CN216641110U - Double-deck furred ceiling construction equipment of clean factory building - Google Patents

Double-deck furred ceiling construction equipment of clean factory building Download PDF

Info

Publication number
CN216641110U
CN216641110U CN202122916899.XU CN202122916899U CN216641110U CN 216641110 U CN216641110 U CN 216641110U CN 202122916899 U CN202122916899 U CN 202122916899U CN 216641110 U CN216641110 U CN 216641110U
Authority
CN
China
Prior art keywords
double
shaped steel
limiting plate
shaped clamping
ceiling construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122916899.XU
Other languages
Chinese (zh)
Inventor
赵全
郭卫平
邓辉
黄栋博
杨南疆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Scegc Equipment Installation Group Co ltd
Original Assignee
Scegc Equipment Installation Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Scegc Equipment Installation Group Co ltd filed Critical Scegc Equipment Installation Group Co ltd
Priority to CN202122916899.XU priority Critical patent/CN216641110U/en
Application granted granted Critical
Publication of CN216641110U publication Critical patent/CN216641110U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a double-layer suspended ceiling construction device for a clean workshop, which comprises a long bolt, wherein two opposite L-shaped clamping plates are arranged at the top of the long bolt, a limiting plate is arranged at one end of each L-shaped clamping plate, a through groove for the L-shaped clamping plates to insert and slide is formed in the surface of the limiting plate, an end groove is further formed in the end surface of one end of each L-shaped clamping plate, a stud is further fixed inside each end groove, a nut is sleeved on the surface of each stud and abuts against the outer surface of the limiting plate, two C-shaped steels are further arranged inside each L-shaped clamping plate, and the bottoms of the two C-shaped steels respectively abut against the inner side surface of the limiting plate and the inner wall of the other end of each L-shaped clamping plate; the L type cardboard and the limiting plate of design have replaced current U type cardboard, not only can guarantee installation stability, and the regulation that can also make the looks adaptation according to the width of C shaped steel is fixed, has perfected a great deal of not enough in the current structure integral type structure, and it is more convenient that the whole is adjusted simultaneously, easily operation.

Description

Double-deck furred ceiling construction equipment of clean factory building
Technical Field
The utility model belongs to the technical field of ceiling construction, and particularly relates to a double-layer ceiling construction device for a clean workshop.
Background
According to the requirements of an electromechanical engineering clean room of the existing electronic factory building, the double-layer ceiling construction method is adopted, a bearing stable structure is reinforced, the space is reasonably utilized, perfect space management is created, an upper support and a lower support are hung, large air pipes, process pipelines and bearing bridges are reasonably arranged, and the space of the plenum box is ensured to be enough for personnel to walk and overhaul.
Current furred ceiling construction structures need carry out spacing support through U type cardboard in the fixing to C shaped steel, but the inboard length of current U type cardboard is fixed, in case the width of C shaped steel is not matched with the inboard length of U type cardboard, cause the not hard up phenomenon of installation easily, influence the holistic fastness in later stage, and in the installation of counterpointing of C shaped steel, not only need align the screw, and because C shaped steel length is longer, still need guarantee in the installation that the level of C shaped steel could construction bolt, the bulk operation is very difficult.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a double-layer suspended ceiling construction device for a clean workshop, which aims to solve the problems in the background technology.
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides a double-deck furred ceiling construction equipment of clean factory building, includes the stay bolt, the top of stay bolt is provided with two relative L type cardboards, the one end of L type cardboard is provided with the limiting plate, the surface of limiting plate is seted up and is supplied L type cardboard to insert and gliding logical groove, the end groove has still been seted up on the one end terminal surface of L type cardboard, the inside of end groove still is fixed with the double-screw bolt, the surperficial cover of double-screw bolt is equipped with the nut, this nut with the surface of limiting plate offsets, the inside of L type cardboard still is provided with two C shaped steel, two the bottom of C shaped steel offsets with the other end inner wall of limiting plate medial surface and L type cardboard respectively.
Preferably, the surface of the L-shaped clamping plate is further provided with a sliding groove, the sliding groove is in through connection with the long bolt, the surface of the long bolt is provided with a plurality of limiting nuts, and the limiting nuts abut against the L-shaped clamping plate.
Preferably, one of them C shaped steel side is fixed with the counterpoint board, and the hole that supplies the counterpoint board to run through is seted up to the side of another C shaped steel, the one end of counterpoint board runs through to the inside of another C shaped steel, and the one end of counterpoint board is formed with and is used for stopping spacing arch with the hole.
Preferably, the aligning plate is located at the middle of the C-shaped steel, and the long bolts are located at both end positions of the C-shaped steel.
Preferably, the bottom of the long bolt is further sleeved with a cross joint, keels are fixed to the periphery of the cross joint through bolts, and steel plates are installed on the inner sides of the keels.
Preferably, a main supporting plate is further mounted on the top end face of the keel, and the longitudinal section of the end of the main supporting plate is of an L-shaped structure.
Compared with the prior art, the utility model has the beneficial effects that:
1. the designed L-shaped clamping plate and the limiting plate replace the existing U-shaped clamping plate, so that the installation stability can be ensured, the adaptive adjustment and fixation can be performed according to the width of the C-shaped steel, the defects in the existing structure integrated structure are overcome, and meanwhile, the overall adjustment is more convenient and easy to operate;
2. through the designed aligning plate, the C-shaped steel can be quickly aligned and connected in use, the time consumed by aligning screw holes in the later period is greatly reduced, meanwhile, the two C-shaped steels can be preliminarily connected, and the later-period installation difficulty is further reduced;
3. by the design of the utility model, the comprehensive management of spatial layout can be realized, the number of top plate holes is reduced, the construction safety, the construction rapidity and the process rationality are reduced, and the structural stability of the static pressure box hanging system is ensured.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the connection between the U-shaped snap-gauge and the limiting plate of the utility model;
FIG. 3 is a sectional view showing the connection of C-shaped steel according to the present invention;
FIG. 4 is a schematic view showing the installation state of the steel sheet of the present invention.
In the figure: 1. c-shaped steel; 2. an L-shaped clamping plate; 3. a long bolt; 4. a cross joint; 5. a keel; 6. a chute; 7. a limiting plate; 8. a through groove; 9. an end slot; 10. a stud; 11. a limiting bulge; 12. a positioning plate; 13. a steel plate; 14. the main supporting plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1 to 4, the present invention provides a technical solution: a double-layer suspended ceiling construction device for a clean workshop comprises a long bolt 3, wherein two opposite L-shaped clamping plates 2 are arranged at the top of the long bolt 3, a limiting plate 7 is arranged at one end of each L-shaped clamping plate 2, a through groove 8 for the L-shaped clamping plates 2 to insert and slide is formed in the surface of the limiting plate 7, an end groove 9 is further formed in the end face of one end of each L-shaped clamping plate 2, a stud 10 is further fixed inside the end groove 9, a nut is sleeved on the surface of the stud 10, the L-shaped clamping plates 2 and the limiting plate 7 are designed to replace the existing U-shaped clamping plates, the stability of installation can be guaranteed, adaptive adjustment and fixation can be performed according to the width of C-shaped steel 1, various defects in the existing structure integrated structure are overcome, meanwhile, the overall adjustment is more convenient, the operation is easy, the nut is abutted against the outer surfaces of the limiting plates 7, two C-shaped steel 1 are further arranged inside the L-shaped clamping plates 2, the bottoms of the two C-shaped steel 1 are respectively abutted against the inner side surface of the limiting plate 7 and the inner wall of the other end of the L-shaped clamping plate 2.
In this embodiment, preferably, the sliding groove 6 has been still seted up on the surface of L type cardboard 2, makes things convenient for the stay bolt 3 to be able to together displace in the later stage, and sliding groove 6 and stay bolt 3 through connection, the surface of stay bolt 3 are provided with a plurality of stop nut, and this stop nut offsets with L type cardboard 2.
In this embodiment, it is preferred, one of them C shaped steel 1 side is fixed with counterpoint board 12, the hole that supplies counterpoint board 12 to run through is seted up to another C shaped steel 1's side, counterpoint board 12 through the design, can in use, the quick counterpoint with C shaped steel 1 is connected, the time that the screw was spent is aligned in the reduction later stage that increases, can also carry out preliminary connection with two C shaped steel simultaneously, further reduce the later stage installation degree of difficulty, the one end of counterpoint board 12 runs through to another C shaped steel 1's inside, and the one end of counterpoint board 12 is formed with and is used for stopping with the spacing protruding 11 in hole.
In the embodiment, preferably, the alignment plate 12 is located in the middle of the C-shaped steel 1, and the long bolts 3 are located at two ends of the C-shaped steel 1, so as to avoid a series of problems such as jamming caused by contact between the alignment plate 12 and the long bolts 3.
In this embodiment, preferably, the bottom of the long bolt 3 is further sleeved with a cross joint 4 for installation and connection, keels 5 are fixed around the cross joint 4 through bolts, and steel plates 13 are installed on the inner sides of the keels 5.
In this embodiment, preferably, a main supporting plate 14 is further installed on the top end face of the keel 5 to improve the supporting capability, and the longitudinal section of the end of the main supporting plate 14 is in an "L" shaped structure.
The working principle and the using process of the utility model are as follows: when the utility model is used, the long bolt 3 penetrates through the sliding groove 6 and is fixed with one L-shaped clamping plate 2, before that, a limiting nut is screwed into the surface of the long bolt 3 to limit the L-shaped clamping plate 2, when the L-shaped clamping plate 2 at the bottom position is placed, the two C-shaped steels 1 are clamped into the inner side of the L-shaped clamping plate 2, in the clamping process, the aligning plate 12 on one C-shaped steel 1 penetrates through the other C-shaped steel 1 to complete the aligning installation of the two C-shaped steels 1, the two C-shaped steels 1 are fixedly connected through the bolt, then the through groove 8 on the limiting plate 7 is sleeved from the end part of the L-shaped clamping plate 2, then the external nut is screwed on the stud 10, the limiting plate 7 is moved towards the other end of the L-shaped clamping plate 2 by rotating the stud 10, and the L-shaped clamping plate 2 and the limiting plate 7 clamp the long bolt 3 tightly and limit, when the long bolt 3 produced the displacement, the equidirectional displacement was done in the inside of spout 6 to long bolt 3, accomplishes the installation back of bottom L type cardboard 2, and the same mode of rethread is established the L type cardboard 2 cover at the top at C shaped steel 1 to accomplish spacing fixed, lay steel sheet 13 on fossil fragments 5 at last again can.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a double-deck furred ceiling construction equipment of clean factory building, includes stay bolt (3), the top of stay bolt (3) is provided with two relative L type cardboard (2), its characterized in that: the one end of L type cardboard (2) is provided with limiting plate (7), confession L type cardboard (2) are seted up on the surface of limiting plate (7) and are inserted and gliding logical groove (8), end groove (9) have still been seted up on the one end terminal surface of L type cardboard (2), the inside of end groove (9) still is fixed with double-screw bolt (10), the surface cover of double-screw bolt (10) is equipped with the nut, this nut with the surface of limiting plate (7) offsets, the inside of L type cardboard (2) still is provided with two C shaped steel (1), two the bottom of C shaped steel (1) offsets with the other end inner wall of limiting plate (7) medial surface and L type cardboard (2) respectively.
2. The double-layer ceiling construction device for the clean factory building according to claim 1, wherein: the surface of the L-shaped clamping plate (2) is further provided with a sliding groove (6), the sliding groove (6) is in through connection with the long bolt (3), the surface of the long bolt (3) is provided with a plurality of limiting nuts, and the limiting nuts are abutted to the L-shaped clamping plate (2).
3. The double-layer ceiling construction device for the clean factory building according to claim 1, wherein: one of them C shaped steel (1) side is fixed with counterpoint board (12), and the hole that supplies counterpoint board (12) to run through is seted up to the side of another C shaped steel (1), the one end of counterpoint board (12) runs through to the inside of another C shaped steel (1), and the one end of counterpoint board (12) is formed with and is used for stopping spacing protruding (11) with the hole.
4. The double-layer ceiling construction device for the clean factory building according to claim 3, wherein: the aligning plate (12) is arranged in the middle of the C-shaped steel (1), and the long bolts (3) are arranged at two end positions of the C-shaped steel (1).
5. The double-layer ceiling construction device for the clean factory building according to claim 1, wherein: the bottom of stay bolt (3) still overlaps and is equipped with cross joint (4), there are fossil fragments (5) all around of cross joint (4) through the bolt fastening, steel sheet (13) are installed to the inboard of fossil fragments (5).
6. The double-layer ceiling construction device for the clean factory building according to claim 5, wherein: still install main tributary fagging (14) on the top surface of fossil fragments (5), the tip longitudinal section of main tributary fagging (14) is "L" type structure.
CN202122916899.XU 2021-11-25 2021-11-25 Double-deck furred ceiling construction equipment of clean factory building Active CN216641110U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122916899.XU CN216641110U (en) 2021-11-25 2021-11-25 Double-deck furred ceiling construction equipment of clean factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122916899.XU CN216641110U (en) 2021-11-25 2021-11-25 Double-deck furred ceiling construction equipment of clean factory building

Publications (1)

Publication Number Publication Date
CN216641110U true CN216641110U (en) 2022-05-31

Family

ID=81737037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122916899.XU Active CN216641110U (en) 2021-11-25 2021-11-25 Double-deck furred ceiling construction equipment of clean factory building

Country Status (1)

Country Link
CN (1) CN216641110U (en)

Similar Documents

Publication Publication Date Title
CN208904578U (en) A kind of buckle-type slot type straight-through cable gantry
CN216641110U (en) Double-deck furred ceiling construction equipment of clean factory building
CN103669663A (en) Back-bolt type dry-hang curtain wall system
CN208268548U (en) A kind of urban Underground pipeline pipe gallery piping lane suspension and support
CN206800733U (en) A kind of energy-saving replaceable units curtain wall system
CN208226933U (en) The special fixture of colored steel roof and photovoltaic bracket connection
CN105014577A (en) Amusement equipment rail splicing and alignment fixture and method
CN211720002U (en) Cubical switchboard is assembled and is used fixing device convenient to adjust
CN204805318U (en) Can realize quick assembly disassembly's roller device
CN209369140U (en) A kind of curtain skeleton
CN218440979U (en) Adjustable assembled integrated support
CN105680784A (en) Double-glass solar photovoltaic plate reinforcing structure and method
CN109112975B (en) Fish-bellied steel box girder assembling auxiliary device and fish-bellied steel box girder assembling method
CN206164449U (en) Adjustable couple of photovoltaic support
CN214367068U (en) Novel asbestos board
CN221030938U (en) Furred ceiling fossil fragments docking mechanism
CN214144288U (en) Interlayer unit curtain wall structure
CN218468399U (en) Novel pipeline location for water conservancy construction device
CN220354219U (en) Aluminum alloy track connecting system
CN218348898U (en) Combined positioning device for modular absorption heat pump
CN219548144U (en) Building assembled wallboard
CN218205636U (en) Spider man node support
CN214194954U (en) Connecting structure for H-shaped steel
CN218118841U (en) T-shaped connecting piece