CN217281856U - Be used for quick installation mould of cable testing bridge - Google Patents

Be used for quick installation mould of cable testing bridge Download PDF

Info

Publication number
CN217281856U
CN217281856U CN202220124033.7U CN202220124033U CN217281856U CN 217281856 U CN217281856 U CN 217281856U CN 202220124033 U CN202220124033 U CN 202220124033U CN 217281856 U CN217281856 U CN 217281856U
Authority
CN
China
Prior art keywords
rod
lead screw
screw rod
rotating screw
sliding block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220124033.7U
Other languages
Chinese (zh)
Inventor
陈启庆
陈启云
葛世杰
金敏秀
陈文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhishuo Electrical Appliance Whole Set Co ltd
Original Assignee
Shanghai Zhishuo Electrical Appliance Whole Set Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhishuo Electrical Appliance Whole Set Co ltd filed Critical Shanghai Zhishuo Electrical Appliance Whole Set Co ltd
Priority to CN202220124033.7U priority Critical patent/CN217281856U/en
Application granted granted Critical
Publication of CN217281856U publication Critical patent/CN217281856U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a be used for quick installation mould of cable testing bridge, have the removal seat of walking wheel including the bottom, be equipped with vertical ascending grudging post on the removal seat, be equipped with the first rotation lead screw of vertical setting on the grudging post, the sliding block that moves along first rotation lead screw on the first rotation lead screw, be fixed with the crane of vertical setting on the outer wall of sliding block, be equipped with the second rotation lead screw of vertical setting on the crane, be equipped with on the second rotation lead screw along the second rotation lead screw removal lift tray, be equipped with on the lift tray and be used for holding in the palm the bracket of carrying to the cable testing bridge, be equipped with the first driving motor who drives first rotation lead screw pivoted on the grudging post, be equipped with the drive second on the crane and rotate lead screw pivoted second driving motor. The utility model discloses carry out automatic lifting, effectively reduced working strength to work efficiency has been improved.

Description

Be used for quick installation mould of cable testing bridge
Technical Field
The utility model relates to a cable testing bridge installation technical field specifically is a be used for quick mold erection of cable testing bridge.
Background
The cable bridge is divided into structures of a groove type, a tray type, a ladder type, a grid type and the like, and comprises a support, a supporting arm, an installation accessory and the like. The inner bridge frame of the building can be independently erected and also can be laid on various buildings (structures) and pipe gallery supports, the characteristics of simple structure, attractive appearance, flexible configuration, convenient maintenance and the like are reflected, all parts need to be galvanized and are arranged on the outdoor bridge frame outside the building; at present, the cable bridge is mainly lifted manually during installation, so that the working strength is high, and the installation efficiency is low. Therefore, the invention provides an improvement on the method and provides a quick installation die for the cable bridge.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a following technical scheme:
the utility model relates to a be used for quick installation mould of cable testing bridge, have the removal seat of walking wheel including the bottom, be equipped with vertical ascending grudging post on the removal seat, be equipped with the first rotation lead screw of vertical setting on the grudging post, first sliding block of first rotation lead screw removal is followed on the first rotation lead screw, be fixed with the crane of vertical setting on the outer wall of first sliding block, be equipped with the second rotation lead screw of vertical setting on the crane, be equipped with on the second rotation lead screw along the second rotation lead screw removal lift tray, be equipped with on the lift tray and be used for the bracket of carrying to cable testing bridge support, be equipped with the first driving motor that rotates lead screw pivoted of drive on the grudging post, be equipped with the drive second on the crane and rotate lead screw pivoted second driving motor.
As a preferred technical scheme of the utility model, the bracket includes the horizontal pole of being connected with the lift tray, the both ends tip of horizontal pole is equipped with the tow bar, be equipped with the inboard spacing gag lever post to the cable testing bridge on the horizontal pole, be equipped with on the tow bar along the gliding second sliding block of tow bar, be equipped with the centre gripping locating lever of vertical setting on the second sliding block, form a centre gripping mouth to the cable testing bridge centre gripping between gag lever post and the locating lever.
As a preferred technical scheme of the utility model, remove the seat and be equipped with the balancing weight in the one side of keeping away from the bracket.
As a preferred technical scheme of the utility model, first sliding block is equipped with two.
As a preferred technical scheme of the utility model, be equipped with on the crane and rotate lead screw parallel arrangement's spacing polished rod with the second, be equipped with on the spacing polished rod along the spacing sleeve that spacing polished rod removed, just spacing sleeve is fixed mutually with the lift tray.
The utility model has the advantages that:
this kind of be used for quick installation mould of cable testing bridge is through rotating first rotation lead screw thereby drive first sliding block and reciprocate along first rotation lead screw, and then drive the crane and carry out the elevating movement, then go up and down the tray through the crane and move along the crane, and then go up and down to the cable testing bridge that lifts on the lift tray, when installing the cable testing bridge, need not the manual work and lift to effectively reduce working strength, improved work efficiency.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the principles of the invention. In the drawings:
fig. 1 is a schematic structural view of a quick installation mold for a cable bridge of the present invention;
fig. 2 is a schematic structural diagram of a bracket for a cable bridge rack quick installation mold according to the present invention;
fig. 3 is a schematic structural view of the limiting polish rod of the quick installation mold for the cable bridge of the present invention.
In the figure: 1. a movable seat; 2. a traveling wheel; 3. erecting a frame; 4. a first rotating screw rod; 5. a first slider; 6. a lifting frame; 7. a second rotating screw rod; 8. lifting the supporting block; 9. a bracket; 10. a first drive motor; 11. a second drive motor; 12. a cross bar; 13. a tow bar; 14. a limiting rod; 15. a second slider; 16. clamping the positioning rod; 17. a balancing weight; 18. a limiting polished rod; 19. and a limiting sleeve.
Detailed Description
The preferred embodiments of the present invention will be described in conjunction with the accompanying drawings, and it will be understood that they are presented herein only to illustrate and explain the present invention, and not to limit the present invention.
Example (b): as shown in figures 1-3, the utility model relates to a quick installation mould for cable bridge, which comprises a movable base 1 with a traveling wheel 2 at the bottom, the moving seat 1 is provided with a vertical upward vertical frame 3, the vertical frame 3 is provided with a first rotating screw rod 4 which is vertically arranged, a sliding block 5 which moves along the first rotating screw rod 4 is arranged on the first rotating screw rod 4, a lifting frame 6 which is vertically arranged is fixed on the outer wall of the sliding block 5, the lifting frame 6 is provided with a second rotating screw rod 7 which is vertically arranged, the second rotating screw rod 7 is provided with a lifting support block 8 which moves along the second rotating screw rod 7, the lifting support block 8 is provided with a bracket 9 for supporting a cable bridge, the vertical frame 3 is provided with a first driving motor 10 for driving the first rotating screw rod 4 to rotate, and the lifting frame 6 is provided with a second driving motor 11 for driving the second rotating screw rod 7 to rotate. Thereby drive first sliding block 5 and reciprocate along first rotation lead screw 4 through rotating first rotation lead screw 4, and then drive crane 6 and carry out the elevating movement, then through 6 ascending lift tray 8 of crane move along crane 6, and then go up and down to the cable testing bridge that lifts on the lift tray 8, when installing the cable testing bridge, need not the manual work and lift to effectively reduce working strength, improved work efficiency.
Bracket 9 includes the horizontal pole 12 of being connected with lift tray 8, the both ends tip of horizontal pole 12 is equipped with tow bar 13, be equipped with the inboard spacing gag lever post 14 to the cable testing bridge on the horizontal pole 12, be equipped with on the tow bar 13 along the gliding sliding block 15 of tow bar 13, be equipped with the centre gripping locating lever 16 of vertical setting on the sliding block 15, form a centre gripping mouth to the cable testing bridge centre gripping between gag lever post 14 and the locating lever 16, conveniently carry on spacingly to the cable testing bridge, avoid taking place the landing phenomenon to the cable testing bridge.
The movable seat 2 is provided with a balancing weight 17 on one side far away from the bracket 9, so that the moving stability is improved, and the side turning is avoided.
First sliding block 5 is equipped with two, has increased the stability that the crane removed.
The lifting frame 6 is provided with a limiting polished rod 18 which is arranged in parallel with the second rotary screw rod 7, the limiting polished rod 18 is provided with a limiting sleeve 19 which moves along the limiting polished rod 18, the limiting sleeve 19 is fixed with the lifting support block 8, the limiting effect is achieved, and the lifting support block is prevented from being damaged.
The working principle is as follows: thereby drive first sliding block 5 and reciprocate along first rotation lead screw 4 through rotating first rotation lead screw 4, and then drive crane 6 and carry out elevating movement, then through 6 ascending and descending tray 8 of crane move along crane 6, and then go up and down to the cable testing bridge that lifts on the ascending and descending tray 8, when installing the cable testing bridge, need not the manual work and lift to effectively reduce working strength, improved work efficiency.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1. The utility model provides a be used for quick installation mould of cable testing bridge which characterized in that: comprises a moving seat (1) with a walking wheel (2) at the bottom, a vertical upward vertical frame (3) is arranged on the moving seat (1), a first rotating screw rod (4) which is vertically arranged is arranged on the vertical frame (3), a first sliding block (5) which moves along the first rotating screw rod (4) is arranged on the first rotating screw rod (4), a lifting frame (6) which is vertically arranged is fixed on the outer wall of the first sliding block (5), a second rotating screw rod (7) which is vertically arranged is arranged on the lifting frame (6), the second rotating screw rod (7) is provided with a lifting support block (8) which moves along the second rotating screw rod (7), the lifting support block (8) is provided with a bracket (9) for supporting the cable bridge, a first driving motor (10) for driving the first rotating screw rod (4) to rotate is arranged on the vertical frame (3), and a second driving motor (11) for driving the second rotating screw rod (7) to rotate is arranged on the lifting frame (6).
2. The die for quickly mounting the cable bridge according to claim 1, wherein the bracket (9) comprises a cross bar (12) connected with the lifting support block (8), the end portions of the two ends of the cross bar (12) are provided with drag rods (13), the cross bar (12) is provided with a limit rod (14) for limiting the inner side of the cable bridge, the drag rod (13) is provided with a second sliding block (15) sliding along the drag rod (13), the second sliding block (15) is provided with a vertically arranged clamping and positioning rod (16), and a clamping opening for clamping the cable bridge is formed between the limit rod (14) and the positioning rod (16).
3. A mould for the quick installation of cable trays, as in claim 2, characterized in that said mobile seat (1) is provided with a counterweight (17) on the side remote from the carriage (9).
4. A mold for the rapid installation of cable trays, as claimed in claim 2, wherein there are two first sliding blocks (5).
5. The mould for quickly installing the cable bridge according to claim 1, wherein the lifting frame (6) is provided with a limiting polished rod (18) which is arranged in parallel with the second rotating screw rod (7), the limiting polished rod (18) is provided with a limiting sleeve (19) which moves along the limiting polished rod (18), and the limiting sleeve (19) is fixed with the lifting support block (8).
CN202220124033.7U 2022-01-18 2022-01-18 Be used for quick installation mould of cable testing bridge Active CN217281856U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220124033.7U CN217281856U (en) 2022-01-18 2022-01-18 Be used for quick installation mould of cable testing bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220124033.7U CN217281856U (en) 2022-01-18 2022-01-18 Be used for quick installation mould of cable testing bridge

Publications (1)

Publication Number Publication Date
CN217281856U true CN217281856U (en) 2022-08-23

Family

ID=82897218

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220124033.7U Active CN217281856U (en) 2022-01-18 2022-01-18 Be used for quick installation mould of cable testing bridge

Country Status (1)

Country Link
CN (1) CN217281856U (en)

Similar Documents

Publication Publication Date Title
CN110027992B (en) Automatic jacking and positioning device and method for standard section of tower crane
CN111980391A (en) Integral hoisting platform and building method of building outer facade construction platform
CN115402909A (en) Super high-rise inclined double-layer special-shaped curtain wall construction device
CN217281856U (en) Be used for quick installation mould of cable testing bridge
CN110778126B (en) Construction method of building glass curtain wall
CN219569621U (en) Assistant installation equipment for assembled building wallboard
CN214935537U (en) Construction equipment for quickly installing roadbed side ditch cover plate
CN211444694U (en) Mobile hoisting device for target processing
CN113955636A (en) Hoisting equipment for assembly type building construction
CN211201081U (en) Auxiliary paving apparatus for building ceramic tile
CN209682522U (en) A kind of shield cement section of jurisdiction curved surface finisher
CN210048399U (en) Crane convenient to height-adjusting
CN214879767U (en) Article overhead hoist is used in room construction
CN218201889U (en) Hoisting structure
CN220685798U (en) Bridge movement hanging basket device for bridge construction
CN213174734U (en) Conveniently remove telescopic building installation gallows
CN219840343U (en) Concrete placement's operation rack
CN213597522U (en) Architectural decoration auxiliary supporting device for building construction
CN220927536U (en) Walking hanging basket for bridge construction
CN218029090U (en) Prefabricated cement roof erection equipment
CN216129301U (en) Electromechanical device elevating gear for interior decoration
CN214495518U (en) Tower crane for municipal house construction
CN220467270U (en) Balanced lifting device with high stability
CN217833991U (en) Keel back nailing device
CN109113412B (en) Automatic assembling and mounting method for multi-section cement electric pole

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant