CN216564415U - Cable support for power engineering - Google Patents

Cable support for power engineering Download PDF

Info

Publication number
CN216564415U
CN216564415U CN202122565988.4U CN202122565988U CN216564415U CN 216564415 U CN216564415 U CN 216564415U CN 202122565988 U CN202122565988 U CN 202122565988U CN 216564415 U CN216564415 U CN 216564415U
Authority
CN
China
Prior art keywords
support
power engineering
sets
adjusting
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122565988.4U
Other languages
Chinese (zh)
Inventor
蒲伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Xinghe Technology Co ltd
Original Assignee
Foshan Xinghe Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Xinghe Technology Co ltd filed Critical Foshan Xinghe Technology Co ltd
Priority to CN202122565988.4U priority Critical patent/CN216564415U/en
Application granted granted Critical
Publication of CN216564415U publication Critical patent/CN216564415U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Clamps And Clips (AREA)

Abstract

The utility model relates to the technical field of electric power engineering and discloses a cable support for electric power engineering, which comprises a base support, wherein two groups of symmetrical limiting slide rods are arranged on the base support, two ends of each limiting slide rod are sleeved with a damping spring and a connecting block, one end of each damping spring is fixed to one side of each connecting block, two groups of connecting blocks are rotatably connected with buffer rods, and a connecting shaft is arranged between the two groups of buffer rods. This a cable support for electric power engineering, install the screw rod through on the left regulation support, screw rod and left alignment jig spiro union, be convenient for rotate the rocker, make with first bevel gear meshed second bevel gear rotate, it rotates to drive the screw rod, the position of adjustment auxiliary stand, the mounted position of adjustment cable, install two sets of stabilization posts through the base bottom, be convenient for improve the overall stability of support, the mounted position of inconvenient according to the cable has been solved and has been adjusted, and the relatively poor problem of stability.

Description

Cable support for power engineering
Technical Field
The utility model relates to the technical field of electric power engineering, in particular to a cable support for electric power engineering.
Background
The cable is laid in cable pit and tunnel, and it is fixed that generally use the support more, and the support commonly used has angle iron bracket and assembled support, and current cable support is mostly angle iron bracket, and its simple structure, when using, inconvenient mounted position to the cable adjusts, and install in the cable pit after, if run into extreme weather and produce and rock, cause wearing and tearing easily, and stability is relatively poor, consequently remains to develop a cable support who is used for electric power engineering.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Aiming at the defects of the prior art, the utility model provides a cable bracket for power engineering, which solves the problems that the adjustment is inconvenient according to the installation position of a cable and the stability is poor.
(II) technical scheme
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides a cable support for electric power engineering, includes the collet, install the spacing slide bar of two sets of symmetries on the collet, spacing slide bar both ends are all overlapped and are equipped with bradyseism spring and linking piece, bradyseism spring one end is fixed with linking piece one side, and is two sets of all rotate on linking piece and be connected with the buffer beam, and is two sets of install the connecting axle between the buffer beam, the base is installed on the buffer beam top.
Preferably, be fixed with two sets of columns of stabilizing on the collet, the column of stabilizing is including spacing support, stabilizing spring and support column, and the support column slides in spacing support, and stabilizing spring installs between support column bottom and spacing support inner wall, and the support column top is installed in the base bottom.
Preferably, a set of adjusting bracket is all installed to the base both sides, all installs the alignment jig in two sets of adjusting brackets, installs the auxiliary stand between two sets of alignment jigs.
Preferably, a limiting column is arranged inside the adjusting bracket on the right side and penetrates through the surface of the adjusting bracket on the right side.
Preferably, the left adjusting support is provided with a screw rod, a rocker and a support frame, a second bevel gear is fixed at the bottom end of the screw rod, a first bevel gear is meshed with the outer side of the second bevel gear, and one end of the rocker penetrates through the left adjusting support and the support frame respectively and is fixed with the middle of the first bevel gear.
Preferably, inserting columns are fixed at the bottoms of the two groups of adjusting brackets, the adjusting brackets are inserted into the base, and the two groups of adjusting brackets are respectively provided with a clamping groove and a clamping block which are matched with each other.
(III) advantageous effects
Compared with the prior art, the utility model provides a cable bracket for power engineering, which has the following beneficial effects:
1. this a cable support for electric power engineering, install the screw rod through on the left regulation support, the screw rod is convenient for rotate the rocker with left alignment jig spiro union, make with the second bevel gear rotation of first bevel gear meshing, it rotates to drive the screw rod, the position of adjustment auxiliary stand, the mounted position of adjustment cable, install two sets of stabilization posts through the base bottom, be convenient for improve the overall stability of support, the inconvenient mounted position according to the cable of having solved adjusts, and the relatively poor problem of stability.
2. This a cable support for electric power engineering installs the spacing slide bar of two sets of symmetries on through the collet, and spacing slide bar both ends are all overlapped and are equipped with bradyseism spring and linking piece, all rotate on two sets of linking pieces to be connected with the buffer beam, and the base is installed on the buffer beam top, is convenient for take place to rock at the auxiliary stand, makes the pressure transmission that receives and extrudees the buffer beam, and on the bradyseism spring of dispersion bottom to play stabilizing effect.
3. This a cable support for electric power engineering all is fixed with the post of inserting through two sets of regulation support bottoms, adjusts the support and pegs graft with the base, is provided with the draw-in groove and the fixture block that match respectively on two sets of alignment brackets, is convenient for install the auxiliary stand back between two sets of alignment brackets to make fixture block and draw-in groove joint on the alignment bracket, peg graft the regulation support of well assembling on the base again, conveniently install the auxiliary stand.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of an adjusting bracket according to the present invention;
FIG. 3 is a schematic structural diagram of the present invention.
In the figure: 1. a bottom support; 2. a limiting slide bar; 3. a cushioning spring; 4. a joining block; 5. a buffer rod; 6. a connecting shaft; 7. a stabilization post; 8. a base; 9. adjusting the bracket; 10. a limiting column; 11. a rocker; 12. a first bevel gear; 13. a second bevel gear; 14. a screw; 15. an adjusting bracket; 16. an auxiliary support; 17. a support frame.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: the utility model provides a cable support for electric power engineering, including collet 1, install the spacing slide bar 2 of two sets of symmetries on collet 1, 2 both ends of spacing slide bar all overlap and are equipped with bradyseism spring 3 and linking piece 4, 3 one ends of bradyseism spring are fixed with linking piece 4 one side, it is connected with buffer beam 5 all to rotate on 4 to link up two sets of blocks, install connecting axle 6 between two sets of buffer beam 5, base 8 is installed on 5 tops of buffer beam, the pressure extrusion buffer beam 5 that receives at auxiliary stand 16, and disperse on the bradyseism spring 3 of bottom, thereby play the stabilizing action.
Specifically, for the convenience of the overall stability of guarantee support, be fixed with two sets of stabilization posts 7 on collet 1, stabilization posts 7 include spacing support, stabilizing spring and support column, and the support column slides in spacing support, and stabilizing spring installs between support column bottom and spacing support inner wall, and the support column top is installed in base 8 bottom, and pressure on the base 8 is through spacing the stabilizing spring dispersion between support and the support column, the overall stability of guarantee support.
Specifically, for the convenience of installing auxiliary stand 16, a set of adjusting bracket 9 is all installed to 8 both sides of base, all installs alignment jig 15 in two sets of adjusting bracket 9, installs auxiliary stand 16 between two sets of alignment jig 15, conveniently installs auxiliary stand 16 on alignment jig 15 to the position of cable on the adjustment auxiliary stand 16.
Specifically, in order to limit the position of the auxiliary bracket 16, a limiting column 10 is arranged inside the right-side adjusting bracket 9, the limiting column 10 penetrates through the surface of the right-side adjusting bracket 15, and when the position of the adjusting bracket 9 is adjusted, the moving position of the adjusting bracket 9 is limited by the limiting column 10.
Specifically, in order to adjust the position of the auxiliary support 16, a screw 14, a rocker 11 and a support frame 17 are installed on the left-side adjusting support 9, a second bevel gear 13 is fixed at the bottom end of the screw 14, a first bevel gear 12 is engaged with the outer side of the second bevel gear 13, one end of the rocker 11 penetrates through the left-side adjusting support 9 and the support frame 17 respectively and is fixed to the middle of the first bevel gear 12, the rocker 11 is rotated to drive the first bevel gear 12 to rotate, so that the engaged second bevel gear 13 rotates to drive the screw 14 to rotate, and the left-side adjusting support 15 screwed with the screw 14 is lifted or lowered.
Specifically, in order to install the auxiliary support 16, the bottom of each of the two sets of adjusting supports 9 is fixed with an inserting column, the adjusting supports 9 are inserted into the base 8, the two sets of adjusting supports 15 are respectively provided with a matched clamping groove and a matched clamping block, the auxiliary support 16 is placed between the two sets of adjusting supports 15, the clamping blocks on the adjusting supports 15 are clamped with the clamping grooves, and the assembled adjusting supports 9 are inserted into the base 8.
The working principle is as follows: place auxiliary stand 16 between two sets of alignment brackets 15, and make fixture block and draw-in groove joint on two sets of alignment brackets 15, peg graft the adjusting bracket 9 of assembling on base 8 again, and rotate rocking bar 11, it rotates to drive first bevel gear 12, make meshed second bevel gear 13 drive screw rod 14 and rotate, and then make 16 lifting of auxiliary stand or descend, when the cable rocks, pressure extrusion buffer beam 5, and disperse to on the bradyseism spring 3 of bottom, cooperate two sets of stabilization posts 7, the overall stability of guarantee support, and avoid the cable to rock the range too big bending that leads to of range.
In conclusion, according to the cable support for electric power engineering, the screw 14 is installed on the left adjusting support 9, the screw 14 is in threaded connection with the left adjusting support 15, the rocker 11 is convenient to rotate, the second bevel gear 13 meshed with the first bevel gear 12 is rotated to drive the screw 14 to rotate, the position of the auxiliary support 16 is adjusted, the installation position of the cable is adjusted, two groups of stabilizing columns are installed at the bottom of the base 8, the overall stability of the support is convenient to improve, the problem that the adjustment is inconvenient to carry out according to the installation position of the cable and the stability is poor is solved, two groups of symmetrical limiting slide rods 2 are installed on the base support 1, the cushioning springs 3 and the connecting blocks 4 are sleeved at the two ends of the limiting slide rods 2, the buffer rods 5 are rotatably connected on the two groups of connecting blocks 4, the base 8 is installed at the top ends of the buffer rods 5, so that when the auxiliary support 16 shakes, the received pressure is transmitted and extrudes the buffer rods 5, and disperse on the bradyseism spring 3 of bottom to play the stabilizing effect, all be fixed with the post of inserting through two sets of regulation support 9 bottoms, adjust support 9 and base 8 and peg graft, be provided with the draw-in groove and the fixture block that match on two sets of regulation framves 15 respectively, be convenient for install back between two sets of regulation framves 15 with auxiliary stand 16, and make the fixture block and the draw-in groove joint on the regulation frame 15, peg graft on base 8 with the regulation support 9 of assembling again, conveniently install auxiliary stand 16.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a cable support for electric power engineering, includes collet (1), install spacing slide bar (2) of two sets of symmetries on collet (1), its characterized in that: spacing slide bar (2) both ends all are equipped with bradyseism spring (3) and link up piece (4), bradyseism spring (3) one end is fixed with link up piece (4) one side, and is two sets of link up and all rotate on piece (4) and be connected with buffer beam (5), and is two sets of install connecting axle (6) between buffer beam (5), base (8) are installed on buffer beam (5) top.
2. A cable holder for power engineering according to claim 1, characterized in that: be fixed with two sets of columns of stabilizing (7) on collet (1), stabilize column (7) including spacing support, stabilizing spring and support column, the support column slides in spacing support, and stabilizing spring installs between support column bottom and spacing support inner wall, and the support column top is installed in base (8) bottom.
3. A cable holder for power engineering according to claim 1, characterized in that: a set of adjusting support (9) is all installed to base (8) both sides, all installs in two sets of adjusting support (9) alignment jig (15), installs between two sets of alignment jig (15) auxiliary stand (16).
4. A cable holder for power engineering according to claim 3, characterized in that: and a limiting column (10) is arranged inside the adjusting bracket (9) on the right side, and the limiting column (10) penetrates through the surface of the adjusting bracket (15) on the right side.
5. A cable holder for power engineering according to claim 3, characterized in that: the left side is installed screw rod (14), rocker (11) and support frame (17) on adjusting support (9), and screw rod (14) bottom mounting has second bevel gear (13), and second bevel gear (13) outside meshing has first bevel gear (12), and left adjusting support (9) and support frame (17) are passed respectively to rocker (11) one end and are fixed with first bevel gear (12) middle part.
6. A cable holder for power engineering according to claim 3, characterized in that: inserting columns are fixed at the bottoms of the two groups of adjusting brackets (9), the adjusting brackets (9) are inserted into the base (8), and the two groups of adjusting brackets (15) are respectively provided with matched clamping grooves and clamping blocks.
CN202122565988.4U 2021-10-25 2021-10-25 Cable support for power engineering Active CN216564415U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122565988.4U CN216564415U (en) 2021-10-25 2021-10-25 Cable support for power engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122565988.4U CN216564415U (en) 2021-10-25 2021-10-25 Cable support for power engineering

Publications (1)

Publication Number Publication Date
CN216564415U true CN216564415U (en) 2022-05-17

Family

ID=81567650

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122565988.4U Active CN216564415U (en) 2021-10-25 2021-10-25 Cable support for power engineering

Country Status (1)

Country Link
CN (1) CN216564415U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116914643A (en) * 2023-09-08 2023-10-20 国网山东省电力公司烟台供电公司 Wind power submarine cable laying system and laying method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116914643A (en) * 2023-09-08 2023-10-20 国网山东省电力公司烟台供电公司 Wind power submarine cable laying system and laying method thereof

Similar Documents

Publication Publication Date Title
CN216564415U (en) Cable support for power engineering
CN112152553B (en) Arc-shaped clamp and clamping method for solar photovoltaic bracket
CN220686465U (en) Suspended ceiling device of steel structure factory building
CN111922411A (en) Steel pipe cutting device is used in civil engineering construction
CN210551003U (en) High security C type table
CN209585740U (en) A kind of adjustable solar carport
CN109759764A (en) A kind of two-way movable clamp plate of automobile welding robot
CN215219276U (en) Wave plate angle adjusting device
CN211269204U (en) Workstation for industrial design convenient to use
CN212027231U (en) A telescopic pillar for building field
CN217883094U (en) Direct current motor convenient to adjust mounted position
CN210587810U (en) Automobile chassis welding support frame
CN209419556U (en) A kind of photovoltaic bracket improving photovoltaic panel generated energy
CN209867762U (en) Welding gun adjusting device in net rack support welding process
CN209106474U (en) A kind of adjustable desk of tabletop angles
CN220629258U (en) Light Fu Banjia convenient to photovoltaic board installation
CN220915218U (en) Assembled photovoltaic support
CN216813519U (en) A mount pad for energy storage equipment for new forms of energy photovoltaic power generation
CN220775722U (en) Engineering building installing support convenient to adjust
CN209105082U (en) A kind of integrally-regulated photovoltaic bracket
CN110677104A (en) Angle-adjustable support and photovoltaic device
CN221227430U (en) Foldable photovoltaic mounting bracket
CN219080795U (en) Solar photovoltaic power generation device for roof
CN218335883U (en) Photovoltaic power plant support convenient to adjust angle of elevation
CN221227431U (en) Height-adjustable solar photovoltaic bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant