CN216238613U - Strong-stability foundation pile for hydraulic engineering - Google Patents

Strong-stability foundation pile for hydraulic engineering Download PDF

Info

Publication number
CN216238613U
CN216238613U CN202121894098.1U CN202121894098U CN216238613U CN 216238613 U CN216238613 U CN 216238613U CN 202121894098 U CN202121894098 U CN 202121894098U CN 216238613 U CN216238613 U CN 216238613U
Authority
CN
China
Prior art keywords
foundation pile
annular frame
clamping block
wall
pile body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202121894098.1U
Other languages
Chinese (zh)
Inventor
周浩城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongke Yongjian Construction Group Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202121894098.1U priority Critical patent/CN216238613U/en
Application granted granted Critical
Publication of CN216238613U publication Critical patent/CN216238613U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a foundation pile with strong stability for hydraulic engineering, which comprises a bearing platform, a main foundation pile and an auxiliary foundation pile, wherein the main foundation pile is arranged at the center of the bottom of the bearing platform, the main foundation pile comprises a foundation pile body and a steel bar cylinder arranged in the foundation pile body, an inner supporting frame is arranged in the steel bar cylinder, and an outer reinforcing mechanism extending to the outer side of the foundation pile body is arranged on the outer wall of the steel bar cylinder. According to the utility model, the outer wall of the reinforcing steel tube is provided with the outer reinforcing mechanism extending to the outer side of the foundation pile body, so that the foundation pile body can be reinforced, the strength of the foundation pile body is improved, and the outer reinforcing mechanism comprises the second annular frame, the first clamping block and the second clamping block are clamped in the inner wall of the pile hole, so that the foundation pile body is assisted and limited, the vertical offset settlement of the foundation pile body is prevented, and the stability of the foundation pile body is further improved.

Description

Strong-stability foundation pile for hydraulic engineering
Technical Field
The utility model relates to the technical field of foundation piles, in particular to a foundation pile with high stability for hydraulic engineering.
Background
Hydraulic engineering is an engineering built for controlling and allocating surface water and underground water in nature to achieve the purposes of removing harmful substances and benefiting. Also known as water engineering. Water is a valuable resource essential for human production and life, but its naturally occurring state does not completely meet the needs of human beings. Only when hydraulic engineering is built, water flow can be controlled, flood disasters are prevented, and water quantity is adjusted and distributed to meet the requirements of people on water resources in life and production. Hydraulic engineering needs to build various types of hydraulic buildings such as dams, dikes, spillways, water gates, water inlets, channels, transition troughs, rafts, fishways and the like so as to achieve the aims.
Present foundation pile for hydraulic engineering, the single reinforcing bar section of thick bamboo cooperation concrete placement that adopts forms, and its stability is lower, and the lower easy deformation of intensity of a reinforcing bar section of thick bamboo on the one hand, on the other hand foundation pile easily takes place to subside, so can not satisfy user's demand.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a foundation pile with strong stability for hydraulic engineering, wherein an outer reinforcing mechanism extending to the outer side of a foundation pile body is arranged on the outer wall of a reinforcing steel cylinder, the foundation pile body can be reinforced, the strength of the foundation pile body is improved, and the outer reinforcing mechanism comprises a second annular frame, a first clamping block and a second clamping block, the first clamping block and the second clamping block are clamped in pile holes, so that the foundation pile body is limited in an auxiliary manner, the foundation pile body is prevented from being deflected and settled up and down, and the stability of the foundation pile is further improved.
In order to achieve the purpose, the utility model adopts the following technical scheme: hydraulic engineering is with strong foundation pile of stability, including plummer, main foundation pile and supplementary foundation pile, the bottom center department of plummer is provided with main foundation pile, main foundation pile includes the foundation pile body and sets up at this internal reinforcing bar section of thick bamboo of foundation pile, be provided with inner supporting frame in the reinforcing bar section of thick bamboo, be provided with the outer strengthening mechanism who extends to the foundation pile body outside on the reinforcing bar section of thick bamboo outer wall.
As a further description of the above technical solution:
the inner support frame comprises a first annular frame and a cross support frame, the cross support frame is welded in the first annular frame, and the first annular frame is welded on the inner wall of the steel bar barrel.
As a further description of the above technical solution:
the outer reinforcing mechanism comprises a second annular frame, first fixture blocks and second fixture blocks, the second annular frame is welded on the outer wall of the steel bar barrel, the first fixture blocks are arranged on the outer wall of the second annular frame, the first fixture blocks are provided with a plurality of parts, the first fixture blocks of the plurality of parts are distributed on the outer wall of the second annular frame in an annular mode, and the second fixture blocks are arranged between the two adjacent first fixture blocks.
As a further description of the above technical solution:
the outside that the plummer lower surface is located main foundation pile is provided with assists the foundation pile, assist the foundation pile and be provided with a plurality of altogether, and a plurality of assists the foundation pile and be the equidistant distribution of annular.
As a further description of the above technical solution:
the second annular frame, the first clamping block and the second clamping block are of a pouring integrated forming structure.
As a further description of the above technical solution:
the inner support frames are arranged in a plurality of numbers, the inner support frames are positioned on the same vertical line, and the distance between every two adjacent inner support frames is equal.
As a further description of the above technical solution:
the outer reinforcing mechanisms are arranged on the same vertical line, and the distance between every two adjacent outer reinforcing mechanisms is equal.
The utility model provides a foundation pile with strong stability for hydraulic engineering. The method has the following beneficial effects:
(1) this foundation pile that stability is strong for hydraulic engineering is provided with the outer strengthening mechanism who extends to the foundation pile body outside on the reinforcing bar section of thick bamboo outer wall, can consolidate the foundation pile body, improves its intensity, and secondly outer strengthening mechanism includes second annular frame, first fixture block and second fixture block, through first fixture block and second fixture block in stake downthehole wall, assists spacingly to the foundation pile body, prevents that it from taking place the skew to subside from top to bottom, further improves its stability.
(2) This foundation pile that stability is strong for hydraulic engineering is provided with the inner support frame in a reinforcing bar section of thick bamboo, including first annular frame and cross support frame, the cross support frame welding can be consolidated a reinforcing bar section of thick bamboo in first annular frame through the setting of inner support frame, improves the intensity of its reinforcing bar section of thick bamboo, prevents that a reinforcing bar section of thick bamboo from taking place deformation and damaging to this foundation pile for hydraulic engineering stability uses has been improved.
Drawings
Fig. 1 is a front view of a strong stability foundation pile for hydraulic engineering according to the present invention;
fig. 2 is a schematic cross-sectional view of a main foundation pile according to the present invention;
FIG. 3 is a schematic structural view of the inner bracket of the present invention;
fig. 4 is a schematic structural diagram of the middle and outer reinforcing mechanisms of the present invention.
Illustration of the drawings:
1. a bearing table; 2. a main foundation pile; 21. a foundation pile body; 22. a reinforcing steel bar cylinder; 23. an inner support frame; 231. a first annular frame; 232. a cross support frame; 24. an outer reinforcement mechanism; 241. a second annular frame; 242. a first clamping block; 243. a second fixture block; 3. and (5) auxiliary foundation piles.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
The first embodiment is as follows: referring to fig. 1-4, hydraulic engineering is with strong foundation pile of stability, including plummer 1, main foundation pile 2 and auxiliary foundation pile 3, the bottom center department of plummer 1 is provided with main foundation pile 2, and main foundation pile 2 includes foundation pile body 21 and sets up a steel reinforcement section of thick bamboo 22 in foundation pile body 21, is provided with inner support frame 23 in the steel reinforcement section of thick bamboo 22, is provided with outer strengthening mechanism 24 that extends to the foundation pile body 21 outside on the steel reinforcement section of thick bamboo 22 outer wall.
Example two: referring to fig. 2 and 3, the inner support frame 23 includes a first annular frame 231 and a cross support frame 232, the cross support frame 232 is welded in the first annular frame 231, the first annular frame 231 is welded on the inner wall of the steel bar cylinder 22, the inner support frame 23 is provided with a plurality of inner support frames 23, the inner support frames 23 are located on the same vertical line, the distance between two adjacent inner support frames 23 is equal, the inner support frames 23 are arranged to strengthen the steel bar cylinder 22, and the steel bar cylinder 22 is prevented from being deformed and damaged in the using process, so that the stability of the foundation pile with strong stability for the hydraulic engineering is improved.
Example three: referring to fig. 2 and 4, the outer reinforcement mechanism 24 includes a second annular frame 241, a first fixture block 242 and a second fixture block 243, the second annular frame 241 is welded on the outer wall of the reinforcement cylinder 22, the outer wall of the second annular frame 241 is provided with the first fixture block 242, the first fixture block 242 is provided with a plurality of first fixture blocks 242, the plurality of first fixture blocks 242 are annularly distributed on the outer wall of the second annular frame 241, the second fixture block 243 is arranged between two adjacent first fixture blocks 242, the second annular frame 241, the first fixture block 242 and the second fixture block 243 are of a cast and integrated structure, the outer reinforcement mechanism 24 is provided with a plurality of outer reinforcement mechanisms 24, the plurality of outer reinforcement mechanisms 24 are positioned on the same vertical line, the distance between two adjacent outer reinforcement mechanisms 24 is equal, the arrangement of the second annular frame 241 in the outer reinforcement mechanism 24 can further reinforce the reinforcement cylinder 22, the strength of the reinforcement cylinder 22 is improved, the arrangement of the first fixture blocks 242 and the second fixture block 243, in the use process, inlay and locate on stake hole inner wall, carry out spacingly to main foundation pile 2, prevent that it from sending subsides from top to bottom.
Example four: referring to fig. 1, the outside that the 1 lower surface of plummer is located main foundation pile 2 is provided with assists foundation pile 3, assists foundation pile 3 to be provided with a plurality of altogether, and a plurality of assists foundation pile 3 to be the equidistant distribution of annular, through main foundation pile 2 and the setting of assisting foundation pile 3, can carry out further spacing support to plummer 1, improves the stability of plummer 1.
In the description herein, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and equivalent alternatives or modifications according to the technical solution of the present invention and the inventive concept thereof should be covered by the scope of the present invention.

Claims (7)

1. Strong foundation pile of stability for hydraulic engineering, including plummer (1), main foundation pile (2) and auxiliary foundation pile (3), its characterized in that, the bottom center department of plummer (1) is provided with main foundation pile (2), main foundation pile (2) are including foundation pile body (21) and a steel bar section of thick bamboo (22) of setting in foundation pile body (21), be provided with inner support frame (23) in steel bar section of thick bamboo (22), be provided with outer strengthening mechanism (24) that extend to foundation pile body (21) outside on steel bar section of thick bamboo (22) outer wall.
2. The foundation pile with high stability for the water conservancy project according to claim 1, wherein the inner support frame (23) comprises a first annular frame (231) and a cross support frame (232), the cross support frame (232) is welded in the first annular frame (231), and the first annular frame (231) is welded on the inner wall of the steel bar barrel (22).
3. The foundation pile with high stability for the hydraulic engineering according to claim 1, wherein the outer reinforcing mechanism (24) comprises a second annular frame (241), a first clamping block (242) and a second clamping block (243), the second annular frame (241) is welded on the outer wall of the steel bar barrel (22), the first clamping block (242) is arranged on the outer wall of the second annular frame (241), the first clamping block (242) is provided with a plurality of clamping blocks, the first clamping blocks (242) are annularly distributed on the outer wall of the second annular frame (241), and the second clamping block (243) is arranged between two adjacent first clamping blocks (242).
4. The foundation pile with high stability for hydraulic engineering according to claim 1, wherein auxiliary foundation piles (3) are arranged on the outer side of the main foundation pile (2) on the lower surface of the bearing platform (1), a plurality of auxiliary foundation piles (3) are arranged, and the plurality of auxiliary foundation piles (3) are distributed in an annular shape at equal intervals.
5. The foundation pile with high stability for the water conservancy project according to claim 3, wherein the second annular frame (241), the first clamping block (242) and the second clamping block (243) are of a pouring and integral molding structure.
6. The foundation pile with high stability for the water conservancy project according to claim 1, wherein a plurality of inner support frames (23) are arranged, the inner support frames (23) are positioned on the same vertical line, and the distance between every two adjacent inner support frames (23) is equal.
7. The foundation pile with high stability for the water conservancy project according to claim 1, wherein a plurality of the outer reinforcing mechanisms (24) are arranged, the outer reinforcing mechanisms (24) are positioned on the same vertical line, and the distance between every two adjacent outer reinforcing mechanisms (24) is equal.
CN202121894098.1U 2021-08-13 2021-08-13 Strong-stability foundation pile for hydraulic engineering Withdrawn - After Issue CN216238613U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121894098.1U CN216238613U (en) 2021-08-13 2021-08-13 Strong-stability foundation pile for hydraulic engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121894098.1U CN216238613U (en) 2021-08-13 2021-08-13 Strong-stability foundation pile for hydraulic engineering

Publications (1)

Publication Number Publication Date
CN216238613U true CN216238613U (en) 2022-04-08

Family

ID=80979703

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121894098.1U Withdrawn - After Issue CN216238613U (en) 2021-08-13 2021-08-13 Strong-stability foundation pile for hydraulic engineering

Country Status (1)

Country Link
CN (1) CN216238613U (en)

Similar Documents

Publication Publication Date Title
CN100535264C (en) Steel boxed cofferdam and recovery method thereof
CN216238613U (en) Strong-stability foundation pile for hydraulic engineering
CN215210491U (en) Four-column type portal pier
CN213625673U (en) Self-supporting polygonal cylindrical foundation for offshore wind power
CN209723230U (en) The connecting node of steel plate combined shear wall and not equal higher baselines
CN216006929U (en) Be suitable for height and have major diameter drilling bored concrete pile of scour prevention
CN111608175B (en) Reinforcing pile for building bridge
CN206859208U (en) Novel building concrete solid pile
CN113700004B (en) Deep foundation pit combined support construction device and method thereof
CN213571905U (en) Foundation structure of large-load industrial building
KR0155648B1 (en) A steel shell and the manufacturing method thereof
CN216839610U (en) Miniature steel-pipe pile underpins independent foundation and seals a pile structure
CN217204033U (en) Bored concrete pile reinforced structure
CN211036967U (en) Variable cross-section prefabricated part and prefabricated part assembly
CN218291971U (en) Inner supporting structure for foundation pit
CN210315504U (en) Underground continuous wall rigid framework module cage and construction site facility
CN219973225U (en) Quick repair assembled structure suitable for side wall collapse of row pile foundation pit
CN212026239U (en) Stiffness composite pile capable of improving bearing capacity
CN218027782U (en) High-rise quick integral embedded type sump pit steel forming die
CN218843154U (en) Steel pipe concrete multi-support-column foundation
CN219196485U (en) Corner reinforcement cage reinforcing assembly
CN217106191U (en) Pressurization honeycomb duct for construction of beam column joint with complex stiffness structure
CN213329087U (en) Pipeline support assembled pile foundation structure
CN211006523U (en) Hydraulic engineering plunger type dykes and dams reinforced structure
CN219862767U (en) Support platform device of filling pile hole opening installation machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220725

Address after: 610000 room 1709, 17th floor, unit 3, building 1, No. 48, yingmenkou Road, Jinniu District, Chengdu, Sichuan Province

Patentee after: Sichuan Xiahe water conservancy and Hydropower Engineering Co.,Ltd.

Address before: 510000 room 117, building 1, No. 12, Jishan kengwei Road, Tianhe District, Guangzhou City, Guangdong Province

Patentee before: Zhou Haocheng

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: 610000 room 1709, 17th floor, unit 3, building 1, No. 48, yingmenkou Road, Jinniu District, Chengdu, Sichuan Province

Patentee after: Zhongke Yongjian Construction Group Co.,Ltd.

Address before: 610000 room 1709, 17th floor, unit 3, building 1, No. 48, yingmenkou Road, Jinniu District, Chengdu, Sichuan Province

Patentee before: Sichuan Xiahe water conservancy and Hydropower Engineering Co.,Ltd.

CP01 Change in the name or title of a patent holder
AV01 Patent right actively abandoned

Granted publication date: 20220408

Effective date of abandoning: 20240412

AV01 Patent right actively abandoned

Granted publication date: 20220408

Effective date of abandoning: 20240412

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned