CN215760391U - Scaffold is encorbelmented and is set up interim supporting connection spare - Google Patents
Scaffold is encorbelmented and is set up interim supporting connection spare Download PDFInfo
- Publication number
- CN215760391U CN215760391U CN202121548179.6U CN202121548179U CN215760391U CN 215760391 U CN215760391 U CN 215760391U CN 202121548179 U CN202121548179 U CN 202121548179U CN 215760391 U CN215760391 U CN 215760391U
- Authority
- CN
- China
- Prior art keywords
- supporting
- plug
- scaffold
- supporting top
- threaded connection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a temporary supporting connecting piece for scaffold overhanging erection, and relates to the technical field of construction tools. The supporting part body consists of a supporting top part, a supporting plug-in part, a lengthened screw rod and a fine leveling screw rod, wherein an internal thread is arranged on the inner side of the lower part of the supporting top part, an external thread is arranged on the periphery of the upper part of the supporting plug-in part, the supporting top part is plugged on the supporting plug-in part, the supporting top part is in threaded connection with the external thread of the supporting plug-in part through the internal thread, the two sides of the supporting top part in the horizontal direction are in threaded connection with the lengthened screw rod, and the supporting top part is in threaded connection with the fine leveling screw rod in the vertical direction; the supporting plug-in unit is reserved with a screw hole for installing an observer or a horizontal tube. The utility model does not need to require the strength of the overhanging layer concrete, can save the installation time, shorten the construction period, reduce the installation cost, ensure the installation quality, and has high safety and wide application prospect.
Description
Technical Field
The utility model relates to the technical field of construction tools, in particular to a temporary supporting connecting piece for overhanging and erecting a scaffold.
Background
The scaffold puts up various supports for workman's operation and aerial work at the job site, along with the national advocates and the attention of safety in production of green construction, for guaranteeing the layer of encorbelmenting of outer scaffold and setting up the quality, will wait usually that the concrete intensity reaches minimum requirement can only install the I-steel of encorbelmenting when setting up the layer of encorbelmenting now, but this requirement is difficult to control. According to the past construction experience, the installation of the outer frame of the overhanging layer takes 2-3 days more than that of the standard layer, the time cost is higher, and the quality of the outer scaffold is not well controlled during early installation. In order to solve the problems, a novel scaffold is designed to be cantilevered and provided with temporary supporting and connecting pieces.
Disclosure of Invention
Aiming at the defects in the prior art, the utility model aims to provide the temporary supporting connecting piece erected by overhanging the scaffold, which has the advantages of simple structure, reasonable design, no requirement on the concrete strength of an overhanging layer, installation time saving, installation cost reduction, installation quality guarantee, high safety, strong practicability and easiness in popularization and use.
In order to achieve the purpose, the utility model is realized by the following technical scheme: the utility model provides a scaffold frame is encorbelmented and is set up interim supporting connection spare, includes the supporting part body, the supporting part body constitute by supporting ejector member, supporting plug-in components, extra long screw rod and fine setting flat screw rod, supporting ejector member lower part inboard is provided with the internal thread silk, supporting plug-in components upper portion periphery is provided with the external screw thread, supporting ejector member pegs graft on supporting plug-in components, supporting ejector member passes through the external screw thread threaded connection of internal thread silk with supporting plug-in components, supporting ejector member in horizontal direction both sides threaded connection have extra long screw rod, supporting ejector member in vertical direction threaded connection have the fine setting flat screw rod.
Preferably, the support insert is reserved with a screw hole for installing the observer or the horizontal tube.
Preferably, the supporting piece body is inserted into the outer scaffold upright rod through the supporting plug-in unit, the I-shaped steel is placed on the supporting piece body through the supporting top piece, the I-shaped steel is tightly supported and fixed through the lengthened screw rods on the two sides, and the level of the I-shaped steel is adjusted through the fine leveling screw rods.
Preferably, the supporting top piece and the supporting plug-in piece are both made of steel plates with the thickness of 5 mm; the lengthened screw rod and the fine adjustment flat screw rod are all national standard bolts with the diameter of 10 mm.
The utility model has the beneficial effects that: the device does not need to require the concrete strength of the overhanging layer, can save the installation time, shorten the construction period, reduce the installation cost, ensure the installation quality, and has high safety and wide application prospect.
Drawings
The utility model is described in detail below with reference to the drawings and the detailed description;
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of the support head of the present invention;
FIG. 3 is a top view of FIG. 2;
FIG. 4 is a left side view of FIG. 2;
FIG. 5 is a schematic structural view of a bearing insert of the present invention;
FIG. 6 is a top view of FIG. 5;
FIG. 7 is a schematic view of the installation of the present invention;
fig. 8 is a left side view of fig. 7.
Detailed Description
In order to make the technical means, the creation characteristics, the achievement purposes and the effects of the utility model easy to understand, the utility model is further described with the specific embodiments.
Referring to fig. 1 to 8, the following technical solutions are adopted in the present embodiment: a temporary supporting and connecting piece for overhanging and erecting a scaffold comprises a supporting piece body, wherein the supporting piece body consists of a supporting top piece 1, a supporting plug-in 2, a lengthened screw rod 3 and a fine-adjustment flat screw rod 4, an internal thread 5 is arranged on the inner side of the lower part of the supporting top piece 1, an external thread 6 is arranged on the periphery of the upper part of the supporting plug-in 2, the supporting top piece 1 is inserted into the supporting plug-in 2, the supporting top piece 1 is in threaded connection with the external thread 6 of the supporting plug-in 2 through the internal thread 5, the lengthened screw rods 3 are in threaded connection with the two sides of the supporting top piece 1 in the horizontal direction, and the fine-adjustment screw rod 4 is in threaded connection with the supporting top piece 1 in the vertical direction; the supporting plug-in 2 is reserved with a screw hole 7 for installing an observer or a horizontal tube.
It is noted that the support body is inserted into the outer scaffolding upright 8 via the support insert 2, and the support body is provided with i-beams 9 via the support head 1.
In addition, the supporting top part 1 and the supporting plug-in part 2 are made of steel plates with the thickness of 5mm, and the lengthened screw rod 3 and the micro leveling screw rod 4 are made of national standard bolts with the diameter of 10 mm.
The installation method of the specific embodiment comprises the following steps: a temporary support frame body is additionally arranged in advance at the position where the overhanging I-steel is installed, a support plug-in 2 of a support body is plugged with an outer scaffold upright rod 8, after the I-steel 9 is placed at a designated position on a safe scaffold by a worker, the I-steel 9 is adjusted by utilizing the small-amplitude adjustment characteristic of the support, wherein the I-steel is tightly fixed by jacking lengthened screw rods 3 at two sides, and the horizontal position is adjusted by a micro-leveling screw rod 4, so that the elevation and the plane position of the overhanging I-steel during installation are accurately controlled. After the I-steel 9 is fastened and adjusted and meets the requirement for erecting the upper-layer external scaffold, the upper-layer external scaffold is directly erected on the I-steel, and when the concrete meets the stress requirement, the temporary supporting frame body can be detached and reused for the next overhanging I-steel layer.
The concrete embodiment is used for building overhanging layers of various building external scaffolds, the frame body for temporarily supporting the I-steel is added when the overhanging I-steel is built, the concrete strength of the overhanging layer is not required, the problems of time saving and safety quality during installation can be effectively solved, the construction period is effectively shortened, the installation quality of the external scaffolds with the overhanging layers is improved, the construction safety is improved, and the wide market application prospect is achieved.
The foregoing shows and describes the general principles and broad features of the present invention and advantages thereof. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, which are described in the specification and illustrated only to illustrate the principle of the present invention, but that various changes and modifications may be made therein without departing from the spirit and scope of the present invention, which fall within the scope of the utility model as claimed. The scope of the utility model is defined by the appended claims and equivalents thereof.
Claims (5)
1. The utility model provides a scaffold frame is encorbelmented and is set up interim supporting connection spare, a serial communication port, including the supporting member body, the supporting member body constitute by supporting top (1), supporting plug-in components (2), extension screw (3) and little leveling screw (4), supporting top (1) lower part inboard is provided with internal thread (5), supporting plug-in components (2) upper portion periphery is provided with external screw thread (6), supporting top (1) is pegged graft on supporting plug-in components (2), supporting top (1) is through external screw thread (6) threaded connection of internal thread (5) and supporting plug-in components (2), supporting top (1) in horizontal direction both sides threaded connection have extension screw (3), supporting top (1) in vertical direction threaded connection have little leveling screw (4).
2. A scaffold cantilever erection temporary support coupling according to claim 1, wherein the support insert (2) is reserved with screw holes (7) for mounting scopes or level tubes.
3. The temporary supporting and connecting member for scaffold cantilever erection according to claim 1, wherein the supporting member body is inserted into the outer scaffold upright rod (8) through the supporting plug-in member (2), the supporting member body is placed with the i-steel (9) through the supporting top member (1), and the i-steel (9) is tightly fixed by the lengthened screws (3) at both sides.
4. A scaffold cantilever erection temporary support connector according to claim 1, wherein said supporting top member (1) and supporting insert (2) are made of steel plate with thickness of 5 mm.
5. A scaffold cantilever erection temporary support connector according to claim 1, wherein said supporting top member (1) and supporting insert (2) are made of steel plate with thickness of 5 mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121548179.6U CN215760391U (en) | 2021-07-08 | 2021-07-08 | Scaffold is encorbelmented and is set up interim supporting connection spare |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121548179.6U CN215760391U (en) | 2021-07-08 | 2021-07-08 | Scaffold is encorbelmented and is set up interim supporting connection spare |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215760391U true CN215760391U (en) | 2022-02-08 |
Family
ID=80104547
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121548179.6U Active CN215760391U (en) | 2021-07-08 | 2021-07-08 | Scaffold is encorbelmented and is set up interim supporting connection spare |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215760391U (en) |
-
2021
- 2021-07-08 CN CN202121548179.6U patent/CN215760391U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN215168054U (en) | Independent supporting device for post-cast strip template | |
CN110016914A (en) | Contrary sequence method steel pipe column perpendicularity correction equipment and steel pipe column construction method | |
CN113417455A (en) | Self-reinforcing supporting rod for slip form construction | |
CN115492399A (en) | Construction method for installing and adjusting hanging steel structure from bottom to top | |
CN109113335B (en) | Parapet wall formwork support and construction method | |
CN215760391U (en) | Scaffold is encorbelmented and is set up interim supporting connection spare | |
CN102926554B (en) | Steel hanging seat formwork support and construction method thereof | |
CN113047666A (en) | Limiting device is supported in installation of assembled PC wall | |
CN210316214U (en) | Assembled steel construction building dysmorphism post | |
CN216109594U (en) | Construction engineering place construction is with scaffold frame of encorbelmenting of dismouting operation of being convenient for | |
CN109332430B (en) | Mast lifting and straightening device | |
CN107939156A (en) | The assembling type enclosing shield and its construction method of a kind of rapid construction | |
CN219973883U (en) | Cantilever climbing frame body | |
CN215717117U (en) | Novel detachable external scaffolding is wall spare even | |
CN220520009U (en) | Upper support of tower crane | |
CN210396176U (en) | Assembled wall body installing support | |
CN214144711U (en) | Be provided with mould reinforcing apparatus's for building aluminum mould board | |
CN221031317U (en) | Construction device for simply and conveniently installing basket cantilever I-shaped steel beam | |
CN218148489U (en) | Circular equipment foundation template device | |
CN216109628U (en) | Quick mounting platform in narrow and small space of extensible | |
CN102535805B (en) | Artificial stone decorative hanging plate for building overlooking inclined plane | |
CN219298784U (en) | Quick detach formula building engineering template bearing structure | |
CN219638356U (en) | Cantilever scaffold | |
CN220848753U (en) | Concrete placement template convenient to dismantle | |
CN210032630U (en) | Interim fixing device of adjustable horizontal component |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |