CN215830084U - Support arrangement is restoreed to section for building engineering - Google Patents

Support arrangement is restoreed to section for building engineering Download PDF

Info

Publication number
CN215830084U
CN215830084U CN202121688144.2U CN202121688144U CN215830084U CN 215830084 U CN215830084 U CN 215830084U CN 202121688144 U CN202121688144 U CN 202121688144U CN 215830084 U CN215830084 U CN 215830084U
Authority
CN
China
Prior art keywords
base
jack
connecting seat
screw rod
support device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121688144.2U
Other languages
Chinese (zh)
Inventor
袁毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202121688144.2U priority Critical patent/CN215830084U/en
Application granted granted Critical
Publication of CN215830084U publication Critical patent/CN215830084U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model belongs to the technical field of fracture surface repairing support, and particularly relates to a fracture surface repairing support device for constructional engineering, which comprises a support device body mainly composed of a temporary support column and four jacks, wherein a connecting assembly is arranged between the temporary support column and the jacks; through the coupling assembling that sets up, link together interim support column and jack for jack and interim support column form a whole, security when having improved the support, and adopt separable setting between interim support column and the coupling assembling, are convenient for transport, and through the base subassembly that sets up, the whole that is convenient for make coupling assembling, jack and base subassembly form removes.

Description

Support arrangement is restoreed to section for building engineering
Technical Field
The utility model belongs to the technical field of section repairing support, and particularly relates to a section repairing support device for constructional engineering.
Background
In the building work progress, when the floor crackle appears, in time, need repair, before repairing, need use strutting arrangement to support near the crackle, but current strutting arrangement is very crude, generally constitute by interim support column and jack, when using, four jacks are placed in interim support column below, support interim support column through the jack, thereby withstand the floor, form interim support, but current strutting arrangement lacks the connection between interim support column and jack, and current strutting arrangement has the problem of inconvenient removal when using.
In order to solve the problems, the application provides a section repairing and supporting device for constructional engineering.
SUMMERY OF THE UTILITY MODEL
To solve the problems set forth in the background art described above. The utility model provides a cross section repairing and supporting device for constructional engineering, which has the characteristics of convenience in disassembly and assembly and convenience in movement.
In order to achieve the purpose, the utility model provides the following technical scheme: a cross section repairing and supporting device for constructional engineering comprises a supporting device body mainly composed of a temporary supporting column and four jacks, wherein a connecting assembly is arranged between the temporary supporting column and the jacks;
the connecting assembly comprises a connecting seat, two screw rods and two clamping blocks, four jacks are symmetrically installed at four corners of the lower surface of the connecting seat, two screw rods are symmetrically arranged on two sides of the connecting seat, the two screw rods penetrate through the connecting seat and are spirally connected with the connecting seat, the adjacent end surfaces of the two screw rods are rotatably connected with the clamping blocks through bearings A, and the clamping blocks are slidably connected with the connecting seat.
Preferably, the connecting assembly further comprises two hand wheels A, and the hand wheels A are mounted on the end faces of the two screws, which are away from each other.
Preferably, in the fracture surface repairing support device for construction engineering of the present invention, the fixture block has a substantially t-shaped cross section.
The section repairing support device for the building engineering is preferable, and further comprises a base assembly, wherein the base assembly comprises a base with a hollow structure, a two-way screw, a hand wheel B, a sleeve block, a connecting rod, a movable plate and four universal wheels, the base is installed at one end, far away from the connecting seat, of the jack, the two-way screw is arranged at one end, close to the jack, of the inner side of the base, one end of the two-way screw is connected with the inner side wall of the base through a bearing B, the other end of the two-way screw penetrates through the base and is connected with the hand wheel B arranged on the outer side of the base, the sleeve block is sleeved on the outer side of the two-way screw, the sleeve block is in threaded connection with the two-way screw, the lower surface of the sleeve block is connected with the connecting rod through a rotating support A, one end, far away from the sleeve block, of the connecting rod is connected with the movable plate through a rotating support B, the fly leaf with base sliding connection, four turnings of fly leaf lower surface are all installed the universal wheel, the base lower surface seted up with the through-hole that the universal wheel cooperation was used.
Preferably, the two ends of the bidirectional screw have the same thread length, the same thread pitch and opposite directions.
Preferably, the outer side wall of the movable plate is attached to the inner side wall of the base.
Preferably, as a fracture repairing support device for construction engineering of the present invention, the diameter of the through hole is larger than the rotation diameter of the universal wheel.
Compared with the prior art, the utility model has the beneficial effects that:
through the coupling assembling that sets up, link together interim support column and jack for jack and interim support column form a whole, security when having improved the support, and adopt separable setting between interim support column and the coupling assembling, are convenient for transport, and through the base subassembly that sets up, the whole that is convenient for make coupling assembling, jack and base subassembly form removes.
Drawings
The accompanying drawings, which are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate embodiments of the utility model and together with the description serve to explain the principles of the utility model and not to limit the utility model. In the drawings:
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of a connecting assembly according to the present invention;
FIG. 3 is a schematic view of a base assembly according to the present invention;
FIG. 4 is a bottom view of the base assembly of the present invention;
in the figure:
10. a support device body; 11. a temporary support post; 12. a jack;
20. a connecting assembly; 21. a connecting seat; 22. a screw; 23. a hand wheel A; 24. a clamping block;
30. a base assembly; 31. a base; 32. a bidirectional screw; 33. a hand wheel B; 34. sleeving blocks; 35. a connecting rod; 36. a movable plate; 37. a universal wheel; 38. and a through hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1
As shown in fig. 1 and 2;
a section repairing and supporting device for constructional engineering comprises a supporting device body 10 mainly composed of a temporary supporting column 11 and four jacks 12, and a connecting assembly 20 is arranged between the temporary supporting column 11 and the jacks 12.
In this embodiment: the existing supporting device body 10 is composed of temporary supporting columns 11 and jacks 12, when the supporting device is used, the four jacks 12 are placed below the temporary supporting columns 11, the temporary supporting columns 11 are supported through the jacks 12, due to the fact that connection between the temporary supporting columns 11 and the jacks 12 is lacked, certain danger exists when the supporting device is used, the temporary supporting columns 11 and the jacks 12 are connected together through the arranged connecting assemblies 20, the jacks 12 and the temporary supporting columns 11 form a whole, the supporting safety is improved, the temporary supporting columns 11 and the connecting assemblies 20 are arranged in a separable mode, and transportation is facilitated.
Further, the method comprises the following steps:
coupling assembling 20 includes connecting seat 21, two screws 22 and two fixture blocks 24, and four jacks 12 are installed to four turning symmetries of connecting seat 21 lower surface, and connecting seat 21 bilateral symmetry is provided with two screws 22, and two screws 22 all run through connecting seat 21 and with connecting seat 21 screwed connection, and two screws 22's adjacent terminal surface all rotates through bearing A and is connected with fixture block 24, fixture block 24 and connecting seat 21 sliding connection.
In this embodiment: when using, place interim support post 11 in connecting seat 21, the staff rotates screw rod 22 afterwards, because of screw rod 22 and connecting seat 21 screwed connection, can change the relative position with connecting seat 21 when screw rod 22 is rotatory, be connected through bearing A and fixture block 24 because of screw rod 22, it is rotatory to make screw rod 22 can not drive fixture block 24 when rotating, and promote fixture block 24 and remove in connecting seat 21, through two fixture block 24 with interim support post 11 centre gripping in connecting seat 21, make jack 12 form a whole through coupling assembling 20 and interim support post 11, and it makes the staff can separate interim support post 11 from connecting seat 21 as required to dismantle the connection between coupling assembling 20 and the interim support post 11, thereby convenient transportation.
Further, the method comprises the following steps:
in an alternative embodiment, the connection assembly 20 further includes two handwheels a23, and handwheels a23 are mounted on the opposite end faces of the two screws 22.
In this embodiment: the handwheel A23 is arranged, so that the screw 22 can be conveniently rotated by a worker.
Further, the method comprises the following steps:
in an alternative embodiment, latch 24 is substantially t-shaped in cross-section.
In this embodiment: because the cross section of fixture block 24 is the gamma form, can make fixture block 24 buckle the protruding strengthening rib in the below of temporary support post 11 to can improve the firm degree of connection.
As shown in fig. 1, 3 and 4:
the section repairing support device for the constructional engineering further comprises a base assembly 30, the base assembly 30 comprises a base 31 with a hollow structure, a bidirectional screw 32, a hand wheel B33, a sleeve block 34, a connecting rod 35, a movable plate 36 and four universal wheels 37, the base 31 is installed at one end, far away from the connecting seat 21, of the jack 12, the bidirectional screw 32 is arranged at one end, close to the jack 12, of the inner side of the base 31, one end of the bidirectional screw 32 is connected with the inner side wall of the base 31 through a bearing B, the other end of the bidirectional screw 32 penetrates through the base 31 and is connected with the hand wheel B33 arranged on the outer side of the base 31, the sleeve block 34 is sleeved on the outer side of the bidirectional screw 32, the sleeve block 34 is in threaded connection with the bidirectional screw 32, the lower surface of the sleeve block 34 is connected with the connecting rod 35 through a rotating support A, one end, far away from the sleeve block 34, of the connecting rod 35 is connected with the movable plate 36 through the rotating support B, and the movable plate 36 is in sliding connection with the base 31, universal wheels 37 are mounted at four corners of the lower surface of the movable plate 36, and through holes 38 matched with the universal wheels 37 are formed in the lower surface of the base 31.
In this embodiment: when the device needs to be moved, a worker can rotate the hand wheel B33, the hand wheel B33 drives the bidirectional screw rod 32 to rotate, the bidirectional screw rod 32 drives the sleeve blocks 34 to move on the bidirectional screw rod 32 when rotating, so that the distance between the two sleeve blocks 34 is changed, the connecting rod 35 is rotated, the movable plate 36 is moved in the base 31, the universal wheel 37 extends out of the base 31 through the through hole 38, the device can be moved at the moment, when the device does not need to be moved, the worker reversely operates the hand wheel B33 to enable the universal wheel 37 to be retracted into the base 31, the contact surface between the lower surface of the base 31 and the ground is large, and the unit pressure intensity is reduced.
Further, the method comprises the following steps:
in an alternative embodiment, the two-way screw 32 has equal thread length, equal pitch and opposite direction at both ends.
In this embodiment: because the two ends of the bidirectional screw 32 have the same thread length, the same thread pitch and the opposite directions, the two sets of blocks 34 can be driven to synchronously move away from or move towards each other at equal intervals at the two ends of the bidirectional screw 32 when the bidirectional screw 32 rotates.
Further, the method comprises the following steps:
in an alternative embodiment, the outer sidewall of the movable plate 36 is attached to the inner sidewall of the base 31.
In this embodiment: because the outer sidewall of the movable plate 36 is attached to the inner sidewall of the base 31, the movable plate 36 can only slide smoothly in the base 31, and the movable plate 36 does not rotate.
Further, the method comprises the following steps:
in an alternative embodiment, the diameter of the through hole 38 is larger than the diameter of rotation of the universal wheel 37.
In this embodiment: because the diameter of the through hole 38 is larger than the rotating diameter of the universal wheel 37, the universal wheel 37 can be smoothly collected into the base 31 no matter where the universal wheel rotates.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that changes may be made in the embodiments and/or equivalents thereof without departing from the spirit and scope of the utility model. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The utility model provides a strutting arrangement is restoreed to section for building engineering, includes mainly by interim support column (11) and strutting arrangement body (10) that four jack (12) constitute, its characterized in that: a connecting assembly (20) is arranged between the temporary supporting column (11) and the jack (12);
coupling assembling (20) are including connecting seat (21), two screw rods (22) and two fixture blocks (24), four are installed to four turning symmetries of connecting seat (21) lower surface jack (12), connecting seat (21) bilateral symmetry is provided with two screw rods (22), two screw rods (22) all run through connecting seat (21) and with connecting seat (21) screwed connection, two adjacent terminal surface of screw rod (22) all rotates through bearing A and is connected with fixture block (24), fixture block (24) with connecting seat (21) sliding connection.
2. A fracture repair support device for construction engineering according to claim 1, wherein: coupling assembling (20) still include two hand wheel A (23), two the terminal surface that leaves of screw rod (22) all installs hand wheel A (23).
3. A fracture repair support device for construction engineering according to claim 1, wherein: the section of the fixture block (24) is in a shape of inverted L.
4. A fracture repair support device for construction engineering according to claim 1, wherein: the lifting jack is characterized by further comprising a base assembly (30), the base assembly (30) comprises a base (31) with a hollow structure, a two-way screw rod (32), a hand wheel B (33), a sleeve block (34), a connecting rod (35), a movable plate (36) and four universal wheels (37), the base (31) is installed at one end, far away from the connecting seat (21), of the jack (12), the two-way screw rod (32) is arranged at one end, close to the jack (12), of the inner side of the base (31), one end of the two-way screw rod (32) is connected with the inner side wall of the base (31) through a bearing B, the other end of the two-way screw rod (32) penetrates through the base (31) and is connected with the hand wheel B (33) arranged on the outer side of the base (31), the sleeve block (34) is sleeved on the outer side of the two-way screw rod (32), and the sleeve block (34) is in threaded connection with the two-way screw rod (32), nest block (34) lower surface through rotate support A with connecting rod (35) are connected, connecting rod (35) are kept away from the one end of nest block (34) through rotate support B with fly leaf (36) are connected, fly leaf (36) with base (31) sliding connection, four corners of fly leaf (36) lower surface are all installed universal wheel (37), base (31) lower surface seted up with through-hole (38) that universal wheel (37) cooperation was used.
5. A fracture repair support device for construction engineering according to claim 4, wherein: the two ends of the bidirectional screw (32) are equal in thread length, equal in thread pitch and opposite in direction.
6. A fracture repair support device for construction engineering according to claim 4, wherein: the outer side wall of the movable plate (36) is attached to the inner side wall of the base (31).
7. A fracture repair support device for construction engineering according to claim 4, wherein: the diameter of the through hole (38) is larger than the rotating diameter of the universal wheel (37).
CN202121688144.2U 2021-07-23 2021-07-23 Support arrangement is restoreed to section for building engineering Active CN215830084U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121688144.2U CN215830084U (en) 2021-07-23 2021-07-23 Support arrangement is restoreed to section for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121688144.2U CN215830084U (en) 2021-07-23 2021-07-23 Support arrangement is restoreed to section for building engineering

Publications (1)

Publication Number Publication Date
CN215830084U true CN215830084U (en) 2022-02-15

Family

ID=80193157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121688144.2U Active CN215830084U (en) 2021-07-23 2021-07-23 Support arrangement is restoreed to section for building engineering

Country Status (1)

Country Link
CN (1) CN215830084U (en)

Similar Documents

Publication Publication Date Title
CN110847620B (en) Assembled wall body temporary connection fixed equipment
CN110932198B (en) Movable cable support
CN211058020U (en) Connecting device for building external hanging and building main body
CN215830084U (en) Support arrangement is restoreed to section for building engineering
CN211974353U (en) Adjustable support for constructional engineering
CN212376322U (en) A consolidate bearing structure for building engineering
CN212428329U (en) Building construction rail guard
CN114541781A (en) Research of guiding and positioning device convenient for assembling large-sized steel members to be installed at high altitude
CN218324291U (en) Safety device is used in construction in room
CN219604945U (en) Building construction strutting arrangement
CN219773627U (en) Reinforced support template for house construction engineering
CN220868820U (en) Novel template fastening device
CN212427541U (en) Steel structure for building
CN217106276U (en) Safety protective net for high-rise building construction
CN220336520U (en) Detachable protection structure
CN219993046U (en) Assembled building construction device
CN219033522U (en) Novel steel skeleton building structure
CN218668845U (en) Building construction safety device
CN214144596U (en) Can improve stability's building scaffold support
CN221095779U (en) Building engineering is with climbing frame
CN212405499U (en) Civil chain building structure
CN211294490U (en) Safety warning device for building construction safety protection
CN218933919U (en) Support structure for building engineering extension
CN215047801U (en) Protective structure of construction well is built in building room
CN220790225U (en) Enhanced small unit assembled curtain wall system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant