliding connection has the first connecting plate that extends to rather than relative first fixed slot in the first connection spout, be connected with a plurality of first springs between the inside wall of first connecting plate and first connection spout, the second connection spout has all been seted up at one section upper and lower both ends that the mounting panel is located second joint inslot, two equal sliding connection has the second connecting plate that extends to rather than relative second fixed slot in the second connection spout, be connected with a plurality of second springs between the inside wall of second connecting plate and second connection spout, be connected through reinforcing mechanism between first heated board and the third heated board.
Preferably, the two first connecting plates are obliquely arranged close to the side wall of the first heat-insulation plate, and the two second connecting plates are obliquely arranged close to the side wall of the second heat-insulation plate.
Preferably, the reinforcing mechanism comprises a first mounting groove arranged at the bottom of the first heat-insulating plate, the inner top of the first mounting groove is fixedly connected with a first magnetic block, the upper end of the third heat-insulating plate is provided with a second mounting groove, the inner bottom of the second mounting groove is fixedly connected with a second magnetic block, the inner top of the first mounting groove is fixedly connected with a first U-shaped plate, the first U-shaped plate is slidably connected with a third magnetic block extending into the second mounting groove, the magnetic poles of the third magnetic block and the second magnetic block are opposite to each other, a plurality of third springs are connected between the third magnetic block and the inner top of the first U-shaped plate, the inner bottom of the second mounting groove is fixedly connected with a second U-shaped plate, the second U-shaped plate is slidably connected with a fourth magnetic block extending into the first mounting groove, and the magnetic poles of the fourth magnetic block and the first opposite to each other side are opposite to each other, and a plurality of fourth springs are connected between the fourth magnetic block and the inner bottom of the second U-shaped plate.
Preferably, the first spring and the second spring are both elastic springs, and the third spring and the fourth spring are both tension springs.
Compared with the prior art, the utility model, its beneficial effect does:
1. through the setting of first heated board, second heated board, latch mechanism and coupling mechanism, can carry out erection joint to adjacent heated board in the horizontal direction, guarantee the stability of its connection, and then can ensure its life.
2. Through the setting of first heated board, third heated board, strengthening mechanism, can carry out erection joint to adjacent heated board in the vertical direction, guarantee the stability of its connection, and then can ensure its life.
To sum up, the utility model has the advantages of reasonable design, can carry out erection joint to adjacent heated board in horizontal direction and the vertical direction respectively, guarantee the stability of heated board avoids it to take place the obscission, and then can ensure its life, and can ensure its aesthetic property.
Drawings
FIG. 1 is a schematic structural view of an external wall insulation board installation and construction mechanism for building construction provided by the utility model;
FIG. 2 is an enlarged view of the structure at A in FIG. 1;
fig. 3 is an enlarged view of the structure at B in fig. 1.
In the figure: 1 first heated board, 2 second heated board, 3 third heated board, 4 first joint grooves, 5 first fixed slots, 6 second joint grooves, 7 second fixed slots, 8 mounting panels, 9 first connecting chutes, 10 first connecting plates, 11 first springs, 12 second connecting chutes, 13 second connecting plates, 14 second springs, 15 first mounting grooves, 16 first magnetic blocks, 17 second mounting grooves, 18 second magnetic blocks, 19 first U-shaped plates, 20 third magnetic blocks, 21 third springs, 22 second U-shaped plates, 23 fourth magnetic blocks, 24 fourth springs.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, an exterior wall insulation board installation and construction mechanism for building construction comprises a first insulation board 1, a second insulation board 2 and a third insulation board 3, wherein the first insulation board 1 and the second insulation board 2 are horizontally arranged, the first insulation board 1 and the third insulation board 3 are vertically arranged, it is noted that installation and connection of two insulation boards in the horizontal direction can be demonstrated through arrangement of the first insulation board 1 and the second insulation board 2, installation and connection of two insulation boards in the vertical direction can be demonstrated through arrangement of the first insulation board 1 and the third insulation board 3, a plurality of clamping mechanisms are arranged on the side wall of the first insulation board 1 opposite to the second insulation board 2 at equal intervals, each clamping mechanism comprises a first clamping groove 4 arranged on the side wall of the first insulation board 1, first fixing grooves 5 are arranged at the upper end and the lower end of each first clamping groove 4, a second clamping groove 6 is formed in the side wall of the second heat-insulation plate 2, and second fixing grooves 7 are formed in the upper end and the lower end of the second clamping groove 6;
a plurality of connecting mechanisms are arranged between the first heat-insulating plate 1 and the second heat-insulating plate 2, the connecting mechanisms respectively extend into the clamping mechanisms opposite to the connecting mechanisms, each connecting mechanism comprises a mounting plate 8 arranged between the first heat-insulating plate 1 and the second heat-insulating plate 2, two ends of each mounting plate 8 respectively extend into the first clamping groove 4 and the second clamping groove 6, the upper end and the lower end of one section of the mounting plate 8, which is positioned in the first clamping groove 4, are respectively provided with a first connecting chute 9, the two first connecting chutes 9 are respectively and slidably connected with first connecting plates 10 extending into the first fixing grooves 5 opposite to the first connecting chutes, a plurality of first springs 11 are connected between the first connecting plates 10 and the inner side walls of the first connecting chutes 9, the upper end and the lower end of one section of the mounting plate 8, which is positioned in the second clamping groove 6, are respectively provided with second connecting chutes 12, the two second connecting chutes 12 are respectively and slidably connected with second connecting plates 13 extending into the second fixing grooves 7 opposite to the second connecting chutes 12, a plurality of second springs 14 are connected between the second connecting plates 13 and the inner side walls of the second connecting chutes 12, the first springs 11 and the second springs 14 are elastic springs, the two first connecting plates 10 are obliquely arranged close to the side walls of the first heat-insulating plates 1, and the two second connecting plates 13 are obliquely arranged close to the side walls of the second heat-insulating plates 2, it is noted that the first springs 11 and the second springs 14 are elastic springs, and the first connecting plates 10 and the second connecting plates 13 can be respectively pushed into the first fixing grooves 5 and the second fixing grooves 7 opposite to the first connecting plates and the second connecting plates in a natural state, so that the first heat-insulating plates 1 and the second heat-insulating plates 2 can be connected, and further, the two heat-insulating plates in the horizontal direction can be stably connected;
the first heat-insulation plate 1 is connected with the third heat-insulation plate 3 through a reinforcing mechanism, the reinforcing mechanism comprises a first mounting groove 15 arranged at the bottom of the first heat-insulation plate 1, the inner top of the first mounting groove 15 is fixedly connected with a first magnetic block 16, the upper end of the third heat-insulation plate 3 is provided with a second mounting groove 17, the inner bottom of the second mounting groove 17 is fixedly connected with a second magnetic block 18, the inner top of the first mounting groove 15 is fixedly connected with a first U-shaped plate 19, the first U-shaped plate 19 is in sliding connection with a third magnetic block 20 extending into the second mounting groove 17, the magnetic poles of the third magnetic block 20 and the second magnetic block 18 are opposite, a plurality of third springs 21 are connected between the third magnetic block 20 and the inner top of the first U-shaped plate 19, the inner bottom of the second mounting groove 17 is fixedly connected with a second U-shaped plate 22, the second U-shaped plate 22 is in sliding connection with a fourth magnetic block 23 extending into the first mounting groove 15, the magnetic poles of the fourth magnetic block 23 and the first magnetic block 16 are opposite to the side walls, a plurality of fourth springs 24 are connected between the inner bottom of the fourth magnetic block 23 and the inner bottom of the second U-shaped plate 22, the third springs 21 and the fourth springs 24 are tension springs, it is noted that the third springs 21 and the fourth springs 24 are tension springs, the third magnetic block 20 can be pulled into the first U-shaped plate 19 and the fourth magnetic block 23 is pulled into the second U-shaped plate 22 naturally, so that the fourth magnetic block is prevented from being exposed outside the first heat-preservation plate 1 or outside the third heat-preservation plate 3, because the third magnetic block 20 and the second magnetic block 18 attract each other, and the fourth magnetic block 23 and the first magnetic block 16 attract each other, the third magnetic block 20 can stably extend into the second mounting groove 17, the fourth magnetic block 23 can stably extend into the first mounting groove 15, the first heat-insulating plate 1 and the third heat-insulating plate 3 can be stably connected, and then two heat-insulating plates in the vertical direction can be connected.
The utility model discloses its functional principle is explained to following mode of operation of accessible:
in the utility model, when the external wall insulation board is required to be installed and constructed, the first insulation board 1 is adhered on the external wall through the adhesive, the mounting board 8 is just opposite to the first clamping groove 4, the mounting board 8 moves in the first clamping groove 4, because the side walls at two ends of the first connecting board 10 are obliquely arranged, when the first connecting board 10 is abutted against the side wall of the first insulation board 1, the two first connecting boards 10 can slide in the first connecting chute 9 firstly, when the first connecting board 10 is opposed to the first fixing groove 5, the first spring 11 can push the first connecting board 10 to the first fixing groove 5 opposite to the first connecting board 10 to stably connect the mounting board 8 with the first insulation board 1, the second insulation board 2 is arranged at the horizontal position of the first insulation board 1, the mounting board 8 is opposed to the second clamping groove 6, the second insulation board 2 is pushed to be abutted against the side wall of the first insulation board 1 gradually, because the side walls at the two ends of the second connecting plate 13 are obliquely arranged, when the second connecting plate 13 abuts against the side walls of the second heat-insulating plate 2, the two second connecting plates 13 can slide towards the second connecting chute 12 firstly, when the second connecting plate 13 faces the second fixing groove 7, the second spring 14 can push the second connecting plate 13 into the second fixing groove 7 opposite to the second connecting plate 13, so that the second heat-insulating plate 2 is stably fixed, at the moment, the second heat-insulating plate 2 abuts against the first heat-insulating plate 1, the second heat-insulating plate 2 is bonded and reinforced through the adhesive, and similarly, the heat-insulating plates adjacent to each other in the horizontal direction can be conveniently installed and fixed;
arrange third heated board 3 in first heated board 1 under and with first heated board 1 alignment, third magnetic path 20 is relative with second magnetic path 18 this moment, the effort that can produce the looks and inhale makes third magnetic path 20 extend to in second mounting groove 17 and inhale mutually with second magnetic path 18, simultaneously, fourth magnetic path 23 is relative with first magnetic path 16, the effort that can produce the looks and inhales makes fourth magnetic path 23 extend to in first mounting groove 15 and inhale mutually with first magnetic path 16, connect first heated board 1 and third heated board 3, bond the reinforcement to third heated board 3 through the adhesive, and in the same way, can be convenient for to the adjacent heated board in the vertical direction fix, guarantee the stability of heated board connection, avoid it to take place the obscission phenomenon, and can avoid connecting it through the screw, guarantee its aesthetic property.
The above, only be the embodiment of the preferred of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, which are designed to be replaced or changed equally, all should be covered within the protection scope of the present invention.

Claims (4)

1. An outer wall insulation board installation and construction mechanism for building construction comprises a first insulation board (1), a second insulation board (2) and a third insulation board (3), and is characterized in that the first insulation board (1) and the second insulation board (2) are horizontally arranged, the first insulation board (1) and the third insulation board (3) are vertically arranged, a plurality of clamping mechanisms are arranged on the side wall of the first insulation board (1) opposite to the second insulation board (2) at equal intervals, each clamping mechanism comprises a first clamping groove (4) formed in the side wall of the first insulation board (1), first fixing grooves (5) are formed in the upper end and the lower end of each first clamping groove (4), second clamping grooves (6) are formed in the side wall of the second insulation board (2), second fixing grooves (7) are formed in the upper end and the lower end of each second clamping groove (6), a plurality of connecting mechanisms are arranged between the first insulation board (1) and the second insulation board (2), a plurality of the connecting mechanisms respectively extend into the clamping mechanisms opposite to the connecting mechanisms, each connecting mechanism comprises a mounting plate (8) arranged between a first heat-insulating plate (1) and a second heat-insulating plate (2), the two ends of each mounting plate (8) respectively extend into a first clamping groove (4) and a second clamping groove (6), first connecting chutes (9) are respectively formed in the upper end and the lower end of one section of each mounting plate (8) positioned in the first clamping groove (4), first connecting plates (10) extending into first fixing grooves (5) opposite to the first connecting chutes are respectively connected in the two first connecting chutes (9) in a sliding manner, a plurality of first springs (11) are connected between the inner side walls of the first connecting plates (10) and the first connecting chutes (9), second connecting chutes (12) are respectively formed in the upper end and the lower end of one section of each mounting plate (8) positioned in the second clamping groove (6), two equal sliding connection has second connecting plate (13) that extends to rather than in the relative second fixed slot (7) in second connecting chute (12), be connected with a plurality of second springs (14) between the inside wall of second connecting plate (13) and second connecting chute (12), be connected through strengthening mechanism between first heated board (1) and third heated board (3).
2. The exterior wall insulation board installation and construction mechanism for building construction according to claim 1 is characterized in that the two first connecting plates (10) are obliquely arranged close to the side walls of the first insulation boards (1), and the two second connecting plates (13) are obliquely arranged close to the side walls of the second insulation boards (2).
3. The exterior wall insulation board mounting construction mechanism for building construction as claimed in claim 1, wherein the reinforcing mechanism comprises a first mounting groove (15) formed at the bottom of the first insulation board (1), the inner top of the first mounting groove (15) is fixedly connected with a first magnetic block (16), the upper end of the third insulation board (3) is provided with a second mounting groove (17), the inner bottom of the second mounting groove (17) is fixedly connected with a second magnetic block (18), the inner top of the first mounting groove (15) is fixedly connected with a first U-shaped board (19), the first U-shaped board (19) is slidably connected with a third magnetic block (20) extending into the second mounting groove (17), the third magnetic block (20) is opposite to the opposite side wall magnetic poles of the second magnetic block (18), and a plurality of third springs (21) are connected between the third magnetic block (20) and the inner top of the first U-shaped board (19), the interior bottom fixedly connected with second U template (22) of second mounting groove (17), sliding connection has fourth magnetic path (23) that extends to in first mounting groove (15) in second U template (22), fourth magnetic path (23) are opposite with first magnetic path (16) relative side wall magnetic pole, be connected with a plurality of fourth springs (24) between the interior bottom of fourth magnetic path (23) and second U template (22).
4. The exterior wall insulation board installation and construction mechanism for building construction according to claim 3, wherein the first spring (11) and the second spring (14) are both elastic springs, and the third spring (21) and the fourth spring (24) are both tension springs.
CN202123272533.XU 2021-12-24 2021-12-24 External wall insulation board installation construction mechanism for building construction Active CN217326211U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123272533.XU CN217326211U (en) 2021-12-24 2021-12-24 External wall insulation board installation construction mechanism for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123272533.XU CN217326211U (en) 2021-12-24 2021-12-24 External wall insulation board installation construction mechanism for building construction

Publications (1)

Publication Number Publication Date
CN217326211U true CN217326211U (en) 2022-08-30

Family

ID=82989037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123272533.XU Active CN217326211U (en) 2021-12-24 2021-12-24 External wall insulation board installation construction mechanism for building construction

Country Status (1)

Country Link
CN (1) CN217326211U (en)

Similar Documents

Publication Publication Date Title
CN206091045U (en) Antinode core precast concrete assembled composite wall
CN106836469B (en) Assembly type building
CN217326211U (en) External wall insulation board installation construction mechanism for building construction
CN101914949B (en) Assembled housing and manufacturing method thereof
CN208473060U (en) A kind of metal curtain wall
CN109610703A (en) A kind of assembled wallboard
CN214833692U (en) House building assembled wallboard structure
CN215166791U (en) Steel construction assembled wallboard node
CN211646807U (en) Light gauge steel sound insulation construction
CN205743141U (en) The frame mounting of inversion machine room
CN211313842U (en) Self-bearing door pocket
CN211114297U (en) Earthquake-resistant structure of GRC curtain wall board
CN209413084U (en) A kind of blind box cover construction node
CN220644746U (en) Prefabricated interior wallboard for building
CN2563202Y (en) Assembling type structure house
CN113356412B (en) Assembled fast-assembling partition wall
CN219451163U (en) Assembled indoor light partition board
CN218970333U (en) Assembled wall structure
CN216921120U (en) Novel external wall heat-insulation board for civil and industrial buildings
CN213928010U (en) Assembly type structure outer wall large plate and ultra-low energy consumption system window assembly reinforcing structure
CN219732406U (en) Assembled unit fossil fragments partition wall device
CN213448993U (en) Assembled wall unit
CN216042341U (en) Assembled GRG embedded type assembling system
CN211666526U (en) Assembling door and window frame
CN220539014U (en) Core-filled precast concrete wallboard

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240614

Address after: No. 19, Group 29, Hainan Village, Nancheng Street, Hai'an County, Nantong City, Jiangsu Province, 226600

Patentee after: Jiang Xianhua

Country or region after: China

Address before: 110000 No. 8-c, Hunnan Third Road, Hunnan District, Shenyang City, Liaoning Province (1102)

Patentee before: Yuzhaozhi (Shenyang) Technology Co.,Ltd.

Country or region before: China