CN215974057U - Belt conveyor in warehouse - Google Patents

Belt conveyor in warehouse Download PDF

Info

Publication number
CN215974057U
CN215974057U CN202122585068.9U CN202122585068U CN215974057U CN 215974057 U CN215974057 U CN 215974057U CN 202122585068 U CN202122585068 U CN 202122585068U CN 215974057 U CN215974057 U CN 215974057U
Authority
CN
China
Prior art keywords
tripper
unloader
materials
pipe
travelling crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122585068.9U
Other languages
Chinese (zh)
Inventor
牛卫波
史梦林
马建伟
王丽普
冯知通
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinxiang Xinding Machinery Co ltd
Original Assignee
Xinxiang Xinding Machinery Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinxiang Xinding Machinery Co ltd filed Critical Xinxiang Xinding Machinery Co ltd
Priority to CN202122585068.9U priority Critical patent/CN215974057U/en
Application granted granted Critical
Publication of CN215974057U publication Critical patent/CN215974057U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Intermediate Stations On Conveyors (AREA)

Abstract

The utility model discloses a belt conveyor in a storage, and relates to the technical field of belt conveyors. The utility model has reasonable design structure, can transfer materials from a feeding conveyor into a first unloader, then transfers the materials into a discharge trolley through a conveying hose, so that the movable travelling crane unloader can move in the front-back direction on two electric slide rails, and unloads the materials in the discharge trolley from the front side and the back side of the movable travelling crane unloader, meanwhile, the materials are discharged from the bottom of the movable travelling crane unloader through the operation of a second unloader, and the discharge trolley can also move left and right on the movable travelling crane unloader, so that the discharge trolley can move in the left-right direction of the storage bin, thereby realizing the high-altitude no-dead-angle discharge of the storage bin, increasing the stacking height of the materials and the volume ratio of the materials in the storage bin.

Description

Belt conveyor in warehouse
Technical Field
The utility model relates to the technical field of belt conveyors, in particular to a belt conveyor in a warehouse.
Background
The belt conveyor is widely applied to various industries such as household appliances, electronics, electrical appliances, machinery, tobacco, injection molding, post and telecommunications, printing, food and the like, and the assembly, detection, debugging, packaging, transportation and the like of objects.
Because the multiple spot is unloaded in the warehouse usually, so belt conveyor need dispose plough tripper or removal tripper to realize the multiple spot and unload in order to fill material warehouse, because tripper and tripper discharge point are more limited, usually in order to improve the material volume in warehouse, need the loader carry out the secondary transport, when piling up certain height with the material to needs, must give the loader headspace, the ability that the material of warehouse was stored just so greatly reduced. To this end, we provide a belt conveyor in a warehouse to solve the above problems.
SUMMERY OF THE UTILITY MODEL
One) technical problem to be solved
The utility model aims to make up for the defects of the prior art and provides a belt conveyor in a warehouse.
II) technical scheme
In order to achieve the purpose, the utility model provides the following technical scheme: the utility model provides a belt conveyor in feed bin, includes the feed bin, and the material loading conveyer is installed to the inner wall of feed bin, and the below of material loading conveyer is provided with portable driving unloader, and electronic slide rail is all installed to the both sides of feed bin inner wall, and the walking wheel is all installed to the left and right sides of portable driving unloader, and two walking wheels and two electronic slide rail sliding connection of feed bin inner wall, and the top of portable driving unloader is provided with the shedding mechanism of unloading to the material, and first tripper is installed at the top of material loading conveyer.
Further, shedding mechanism includes tripper, inlet pipe and defeated material hose, and the tripper is installed in the upper surface of portable driving unloader, and the inlet pipe is installed in the top of tripper, and the inlet pipe is linked together with the inside of tripper, and the top of defeated material hose is fixed with the defeated material end of first tripper and is linked together, and the bottom of defeated material hose is fixed with the top of inlet pipe and is linked together.
Further, shedding mechanism still includes row material pipe, second tripper, connecting cable rope and unloading pipe, and connecting cable rope installs in the bottom of tripper, and the second tripper is installed in the bottom of connecting cable rope, arranges the material pipe and fixes the defeated material end that communicates in the second tripper, and the bottom mounting of unloading pipe communicates in the feed end of second tripper, and the top of unloading pipe runs through portable driving unloader and is linked together with the inside discharge strip of tripper.
Thirdly), the beneficial effects are as follows:
compared with the prior art, the belt conveyor in the material warehouse has the following beneficial effects:
the utility model can transfer the materials from the feeding conveyor to the first discharger through the matching arrangement of the feeding conveyor, the movable travelling crane discharger, the travelling wheels, the electric slide rail, the first discharger and the discharging mechanism, then the materials are transferred into the discharging trolley through the material conveying hose, so that the movable travelling crane discharger can move in the front-back direction on the two electric slide rails, and the materials in the discharging trolley are discharged from the front side and the rear side of the movable travelling crane discharger, meanwhile, the materials are discharged from the bottom of the movable travelling crane unloader through the operation of the second unloader, and the dump car can be used for moving left and right on the movable travelling crane unloader so that the dump car can move in the left and right directions of the storage bin, therefore, the high-altitude dead-angle-free discharging of the storage bin is realized, the stacking height of materials is increased, and the volume rate of the materials in the storage bin is increased.
Drawings
FIG. 1 is a schematic front view of the present invention;
FIG. 2 is an enlarged view of the structure at A in FIG. 1 according to the present invention.
In the figure: 1. a storage bin; 2. a feeding conveyor; 3. the travelling crane unloader can be moved; 4. a traveling wheel; 5. an electric slide rail; 6. a first discharger; 7. a discharge mechanism; 71. a discharge trolley; 72. a feed pipe; 73. a discharge pipe; 74. a second discharger; 75. connecting a cable; 76. a discharging pipe; 77. a delivery hose.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1-2, the present invention provides a technical solution: a belt conveyor in a material warehouse comprises a material warehouse 1, a feeding conveyor 2 is arranged on the inner wall of the material warehouse 1, a movable travelling crane unloader 3 is arranged below the feeding conveyor 2, electric slide rails 5 are arranged on two sides of the inner wall of the material warehouse 1, the left side and the right side of the movable travelling crane unloader 3 are both provided with travelling wheels 4, and the two travelling wheels 4 are in sliding connection with two electric slide rails 5 on the inner wall of the storage bin 1, so that the two travelling wheels 4 can be driven to drive the movable travelling crane unloader 3 to move in the front-back direction in the storage bin 1 by utilizing the arrangement of the two electric slide rails 5, the top of portable driving tripper 3 is provided with the shedding mechanism 7 of unloading to the material, and first tripper 6 is installed at the top of material loading conveyor 2, can be with the material through the transport of material loading conveyor 2 down will fall to first tripper 6 in to subsequent unloading.
Discharge mechanism 7 includes tripper 71, inlet pipe 72 and defeated material hose 77, tripper 71 is installed in the upper surface of portable driving tripper 3, can will drive tripper 71 and remove in the left and right directions of feed bin 1 through the operation of portable driving tripper 3, inlet pipe 72 is installed in the top of tripper 71, and inlet pipe 72 is linked together with the inside of tripper 71, the top of defeated material hose 77 is fixed with the defeated material end of first tripper 6 and is linked together, the bottom of defeated material hose 77 is fixed with the top of inlet pipe 72 and is linked together, can carry the material after first tripper 6 is collected to inlet pipe 72 and tripper 71 in through defeated material hose 77, and defeated material hose 77 has tensile effect, consequently tripper 71 also can be normal when removing carry the material.
The discharging mechanism 7 further comprises a discharging pipe 73, a second discharger 74, a connecting cable 75 and a discharging pipe 76, the connecting cable 75 is installed at the bottom of the discharging trolley 71, so that the discharging trolley 71 can drive the connecting cable 75 to move when moving on the movable travelling crane discharger 3, the second discharger 74 is installed at the bottom of the connecting cable 75, so that the connecting cable 75 can fix the second discharger 74, the discharging pipe 73 is fixedly communicated with the conveying end of the second discharger 74, the bottom end of the discharging pipe 76 is fixedly communicated with the feeding end of the second discharger 74, the top end of the discharging pipe 76 penetrates through the movable travelling crane discharger 3 and is communicated with a discharging belt inside the discharging trolley 71, after materials are conveyed into the discharging trolley 71, part of the materials can be conveyed to the discharging pipe 73 through the discharging pipe 76, and then the materials are discharged from the bottom of the movable travelling crane discharger 3, thereby increasing the volume ratio of the materials.
Under setting up through the cooperation between the above structure, can be with the material from material loading conveyer 2 in transporting to first tripper 6, the material is in transporting to tripper 71 through defeated material hose 77 after that, make portable driving tripper 3 can carry out fore-and-aft direction's removal on two electric slide rail 5, and make the material in the tripper 71 unload from portable driving tripper 3 front and back both sides, the material will be discharged from portable driving tripper 3's bottom through the operation of second tripper 74 simultaneously, can also utilize tripper 71 to remove about portable driving tripper 3 goes up, make tripper 71 can remove in the left and right directions of feed bin 1, just so realized that feed bin 1 high altitude does not have the dead angle and unload, increase the pile up height of material, material storehouse material volume ratio.
The working principle is as follows: when the material unloading device is used, firstly, materials are transferred into the first discharger 6 from the feeding conveyor 2, then the materials are transferred into the unloading trolley 71 through the material conveying hose 77, so that the movable travelling crane unloader 3 can move in the front-back direction on the two electric slide rails 5, the materials in the unloading trolley 71 are unloaded from the front side and the rear side of the movable travelling crane unloader 3, meanwhile, the materials are discharged from the bottom of the movable travelling crane unloader 3 through the operation of the second discharger 74, the unloading trolley 71 can also be utilized to move left and right on the movable travelling crane unloader 3, so that the unloading trolley 71 can move in the left-right direction of the storage bin 1, and accordingly, the high-altitude dead-angle-free unloading of the storage bin 1 is realized, the accumulation height of the materials is increased, and the material volume rate of the storage bin is increased.

Claims (3)

1. A belt conveyor in a silo, comprising a silo (1), characterized in that: material loading conveyor (2) are installed to the inner wall of feed bin (1), the below of material loading conveyor (2) is provided with portable driving unloader (3), electronic slide rail (5) are all installed to the both sides of feed bin (1) inner wall, walking wheel (4) are all installed to the left and right sides of portable driving unloader (3), and two walking wheels (4) and two electronic slide rail (5) sliding connection of feed bin (1) inner wall, the top of portable driving unloader (3) is provided with shedding mechanism (7) of unloading to the material, first tripper (6) are installed at the top of material loading conveyor (2).
2. The belt conveyor in a warehouse of claim 1, wherein: discharge mechanism (7) are including tripper car (71), inlet pipe (72) and defeated material hose (77), install in the upper surface of portable driving unloader (3) tripper car (71), install in the top of tripper car (71) inlet pipe (72), and inlet pipe (72) are linked together with the inside of tripper car (71), the top of defeated material hose (77) and the fixed intercommunication of defeated material end of first tripper (6), the bottom of defeated material hose (77) and the fixed intercommunication in top of inlet pipe (72).
3. The belt conveyor in a warehouse of claim 2, wherein: discharge mechanism (7) are still including arranging material pipe (73), second tripper (74), connecting cable rope (75) and unloading pipe (76), connecting cable rope (75) are installed in the bottom of tripper (71), the bottom in connecting cable rope (75) is installed in second tripper (74), arrange material pipe (73) fixed intercommunication in the defeated material end of second tripper (74), the bottom mounting of unloading pipe (76) communicates in the feed end of second tripper (74), the top of unloading pipe (76) is run through portable driving tripper (3) and is linked together with the inside discharge strip of tripper (71).
CN202122585068.9U 2021-10-27 2021-10-27 Belt conveyor in warehouse Active CN215974057U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122585068.9U CN215974057U (en) 2021-10-27 2021-10-27 Belt conveyor in warehouse

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122585068.9U CN215974057U (en) 2021-10-27 2021-10-27 Belt conveyor in warehouse

Publications (1)

Publication Number Publication Date
CN215974057U true CN215974057U (en) 2022-03-08

Family

ID=80572141

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122585068.9U Active CN215974057U (en) 2021-10-27 2021-10-27 Belt conveyor in warehouse

Country Status (1)

Country Link
CN (1) CN215974057U (en)

Similar Documents

Publication Publication Date Title
CN204957857U (en) Automatic pile up neatly system of unloading
CN201573986U (en) Stacker for stockyard stacking
US4562918A (en) En-mass conveyor for verticle or steep delivery of bulk material
CN205367206U (en) Board buffer memory machine is received in plane panel conveyer belt and miniature automation
CN212531136U (en) Bagged material car loader capable of feeding materials in wide and narrow range
CN206407492U (en) chain belt conveyer
CN215974057U (en) Belt conveyor in warehouse
CN208150473U (en) Pallet interpreter
CN216335415U (en) Bulk truck unloading system
CN213264763U (en) Chain plate mechanism of mobile ship loader
CN209023840U (en) A kind of discharging mechanism of ship unloaders
CN209922449U (en) Rectangular raw material warehouse
CN102718035B (en) Reclaimer with self-releasing buffer bed
CN213264762U (en) Fixed powder discharge system
CN217920407U (en) Container loading and unloading system
CN206203482U (en) A kind of giant tire conveying equipment
CN220011462U (en) Multifunctional C-shaped warehouse feeding system
CN220975886U (en) Chain type whole-vehicle material loading system
CN214878693U (en) Vertical conveyer is used in powder transmission
CN211443806U (en) Continuous vertical conveyor
CN218663648U (en) Vertical continuous food conveyor
CN216402961U (en) Movable driving unloading conveyor
CN211846399U (en) Automatic loading and dumping device for framed oranges
CN214295715U (en) Vehicle-mounted universal conveyor
CN215159369U (en) Bulk cargo unloading device based on single piece separation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant