CN216342114U - Mine underground double-rake-channel ore removal structure - Google Patents

Mine underground double-rake-channel ore removal structure Download PDF

Info

Publication number
CN216342114U
CN216342114U CN202123075418.3U CN202123075418U CN216342114U CN 216342114 U CN216342114 U CN 216342114U CN 202123075418 U CN202123075418 U CN 202123075418U CN 216342114 U CN216342114 U CN 216342114U
Authority
CN
China
Prior art keywords
scraper
ore
way
channel
rake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123075418.3U
Other languages
Chinese (zh)
Inventor
袁诗越
赵刚
段琼
彭鹏
王壮
刘世恒
慕林涛
焦斌
王凯
高宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA NONFERROUS HONGTOUSHAN FUSHUN MINING GROUP CO LTD
Original Assignee
CHINA NONFERROUS HONGTOUSHAN FUSHUN MINING GROUP CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA NONFERROUS HONGTOUSHAN FUSHUN MINING GROUP CO LTD filed Critical CHINA NONFERROUS HONGTOUSHAN FUSHUN MINING GROUP CO LTD
Priority to CN202123075418.3U priority Critical patent/CN216342114U/en
Application granted granted Critical
Publication of CN216342114U publication Critical patent/CN216342114U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model provides a mine underground double-rake-way ore removal structure, which comprises: a lower middle section roadway; a first scraper channel; a second scraper channel; first scraper plough say with second scraper plough say and set up in the both sides of ore body first scraper plough say the top and the top of second scraper plough say all be connected with a plurality of ore buckets of going out first scraper plough say the left end below with the first drop shaft that lower part middle section tunnel link up mutually the front side of first drop shaft be equipped with the first people's shaft that lower part middle section tunnel link up mutually the right-hand member below of second scraper plough way be equipped with the second drop shaft that lower part middle section tunnel link up mutually the rear side of second drop shaft be equipped with the second people's shaft that lower part middle section tunnel link up mutually. The mine underground double-rake-way ore removal structure is reasonable in design and low in investment cost, and can effectively solve the problem that the direction of an ore body cannot be continuously mined and changed when the direction of the ore body is changed by a conventional ore-sliding method and a stage caving method.

Description

Mine underground double-rake-channel ore removal structure
Technical Field
The utility model relates to an underground mine double-rake-channel ore removal structure.
Background
In the underground production process of the mine, the corresponding mining method is required to complete mining and ore removal tasks. The existing mining methods comprise a ore-sliding method and a stage caving method, the two methods are very widely applied to mine production, a plurality of mines are mined by the two mining methods, and the two mining methods bring huge economic benefits to the mines. Corresponding scraper path engineering is required to be constructed in the two mining methods to complete the ore removal task of a stope. However, the existing scraper path engineering can not turn, so that the ore body with the changed ore body trend can not be removed by the existing scraper path engineering. This has caused many mines to divide into two stopes for a stope, has brought huge potential safety hazard and huge waste for the exploitation of mine. Because the minimum 3 meters of mine wall must be reserved between two stopes, if the control is not good in the mining process, the mine wall can be accidentally run through or inclined slope occurs, so that safety accidents are caused, a new mine underground double-rake-way ore removal structure is needed to be developed, and the problem that the scraper track engineering can not turn is solved.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem of providing a mine underground double-rake-way ore removal structure which is reasonable in design, rapid in construction, safe, reliable, low in investment cost, high in combination degree of an ore removal hopper and a cutting layer, realizes optimization of an overall structure, and can effectively solve the problem that the ore-sliding method and the stage caving method cannot continue to mine and change direction when the trend of an ore body changes.
In order to solve the technical problem, the utility model provides an underground mine dual-rake-way ore removal structure, which comprises:
a lower middle section roadway;
the first scraper path is arranged above the lower middle roadway;
the second scraper channel is arranged above the lower middle roadway and communicated with the first scraper channel;
the method is characterized in that: first scraper plough say with second scraper plough say and set up in the both sides of ore body first scraper plough say the top and the top of second scraper plough say all be connected with a plurality of ore buckets of going out first scraper plough say the left end below with the first drop shaft that lower part middle section tunnel link up mutually the front side of first drop shaft be equipped with the first people's shaft that lower part middle section tunnel link up mutually the right-hand member below of second scraper plough way be equipped with the second drop shaft that lower part middle section tunnel link up mutually the rear side of second drop shaft be equipped with the second people's shaft that lower part middle section tunnel link up mutually.
In the structure, the top ends of the ore discharge hoppers are provided with horn-shaped ore sliding openings, the bottom ends of the ore discharge hoppers are provided with downward inclined ore sliding tunnels, and the distance between every two adjacent ore discharge hoppers is 4 m.
In the structure, one ore two ore discharging buckets are arranged at the through position of the first scraper channel and the second scraper channel.
In the above structure, the electric raker is arranged in the first electric rake channel and the second electric rake channel.
In the structure, a return air shaft communicated with the lower middle roadway is arranged on the front side of the communicated part of the first rake channel and the second rake channel.
In the structure, the first orepass and the first sidewalk well are vertically arranged between the first scraper track and the lower middle roadway.
In the structure, the second orepass and the second manway shaft are vertically arranged between the second scraper track and the lower middle roadway.
The utility model achieves the following beneficial effects:
1. the situation that one stope is divided into two stopes due to the change of the trend of the ore body in the mining process of the ore-sliding method and the stage caving method is avoided, and huge potential safety hazards in the mining process are eliminated;
2. the condition of ore loss caused by the change of the trend of the ore body in the mining process of the ore-sliding method and the staged caving method is avoided, and great economic benefit is brought to the mine;
3. the two scraper roads are high in combination degree with the cutting layer of the stope, have the characteristics of simple structure, safety, reliability, short construction period, low input cost and the like, realize the optimization of the whole structure, and can effectively solve the problems of difficult slag discharge transportation and the like that the scraper roads can not change directions in the prior art;
4. the two scraper roads can be constructed simultaneously, the airflow in the roadway at the middle section of the lower part can directly flow to the scraper roads through the drop shaft and the manhole shaft, and the natural airflow for returning air is formed through the return air shaft after the two scraper roads are communicated, so that the electric energy consumption and the noise pollution caused by the continuous operation of a plurality of fans are avoided; and moreover, the occurrence probability of smokers accidents caused by the fact that the wind and the blast can not be scattered due to the fact that the rake channel is too long is reduced.
Drawings
FIG. 1 is a schematic structural diagram of an underground mine dual-rake-way ore removal structure according to an embodiment of the utility model;
fig. 2 is a schematic structural diagram of an ore discharge hopper in an underground double-rake-way ore discharge structure of a mine according to an embodiment of the utility model.
In the figure: 1. a lower middle section roadway; 2. a first scraper channel; 3. a second scraper channel; 4. discharging ore from an ore hopper; 5. a first draw shaft; 6. a first manhole; 7. a second draw shaft; 8. a second manhole; 9. ore slipping port; 10. ore pass roadways; 11. and a return air shaft.
Detailed Description
The technical scheme of the utility model is clearly and completely described in the following with reference to the accompanying drawings.
As shown in fig. 1-2, the mine underground double-rake-way ore removal structure of the utility model comprises:
a lower middle section roadway 1;
the first scraper way 2 is arranged above the lower middle roadway 1;
the second scraper path 3 is arranged above the lower middle roadway 1 and communicated with the first scraper path 2;
the method is characterized in that: first scraper pan 2 with second scraper pan 3 set up the both sides at the ore body first scraper pan 2 the top and second scraper pan 3 the top all be connected with a plurality of ore buckets 4 first scraper pan 2 the left end below with first drop shaft 5 that lower part middle section tunnel 1 link up mutually first drop shaft 5 the front side be equipped with lower part middle section tunnel 1 first people's lane 6 that link up mutually second scraper pan 3 the right-hand member below be equipped with second drop shaft 7 that lower part middle section tunnel 1 link up mutually the rear side of second drop shaft 7 be equipped with the second people's lane 8 that lower part middle section tunnel 1 link up mutually.
Preferably, the top ends of the ore drawing hoppers 4 are provided with horn-shaped ore chutes 9 so that the crushed ore on the cutting layer of the stope can enter the ore drawing hoppers 4, the bottom ends of the ore drawing hoppers 4 are provided with downward inclined ore drawing tunnels 10 (the bottom ends of the ore drawing tunnels 10 are communicated with the first scraper channel 2 and the second scraper channel 3) so that the crushed ore on the cutting layer of the stope can enter the scraper channels, and the distance between two adjacent ore drawing hoppers 4 is 4 m; and the ore removal hopper 4 is vertically arranged between the first scraper path 2, the second scraper path 3 and the cutting layer of the stope.
Preferably, one or two ore drawing buckets 4 are arranged at the penetrating position of the first scraper way 2 and the second scraper way 3.
Preferably, harrowing machines are arranged in the first harrow plate 2 and the second harrow plate 3.
Preferably, a return air shaft 11 communicated with the lower middle roadway 1 is arranged on the front side of the communicated part of the first scraper track 2 and the second scraper track 3.
Preferably, the first draw shaft 5 and the first man-way shaft 6 are vertically arranged between the first scraper shaft 2 and the lower middle roadway 1, and a detour is provided at the front side of the first draw shaft 5 so as not to cause a safety problem.
Preferably, the second draw shaft 7 and the second manway shaft 8 are vertically arranged between the second scraper shaft 3 and the lower middle roadway 1, and a bypass is arranged at the front side of the second draw shaft 7 so as not to cause a safety problem.
When the underground mine double-rake-channel ore removal structure works specifically, crushed ore mined in a stope enters the ore removal hopper through the cutting layer, flows into the first electric rake channel and the second electric rake channel through the ore removal hopper, can be conveyed to a chute through the electric rake, and enters a lower middle section roadway from the chute to finish ore removal and transportation. The first scraper path and the second scraper path can be constructed simultaneously in the construction process, the airflow in the roadway at the middle section of the lower part can directly flow into the first scraper path and the second scraper path through the chute and the sidewalk well, and the natural airflow of return air is formed through the return air shaft after the two scraper paths are communicated. Therefore, the power consumption and noise pollution caused by continuous operation of a plurality of fans are avoided. And moreover, the occurrence probability of smokers accidents caused by the fact that the wind and the blast smoke are easily scattered due to the overlong rake channel is reduced.
The above examples are only intended to illustrate the technical solution of the present invention, but not to limit it; while the utility model has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; and the modifications or the substitutions do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; the connection can be mechanical connection or electrical connection; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.

Claims (7)

1. A mine underground double-rake-channel ore removal structure comprises:
a lower middle section roadway (1);
the first scraper channel (2) is arranged above the lower middle roadway (1);
the second scraper channel (3) is arranged above the lower middle roadway (1) and communicated with the first scraper channel (2);
the method is characterized in that: first scraper plough way (2) with second scraper plough way (3) set up the both sides at the ore body the top of first scraper plough way (2) and the top of second scraper plough way (3) all be connected with a plurality of ore buckets (4) of going out the left end below of first scraper plough way (2) be equipped with first drop shaft (5) that lower part middle section tunnel (1) link up mutually the front side of first drop shaft (5) be equipped with first people way well (6) that lower part middle section tunnel (1) link up mutually the right-hand member below of second scraper plough way (3) be equipped with second drop shaft (7) that lower part middle section tunnel (1) link up mutually the rear side of second drop shaft (7) be equipped with second people way well (8) that lower part middle section (1) link up mutually.
2. The mine underground double-rake-way ore removal structure as defined in claim 1, wherein: the top of ore drawing fill (4) all be equipped with tubaeform ore pass mouth (9) ore drawing fill (4) the bottom of ore drawing fill (4) all be equipped with ore pass tunnel (10) of downward sloping, the distance between two adjacent ore drawing fill (4) is 4 m.
3. The mine underground double-rake-way ore removal structure as defined in claim 1, wherein: one or two ore discharge hoppers (4) are arranged at the through position of the first scraper channel (2) and the second scraper channel (3).
4. The mine underground double-rake-way ore removal structure as defined in claim 1, wherein: the inside of the first scraper channel (2) and the inside of the second scraper channel (3) are both provided with a scraper.
5. The mine underground double-rake-way ore removal structure as defined in claim 1, wherein: and a return air shaft (11) communicated with the lower middle roadway (1) is arranged on the front side of the communicated part of the first scraper channel (2) and the second scraper channel (3).
6. The mine underground double-rake-way ore removal structure as defined in claim 1, wherein: the first draw shaft (5) and the first manhole shaft (6) are vertically arranged between the first scraper shaft (2) and the lower middle section roadway (1).
7. The mine underground double-rake-way ore removal structure as defined in claim 1, wherein: the second orepass (7) and the second sidewalk well (8) are vertically arranged between the second scraper track (3) and the lower middle section roadway (1).
CN202123075418.3U 2021-12-08 2021-12-08 Mine underground double-rake-channel ore removal structure Active CN216342114U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123075418.3U CN216342114U (en) 2021-12-08 2021-12-08 Mine underground double-rake-channel ore removal structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123075418.3U CN216342114U (en) 2021-12-08 2021-12-08 Mine underground double-rake-channel ore removal structure

Publications (1)

Publication Number Publication Date
CN216342114U true CN216342114U (en) 2022-04-19

Family

ID=81162658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123075418.3U Active CN216342114U (en) 2021-12-08 2021-12-08 Mine underground double-rake-channel ore removal structure

Country Status (1)

Country Link
CN (1) CN216342114U (en)

Similar Documents

Publication Publication Date Title
CN104141495B (en) Filling mining method for gently inclined medium-thickness phosphate ore body
CN107893658B (en) Big thick ore body stage open stope afterwards filling mining methods in pole under strong ground pressure ring border
CN101509377B (en) High-dipping ore block house column mining method
CA2745066C (en) Continuous mining
CN110359914B (en) Safe and low-cost combined sublevel mining method for gently inclined medium-thickness ore body
CN104695960B (en) Air column becomes well back coming afterwards filling mining method
CN110905516B (en) High-sublevel cut-and-fill mining method with downward layered horizontal access
CN102162364A (en) Layout method for underground dense-medium shallow-slot coal preparation in coal mine
CN103670417B (en) Utilize the bottom-column-free sectional caving stoping method of scraper tunnel sidepiece ore removal
CN108533265A (en) The filling mining method of foundation is assembled using concrete component
CN216342114U (en) Mine underground double-rake-channel ore removal structure
CN109252863B (en) Method for exploiting broken thick ore body by using coal roadway tunneling machine
CN109026113B (en) Method for using goaf as mine total return air shaft
CN108301835B (en) Pseudo- inclined ramp road panel point pillar method of stoping
CN110388210B (en) Stope structure arrangement mode suitable for combined sectional mining of slowly-inclined medium-thickness ore body
CN102979532B (en) A kind of assistance with hill road coordinates the development method of belt inclined shaft haulage
CN109339790B (en) Mining method of medium-thickness gently-inclined broken ore body
CN111828008A (en) Filling mining method for downward layered herringbone access arrangement
Kamp Backfilling on gold mines of the Gold Fields group
CN116537786A (en) Mining method for filling and replacing coal pillars without lifting gangue
CN113944464B (en) Coal mining method of corner coal full-negative-pressure continuous miner
CN102704978A (en) High fully mechanized filling, mining and screening hydraulic support
CN113062740B (en) Small layered filling mining method for multi-directional ramp without ore pillar
CN102269012B (en) Process and equipment for increasing block coal rate
CN114000882A (en) Caving method and filling method collaborative mining method for same mining area

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant