CN216042876U - Building site board house protection canopy - Google Patents

Building site board house protection canopy Download PDF

Info

Publication number
CN216042876U
CN216042876U CN202121463804.7U CN202121463804U CN216042876U CN 216042876 U CN216042876 U CN 216042876U CN 202121463804 U CN202121463804 U CN 202121463804U CN 216042876 U CN216042876 U CN 216042876U
Authority
CN
China
Prior art keywords
metal layer
board room
board
protection
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121463804.7U
Other languages
Chinese (zh)
Inventor
张善硕
夏文
骆俊竹
赵琳
廖裕海
黄国森
刘琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN202121463804.7U priority Critical patent/CN216042876U/en
Application granted granted Critical
Publication of CN216042876U publication Critical patent/CN216042876U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model discloses a protection shed for a board house in a construction site, which is used for being installed at the top of the board house and comprises: a protection plate; the support assemblies are arranged at the bottoms of the protection plates; and the fastening assembly is arranged at the bottom of the supporting assembly and is used for being connected with the board room. According to the utility model, the protection plate is arranged at the top of the board room through the supporting component and the fastening component, the crane construction is not required, the construction difficulty is reduced, the potential safety hazard of hoisting operation is eliminated, the protection plate is directly arranged on the board room, and no extra construction space is required, so that the occupied construction site area can be reduced.

Description

Building site board house protection canopy
Technical Field
The utility model relates to the technical field of building construction, in particular to a protective shed for a board house in a construction site.
Background
In the process of building construction, a tower crane is generally required to be installed as vertical transportation equipment of construction materials in the main structure and decoration construction stage. The operation radius of the tower crane covers the movable board house in a living area, and the construction site environment is complex, so that the phenomenon of falling objects frequently exists, and potential safety hazards exist.
In order to increase the safety factor of the site office or living board house, a protective shed is additionally arranged after the board house is installed, so that the office or living safety of managers is guaranteed. At present, traditional board house protection canopy needs to utilize board house ground all around as the basis of protection canopy because of the component is great to accomplish the installation of protection canopy through the mode of hoist and mount assembly. However, the existing protection shed is not only difficult to construct, but also needs to occupy additional construction site area.
Accordingly, the prior art is yet to be improved and developed.
SUMMERY OF THE UTILITY MODEL
In view of the defects of the prior art, the utility model aims to provide a protection shed for a board house in a construction site, so as to solve the problems that the existing protection shed is difficult to construct and needs to occupy additional construction site area.
The technical scheme of the utility model is as follows:
a building site board room protection canopy for install to the board room top, it includes:
a protection plate;
the support assemblies are arranged at the bottoms of the protection plates;
and the fastening assembly is arranged at the bottom of the supporting assembly and is used for being connected with the board room.
In a further aspect of the utility model, the protection plate comprises:
a first metal layer;
the buffer layer is arranged at the bottom of the first metal layer;
the second metal layer is arranged at the bottom of the buffer layer;
wherein the support component is connected with the second metal layer.
According to a further arrangement of the present invention, the first metal layer is a metal layer made of an aluminum alloy plate; the second metal layer is made of an aluminum alloy plate.
According to a further development of the utility model, the buffer layer is made of foamed plastic.
In a further arrangement of the utility model, the support assembly comprises:
a support connected to the second metal layer;
and the fixing plate is arranged at the bottom of the support piece and is used for being connected with the board room.
According to the utility model, the supporting piece is a square steel pipe.
In a further arrangement of the utility model, the fastening assembly comprises:
fastening a bolt;
the nut is in threaded connection with the fastening bolt;
two metal washers disposed on the fastening bolt;
and the sealing washer is arranged on the fastening bolt and is positioned between the two metal washers.
According to the further arrangement of the utility model, a first through hole is formed in the fixing plate, and the fastening bolt penetrates through the first through hole.
According to a further arrangement of the present invention, the metal gasket is a galvanized steel gasket; the sealing washer is a rubber washer.
According to a further development of the utility model, the fastening plate is connected to the support in a welded manner; the support and the second metal layer are connected in a welding mode.
The utility model provides a protection shed for a board house in a construction site, which is used for being installed at the top of the board house and comprises: a protection plate; the support assemblies are arranged at the bottoms of the protection plates; and the fastening assembly is arranged at the bottom of the supporting assembly and is used for being connected with the board room. According to the utility model, the protection plate is arranged at the top of the board room through the supporting component and the fastening component, the crane construction is not required, the construction difficulty is reduced, the potential safety hazard of hoisting operation is eliminated, the protection plate is directly arranged on the board room, and no extra construction space is required, so that the occupied construction site area can be reduced.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the structures shown in the drawings without creative efforts.
FIG. 1 is a schematic view of the overall structure of the shelter of the construction site plank house of the present invention.
Fig. 2 is a schematic view of the connection between the shelter and the board room in the construction site.
Fig. 3 is a schematic structural view of a guard plate according to the present invention.
Fig. 4 is a schematic structural view of the support assembly of the present invention.
Fig. 5 is a schematic view of the construction of the fastening assembly of the present invention.
The various symbols in the drawings: 100. a protection plate; 101. a first metal layer; 102. a buffer layer; 103. a second metal layer; 200. a support assembly; 201. a support member; 202. a fixing plate; 2021. a first through hole; 300. a fastening assembly; 301. fastening a bolt; 302. a nut; 303. a metal washer; 304. a sealing gasket; 400. a board house.
Detailed Description
The utility model provides a protective shed for a construction site plank house, which is further described in detail below by referring to the attached drawings and examples in order to make the purpose, technical scheme and effect of the utility model clearer and clearer. It should be understood that the specific embodiments described herein are merely illustrative of the utility model and are not intended to limit the utility model.
In the embodiments and claims, the articles "a", "an", "the" and "the" may include plural forms as well, unless the context specifically dictates otherwise. If there is a description of "first", "second", etc. in an embodiment of the present invention, the description of "first", "second", etc. is for descriptive purposes only and is not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one such feature.
It will be further understood that the terms "comprises" and/or "comprising," when used in this specification, specify the presence of stated features, integers, steps, operations, elements, and/or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and/or groups thereof. It will be understood that when an element is referred to as being "connected" or "coupled" to another element, it can be directly connected or coupled to the other element or intervening elements may also be present. Further, "connected" or "coupled" as used herein may include wirelessly connected or wirelessly coupled. As used herein, the term "and/or" includes all or any element and all combinations of one or more of the associated listed items.
It will be understood by those skilled in the art that, unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. It will be further understood that terms, such as those defined in commonly used dictionaries, should be interpreted as having a meaning that is consistent with their meaning in the context of the prior art and will not be interpreted in an idealized or overly formal sense unless expressly so defined herein.
In addition, technical solutions between various embodiments may be combined with each other, but must be realized by a person skilled in the art, and when the technical solutions are contradictory or cannot be realized, such a combination should not be considered to exist, and is not within the protection scope of the present invention.
Referring to fig. 1 to 5, the present invention provides a protection shed for a building site plank house according to a preferred embodiment.
As shown in fig. 1 and 2, the present invention provides a site board room protection shed which can be used to be installed on top of a board room 400 to secure the board room 400. Wherein, building site board house protection canopy includes: the fender 100, the support assembly 200 and the fastening assembly 300. Wherein, the support assemblies 200 are provided with a plurality of groups and are arranged at the bottom of the protection plate 100, and the fastening assemblies 300 are arranged at the bottom of the support assemblies 200 and are used for connecting with the board room 400.
Specifically, the protection plate 100 has a square structure, the support assemblies 200 are disposed at the bottom of four corners of the protection plate 100 to support the protection plate 100, so that a certain space is formed between the protection plate 100 and the board room 400 and a certain buffering effect is achieved, and the fastening assemblies 300 are used to connect the board room 400 and the support assemblies 200 so that the protection plate and the board room 400 are fixed together. The protection plate 100 is used as a main impact-resistant component, and can play a good energy-absorbing role when the board room 400 is hit by a falling object, so that the board room 400 is prevented from being damaged.
In the technical scheme, the protection plate 100 is arranged at the top of the board room 400 through the supporting component 200 and the fastening component 300, compared with the traditional protection shed, the protection shed is light in weight, does not need to be constructed by a crane, reduces construction difficulty, saves crane leasing cost, can be completed by manpower in the installation process, reduces construction requirements, and eliminates potential safety hazards of hoisting operation. In addition, the protection plate 100 is directly installed on the board room 400, and does not need to occupy additional construction space, so that the occupied construction site area can be reduced, and the protection plate is particularly suitable for projects in urban central zones with narrow sites.
Referring to fig. 2 and 3, in a further implementation of an embodiment, the protection plate 100 includes: a first metal layer 101, a buffer layer 102 and a second metal layer 103. The buffer layer 102 is disposed at the bottom of the first metal layer 101, and the second metal layer 103 is disposed at the bottom of the buffer layer 102. Wherein the support member 200 is connected to the second metal layer 103.
Specifically, the first metal layer 101 is a metal layer made of an aluminum alloy plate or a galvanized steel sheet, and the second metal layer 103 is a metal layer made of an aluminum alloy plate or a galvanized steel sheet, for example, the first metal layer 101 and the second metal layer 103 are both formed by processing an aluminum alloy plate through a stamping process, i.e., a cutting process. In one implementation, the length, width, and height of the first metal layer 101 and the second metal layer 103 may be 1200mm, and 2mm, respectively. The buffer layer 102 is made of foam, for example, the buffer layer 102 may be made of foam material by cutting process, wherein the foam material may be any one of PU material, PS material or PE material. In one implementation, the buffer layer 102 may be a cuboid structure cut from a PU material and having a length, a width, and a height of 1200mm, and 96mm, respectively. In the installation process, the upper and lower surfaces of the buffer layer 102 are respectively bonded to the first metal layer 101 and the second metal layer 103 to form the protection plate 100, wherein a dedicated foam adhesive (e.g., HY-T160) may be used to bond the first metal layer 101 and the buffer layer 102 and the second metal layer 103 and the buffer layer 102. It can be seen that the central portion of the protection plate 100 is made of a light foam material, the upper and lower layers are made of metal layers with high hardness, the metal layers can prevent the protection layer from being damaged by impact, and the buffer layer 102 can play a role in buffering and can absorb part of impact energy. In addition, the center of the protection plate 100 is made of foam material, so that the weight of the protection plate 100 can be reduced, constructors can conveniently carry the protection plate, the construction difficulty is reduced, compared with the traditional protection shed, the protection shed has smaller components, and the cost for purchasing materials is lower. Moreover, the installation process of the protection plate 100 is also simple, and the second metal layer 103 and the support assembly 200 are directly fixed together.
It should be noted that, for the convenience of transportation and installation of the shelter, the area of the protection plate 100 is generally smaller than the top area of the board room 400, and the weight and the volume are both smaller, so that a plurality of protection plates 100 can be installed by splicing together to form a board room protection system, so as to be suitable for board rooms of various sizes.
It should be further noted that the number of layers of the protection plate 100 may be adjusted appropriately, for example, the number of metal layers or buffer layers may be increased.
Referring to fig. 2 and 4, in a further implementation of one embodiment, the support assembly 200 includes: a support member 201 and a fixing plate 202. Wherein the supporting member 201 is connected to the second metal layer 103, and the fixing plate 202 is disposed at the bottom of the supporting member 201 and is used for connecting to the board house 400.
In particular, the support member 201 may be a square steel pipe, for example, an aluminum alloy square steel with an opening of 30 × 1 may be processed by a cutting process, and in one implementation, the square steel pipe may be cut into a length of 100 mm. The fixing plate 202 may be an aluminum alloy plate, and may be formed by cutting an aluminum alloy plate with a thickness of 3 mm. In some embodiments, the supporting member 201 and the fixing plate 202 are connected together by a welding process to form a whole, and the welded supporting member 201 and the fixing plate 202 form a leg to support the fender 100, wherein the supporting member 201 can play a certain role in buffering.
In some embodiments, the supporting member 201 is connected to the second metal layer 103 by welding to ensure the stability of the installation between the protection plate 100 and the supporting member 200.
It should be noted that the protection plate 100 can also be directly connected with the top plate of the board room 400, that is, the support member 201 is not needed for transition, and the protection plate 100 is directly bonded with the top plate of the board room 400, although the protection effect can be achieved, the installation stability of the protection plate 100 is poor, and the protection effect is relatively weak.
Referring to fig. 2 and 5, in a further implementation of one embodiment, the fastening assembly 300 includes: a fastening bolt 301, a nut 302, two metal washers 303, and a sealing washer 304. The nut 302 is in threaded connection with the fastening bolt 301, the metal washer 303 is disposed on the fastening bolt 301, and the sealing washer 304 is disposed on the fastening bolt 301 and between the two metal washers 303.
Specifically, the fixing plate 202 is provided with a first through hole 2021, and the fastening bolt 301 is inserted into the first through hole 2021 to connect the fixing plate 202 and the top of the board room 400, so as to connect the protection board 100 and the board room 400 together. The nuts 302 are located below the fixing plate 202 and the board room 400, one of the metal washers 303 is located between the fixing plate 202 and the nuts 302, and the other metal washer 303 is located between the fixing plate 202 and the nut of the fastening bolt 301, and the metal washer 303 is disposed on the fastening bolt 301, so that the connection stability between the fixing plate 202 and the board room 400 can be enhanced. In addition, the sealing washer 304 is located between the fixing plate 202 and the metal washer 303 located between the fixing plate 202 and the nut of the fastening bolt 301, and may perform a sealing and water-proof function.
In some embodiments, the fastening bolt 301 is a M6 bolt, the length is selected according to the thickness of the top of the board room 400, and the nut 302 is adapted to the fastening bolt 301. In some embodiments, the metal gasket 303 may be a 1mm thick galvanized steel gasket, such as a 7mm inner diameter and a 14mm outer diameter galvanized steel gasket, and the sealing gasket 304 may be a 3mm thick rubber gasket, such as a silicone rubber gasket, a nitrile rubber gasket, or the like.
In conclusion, the protection shed for the construction site plank house provided by the utility model has the following beneficial effects: the protection plate is arranged at the top of the board room through the supporting component and the fixing component, compared with the traditional protection shed, the protection shed is light in weight, does not need to be constructed by a crane, reduces the construction difficulty, saves the crane leasing cost, can be completed by only manpower in the installation process, reduces the construction requirement, and eliminates the potential safety hazard of hoisting operation; the protective plate is directly installed on the board house, and extra construction space is not required to be occupied, so that the occupied construction site area can be reduced, and the protective plate is particularly suitable for projects in downtown areas with narrow sites; a plurality of protection plates are spliced and installed to form a board room protection system, so that the board rooms of different sizes can be adapted.
It is to be understood that the utility model is not limited to the examples described above, but that modifications and variations may be effected thereto by those of ordinary skill in the art in light of the foregoing description, and that all such modifications and variations are intended to be within the scope of the utility model as defined by the appended claims.

Claims (10)

1. The utility model provides a building site board house protection canopy for install to the board house top, its characterized in that includes:
a protection plate;
the support assemblies are arranged at the bottoms of the protection plates;
and the fastening assembly is arranged at the bottom of the supporting assembly and is used for being connected with the board room.
2. The worksite board room shelter of claim 1, wherein the protection plate comprises:
a first metal layer;
the buffer layer is arranged at the bottom of the first metal layer;
the second metal layer is arranged at the bottom of the buffer layer;
wherein the support component is connected with the second metal layer.
3. The worksite board room shelter of claim 2, wherein the first metal layer is a metal layer made of an aluminum alloy plate; the second metal layer is made of an aluminum alloy plate.
4. The worksite board room shelter of claim 2, wherein the cushioning layer is a foam cushioning layer.
5. The worksite board room shelter of claim 2, wherein the support assembly comprises:
a support connected to the second metal layer;
and the fixing plate is arranged at the bottom of the support piece and is used for being connected with the board room.
6. The site shelter of claim 5, wherein the support member is a square steel tube.
7. The worksite board room shelter of claim 5, wherein the fastening assembly comprises:
fastening a bolt;
the nut is in threaded connection with the fastening bolt;
two metal washers disposed on the fastening bolt;
and the sealing washer is arranged on the fastening bolt and is positioned between the two metal washers.
8. The shelter of claim 7, wherein the fixing plate is provided with a first through hole, and the fastening bolt is arranged through the first through hole.
9. The worksite board room shelter of claim 7, wherein the metal gasket is a galvanized steel gasket; the sealing washer is a rubber washer.
10. The worksite board room shelter of claim 5, wherein the fixing plate is connected with the support in a welded manner; the support and the second metal layer are connected in a welding mode.
CN202121463804.7U 2021-06-29 2021-06-29 Building site board house protection canopy Expired - Fee Related CN216042876U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121463804.7U CN216042876U (en) 2021-06-29 2021-06-29 Building site board house protection canopy

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121463804.7U CN216042876U (en) 2021-06-29 2021-06-29 Building site board house protection canopy

Publications (1)

Publication Number Publication Date
CN216042876U true CN216042876U (en) 2022-03-15

Family

ID=80554492

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121463804.7U Expired - Fee Related CN216042876U (en) 2021-06-29 2021-06-29 Building site board house protection canopy

Country Status (1)

Country Link
CN (1) CN216042876U (en)

Similar Documents

Publication Publication Date Title
JP2020528974A (en) Damping mesosphere embedded double steel plate concrete composite assembly type shear wall and its mounting method
KR101927204B1 (en) Toilet for container house with earthquake-proof device
CN217811697U (en) Assembled building side fascia with sound insulation function
CN216042876U (en) Building site board house protection canopy
CN211817259U (en) Bidirectional damping connecting device for aerated concrete externally-hung wall plate
CN211313085U (en) Steel structure box column member
KR101924135B1 (en) Wall structure of container house with seismic device
JP3162410U (en) Solar panel support structure
CN212613011U (en) Assembled shock attenuation frame
JP2002088721A (en) Sound insulating wall panel and its mounting method
KR101924136B1 (en) Container house with seismic device
CN220190436U (en) Visual cable trench cover plate
JP2019199920A (en) Frame
CN213062593U (en) Hoisting hole plugging structure
JP7400779B2 (en) Building
CN215106637U (en) Round glass ceiling connecting structure
CN219638131U (en) Support-bracket-connection cushion block coupling structure
CN213205147U (en) Roof truss support member
CN209742251U (en) Gutter
CN217027662U (en) Inhaul cable and glass rib composite supporting structure based on full-glass curtain wall
CN210508102U (en) Waterproof node of steel construction roofing
CN212957101U (en) Connecting device for upper and lower wall bodies of steel structure building
CN211714476U (en) All-aluminum honeycomb antistatic floor
KR101923558B1 (en) Toilet for container house with earthquake-proof device
CN210289369U (en) Novel glass steel keeps out wind and presses down dirt wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220315

CF01 Termination of patent right due to non-payment of annual fee