CN217176701U - Geological engineering prevents and controls water installation - Google Patents

Geological engineering prevents and controls water installation Download PDF

Info

Publication number
CN217176701U
CN217176701U CN202220212968.0U CN202220212968U CN217176701U CN 217176701 U CN217176701 U CN 217176701U CN 202220212968 U CN202220212968 U CN 202220212968U CN 217176701 U CN217176701 U CN 217176701U
Authority
CN
China
Prior art keywords
water
suction
suction box
geological engineering
control device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220212968.0U
Other languages
Chinese (zh)
Inventor
王文龙
路清
程博志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Lineng Liyan Mining Co ltd
Original Assignee
Shandong Lineng Liyan Mining Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Lineng Liyan Mining Co ltd filed Critical Shandong Lineng Liyan Mining Co ltd
Priority to CN202220212968.0U priority Critical patent/CN217176701U/en
Application granted granted Critical
Publication of CN217176701U publication Critical patent/CN217176701U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/20Controlling water pollution; Waste water treatment

Landscapes

  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

The utility model relates to a geological engineering water control device, which comprises a water pump, a connecting water tank and a plurality of suction devices, wherein the connecting water tank is communicated with the water pump, each suction device comprises a fixing frame, a suction box vertically connected on the fixing frame in a sliding way and a lifting device for driving the suction box to lift, the suction box is communicated with the connecting water tank through a water pumping pipe, the lower end surface of the suction box is provided with a water inlet hole, the fixing frame is provided with a plurality of vertically arranged water level switches, the suction devices are placed everywhere, so that the water pump can suck everywhere, the water level switch is used for detecting the water level of the position of the suction device, the position of the suction box is adjusted through the lifting device, the suction box is kept at the position with a cleaner upper layer of the water level, the pipeline and the water pump are prevented from being blocked, when the water level of a certain suction device reaches the lower limit, the corresponding switch valve is closed, preventing air from being sucked in.

Description

Geological engineering prevents and controls water installation
Technical Field
The utility model relates to a prevention and cure water field specifically indicates a geological engineering prevents and cures water installation.
Background
In the geological engineering construction operation process, because the operation environment is severe, some inevitable safety accidents occur, and large-scale catastrophic accidents also occur sometimes, at present, underground water seepage cannot be well detected and early warned, and only can be prevented and treated through quick discharge.
The discharge of secret infiltration usually adopts the suction pump directly to take out, but because trickling through ground when secret infiltration outflows, rivers trickle area is big, and the degree of depth is little, and the water depth can't cover the suction pump, and the quick discharge of infiltration is hardly realized to current suction pump, because the infiltration bottom is very muddy, often leads to the water pump import to block up when placing the water pump at the bottom simultaneously.
Disclosure of Invention
The utility model discloses to prior art's not enough, provide an efficient geological engineering prevention and cure water installation of drainage.
The utility model discloses a through following technical scheme realizes, provides a geological engineering prevents and treats water installation, including water pump, connection water tank and a plurality of suction device, connect water tank and water pump intercommunication, suction device includes that mount, vertical sliding joint take out the elevating gear that box and drive take out and inhale the box lift on the mount, take out and inhale the box and pass through the drinking-water pipe and be connected the water tank intercommunication, the terminal surface is opened under the suction box has the inlet opening, a plurality of vertical water level switches of arranging are equipped with on the mount.
Suction device in this scheme places everywhere to suck everywhere through the water pump, water level switch is used for detecting the water level of suction device place position, thereby adjusts the position of suction box through elevating gear, makes the suction box keep in the comparatively clean position of water level upper strata, thereby prevents to suck the muddy water of bottom, prevents to block up pipeline and water pump.
Preferably, the water pumping pipe is provided with a switch valve. The switch valve that sets up in this scheme, when certain suction device place water level reached the lower limit, corresponding switch valve closed, prevents to inhale the air.
Preferably, a safety valve is arranged at the top of the connecting water tank. The relief valve that sets up in this scheme plays pressure protection effect, prevents that the water pump from damaging.
Preferably, the lower end of the suction box is provided with a filter screen. The filter screen that sets up in this scheme plays the filtering action.
Preferably, the lifting device comprises a ball screw mounted on the fixed frame and a lifting motor for driving the ball screw, and a nut of the ball screw is connected with the suction box. The lifting motor in this scheme drives the nut of ball to go up and down to drive the suction box to go up and down.
As optimization, the upper end of the fixing frame is fixedly connected with a guide sleeve sleeved on the water pumping pipe. The uide bushing in this scheme plays the guide effect to the drinking-water pipe of mount upper end position.
Preferably, the water pump is communicated with the bottom of the connecting water tank. The water pump communicates with the bottom of connecting the water tank in this scheme to be convenient for take out the deposit water in connecting the water tank.
The utility model has the advantages that: the utility model discloses a geological engineering prevents and controls water installation is through placing a plurality of suction device everywhere to through the water pump to suction everywhere, water level switch is used for detecting the water level of suction device position, adjusts the position of suction box through elevating gear, makes the suction box keep in the comparatively clean position of water level upper strata, prevents to block up pipeline and water pump, and when certain suction device place water level reachd the lower limit, corresponding ooff valve closed, prevents the induction air.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a front view of the suction device of the present invention;
FIG. 3 is a bottom view of the suction box of the present invention;
FIG. 4 is a front view of the suction box of the present invention;
shown in the figure:
1. the device comprises a suction device, 2, a water pump, 3, a connecting water tank, 4, a safety valve, 5, a water pumping pipe, 6, a switch valve, 11, a fixing frame, 12, a suction box, 13, a guide sleeve, 14, a sliding rail, 15, a water level switch, 16, a ball screw, 17, a lifting motor, 18, a filter screen, 19 and a water inlet hole.
Detailed Description
In order to clearly illustrate the technical features of the present solution, the present solution is explained below by way of specific embodiments.
As shown in fig. 1-4, the utility model discloses a geological engineering water control device, including water pump 2, connection water tank 3 and a plurality of suction device 1, connect water tank 3 and water pump 2 intercommunication, this embodiment normal water pump 2 and the bottom intercommunication of connecting water tank 3.
The connecting water tank 3 is a closed metal box, the safety valve 4 is installed at the top of the connecting water tank 3, and when the vacuum degree in the connecting water tank 3 reaches a certain degree, the safety valve 4 is opened to prevent the water pump 2 from being damaged due to the overlarge vacuum degree.
The number of the suction devices 1 in this embodiment is 4, and the suction operation can be simultaneously performed on 4 places.
The suction device 1 comprises a fixed frame 11, a suction box 12 vertically connected to the fixed frame 11 in a sliding mode and a lifting device for driving the suction box 12 to lift, the fixed frame 11 comprises a bottom plate and a vertical plate fixedly connected to the bottom plate, the bottom plate is a steel plate, the weight is as large as possible, the fixed frame 11 is prevented from being washed down by water, and the suction box 12 is connected to the vertical plate in a sliding mode.
The suction box 12 is communicated with the connecting water tank 3 through a water pumping pipe 5 and is communicated with the side face of the connecting water tank 3, the switching valve 6 is installed on the water pumping pipe 5, and the safety valve is an electric control valve and can be switched on and off.
The lifting device comprises a ball screw 16 installed on the fixed frame 11 and a lifting motor 17 driving the ball screw 16, a nut of the ball screw 16 is connected with the suction box 12, the fixed frame 11 is fixedly connected with a vertical sliding rail, and a sliding block is installed on the back of the suction box 12.
The upper end of the fixing frame 11 is fixedly connected with a guide sleeve 13 sleeved on the water pumping pipe 5, and when the water pumping pipe 5 goes up and down along with the pumping box 12, the guide sleeve 13 plays a role in guiding the water pumping pipe 5.
The lower end surface of the suction box 12 is provided with water inlet holes 19, and the water inlet holes 19 are densely distributed round holes.
The fixed frame 11 is provided with a plurality of vertically arranged water level switches 15 for detecting water levels.
The lower end of the suction box 12 is provided with a filter screen 18, and the filter screen 18 is detachably connected.
Of course, the above description is not limited to the above examples, and technical features of the present invention that are not described in the present application may be implemented by or using the prior art, and are not described herein again; the above embodiments and drawings are only used for illustrating the technical solutions of the present invention and are not intended to limit the present invention, and the present invention has been described in detail with reference to the preferred embodiments, and those skilled in the art should understand that changes, modifications, additions or substitutions made by those skilled in the art within the spirit of the present invention should also belong to the protection scope of the claims of the present invention.

Claims (7)

1. A geological engineering water control device is characterized in that: including water pump (2), connection water tank (3) and a plurality of suction device (1), connect water tank (3) and water pump (2) intercommunication, suction device (1) is including mount (11), vertical sliding joint suction box (12) on mount (11) and the elevating gear that drive suction box (12) go up and down, suction box (12) are through drinking-water pipe (5) and connection water tank (3) intercommunication, and the terminal surface is opened under suction box (12) has inlet opening (19), a plurality of vertical water level switch (15) of arranging are equipped with on mount (11).
2. A geological engineering water control device according to claim 1, characterized in that: and the water pumping pipe (5) is provided with a switch valve (6).
3. A geological engineering water control device according to claim 1, characterized in that: and a safety valve (4) is arranged at the top of the connecting water tank (3).
4. A geological engineering water control device according to claim 1, characterized in that: the lower end of the suction box (12) is provided with a filter screen (18).
5. A geological engineering water control device according to claim 1, characterized in that: the lifting device comprises a ball screw (16) arranged on the fixed frame (11) and a lifting motor (17) driving the ball screw (16), and a nut of the ball screw (16) is connected with the suction box (12).
6. A geological engineering water control device according to claim 1, characterized in that: the upper end of the fixing frame (11) is fixedly connected with a guide sleeve (13) sleeved on the water pumping pipe (5).
7. A geological engineering water control device according to claim 1, characterized in that: the water pump (2) is communicated with the bottom of the connecting water tank (3).
CN202220212968.0U 2022-01-26 2022-01-26 Geological engineering prevents and controls water installation Active CN217176701U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220212968.0U CN217176701U (en) 2022-01-26 2022-01-26 Geological engineering prevents and controls water installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220212968.0U CN217176701U (en) 2022-01-26 2022-01-26 Geological engineering prevents and controls water installation

Publications (1)

Publication Number Publication Date
CN217176701U true CN217176701U (en) 2022-08-12

Family

ID=82738235

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220212968.0U Active CN217176701U (en) 2022-01-26 2022-01-26 Geological engineering prevents and controls water installation

Country Status (1)

Country Link
CN (1) CN217176701U (en)

Similar Documents

Publication Publication Date Title
JP4503467B2 (en) Sanding system
CN217176701U (en) Geological engineering prevents and controls water installation
CN1975073A (en) Water stage lifting device
CN201263905Y (en) Laminar current type suction dredger
CN204619462U (en) Filter tank water inlet automaton
CN208152233U (en) A kind of horizontal underground sewage disposal system Boosting pumping station
CN217103231U (en) Sewage treatment equipment using pipeline to replace impeller and not generating excessive sludge
CN216664438U (en) Integrated intelligent lifting pump station
CN213141767U (en) Multifunctional bottom sediment elution disturbance device
CN200982087Y (en) Waterborne stage lifting device
CN210621730U (en) Precipitation well structure and automatic precipitation water level monitoring device of foundation pit
CN211113693U (en) Hydraulic engineering construction is with preventing blockking up drainage device
CN211597013U (en) Integrated intelligent intercepting well
CN219080558U (en) Intelligent intercepting well for sewage disposal and diversion
CN208073384U (en) A kind of Multifunctional spray device for accelerating drilling mud pond evaporation rate
CN111792805A (en) Multifunctional bottom sediment elution disturbance device
CN221319482U (en) Multistage processing apparatus is restoreed to groundwater
CN113417356B (en) Vertical submersible electric pump mounting structure combining self-drainage and bidirectional pumping drainage
CN219906777U (en) Self-made rail-type electric hoisting device
CN216170179U (en) Sludge discharge system of sedimentation tank
CN219231535U (en) Quick drainage's whirl sedimentation tank structure
CN219299370U (en) Underground movable drainage device for coal mine
CN218709258U (en) Sewage treatment device for automatic backflow of overproof sewage
CN220887067U (en) Be applied to automatic sewage system of effluent water sump
CN216195352U (en) Novel integrated pump station

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant