High-rise hanging flower basket structure Download PDF

Info

Publication number
CN216239655U
CN216239655U CN202122309128.4U CN202122309128U CN216239655U CN 216239655 U CN216239655 U CN 216239655U CN 202122309128 U CN202122309128 U CN 202122309128U CN 216239655 U CN216239655 U CN 216239655U
Authority
CN
China
Prior art keywords
scaffold
basket structure
lower floor
bracing piece
structure according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122309128.4U
Other languages
Chinese (zh)
Inventor
斯新
李明
朱黎明
丁旺
石晓玲
金余胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Fuxia Construction Decorations Engineering Co ltd
Original Assignee
Zhejiang Sanjian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Sanjian Construction Group Co Ltd filed Critical Zhejiang Sanjian Construction Group Co Ltd
Priority to CN202122309128.4U priority Critical patent/CN216239655U/en
Application granted granted Critical
Publication of CN216239655U publication Critical patent/CN216239655U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model relates to a high-rise hanging flower basket structure, it includes a plurality of bracing pieces, and is a plurality of bracing piece one end all is used for setting up on the floor face down, and is a plurality of the bracing piece other end all is used for wearing out the floor face down, and is a plurality of be provided with the scaffold frame on the bracing piece. This application has the effect that makes things convenient for operating personnel to build the scaffold to high-rise building.

Description

High-rise hanging flower basket structure
Technical Field
The application relates to the field of buildings, in particular to a high-rise hanging basket structure.
Background
The hanging basket is a building tool for high-altitude operation in building engineering and is used for curtain wall installation or outer wall cleaning.
At present, when a curtain wall is installed on a building, an operator builds a scaffold around the building and then installs the curtain wall on the building.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: when the curtain wall is installed on a high-rise building, an operator needs to build the scaffold to the height of the high-rise building from the ground, and time and labor are wasted.
SUMMERY OF THE UTILITY MODEL
In order to build a scaffold for high-rise buildings for operating personnel, the application provides a high-rise hanging flower basket structure.
The application provides a high-rise hanging flower basket structure adopts following technical scheme:
the utility model provides a high-rise hanging flower basket structure, includes a plurality of bracing pieces, and is a plurality of bracing piece one end all is used for setting up on the floor face down, and is a plurality of the bracing piece other end all is used for wearing out the floor face down, and is a plurality of be provided with the scaffold frame on the bracing piece.
Through adopting above-mentioned technical scheme, during the use operating personnel sets up a plurality of bracing pieces on the floor face of going downstairs for the floor face of going downstairs is worn out to a plurality of bracing pieces, and operating personnel sets up the scaffold frame on a plurality of bracing pieces afterwards, makes things convenient for operating personnel to carry out the installation of curtain to high-rise building, and operating personnel only need build the height of a floor with the scaffold frame and just can realize carrying out the installation of curtain to high-rise building.
Optionally, be provided with the reinforcement assembly on the bracing piece, the reinforcement assembly is including strengthening the hoist cable, it is used for setting up on the floor face to strengthen hoist cable one end, strengthen the hoist cable other end be used for set up in the bracing piece is worn out the one end on the floor face down.
Through adopting above-mentioned technical scheme, during the use, strengthen the hoist cable and strengthened the supporting role to the bracing piece, improve holistic structural strength.
Optionally, the reinforcing assembly further comprises a threaded pipe, a mounting ring and a screw; the mounting ring is arranged on the upper floor; one end of the threaded pipe is rotatably connected to the supporting rod; the screw rod is in threaded connection with the threaded pipe; one end of the reinforcing sling, which is far away from the supporting rod, penetrates through the mounting ring and is arranged on the screw rod.
Through adopting above-mentioned technical scheme, the screw rod is rotated to operating personnel accessible during the use, realizes carrying out the tensioning to strengthening the hoist cable, improves and strengthens the hoist cable to the support effect of bracing piece, improves holistic structural strength.
Optionally, a plurality of expansion bolts are arranged on the supporting rod and penetrate through the supporting rod, and tail portions of the expansion bolts are used for penetrating into a floor surface.
Through adopting above-mentioned technical scheme, make things convenient for operating personnel to the installation and the dismantlement of bracing piece.
Optionally, the bottom surface of the scaffold is provided with a horizontal plate, and one end of the scaffold far away from the downstairs surface is provided with a vertical plate.
Through adopting above-mentioned technical scheme, improve the factor of safety of operating personnel when the installation curtain, reduce construction waste and pass through the scaffold and drop to ground.
Optionally, one end of the scaffold far away from the lower floor is provided with a falling prevention net.
Through adopting above-mentioned technical scheme, prevent weighing down the net and block construction waste, reduce the construction waste on scaffold frame upper strata and drop to subaerial condition and take place.
Optionally, prevent weighing down the net rotate connect in on the scaffold, prevent weighing down the net with be provided with spacing hoist cable between the scaffold, spacing hoist cable one end set up in prevent weighing down on the net, the spacing hoist cable other end set up in on the scaffold.
Through adopting above-mentioned technical scheme, during the use operating personnel accessible spacing hoist cable drives prevents weighing down the net and rotates along the direction that is close to the scaffold, makes things convenient for operating personnel to clear up the waste material that prevents weighing down on the net.
Optionally, a blocking plate is arranged on the scaffold, and one end, far away from the scaffold, of the blocking plate is used for being abutted against the lower floor surface.
Through adopting above-mentioned technical scheme, it takes place to subaerial condition to reduce construction waste to drop through the clearance between scaffold frame and the bracing piece.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the scaffold is conveniently arranged on a high floor through a plurality of support rods;
2. the structural strength of the support rod is improved through the reinforcing component;
3. the condition that the construction waste falls to the ground is reduced through the anti-falling net, the horizontal plate, the vertical plate and the blocking plate.
Drawings
Fig. 1 is a schematic structural diagram of a specific embodiment of the present application.
Fig. 2 is a schematic structural view of the reinforcement assembly of fig. 1.
Fig. 3 is an enlarged view at a in fig. 2 for showing the structure of the reinforcing slings, the turning blocks, the mounting rings and the screws.
Fig. 4 is a sectional view of fig. 1 for showing the structures of the horizontal plate, the vertical plate, and the blocking plate.
Reference numerals: 1. going up to the floor; 2. going down a floor level; 21. a support bar; 22. an expansion bolt; 3. a reinforcement assembly; 31. reinforcing the sling; 32. a threaded pipe; 33. rotating the block; 34. a mounting ring; 35. a screw; 4. a scaffold; 41. a horizontal plate; 42. a vertical plate; 43. a blocking plate; 44. the anti-falling net; 45. a limiting sling.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
The embodiment of the application discloses high-rise hanging flower basket structure. Referring to fig. 1 and 2, a high-rise hanging basket structure comprises a plurality of support rods 21, wherein one end of each support rod 21 is mounted on a lower floor 2 through three expansion bolts 22, and the tail parts of the three expansion bolts 22 vertically penetrate through the support rods 21 downwards and penetrate into the lower floor 2; the other end of the support rod 21 passes through the lower floor 2.
Referring to fig. 1 and 2, a reinforcing assembly 3 is arranged between the support rod 21 and the upper floor 1, and the reinforcing assembly 3 comprises a reinforcing sling 31, a threaded pipe 32, a rotating block 33, a mounting ring 34 and a screw 35; the mounting ring 34 is fixedly connected to the upper deck level 1; one end of the threaded pipe 32 is rotatably connected to one end of the support rod 21 penetrating through the lower floor 2; the screw 35 is screwed to an end of the threaded pipe 32 remote from the support rod 21.
Referring to fig. 2 and 3, the rotating block 33 is rotatably connected to one end of the screw rod 35 away from the threaded pipe 32; one end of the reinforcing sling 31 is fixedly connected to the end of the support rod 21 penetrating the lower floor 2, and the other end of the reinforcing sling 31 penetrates the mounting ring 34 and is fixedly connected to an end face of the turning block 33 far away from the screw 35.
Referring to fig. 1 and 2, a scaffold 4 is placed on the upper end surfaces of a plurality of support rods 21, the scaffold 4 is close to a horizontal plate 41 fixedly connected to the position of the support rod 21, the scaffold 4 is far away from a vertical plate 42 fixedly connected to one end of the lower floor 2, the horizontal plate 41 is located on one side of the vertical plate 42 facing the lower floor 2, and one end surface of the horizontal plate 41 close to the vertical plate 42 is abutted to the vertical plate 42.
Referring to fig. 1 and 4, a blocking plate 43 is obliquely arranged between the upper floor surface and the lower floor surface 2 of the scaffold 4, one end of the blocking plate 43 is fixedly connected to one end surface of the horizontal plate 41 far away from the vertical plate 42, the other end of the blocking plate 43 is abutted against the upper end surface of the lower floor surface 2, and the distance between the blocking plate 43 and the lower floor surface 2 is gradually reduced along the direction from the vertical plate 42 to the horizontal plate 41.
Referring to fig. 1 and 4, the one end of the scaffold 4 far away from the lower floor 2 is rotatably connected with an anti-falling net 44, two limiting slings 45 are arranged between the anti-falling net 44 and the scaffold 4, one ends of the two limiting slings 45 are fixedly connected to the end of the scaffold 4 far away from the lower floor 2, and the other ends of the two limiting slings 45 are fixedly connected to the end face of the anti-falling net 44 far away from the scaffold 4.
The implementation principle of the high-rise hanging basket structure in the embodiment of the application is as follows: before use, an operator drives the screw 35 to rotate, so that the tensile force of the reinforcing sling 31 is adjusted, and the structural strength of the plurality of support rods 21 is improved; the horizontal plate 41, the vertical plate 42, the anti-falling net 44 and the blocking plate 43 can reduce the occurrence of the situation that waste materials on the building fall to the ground, and an operator can conveniently install the scaffold 4 on a high-rise building through the plurality of support rods 21; when the anti-falling net is used, an operator can drive the limiting sling 45 to move, so that the anti-falling net 44 rotates along the direction close to the vertical plate 42, and the operator can clean the construction waste in the anti-falling net 44 conveniently.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. A high-rise hanging flower basket structure which characterized in that: including a plurality of bracing pieces (21), a plurality of bracing piece (21) one end all is used for setting up on lower floor face (2), and is a plurality of bracing piece (21) other end is located lower floor face (2) outside, and is a plurality of be provided with scaffold (4) on bracing piece (21).
2. The high-rise hanging basket structure according to claim 1, wherein: be provided with on bracing piece (21) and strengthen subassembly (3), strengthen subassembly (3) including strengthening hoist cable (31), strengthen hoist cable (31) one end and be used for setting up on going up floor face (1), strengthen hoist cable (31) other end be used for set up in the one end of downstairs face (2) is worn out in bracing piece (21).
3. A high-rise gondola structure according to claim 2 characterized in that: the reinforcing component (3) further comprises a threaded pipe (32), a mounting ring (34) and a screw (35); the mounting ring (34) is arranged on the upper floor (1); one end of the threaded pipe (32) is rotatably connected to the support rod (21); the screw rod (35) is in threaded connection with the threaded pipe (32); one end, far away from the supporting rod (21), of the reinforcing sling (31) penetrates through the mounting ring (34) and is arranged on the screw (35).
4. The high-rise hanging basket structure according to claim 1, wherein: the support rod (21) is provided with a plurality of expansion bolts (22), the expansion bolts (22) penetrate through the support rod (21), and the tail parts of the expansion bolts (22) are used for penetrating into the lower floor surface (2).
5. The high-rise hanging basket structure according to claim 1, wherein: the scaffold (4) bottom surface is provided with horizontal plate (41), the one end that lower floor face (2) was kept away from in scaffold (4) is provided with vertical board (42).
6. The high-rise hanging basket structure according to claim 1, wherein: and one end of the scaffold (4) far away from the lower floor surface (2) is provided with an anti-falling net (44).
7. The high-rise hanging basket structure according to claim 6, wherein: prevent weighing down net (44) rotate connect in on scaffold (4), prevent weighing down net (44) with be provided with spacing hoist cable (45) between scaffold (4), spacing hoist cable (45) one end set up in prevent weighing down on net (44), spacing hoist cable (45) other end set up in on scaffold (4).
8. The high-rise hanging basket structure according to claim 1, wherein: be provided with on scaffold frame (4) baffle (43), the one end that scaffold frame (4) were kept away from in baffle (43) is used for inconsistent with lower floor face (2).
CN202122309128.4U 2021-09-22 2021-09-22 High-rise hanging flower basket structure Active CN216239655U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122309128.4U CN216239655U (en) 2021-09-22 2021-09-22 High-rise hanging flower basket structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122309128.4U CN216239655U (en) 2021-09-22 2021-09-22 High-rise hanging flower basket structure

Publications (1)

Publication Number Publication Date
CN216239655U true CN216239655U (en) 2022-04-08

Family

ID=80987239

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122309128.4U Active CN216239655U (en) 2021-09-22 2021-09-22 High-rise hanging flower basket structure

Country Status (1)

Country Link
CN (1) CN216239655U (en)

Similar Documents

Publication Publication Date Title
CN201826516U (en) Novel attached lifting scaffold
CN107558723B (en) Method for manufacturing and installing hanging bracket of hanging basket for inclined roof
CN110528863B (en) Hanging basket device for outer inclined plane construction and construction method
CN213329955U (en) Flower basket diagonal rod type overhanging scaffold
CN215052154U (en) A suspension type handling frame for construction outside concrete barrier
CN105484485A (en) Attached lifting scaffold
CN205577383U (en) Attached lifting scaffold
CN216239655U (en) High-rise hanging flower basket structure
CN207144446U (en) A kind of construction Skidproof hanging cradle
CN108316630B (en) High-altitude hanging scaffold
CN111206762A (en) Building outer wall operation platform capable of being clamped on floor slab and being quickly disassembled and assembled
CN110778095A (en) External protection frame of assembled structure
CN214423956U (en) Multifunctional hanging basket for building construction
CN213171212U (en) A hoisting apparatus for building engineering
CN2216104Y (en) Hanging lift scaffold
CN211037771U (en) Hanging basket device for outer slope construction
CN209817386U (en) Outer enclosure structure of overhanging balcony position of prefabricated building
CN108775016B (en) Concrete support horizontal movement adjustable hanging basket
CN208202604U (en) A kind of construction discharging platform
CN201730306U (en) Light-weight scaffold
CN219451453U (en) Scaffold protection steel mesh
CN205713035U (en) All steel for climbing frame protects crane
CN216239637U (en) Movable hanging basket suitable for high-altitude construction operation
CN209651840U (en) A kind of hydraulic hanging basket of full-automatic self-balancing
CN214498436U (en) Convenient type construction platform of unloading

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240415

Address after: Building 7, No. 178 Qiutao Road, Hangzhou City, Zhejiang Province, 310000

Patentee after: Zhejiang Fuxia Construction Decorations Engineering Co.,Ltd.

Country or region after: China

Address before: 310002 great wall building, No. 60, Leiting Road, Shangcheng District, Hangzhou City, Zhejiang Province

Patentee before: ZHEJIANG PROVINCE SANJIAN CONSTRUCTION GROUP CO.,LTD.

Country or region before: China