CN215977337U - Composite sandwich liner barrier type impervious wall - Google Patents

Composite sandwich liner barrier type impervious wall Download PDF

Info

Publication number
CN215977337U
CN215977337U CN202122500913.8U CN202122500913U CN215977337U CN 215977337 U CN215977337 U CN 215977337U CN 202122500913 U CN202122500913 U CN 202122500913U CN 215977337 U CN215977337 U CN 215977337U
Authority
CN
China
Prior art keywords
natural
layer
seepage
geomembrane
composite sandwich
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122500913.8U
Other languages
Chinese (zh)
Inventor
徐磊
易伟功
谢世平
杨柱
朱承敏
高超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Institute of Mining Research Co Ltd
Original Assignee
Changsha Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Institute of Mining Research Co Ltd filed Critical Changsha Institute of Mining Research Co Ltd
Priority to CN202122500913.8U priority Critical patent/CN215977337U/en
Application granted granted Critical
Publication of CN215977337U publication Critical patent/CN215977337U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model discloses a composite sandwich liner barrier type impervious wall, which comprises: 2 natural impervious material layers and geomembrane layers are laid along the seepage side slope, the geomembrane layer is clamped in the 2 natural impervious material layers, and an anchoring ditch is arranged at the platform position of the side slope and used for fixing the geomembrane. The utility model equally divides the natural anti-seepage material into two parts according to the thickness for construction, the two parts are divided into a lower half part and an upper half part, the artificial anti-seepage material is evenly paved on the natural anti-seepage material after the lower half part is constructed, then the upper half part of the natural anti-seepage material is constructed, and the artificial material is constructed into the natural material in a sandwich mode to form the composite sandwich lining barrier which achieves the anti-seepage effect. The two materials are combined together, and the artificial material is embedded into a natural material as a sandwich, so that the method can overcome the risk that the permeability coefficient is smaller and the service life is longer, and can solve the problems of poor anti-cracking performance and poor shear strength capability.

Description

Composite sandwich liner barrier type impervious wall
Technical Field
The utility model belongs to the technical field of diaphragm wall construction, and particularly relates to a composite sandwich liner barrier type diaphragm wall.
Background
Seepage prevention is one of the key problems to be faced and solved in various engineering fields such as water conservancy, open mines, refuse landfills, tailings, industrial waste storage yards, urban construction and the like. Seepage of reservoir dam side slopes is often the direct cause of piping and dam break; the seepage of the surface mine side slope increases the drainage cost and mining difficulty of a pit on one hand, and on the other hand, the seepage reduces the rock mass mechanical property of the side slope, so that the side slope instability is easily caused; harmful ingredients in the refuse landfill, the tailings and the industrial waste storage yard flow into a peripheral aquifer along with water flow through a seepage channel of the side slope, so that the pollution is caused to the underground water nearby the aquifer; collapse of urban underground engineering slopes and debris flow geological disasters are mostly caused by underground water leakage. Through long-term engineering practice and research, new technology, new materials and new process for slope seepage-proofing treatment are continuously developed, and according to the current technical situation at home and abroad, the slope seepage-proofing technology mainly comprises three categories of underground grouting water-plugging curtains, underground continuous walls and lining barrier type seepage-proofing walls.
In the construction process of seepage-proofing engineering, the underground water-plugging curtain has the advantages of simple operation environment, small construction difficulty and the like, but the water-plugging rate of the method is not very high, so that the permeability coefficient of the curtain body formed by the method is generally larger and not less than 10-5cm/s, which can not meet the requirements for certain seepage-proofing construction with higher requirements; the underground continuous wall forms a path with smaller permeability coefficient (10)-7cm/s) and more stable, but are subject toConstruction conditions are influenced, construction difficulty is high, and construction cost is high; the liner barrier type impervious wall has the advantages of convenient construction and low cost, the impervious materials of the liner barrier type impervious wall are natural and artificial, the impervious wall formed by natural materials also has the problems of overlarge permeability coefficient and short service life of being easily eroded by water, the artificial materials have higher impervious performance, the permeability coefficient is smaller, the service life of being not easily eroded by water is longer, but the artificial materials have poorer anti-dry cracking performance and shear strength capability, and the anti-deformation capability of not generating cracks when the artificial materials are subjected to interface friction and settlement with other impervious materials covered on the surface of the artificial materials.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a composite sandwich liner barrier type impervious wall with good dry cracking resistance, good shear strength and good seepage resistance.
The composite sandwich liner barrier type impervious wall comprises 2 natural impervious material layers and a geomembrane layer, wherein the 2 natural impervious material layers and the geomembrane layer are laid along a seepage side slope, the geomembrane layer is clamped in the 2 natural impervious material layers, and an anchoring ditch is formed in the platform position of the side slope and used for fixing the geomembrane.
Preferably, the composite sandwich liner barrier type impervious wall further comprises a buffer barrier arranged at the bottom of the side slope.
The natural impermeable material layer is a clay layer or a bentonite layer, and is preferably a clay layer; the geomembrane layer is an HDPE film layer, and preferably has two rough surfaces with the thickness of 2 mm.
The buffer barrier is a pollution-free benign waste stone layer, and the thickness of the buffer barrier is more than or equal to 5 m.
The geomembrane is fixed in an anchoring mode or a ballasting mode in the anchoring ditch.
In the geomembrane construction process, the lap joint between the geomembranes adopts double-track welding, and the connecting part between the geomembranes needs to be controlled at the position of the anchoring ditch, so that transverse welding seams do not appear on the side slope as much as possible.
The water content of the natural impermeable material is controlled to be 16.5-22.0%, and the total thickness of the 2 layers of natural impermeable material layers is more than or equal to 10 m.
The utility model has the beneficial effects that: the utility model equally divides the natural anti-seepage material into two parts according to the thickness for construction, the two parts are divided into a lower half part and an upper half part, the artificial anti-seepage material is evenly paved on the natural anti-seepage material after the lower half part is constructed, then the upper half part of the natural anti-seepage material is constructed, and the artificial material is constructed into the natural material in a sandwich mode to form the composite sandwich lining barrier which achieves the anti-seepage effect. The two materials are combined together, and the artificial material is embedded into a natural material as a sandwich, so that the method can overcome the risk that the permeability coefficient is smaller and the service life is longer, and can solve the problems of poor anti-cracking performance and poor shear strength capability.
Drawings
FIG. 1 is a schematic structural view of an anti-seepage wall;
wherein: 1. leaking the side slope; 2. the lower half part of the natural impermeable material layer; 3. a geomembrane layer; 4. the upper half part of the natural impermeable material layer; 5. buffering the barrier; 6. and (6) anchoring the ditch.
Detailed Description
Example 1
Taking a certain slope seepage-proofing project as an example, the structure schematic diagram of the seepage-proofing wall is shown in fig. 1, and the specific construction process is as follows:
the method comprises the following steps: designing the impervious wall: the design slope ratio of the impervious wall is less than or equal to 1:2, the horizontal total thickness of the natural impervious material layer 4 on the upper half part and the natural impervious material layer on the lower half part is more than or equal to 10m, the natural impervious material layer adopts clay as a material, and the geomembrane adopts a high-density polyethylene geomembrane (HDPE) with 2mm thick double rough surfaces. The construction process of the impervious wall comprises the following steps: the method comprises the following steps: constructing a buffer barrier 6+ the lower half part of the natural impermeable material layer 2, laying and welding the geomembrane layer 3, and constructing the upper half part of the natural impermeable material layer 4.
Step two: construction of buffer barrier 6+ lower half part natural impermeable material layer 2
(1) The filling construction preparation comprises the steps of firstly, completely cleaning loose blocks of andesite rocks (bottom boundaries of the impervious walls) on the side slopes by using a hydraulic stone breaking machine before filling the impervious walls, cleaning the loose blocks by using a high-pressure water gun without other sundries such as broken stones, slurry and the like, carrying out combined concealed engineering acceptance after cleaning, and filling clay wall materials after acceptance.
(2) And (3) measurement and paying-off: because the slope ratio of the lower impervious wall is 1:2, the initial elevation is low in the north and the south, and the slope change of the east side slope of the S pit is large under the current situation, the bottom edge boundary line of each filling area needs to be measured and determined according to the design requirements in different areas, the bottom edge boundary line is marked by using piles or lime spraying lines, and the impervious wall is filled according to the designed slope ratio by paying off every 2m in the wall filling process.
(3) Filling of the buffer barrier: at the bottom of the impervious wall, a layer of non-pollution benign waste rock (NAF) with the thickness of 5m is filled firstly to be used as a first buffer barrier 5 between the acidic waste rock and the impervious wall body. The layer is compacted in a backfill process, and the layering thickness is 0.5-1 m.
(4) And (3) constructing the lower half part of the natural impermeable material layer 2:
4.1 soil body spreading: clay materials are paved along the slope trend of the impervious wall, the once paving thickness is controlled to be 30cm, soil materials are paved and leveled by a bulldozer and a loader, and the paving thickness is measured at any time, so that the uniformity of thick soil materials is ensured;
4.2 soil moisture content control: according to the results of the indoor geotechnical tests, the optimal water content is controlled to be 16.5-17.8%. The water amount of sprinkling is according to the design standard and the rolling test result, the climatic conditions of Burma high temperature are considered, and the actual soil requires that the water content is higher than the optimal water content (+ 1% -3%). According to the rolling test data and the characteristics of the engineering terrain, water in the slope intercepting ditch is utilized, and two sets of water spraying pipelines are adopted to properly add water to the incoming soil on the working face.
4.3 rolling the soil body: the rolling is carried out along the axial direction of the wall body by adopting a 15t bump vibration rolling mode, wherein the rolling mode is a forward-backward offset method, and the offset width is 0.27 cm. Preliminarily determining that rolling is carried out for 8 times, alternately carrying out static pressure and vibration, carrying out static pressure for 4 times and vibrating for 4 times, determining the actual rolling times according to a field compaction test, and controlling the rolling walking speed to be 2.5 km/h. Tamping the corner parts by a frog rammer. The soil body compactness is not less than 95%.
4.4 on-site detection in the soil compaction process, every time in the soil compaction process of the wall bodyThe soil material of 3 ten thousand squares is subjected to a group of clay undisturbed sample soil working tests, and the particle size distribution, the natural water content, the plastic limit and the liquid limit of the soil body, the optimal water content and the maximum dry density of the soil body are measured. Each layer is 50m2And one group of cutting ring samples are adopted on site, and the compactness and the dry density are detected on site. Soil samples should be collected for further testing; the wall body is filled by adopting sectional flow line production, and the wall body rises uniformly;
4.5 repeating the steps 4.1-4.4 until the thickness of the clay layer reaches 5m, and obtaining a clay layer which is the lower half part of the natural impermeable material layer 2.
Step three: laying and welding geomembrane
(1) And the lower half part of the natural impermeable material layer 2 is compacted to be qualified, after slope repairing, the lower half part of the natural impermeable material layer reports to the supervision and the acceptance of an owner, sharp sundries such as broken stones, rubbles, root hairs, reinforced concrete particles or glass fragments and the like can not appear on the inner side compacted clay slope surface contacted with the geomembrane, and after the acceptance is qualified, the HDPE impermeable film is laid.
(2) The type, specification and quality of the HDPE impermeable membrane are subjected to standardized inspection before construction, the inspection and acceptance of the impermeable membrane are strictly in accordance with relevant standard standards, and the impermeable membrane is accepted and used after being qualified.
(3) Laying an HDPE impermeable film: after the roll-pressing slope repairing of the inner side impervious wall is finished (one subsection is 5-6 m high), the geomembrane is laid along the axial direction of the impervious wall, smooth and solid laying is carried out, wrinkles are reduced as much as possible, and the geomembrane is timely ballasted or anchored after the laying. When the construction is carried out on a side slope, the soft climbing ladder is adopted to ascend and descend.
(4) The fixing of the earth work die (HDPE) is realized through an anchoring ditch, every 5m (vertical height) utilizes a 5m wide soil platform filled on the inner side of the side slope as an anchoring platform, the size of the anchoring ditch is 1m (width) multiplied by 1m (depth), the reserved amount of the seepage-proofing material is anchored in the anchoring ditch, and the seepage-proofing material is turned out after the construction of the next stage and is connected with the seepage-proofing material of the next stage. Meanwhile, the part of the anchoring ditch is used as the position of the upper roll and the lower roll of the geomembrane for transverse welding joints.
(5) The geomembrane welding is from bottom to top, and transverse welding seams do not appear on the side slope as much as possible. Two connected rolls of transverse joints are arranged in the anchoring ditch as much as possible, and adjacent seams are staggered by more than 1 m.
(6) The overlapping of the HDPE anti-seepage films is welded by adopting a hot melting double rail of an HDPE anti-seepage film automatic welding machine, the welding width is 10cm, and the allowable error is 2 cm. The welding should be carried out at 40 ℃ avoiding the high noon time in the mine.
(7) The welding rod material used for connecting the HDPE anti-seepage film and the HDPE anti-seepage film are made of the same material and are produced by the same material in the same factory, and substitute welding rods cannot be adopted.
(10) And (3) air tightness detection: and the air tightness is detected by an air pressure detector. And (3) forming a double-track welding line by hot melting welding, reserving an air cavity in the middle of the welding line, plugging two ends of the welding line air cavity after one welding line is constructed, pressurizing the welding line air cavity to 250kPa by using a pressure detector, maintaining for 3-5 min, wherein the air pressure is not lower than 240kPa, then opening a hole at the other end of the welding line to deflate, and rapidly returning to zero to be qualified by using an air pressure gauge pointer. The needle hole left by the air pressure detection must be sealed by welding.
Step four, constructing the upper half natural impervious material layer 4
4.1 soil body spreading: clay materials are paved on the geomembrane along the slope direction of the impervious wall, the thickness of the paving materials at one time is controlled to be 30cm, soil materials are paved and leveled by a bulldozer and a loader, and the thickness of the paving materials is measured at any time, so that the uniformity of thick soil materials is ensured;
4.2 soil moisture content control: according to the results of the indoor geotechnical tests, the optimal water content is controlled to be 16.5-17.8%. The water amount of sprinkling is according to the design standard and the rolling test result, the climatic conditions of Burma high temperature are considered, and the actual soil requires that the water content is higher than the optimal water content (+ 1% -3%). According to the rolling test data and the characteristics of the engineering terrain, water in the slope intercepting ditch is utilized, and two sets of water spraying pipelines are adopted to properly add water to the incoming soil on the working face.
4.3 rolling the soil body: the rolling is carried out along the axial direction of the wall body by adopting a 15t bump vibration rolling mode, wherein the rolling mode is a forward-backward offset method, and the offset width is 0.27 cm. Preliminarily determining that rolling is carried out for 8 times, alternately carrying out static pressure and vibration, carrying out static pressure for 4 times and vibrating for 4 times, determining the actual rolling times according to a field compaction test, and controlling the rolling walking speed to be 2.5 km/h. Tamping the corner parts by a frog rammer. The soil body compactness is not less than 95%.
4.4 field detection in the soil body rolling process, in the wall body soil compaction process, performing a group of clay undisturbed sample soil working tests every 3 ten thousand square of soil materials, and determining the particle size distribution, the natural water content, the plastic limit and the liquid limit of the soil body, the optimal water content and the maximum dry density of the soil body. Each layer is 50m2And one group of cutting ring samples are adopted on site, and the compactness and the dry density are detected on site. Soil samples should be collected for further testing; the wall body is filled by adopting sectional flow line production, and the wall body rises uniformly;
4.5 repeating the steps 4.1-4.4 until the thickness of the clay layer reaches 5m, and obtaining a clay layer which is the lower half part of the natural impermeable material layer 4.
The structure of the diaphragm wall obtained after construction is shown in figure 1, a layer of waste rock buffer barrier 5 with the thickness of 5m is filled at the bottom boundary of a seepage side slope 1, a layer of lower half part natural seepage-proof material layer 2 is rolled and filled along the slope of the seepage side slope 1, a layer of geomembrane layer 3 is laid on the lower half part natural seepage-proof material layer 2, and the geomembrane layer 3 is fixed on the side slope in a ballasting or anchoring mode through an anchoring ditch 6; the anchoring ditch 6 is arranged at the platform position of the seepage side slope 1; the geomembrane layer 3 is filled with an upper half part of a natural impermeable material layer 4 in a rolling way.
Through tests, compared with the common construction method, the impervious wall structure in the embodiment can save impervious materials, has good impervious effect, and the saturated impervious coefficient of the impervious wall is less than 1 multiplied by 10-9cm/s, long service life of the impervious wall, and 100 years of endurance life.

Claims (8)

1. A composite sandwich liner barrier type impervious wall is characterized by comprising: 2 natural impervious material layers and geomembrane layers are laid along the seepage side slope, the geomembrane layer is clamped in the 2 natural impervious material layers, and an anchoring ditch is arranged at the platform position of the side slope and used for fixing the geomembrane layer.
2. The composite sandwich liner barrier type cutoff wall of claim 1, wherein the cutoff wall further comprises a cushioning barrier disposed at the bottom of the slope.
3. The composite sandwich liner barrier type impermeable wall according to claim 1, wherein the natural impermeable material layer is a clay layer or a bentonite layer, and the geomembrane layer is an HDPE film layer.
4. The composite sandwich liner barrier diaphragm headwall of claim 3, wherein the natural barrier material layer is a clay layer and the HDPE film layer is a double-sided HDPE film having a thickness of 2 mm.
5. The composite sandwich liner barrier type impermeable wall as claimed in claim 2, wherein the buffer barrier is a pollution-free benign waste stone layer with a thickness of more than or equal to 5 m.
6. The composite sandwich liner barrier diaphragm headwall of claim 1 wherein the geomembrane is anchored or ballasted in the anchoring trench.
7. The composite sandwich liner barrier type impermeable wall according to claim 6, wherein during the construction of the geomembranes, the overlapping joints between the geomembranes are welded by adopting double rails, the positions of the connecting parts between the geomembranes are required to be controlled at the anchoring ditches, and transverse welding seams on the side slopes are avoided as far as possible.
8. The composite sandwich liner barrier type impervious wall as claimed in claim 1, wherein the water content of the natural impervious material is controlled to be 16.5-22.0%, and the total thickness of the 2 layers of natural impervious material layers is more than or equal to 10 m.
CN202122500913.8U 2021-10-18 2021-10-18 Composite sandwich liner barrier type impervious wall Active CN215977337U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122500913.8U CN215977337U (en) 2021-10-18 2021-10-18 Composite sandwich liner barrier type impervious wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122500913.8U CN215977337U (en) 2021-10-18 2021-10-18 Composite sandwich liner barrier type impervious wall

Publications (1)

Publication Number Publication Date
CN215977337U true CN215977337U (en) 2022-03-08

Family

ID=80573216

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122500913.8U Active CN215977337U (en) 2021-10-18 2021-10-18 Composite sandwich liner barrier type impervious wall

Country Status (1)

Country Link
CN (1) CN215977337U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114837132A (en) * 2022-06-10 2022-08-02 河海大学 Shallow seawater intrusion prevention and control method based on anti-seepage geomembrane

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114837132A (en) * 2022-06-10 2022-08-02 河海大学 Shallow seawater intrusion prevention and control method based on anti-seepage geomembrane

Similar Documents

Publication Publication Date Title
CN110306616B (en) Construction method of sewage pipeline
CN102817366B (en) Prevention and treatment method for full-mechanized caving mining collapse trap area water disaster for shallow-buried ultra-thick coal seam
CN113445396B (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN104018485B (en) Bed course carbonization reinforcement means is filled out in changing of a kind of soft foundation
CN109736141A (en) The anti-freeze expansion structural body and paving method of Railway Roadbed in Permafrost Regions
CN101806055B (en) Vacuum pre-pressed joint rigid pile composite foundation reinforcing method
CN111851505A (en) Construction method and structure of pouring type impervious core earth-rock dam
CN215977337U (en) Composite sandwich liner barrier type impervious wall
CN106284434A (en) The anti-float method of a kind of underground structure and every oozing device
CN112523264B (en) High-steep side slope seepage prevention system and laying method thereof
CN207032212U (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN213143069U (en) Pouring type impervious core earth-rock dam structure
CN109469042A (en) Seepage-proofing karst cave processing structure for storage yard field area
CN112195965A (en) Expansive soil cutting retaining wall
CN107964843A (en) A kind of high-speed railway Karst Subgrade construction and its restorative procedure for having warning function
CN208455387U (en) Mountain highway, which is filled out, digs intersection road structure
CN110454189A (en) A kind of river tunnel Xia Chuan construction technology
CN215976663U (en) Excavation area composite foundation treatment structure crossing under high-voltage line
US11598065B2 (en) Method for stabilizing and lifting channel boards by underwater grouting
CN113700013A (en) High-pressure jet grouting and clay core wall combined earth-rock cofferdam seepage-proofing construction method
CN114277762A (en) Foundation treatment method for vibration control of power machine foundation
CN203741855U (en) Foundation pit waterproof curtain capable of being repaired manually and with multifunctional coagulation body with quickly hardening silica fume layer and integrating water guiding, discharging and filtering functions
CN209482289U (en) Seepage-proofing karst cave processing structure for storage yard field area
CN110512571B (en) Roller compacted concrete dam containing rock-fill concrete core wall and construction method thereof
CN113374055A (en) Construction method of buried reinforced HDPE (high-density polyethylene) spiral corrugated pipe

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant